CN110331992A - A kind of hole daguanpeng construction method - Google Patents

A kind of hole daguanpeng construction method Download PDF

Info

Publication number
CN110331992A
CN110331992A CN201910601404.9A CN201910601404A CN110331992A CN 110331992 A CN110331992 A CN 110331992A CN 201910601404 A CN201910601404 A CN 201910601404A CN 110331992 A CN110331992 A CN 110331992A
Authority
CN
China
Prior art keywords
pipe
hole
steel
concrete
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910601404.9A
Other languages
Chinese (zh)
Inventor
张旭海
朱连臣
王有旗
汤吉良
朱士勇
黄远平
朱时标
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN201910601404.9A priority Critical patent/CN110331992A/en
Publication of CN110331992A publication Critical patent/CN110331992A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention relates to constructing tunnel fields, and in particular to a kind of hole daguanpeng construction method.It includes the following steps: that step S1 surveying setting-out, step S2 face upward slope molding and lead arch construction operation platform, step S3 applies set and encircles, installs guide pipe, the construction of step S4 drilling machine workbench, step S5 drilling, step S6 pipe roof construction, step S7 closing excavation face and step S8 slip casting.It not only ensure that the safety of construction, also effectively increase pipe roof construction speed;It can ensure that hole top coating is in stablize, be adapted to complex geologic conditions, the loose layer of sand of soil property, argillic horizon etc., apply that process power output is uniform, it is few to the interference of geology.

Description

A kind of hole daguanpeng construction method
Technical field
The present invention relates to constructing tunnel fields, and in particular to a kind of hole daguanpeng construction method.
Background technique
Big for slope surface rickle thickness, harmful engineering ground phenomenon is avalanche, shows as the slope of collapsed accumulation body Body is in stable state in its natural state, but under mankind's activity, stability is poor, especially when outlet section country rock is broken Shi Shi carries out tunnel excavation in loosely-packed layer, and surrounding rock stability is poor, is easy to happen collapse and cave-in.The installation of pipe canopy Reasonability is to the construction important in inhibiting of subsequent tunnel, and therefore, reasonable pipe shed construction method is particularly important.Currently, existing Pipe shed construction method to easily lead to supporting effect lower.
Summary of the invention
Present invention seek to address that the above problem, provides a kind of hole daguanpeng construction method, it not only ensure that construction Safety, also effectively increase pipe roof construction speed;It can ensure that hole top coating is in stablize, it is multiple to be adapted to geological conditions Miscellaneous, the loose layer of sand of soil property, argillic horizon etc. apply that process power output is uniform, the technical side that uses few to the interference of geology Case is as follows:
A kind of hole daguanpeng construction method, which comprises the steps of:
Step S1 surveying setting-out, first review line midline, level, the wire center line traffic control stake of root Ju and vertical control point Facing upward slope surface, to identify tunnel center line and bowed out top mark high, and draws bowed out arc facing upward slope surface according to dark hole excavation contour line, As the foundation of guiding wall formwork erection, the height for being oriented to external mold within the walls is controlled according to the mileage of guiding wall, and reserved corresponding heavy Drop amount;
Step S2 faces upward slope molding and leads arch construction operation platform, according to design mileage, elevation and radius, excavates trim edges and faces upward Slope and hole Core Soil are all satisfied its bearing capacity, compactness, radian and lead arch bed die requirement, and excavation leads skewback plinth, and masonry grouts Piece stone foundation is laid with bamboo slab rubber as arch construction bottom die plate is led on Core Soil, erects I-steel steelframe according to design, welding connects Muscle and orifice tube are connect, installation leads arch side template and two side portions top template, pours and lead arch concrete;
Step S3 applies set arch, installs guide pipe;
The construction of step S4 drilling machine workbench, drilling machine construction podium level apply height lower than guiding wall, will excavate platform Deepened position other than two sides;
Step S5 drilling, is carried out using pipe shed drilling rig, and the height of drilling machine platform is according to the controllable range and brill of drilling machine Hole mistake hole (subdrilling odd number) is determined, and since drill hole of drilling machine sequence is carried out by high hole location to low hole location, position of platform is corresponding certainly It is gradually reduced under above, to meet drilling needs;
Step S6 pipe roof construction;
Step S7 closes excavation face, excavates face closure and uses wet shotcreting mode, forms wall for grouting, prevent slurry reflux Influence slip casting effect;
Step S8 slip casting.
