[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN110374014B - Construction method of long-span continuous beam UHPC column - Google Patents

Construction method of long-span continuous beam UHPC column Download PDF

Info

Publication number
CN110374014B
CN110374014B CN201910733636.XA CN201910733636A CN110374014B CN 110374014 B CN110374014 B CN 110374014B CN 201910733636 A CN201910733636 A CN 201910733636A CN 110374014 B CN110374014 B CN 110374014B
Authority
CN
China
Prior art keywords
uhpc
section
concrete
uhpc column
sections
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910733636.XA
Other languages
Chinese (zh)
Other versions
CN110374014A (en
Inventor
杨纪
怀臣子
徐世俊
张阳
冯仲林
陈阳阳
杨磊
宋银平
黄毅
余方亮
魏星
黄泰鑫
赵海增
郭坤领
熊东
张铎
王睿
管曼羽
张小涛
高香玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201910733636.XA priority Critical patent/CN110374014B/en
Publication of CN110374014A publication Critical patent/CN110374014A/en
Application granted granted Critical
Publication of CN110374014B publication Critical patent/CN110374014B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method of a large-span continuous beam UHPC column, which comprises the steps of prefabricating UHPC column sections, installing 0-section UHPC column sections on a main pier bracket, pouring common concrete, tensioning prestressed bundles, assembling a hanging basket, installing 1-section UHPC column sections on a hanging basket template, positioning the 1-section UHPC column sections through U-shaped positioning steel plates of the 0-section UHPC column sections, forming a rhombic pouring cavity by a cast-in-place joint surface structure and the U-shaped positioning steel plates which are opposite to each other, casting RPC into the rhombic pouring cavity, pouring 1-section common concrete, tensioning the prestressed bundles, moving and assembling the hanging basket, constructing other concrete sections with UHPC columns, constructing other common prestressed concrete sections and folding sections, and completing construction. The invention has the advantages of ingenious structure, convenient operation and convenient implementation, reduces the interference of secondary vertical molds, ensures the effective combination of the UHPC precast column and the post-cast joint, and solves the problem of continuous increase of deformation of the large-span prestressed concrete continuous beam structure caused by shrinkage and creep.

Description

Construction method of long-span continuous beam UHPC column
Technical Field
The invention relates to the technical field of bridge construction, in particular to a construction method of a long-span continuous beam UHPC column.
Background
The continuous span deflection of a long-span continuous beam (continuous rigid frame) caused by the shrinkage and creep of concrete in the operation process is a common problem in bridge engineering. UHPC (Ultra-High Performance Concrete) is an Ultra-High Performance Concrete material, has Ultra-High compressive strength, flexural strength and toughness, and compared with common Concrete, the UHPC has the characteristics of extremely low shrinkage Performance and small creep coefficient after being subjected to thermal curing due to the addition of active powder in the preparation process. Based on the characteristics, researchers assume that UHPC columns are arranged in a compression area of the continuous beam so as to solve the problem that the deformation of a large-span prestressed concrete continuous beam structure is continuously increased due to shrinkage and creep. However, how to design a bridge structure, simplify construction steps and reduce construction cost becomes a difficult problem to be solved urgently when the UHPC is applied to the construction of the long-span continuous beam.
Disclosure of Invention
In order to solve the problems, the invention provides a construction method of a long-span continuous beam UHPC column, which can adopt the following technical scheme:
the invention relates to a construction method of a long-span continuous beam UHPC column, which comprises the following steps:
prefabricating a UHPC column segment, wherein longitudinal steel bars are arranged in the UHPC column segment, cast-in-place joint surface structures are arranged at two ends of the UHPC column segment, a U-shaped positioning steel plate used for connecting adjacent UHPC column segments is coated at one end of the UHPC column segment, and shear nails are welded at the inner side and the outer side of a bottom plate, a left side plate and a right side plate of the U-shaped positioning steel plate;
secondly, erecting a bracket beside the main pier, then installing a No. 0 section of UHPC column segment on the template near the bottom, pouring No. 0 section of common concrete, stretching a No. 0 section of prestressed bundles after the strength of the concrete meets the design requirement, and assembling a hanging basket for symmetrical cantilever construction;
thirdly, installing a No. 1 section of UHPC column segment on the hanging basket template, positioning the No. 1 section of UHPC column segment through a U-shaped positioning steel plate of a No. 0 section of UHPC column segment, and forming a rhombic casting cavity by a cast-in-place joint surface structure and the U-shaped positioning steel plate which are opposite to each other;
fourthly, pouring RPC in a rhombic pouring cavity in the third step, pouring 1 section of common concrete, stretching 1 section of prestressed bundles after the strength of the concrete meets the design requirement, and moving and assembling the hanging basket for symmetrical cantilever construction;
fifthly, according to the method of the third step and the fourth step, the rest concrete segments designed with UHPC columns are constructed in sequence;
and sixthly, constructing other common prestressed concrete sections and closure sections in sequence according to a conventional construction method to finish bridge construction.
The total length of the concrete segment designed with UHPC columns in each span is 1/4-1/5 of the main span.
The concrete segment designed with the UHPC columns is provided with 1-10 UHPC column segments in parallel along the bridge width direction.
The invention has the advantages of ingenious structure, convenient operation and convenient implementation, can effectively reduce the interference of secondary vertical molds, ensure the effective combination of the UHPC precast column and the post-cast joint, can solve the problem of continuous deformation increase of the large-span prestressed concrete continuous beam structure caused by shrinkage and creep, and provides technical support for the construction of the large-span continuous beam with the UHPC column.
Drawings
FIGS. 1-7 are schematic illustrations of the construction steps of the present invention.
Fig. 8 is an enlarged view of a portion a in fig. 2.
Fig. 9 is a cross-sectional view taken along line I-I of fig. 8.
Detailed Description
The construction method of the long-span continuous beam UHPC column according to the invention is described in the following by specific examples.
As shown in fig. 1 to 7, the construction method includes the steps of:
firstly, prefabricating UHPC column sections 1, as shown in figures 8 and 9, wherein each UHPC column section 1 is internally provided with a longitudinal steel bar 1.1, two ends of each UHPC column section 1 are provided with cast-in-place joint surface structures 1.2 with concave middle parts, one end of each UHPC column section 1 is coated with a U-shaped positioning steel plate 1.3 for connecting adjacent UHPC column sections, and the inner side and the outer side of a bottom plate, a left side plate and a right side plate of each U-shaped positioning steel plate 1.3 are welded with shear nails 1.4;
secondly, erecting a bracket beside the main pier, prepressing the bracket, then installing a No. 0 UHPC column segment on the template close to the bottom, pouring No. 0 common concrete, tensioning a No. 0 prestressed bundle after the strength of the concrete reaches 90% of the design strength, and assembling a symmetrical hanging basket 2 for cantilever construction on the No. 0 segment; typically, according to design, the UHPC column segments are arranged 1-10 side by side in the bridge width direction.
Thirdly, installing a No. 1 section of UHPC column segment on the hanging basket template, positioning the No. 1 section through a U-shaped positioning steel plate 1.3 of a No. 0 section of UHPC column segment, and forming a rhombic casting cavity 1.5 (see figure 8) by a cast-in-place joint surface structure 1.2 and the U-shaped positioning steel plate 1.3 which are opposite to each other;
fourthly, pouring RPC (reactive powder concrete) into the rhombic casting cavity 1.5 in the third step in a cast-in-place mode to integrally connect the two UHPC column sections, then casting the common concrete of the section 1, tensioning the prestressed bundles of the section 1 after the strength of the concrete reaches 90% of the design strength, and moving and assembling the hanging basket 2 for symmetrical cantilever construction;
fifthly, according to the method of the third step and the fourth step, the rest concrete segments designed with UHPC columns are constructed in sequence; generally, the total length of each concrete section designed with UHPC columns in the bridge is 1/4-1/5 of the main span of the bridge, and the concrete section designed with UHPC columns in the embodiment is 0-8 sections.
And sixthly, constructing other common prestressed concrete sections and closure sections in sequence according to a conventional construction method to finish bridge construction.
Specifically, for the common prestressed concrete segments, common concrete is poured firstly, after the strength of the concrete reaches 90% of the designed strength, the segment prestressed tendons are tensioned, then the hanging baskets 2 for symmetrical cantilever construction are moved and assembled, the operations are repeated, and all the common prestressed concrete segments are constructed in sequence.
When the folding section construction is carried out, firstly, a support beside the side pier is erected, a construction side span beam section is poured on the support, and then the folding section is constructed in sequence according to the design folding sequence.
And finally, dismantling the support, and constructing a bridge deck system, traffic engineering and other auxiliary facilities to complete bridge construction.
Compared with the common large-span continuous beam, the large-span continuous beam constructed by the invention has the advantages that the mid-span vertical displacement caused by 10-year shrinkage and creep is reduced by about 40-50%, the structure corner in the negative moment area is reduced by about 40%, the problem of continuous increase of the structure deformation caused by shrinkage and creep can be fully solved, and the service life of the large-span prestressed concrete continuous beam is effectively prolonged.