On that basis of the above technical scheme, the step S3 applies set arch, installs guide pipe and include the following steps:
I-steel installation: to guarantee pipe roof construction rigidity, 4 Pin i-beam frames are set within the walls in guiding, every Pin steelframe is divided into five A unit, steelframe guarantee that the radian of every section and size meet design requirement, and fishplate bar, I-steel are each in succession at every section steelframe both ends Unit couples blending bolt by connecting plate and connects firm, and connecting plate is answered closely connected, examination is carried out after processing spells to check, every Pin steelframe is every End needs 4 sets of bolts, nuts altogether, should set up in strict accordance with design middle line and horizontal position when steelframe is installed, the lower end of steelframe is located at On firm stratum, arch springing height excavates 15~20cm of baseline or less lower than top, when arch springing excavates ultra-deep, adds steel plate or mixed Solidifying soil cushion block, in concrete perfusion, steelframe should be covered all by concrete, and steelframe protective layer thickness is not less than 40mm, and steelframe exists It should try to spell on cement floor after completion of processing, longitudinally be arranged using reinforcing bar circumferential direction spacing between 2 Pin steelframes, and couple jail with steelframe Gu steelframe is bottomed need to be placed on firm basement rock, when arch springing excavates ultra-deep, steel plate or concrete pad need to be added;
Guide pipe is embedded: after the completion of i-beam frame is set up, carry out the embedded of guide pipe, circumferential spacing according to pipe canopy spacing and Fixed, guide pipe is subjected to displacement in concrete perfusion in order to prevent, and guide pipe is connected on i-beam frame according to design requirement, peace When filling guide pipe, the circumferential spacing and lengthwise position of guide pipe are controlled, to meet design requirement, can first be marked in i-beam frame top surface The position of guide pipe is made, and arranges guide pipe by spacing, deflection requirement, guide pipe is longitudinal to be needed unanimously, outside with line direction Limb angle is 1 °~3 °, in order to avoid pipe shed drilling rig drilling intrusion tunnel cutting section, mortar enters when to avoid concrete from being poured And guide pipe is blocked, need to be pushed against with end mould when guide pipe is installed and is secured firmly to it on mould of end;
Template installation: being bolted between set arch steel form, smoother to ensure to be oriented to mould within the walls, is oriented to wall end mould Plate is installed using plank, between plank connection using plus back up mode reinforced, between plank sheathing and steel form using dog or Steel nail is connected firmly, and checks that template size is flat except elevation of top surface deviation, guiding wall marginal position deviation, template before installation template Whole degree, template surface faulting of slab ends deviation, template installation need solid and reliable, template and concrete surface brushing release agent;
Concrete casting: before concrete casting, template, guide pipe need to be checked again, and make calibration, in template Line, level and size have to comply with design requirement, and the position of built-in fitting must be correct, and template installation and bracket must be securely tight Close, set arch is poured using concrete, and concrete is unified by mixing station centralizedly supply, and concrete fills vehicle transport, and hand fit is mechanical It is poured and makes firm by ramming closely knit, casting sequence is symmetrically to be poured from arch springing two sides, until vault;
Concrete demoulding and maintenance: after concrete is poured, need to be conserved in time, and curing age must not be less than 7 days, Concrete strength reach design strength 70% after remove non-bearing template and Side Template, intensity and reach the 100% of design strength Internal model and bracket are removed afterwards.
On that basis of the above technical scheme, the step S6 pipe roof construction includes the following steps:
Borehole cleaning and down tube immediately after pore-forming, in order to avoid because the hole that collapses causes to can not be successfully installation due to blocking in hole, when down tube, need to be taken If the landing stage of scaffold, manually to push and pull based on jacking, it is aided with digging machine ejection,
Pipe canopy steel splitting pipe and steel floral tube, when construction, first set steel floral tube and cementing slurries, play steel pipe, then to check The grouting quality of steel floral tube;
Pipe canopy carries out cleaning bottom of hole, borehole cleaning, dross in cleaning hole with high-pressure blast device to hole is interior in a pre-installation, it is ensured that aperture, hole depth symbol It closes and requires, prevent plug-hole, pipe canopy is installed using jacking, section by section spreading, the joint steel pipe hot rolling seamless steel for spreading tube coupling Pipe is attached by outer thread button and interior thread button, and in order to improve the bending resistance of pipe canopy, steel reinforcement cage is added in pipe canopy, main Muscle is using overlap joint connection, side item connection.
On that basis of the above technical scheme, the S8 grouting includes the following steps:
Pipe canopy and steel reinforcement cage carry out slip casting after being installed, injecting paste material uses cement slurry, ratio of mud 1:1, and slip casting is suitable Sequence is carried out from low hole location to high hole location in principle, and complete opening uses disposable slip casting, fills steel using cement mortar after slip casting Pipe;
Since pipe canopy spacing is smaller, adjacent steel floral tube hole is caused to avoid occurring when slip casting string hole when geological condition is poor Blocking, hole-specifically slip casting, while slurries being allowed to be diffused filling in loose country rock, broken rock stratum is consolidated, phase is conducive to Chip off-falling is reduced in drilling in adjacent hole, avoids that bit freezing occurs or falls bore, fall pricker phenomenon, is conducive to accelerate construction progress;
Injected hole blocks mode: being coupled using steel plate in steel pipe opening and is blocked, reserves Grouting Pipe and exhaust pipe, Grouting Pipe installation Valve, plug closing is tight, grouting mode: in the direct slip casting of Guan Pengkou.
The invention has the benefit that not only ensure that the safety of construction, pipe roof construction speed is also effectively increased;It can Ensure that hole top coating is in stablize, is adapted to complex geologic conditions, the loose layer of sand of soil property, argillic horizon etc., it is dynamic to apply process Power output is uniformly, few to the interference of geology.
Detailed description of the invention
Fig. 1 is construction process figure of the invention;
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples:
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " etc. Term shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be direct phase Even, can also indirectly connected through an intermediary, the interaction that can be connection or two elements inside two elements is closed System.For the ordinary skill in the art, above-mentioned term in the present invention specific can be understood as the case may be Meaning.
As shown in Figure 1, a kind of hole daguanpeng construction method, which comprises the steps of:
Step S1 surveying setting-out, first review line midline, level, the wire center line traffic control stake of root Ju and vertical control point Facing upward slope surface, to identify tunnel center line and bowed out top mark high, and draws bowed out arc facing upward slope surface according to dark hole excavation contour line, As the foundation of guiding wall formwork erection, the height for being oriented to external mold within the walls is controlled according to the mileage of guiding wall, and reserved corresponding heavy Drop amount;
Step S2 faces upward slope molding and leads arch construction operation platform, according to design mileage, elevation and radius, excavates trim edges and faces upward Slope and hole Core Soil are all satisfied its bearing capacity, compactness, radian and lead arch bed die requirement, and excavation leads skewback plinth, and masonry grouts Piece stone foundation is laid with bamboo slab rubber as arch construction bottom die plate is led on Core Soil, erects I-steel steelframe according to design, welding connects Muscle and orifice tube are connect, installation leads arch side template and two side portions top template, pours and lead arch concrete;
Step S3 applies set arch, installs guide pipe;
The construction of step S4 drilling machine workbench, drilling machine construction podium level apply height lower than guiding wall, will excavate platform Deepened position other than two sides;
Step S5 drilling, is carried out using pipe shed drilling rig, and the height of drilling machine platform is according to the controllable range and brill of drilling machine Hole mistake hole (subdrilling odd number) is determined, and since drill hole of drilling machine sequence is carried out by high hole location to low hole location, position of platform is corresponding certainly It is gradually reduced under above, to meet drilling needs;The side combined is oriented to total station, hanging wire, drilling rod when drilling machine is in place Method adjusts repeatedly, it is ensured that borer drill rod axis and guidance axis match, in drilling, if occurring answering slip casting when bit freezing, collapse hole It bores again afterwards.When drilling, borehole log should be conscientiously filled in, in addition to record drilling depth, deflection, should also consider to be worth doing or take according to drilling out Stamen situation records country rock situation when different holes, achievees the purpose that forward probe country rock.Hole should carry out borehole cleaning after being drilled;
Step S6 pipe roof construction;
Step S7 closes excavation face, excavates face closure and uses wet shotcreting mode, forms wall for grouting, prevent slurry reflux Influence slip casting effect;
Step S8 slip casting.