Claims (1)

1. A construction method of a long-span continuous beam UHPC column is characterized by comprising the following steps: the method comprises the following steps:
prefabricating a UHPC column segment, wherein longitudinal steel bars are arranged in the UHPC column segment, cast-in-place joint surface structures are arranged at two ends of the UHPC column segment, a U-shaped positioning steel plate used for connecting adjacent UHPC column segments is coated at one end of the UHPC column segment, and shear nails are welded at the inner side and the outer side of a bottom plate, a left side plate and a right side plate of the U-shaped positioning steel plate;
secondly, erecting a bracket beside the main pier, then installing a No. 0 section of UHPC column segment on the template near the bottom, pouring No. 0 section of common concrete, stretching a No. 0 section of prestressed bundles after the strength of the concrete meets the design requirement, and assembling a hanging basket for symmetrical cantilever construction;
thirdly, installing a No. 1 section of UHPC column segment on the hanging basket template, positioning the No. 1 section of UHPC column segment through a U-shaped positioning steel plate of a No. 0 section of UHPC column segment, and forming a rhombic casting cavity by a cast-in-place joint surface structure and the U-shaped positioning steel plate which are opposite to each other;
fourthly, pouring RPC in a rhombic pouring cavity in the third step, pouring 1 section of common concrete, stretching 1 section of prestressed bundles after the strength of the concrete meets the design requirement, and moving and assembling the hanging basket for symmetrical cantilever construction;
fifthly, according to the method of the third step and the fourth step, the rest concrete segments designed with UHPC columns are constructed in sequence;
sixthly, constructing other common prestressed concrete sections and closure sections in sequence according to a conventional construction method to finish bridge construction;
the total length of the concrete segment designed with the UHPC column in each span is 1/4-1/5 of the main span;
the concrete segment designed with the UHPC columns is provided with 1-10 UHPC column segments in parallel along the bridge width direction.
CN201910733636.XA 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column Active CN110374014B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910733636.XA CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910733636.XA CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Publications (2)

Publication Number Publication Date
CN110374014A CN110374014A (en) 2019-10-25
CN110374014B true CN110374014B (en) 2021-06-25

Family

ID=68258804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910733636.XA Active CN110374014B (en) 2019-08-09 2019-08-09 Construction method of long-span continuous beam UHPC column

Country Status (1)

Country Link
CN (1) CN110374014B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119071A (en) * 2020-01-16 2020-05-08 中建七局安装工程有限公司 Construction method for assembling precast concrete segment box girder
CN112081017A (en) * 2020-08-20 2020-12-15 河南五建建设集团有限公司 Construction method for assembling prefabricated cantilever on long-span segment of bridge to span existing bridge
CN112523061B (en) * 2020-11-24 2022-06-14 广西交通设计集团有限公司 UHPC stiffened prestressed concrete box girder bridge structure and construction process thereof