Preferably, the step S3 applies set arch, installs guide pipe and include the following steps:
I-steel installation: to guarantee pipe roof construction rigidity, 4 Pin i-beam frames are set within the walls in guiding, I-steel radius is 6.54m, spacing 0.5m, every Pin steelframe are divided into five units, and steelframe guarantees that the radian of every section and size meet design requirement, often Save steelframe both ends fishplate bar in succession, it is firm that I-steel each unit by connecting plate couples blending bolt connection, connecting plate answer it is closely connected, Examination is carried out after processing and spells inspection, and every every end of Pin steelframe needs 4 sets of bolts, nuts altogether, should be in strict accordance with design middle line when steelframe is installed And horizontal position is set up, installation dimension tolerance: laterally and elevation is 0~+5cm, and the lower end of verticality ± 2 °, steelframe is located at On firm stratum, arch springing height excavates 15~20cm of baseline or less lower than top, when arch springing excavates ultra-deep, adds steel plate or mixed Solidifying soil cushion block, in concrete perfusion, steelframe should be covered all by concrete, and steelframe protective layer thickness is not less than 40mm, and steelframe exists Should try after completion of processing to spell on cement floor, assembly tolerance in steelframe periphery is ± 3cm, and plane warping should be less than 2cm, 2 It is longitudinally arranged using reinforcing bar circumferential direction spacing between Pin steelframe, and coupled securely with steelframe, steelframe is bottomed need to be placed on firm basement rock, When arch springing excavates ultra-deep, steel plate or concrete pad need to be added, when I-steel is installed, should ensure that I-steel bottom to internal model top surface Distance reach 2.5cm (i.e. the thickness of concrete cover of I-steel bottom);
Guide pipe is embedded: after the completion of i-beam frame is set up, carrying out the embedded of guide pipe, guide pipe uses diameter for Φ The seamless steel pipe of 127mm, wall thickness 6.5mm, the length of guide pipe are 2.0m, and circumferential spacing is depending on pipe canopy spacing Guide pipe is prevented to be subjected to displacement in concrete perfusion, guide pipe is connected on i-beam frame according to design requirement, installation is led When to pipe, the circumferential spacing and lengthwise position of guide pipe are controlled, to meet design requirement, can first be calibrated in i-beam frame top surface The position of guide pipe, and guide pipe is arranged by spacing, deflection requirement, guide pipe is longitudinal to need consistent, outer limb with line direction Angle is 1 °~3 °, in order to avoid pipe shed drilling rig drilling intrusion tunnel cutting section, mortar enters and blocks up when to avoid concrete from being poured Guide pipe is filled in, need to be pushed against with end mould when guide pipe is installed and is secured firmly to it on mould of end;
Template installation: being bolted between set arch steel form, smoother to ensure to be oriented to mould within the walls, is oriented to wall end mould Plate is installed using 5cm solid wood, and connection is used between plank sheathing and steel form and taken off using adding back up mode to be reinforced between plank Nail or steel nail are connected firmly, and check template size except elevation of top surface tolerance 10mm, guiding wall margin location before installation template Tolerance+10mm or 0mm, template flatness are set no more than 5mm, template surface faulting of slab ends tolerance 2mm, template installation needs jail Gu reliable, template and concrete surface brushing release agent;
Concrete casting: before concrete casting, template, guide pipe need to be checked again, and make calibration, in template Line, level and size meet design requirement, and the position of built-in fitting must be correct, and template installation and bracket secure rigid, set arch are adopted It is poured with concrete, concrete is unified by mixing station centralizedly supply, and concrete fills vehicle transport, and hand fit's machinery is poured and makes firm by ramming Closely knit, casting sequence is symmetrically to be poured from arch springing two sides, until vault;
Concrete demoulding and maintenance: after concrete is poured, need to be conserved in time, and curing age must not be less than 7 days, Concrete strength reach design strength 70% after remove non-bearing template (external mold) and Side Template, intensity and reach design strength Internal model and bracket are removed after 100%.
Preferably, the step S6 pipe roof construction includes the following steps:
Borehole cleaning and down tube immediately after pore-forming, in order to avoid because the hole that collapses causes to can not be successfully installation due to blocking in hole, when down tube, need to be taken If the landing stage of scaffold, manually to push and pull based on jacking, it is aided with digging machine ejection,
Pipe canopy steel splitting pipe and steel floral tube, when construction, first set steel floral tube and cementing slurries, play steel pipe, then to check The grouting quality of steel floral tube,
Long pipe shed is the seamless steel pipe that diameter is 108mm, wall thickness is 6mm, boring aperture 12mm on pipe canopy tube wall, and is in plum Flower-shape arranges that longitudinally, laterally spacing is 15cm for it, and tail portion is that only slurry section 300cm, the steel floral tube not drilled connect same section Head number must not exceed the 50% of pipe number;
Pipe canopy carries out cleaning bottom of hole, borehole cleaning, dross in cleaning hole with high-pressure blast device to hole is interior in a pre-installation, it is ensured that (aperture is or not aperture It obtains and meets the requirements less than 127cm), hole depth, prevent plug-hole, pipe canopy is installed using jacking, section by section spreading, for connecing for spreading tube coupling Head steel pipe is buckled with hot rolled seamless steel tube by outer thread and interior thread is buckled and is attached, in order to improve the bending resistance of pipe canopy, Steel reinforcement cage is added in pipe canopy, steel reinforcement cage uses 4 main reinforcements for the screw-thread steel of 16mm, and fixed ring uses diameter for the reinforcing bar of 6.5mm, Main reinforcement is using overlap joint connection, side item connection.
Preferably, the S8 grouting includes the following steps:
Pipe canopy and steel reinforcement cage carry out slip casting after being installed, injecting paste material uses cement slurry, ratio of mud 1:1, and slip casting is suitable Sequence is carried out from low hole location to high hole location in principle, and grouting pressure first pressing takes 0.8~1.0MPa, final pressure 2.0MPa, and complete opening uses Disposable slip casting fills steel pipe using cement mortar after slip casting;
Since pipe canopy spacing is smaller, adjacent steel floral tube hole is caused to avoid occurring when slip casting string hole when geological condition is poor Blocking, hole-specifically slip casting, while slurries being allowed to be diffused filling in loose country rock, broken rock stratum is consolidated, phase is conducive to Chip off-falling is reduced in drilling in adjacent hole, avoids that bit freezing occurs or falls bore, fall pricker phenomenon, is conducive to accelerate construction progress;
Injected hole blocks mode: being coupled using steel plate in steel pipe opening and is blocked, reserves Grouting Pipe and exhaust pipe, Grouting Pipe installation Valve, plug closing is tight, and grouting mode: in the direct slip casting of Guan Pengkou, Grouting Pipe gos deep into pipe 0.2~0.5m of canopy, grouting pressure Depending on the difference of nature of ground, groundwater condition and injecting paste material, final grouting pressure takes 2.0Mpa under normal circumstances, with single hole Grouting amount and grouting pressure are designed as slip casting ending standard, wherein based on should being controlled with single hole grouting amount, grouting pressure control Supplemented by.
The hole daguanpeng construction method can also include that grouting small pilot pipe is constructed, grouting small pilot pipe construction party Method includes:
The processing and fabricating of step A1 ductule
Ductule is processed using steel pipe, and the nozzle position of conduit sets reinforcing bar reinforcing ring;Steel pipe leading portion is not less than 30cm range Do not bore slurry outlet inside, rest part is circumferential at a certain distance to bore four holes, and adjacent twice aperture direction interlocks 45° angle;Tip Long 10cm, first cuts off notch, is being processed into tip, and coupled;
Step A2 drilling and jacking
It excavates forward position arch excavation contour line external standard and goes out hole location, drilled using rock bolting jumbo or air pressure gun, using certainly in construction The drilling rod of system, connector sleeve carry out spreading construction, and ductule is penetrated steelframe using the air drill with impact and is headed into hole, ductule Exposed junction is supported on the steel arch-shelf being subsequently mounted, and collectively constitutes pre support system with profile steel frame, will be in steel pipe with high-pressure blast Sandstone blowout, block aperture and surrounding crack with plasticine for physical after borehole cleaning is clean;
Step A3 prepares slurries
The stirring of cement slurry carries out in high-speed mixer, feeds intake in strict accordance with coordination in works, configured slurry Liquid is stored in the slurry can by low-speed agitator, prevents slurries due to resting period slightly long phenomena such as generating precipitating, isolation;
Step A4 slip casting
First gunite concrete closing face, which makees only slurry disk, grouting sequence, before slip casting follows in principle " in behind first two sides Between ", " jump hole slip casting ", " from thin to thick " principle.To prevent grout leaking and running pulp, using dividing slurry device, while four small lead is perfused It manages, can make to be mixed into some rubbles and clast in pipe in jacking construction operation process, be blown before mortar depositing construction with high pressure geomantic omen It washes, grouting equipment uses high-pressure injection pump, cement injection, and grouting pressure is generally 0.5~1Mpa;Single hole grouting amount:
Single hole grouting amount is related with the porosity of country rock, is estimated with following formula:
Q=π R2Ln β
In formula: Q-single hole slurries injection rate (m3);
R-grout spreading range (m);
L-slip casting segment length (m);
N-rock gap rate, generally takes 0.1~0.3;
Effective volumetric efficiency of the β-slurries in blowhole, generally 0.6~0.9.
The sundries such as paper scrap are forbidden to be mixed into slurries when mixing slurry, the slurries mixed will be forbidden by filtering, filtered slurries Into the pump housing, with anti-clogging, during slip casting, the moment to pay attention to the pressure changing in pumping hole and aperture, found the problem in time Processing;
Drilling, slip casting record are carried out, foundation is provided for analysis slip casting effect, after slip casting, thoroughly to clean the pump housing And pipeline, to guarantee the safe and smooth progress of next slip casting, such as discovery face spillage during mortar depositing construction is sealed with burlap It is stifled;
Step A5 mortar depositing construction quality assurance
In mortar depositing construction operation, the pressure of slurries injection is a most key site operation process control factors, root The aperture pressure change shown according to flowmeter may determine that the basic development situation of mortar depositing construction, and take corresponding measure in time,
If a, pressure is gradually increasing, but is not achieved the pressure of design requirement, the reason is that: concentration of slurry is low, gel time compared with Long, slurries form splitting arteries and veins either fraction slurries in rubble and overflow, and appropriateness increases concentration of slurry, short time interval slip casting;
If b, slip casting starts rear pressure and do not rise, or even there is initial pressure in downward trend, the reason is that: show slurries It is excessive.Big concentration slurries and lower injection rate are taken at this time, if situation first stops slip casting without change;
If c, grouting pressure declines suddenly after rising, show that slurries overflow or injection rate mistake around Grouting Pipe Greatly, rubble rock stratum is disturbed, or encounters gap weak part.Appropriateness reduces injection rate at this time;
D, if pressure is gone up and down repeatedly, but general trend in rise situation, the reason is that: due to grouting serous fluid gel time compared with Short, appropriateness adjusts long slurries gel time at this time;
If e, pressure rises quickly, and injection rate does not increase, the reason is that: show that slip casting rock stratum is more closely knit or slurries Gel time it is too short;
If f, the regular rising of pressure, even if reach allowable pressure, injection speed is also relatively more normal, this shows that slip casting is applied The industry that works is successful;
If decline after g, pressure rises again, however pressure rose once again again later, and reached the required value of design, can recognize To be successful.
The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention, for this field skill For art personnel, it is clear that invention is not limited to the details of the above exemplary embodiments, and without departing substantially from spirit of the invention or In the case where essential characteristic, the present invention can be realized in other specific forms.Therefore, in all respects, should all incite somebody to action Embodiment regards exemplary as, and is non-limiting, the scope of the present invention by appended claims rather than on state Bright restriction, it is intended that including all changes that fall within the meaning and scope of the equivalent elements of the claims in the present invention It is interior.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (4)

1. a kind of hole daguanpeng construction method, which comprises the steps of:
Step S1 surveying setting-out, first review line midline, level, the wire center line traffic control stake of root Ju and vertical control point are being faced upward It is high that slope surface identifies tunnel center line and bowed out top mark, and draws bowed out arc facing upward slope surface according to dark hole excavation contour line, as It is oriented to the foundation of wall formwork erection, the height for being oriented to external mold within the walls is controlled according to the mileage of guiding wall, and reserve corresponding settling amount;
Step S2 faces upward slope molding and leads arch construction operation platform, according to design mileage, elevation and radius, excavate finishing face-upward slope and Hole Core Soil is all satisfied its bearing capacity, compactness, radian and leads arch bed die requirement, and excavation leads skewback plinth, builds mortar flag stone Basis is laid with bamboo slab rubber as arch construction bottom die plate is led on Core Soil, erects I-steel steelframe according to design, be welded to connect muscle And orifice tube, installation lead arch side template and two side portions top template, pour and lead arch concrete;
Step S3 applies set arch, installs guide pipe;
The construction of step S4 drilling machine workbench, drilling machine construction podium level apply height lower than guiding wall, will excavate platform two sides Deepened position in addition;
Step S5 drilling, is carried out using pipe shed drilling rig, and the height of drilling machine platform is wrong according to the controllable range of drilling machine and drilling Hole (subdrilling odd number) is determined, since drill hole of drilling machine sequence is carried out by high hole location to low hole location, position of platform accordingly from upper and Under gradually reduced, to meet drilling needs;
Step S6 pipe roof construction;
Step S7 closes excavation face, excavates face closure and uses wet shotcreting mode, forms wall for grouting, prevent slurry reflux from influencing Slip casting effect;
Step S8 slip casting.
2. a kind of hole daguanpeng construction method according to claim 1, it is characterised in that: the step S3 applies set Encircle, install guide pipe and include the following steps:
I-steel installation: to guarantee pipe roof construction rigidity, 4 Pin i-beam frames are set within the walls in guiding, every Pin steelframe is divided into five lists Member, steelframe guarantees the radian of every section and size meets design requirement, every section steelframe both ends fishplate bar in succession, I-steel each unit Couple blending bolt by connecting plate and connect firm, connecting plate is answered closely connected, examination is carried out after processing spells to check, every every end of Pin steelframe is total 4 sets of bolts, nuts are needed, should be set up in strict accordance with design middle line and horizontal position when steelframe is installed, the lower end of steelframe is located at firm Stratum on, arch springing height lower than top excavate baseline below 15~20cm, arch springing excavate ultra-deep when, add steel plate or concrete Cushion block, in concrete perfusion, steelframe should be covered all by concrete, and steelframe protective layer thickness is not less than 40mm, and steelframe is being processed It should try to spell on cement floor after finishing, longitudinally be arranged using reinforcing bar circumferential direction spacing between 2 Pin steelframes, and couple securely with steelframe, Steelframe is bottomed need to be placed on firm basement rock, when arch springing excavates ultra-deep, need to add steel plate or concrete pad;
Guide pipe is embedded: after the completion of i-beam frame is set up, carry out the embedded of guide pipe, circumferential spacing depending on pipe canopy spacing, Guide pipe is subjected to displacement in concrete perfusion in order to prevent, and guide pipe is connected on i-beam frame according to design requirement, installation When guide pipe, the circumferential spacing and lengthwise position of guide pipe are controlled, to meet design requirement, can first be demarcated in i-beam frame top surface The position of guide pipe out, and guide pipe is arranged by spacing, deflection requirement, guide pipe is longitudinal to need consistent, extrapolation with line direction Angle angle is 1 °~3 °, in order to avoid pipe shed drilling rig drilling intrusion tunnel cutting section, mortar enters simultaneously when to avoid concrete from being poured Guide pipe is blocked, need to be pushed against with end mould when guide pipe is installed and is secured firmly to it on mould of end;
Template installation: being bolted between set arch steel form, and smoother to ensure to be oriented to mould within the walls, guiding wall end head formwork is adopted It is installed with plank, connection uses dog or steel nail using adding back up mode to be reinforced between plank between plank sheathing and steel form It is connected firmly, checks that template size is smooth except elevation of top surface deviation, guiding wall marginal position deviation, template before installation template Degree, template surface faulting of slab ends deviation, template installation need solid and reliable, template and concrete surface brushing release agent;
Concrete casting: before concrete casting, need to again check template, guide pipe, and make calibration, the middle line of template, Horizontal and size meets design requirement, template installation and bracket secure rigid, and set arch is poured using concrete, concrete it is unified by Mixing station centralizedly supply, concrete fill vehicle transport, and hand fit's machinery be poured and makes firm by ramming closely knit, and casting sequence is from arch springing two sides Symmetrical casting, until vault;
Concrete demoulding and maintenance: after concrete is poured, need to be conserved in time, and curing age must not be less than 7 days, coagulation Native intensity reach design strength 70% after remove non-bearing template and Side Template, intensity reach design strength 100% after tear open Except internal model and bracket.
3. a kind of hole daguanpeng construction method according to claim 2, it is characterised in that: the step S6 pipe roof construction Include the following steps:
Borehole cleaning and down tube immediately after pore-forming, in order to avoid because the hole that collapses causes to can not be successfully installation due to blocking in hole, when down tube, need to set up foot Hand cradle platform is aided with digging machine ejection manually to push and pull based on jacking,
Pipe canopy steel splitting pipe and steel floral tube, when construction, first set steel floral tube and cementing slurries, play steel pipe, then to check the spray of molten steel The grouting quality of pipe,
Pipe canopy carries out cleaning bottom of hole, borehole cleaning, dross in cleaning hole with high-pressure blast device to hole is interior in a pre-installation, it is ensured that aperture, hole depth conform to It asks, prevents plug-hole, pipe canopy is installed using jacking, section by section spreading, and the joint steel pipe for spreading tube coupling is logical with hot rolled seamless steel tube It crosses outer thread button and interior thread button is attached, in order to improve the bending resistance of pipe canopy, steel reinforcement cage is added in pipe canopy, main reinforcement is adopted With overlap joint connection, side item connection.
4. a kind of hole daguanpeng construction method according to claim 3, it is characterised in that: the S8 grouting includes Following steps:
Pipe canopy and steel reinforcement cage carry out slip casting after being installed, injecting paste material uses cement slurry, ratio of mud 1:1, grouting sequence original It is carried out on then from low hole location to high hole location, complete opening uses disposable slip casting, fills steel pipe using cement mortar after slip casting;
Since pipe canopy spacing is smaller, cause adjacent steel floral tube hole stifled to avoid occurring when slip casting string hole when geological condition is poor Plug, hole-specifically slip casting, while slurries being allowed to be diffused filling in loose country rock, broken rock stratum is consolidated, is conducive to adjacent Chip off-falling is reduced in drilling in hole, avoids that bit freezing occurs or falls bore, fall pricker phenomenon, is conducive to accelerate construction progress;
Injected hole blocks mode: being coupled using steel plate in steel pipe opening and is blocked, reserve Grouting Pipe and exhaust pipe, Grouting Pipe installs valve Door, plug closing is tight, grouting mode: in the direct slip casting of Guan Pengkou.
CN201910601404.9A 2019-07-03 2019-07-03 A kind of hole daguanpeng construction method Pending CN110331992A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910601404.9A CN110331992A (en) 2019-07-03 2019-07-03 A kind of hole daguanpeng construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910601404.9A CN110331992A (en) 2019-07-03 2019-07-03 A kind of hole daguanpeng construction method

Publications (1)

Publication Number Publication Date
CN