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1279918B (en) * 1963-05-25 1968-10-10 Krupp Gmbh Cast joint connection of two components
US5437072A (en) * 1992-01-23 1995-08-01 J. Muller International Rapid transit viaduct with post-tensioning cable system
FR2910502B1 (en) * 2006-12-21 2015-05-15 Lafarge Sa MANUFACTURING METHOD AND STRUCTURE ELEMENT
KR101198200B1 (en) * 2009-10-30 2012-11-07 고려대학교 산학협력단 Orthotropic steel bridge deck with improved fatigue strength having UHPC pavement and polyurethane foam tamping and constructing method of the same
CN203559329U (en) * 2013-11-11 2014-04-23 中铁第一勘察设计院集团有限公司 Steel-RPC (reactive powder concrete) combined bridge
CN104131510A (en) * 2014-07-17 2014-11-05 湖南大学 Prefabricated reactive powder concrete (RPC) beam joint connecting method
PL2993279T3 (en) * 2014-09-03 2017-05-31 Halfen Gmbh Building with a reinforcing element made of high-strength concrete for increasing puncture resistance
CN104746416B (en) * 2015-02-03 2016-08-31 湖南大学 A kind of RPC(Reactive Powder Concrete)-normal concrete compound cross-section structure
CN206328864U (en) * 2016-11-30 2017-07-14 上海建工二建集团有限公司 Assembled beam-column node structure
CN207277614U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall flat shape piecing connection structure
CN207277570U (en) * 2017-09-26 2018-04-27 华南理工大学 A kind of assembled steel plate concrete combined shear wall concave-convex piecing connection structure
CN207700481U (en) * 2017-11-20 2018-08-07 中国航天建设集团有限公司 Concrete rib beam splice and assembly concrete girt strip
US9988775B1 (en) * 2017-12-04 2018-06-05 The Florida International University Board Of Trustees Concrete i-beam for bridge construction
CN208440963U (en) * 2018-06-07 2019-01-29 广州市市政工程设计研究总院有限公司 A kind of UHPC small box girder structure
CN109057116A (en) * 2018-08-15 2018-12-21 湖南大学 A kind of ultra-high performance concrete sandwich floor slab and its manufacturing method
CN109281249B (en) * 2018-11-16 2023-12-12 福州大学 UHPC-NC superposed trestle bridge deck structure and construction method thereof
CN109487686A (en) * 2018-12-29 2019-03-19 武汉理工大学 A kind of unit construction bridge panel transverse joint using UHPC grouting material
CN109763433B (en) * 2019-01-23 2021-03-26 开封市农村公路管理处 Method for reinforcing assembled beam slab bridge

Also Published As

Publication number Publication date
CN110374014A (en) 2019-10-25

Similar Documents

Publication Publication Date Title
JP5945418B2 (en) How to build a box girder bridge
US8544129B2 (en) Composite girder for bridge construction
KR101177342B1 (en) Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same
CN110374014B (en) Construction method of long-span continuous beam UHPC column
CN107806008B (en) Integrated hollow slab bridge structure based on ultra-high performance concrete connection and construction method thereof
KR101283535B1 (en) Fully-precast prestressed concrete girder bridges and construction method of such bridges
CN207633207U (en) A kind of ultra-high performance concrete seam construction for assembly hollow slab bridges beam
CN113481826B (en) Prefabricated assembled corrugated steel web plate combined box girder
CN113957782A (en) Bent cap structure adopting double-main-beam prefabrication and assembly method and construction method thereof
CN112012091A (en) UHPC-NC mixed box girder, large-span rigid frame bridge and construction method thereof
KR101196874B1 (en) Girder making methos for precast end seggement using end mold and girder therewith
KR20160010783A (en) Method of manufacturing composite girder and of constructing birdge upper structure using same
CN113718632A (en) Bent cap structure that segmentation prefabrication was assembled
KR101075756B1 (en) A manufacturing process for the Truss Half Precast Prestressed Concrete Panel
CN110117933B (en) Cast-in-situ movable formwork for pier top of segmental beam
KR102203826B1 (en) Prestressed Concrete Spliced Girder Bridge and Construction method thereof
KR101034973B1 (en) Bridge and its construction method using tide arch hybrid girders by connecting precast blocks
CN111206488A (en) Large-span widened corrugated web steel box-concrete continuous beam bridge and construction method
KR20110067942A (en) Bridge having continuous arch hybrid girders and the bridge construction method using the same
CN211772741U (en) Large-span variable-width corrugated web steel box-concrete continuous beam bridge
KR101191647B1 (en) Constructing method of continuous bridge with complex upper structure
CN207633187U (en) A kind of integration hollow slab bridge girder construction based on ultra-high performance concrete connection
KR101698807B1 (en) Manufacturing method of the psc girder using the corrugated steel plate and the psc girder manufactured thereby
JP2000104221A (en) Combined truss bridge and erection method of the same
CN115287996A (en) Pier top UHPC-NC combined structure UHPC continuous box girder bridge and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant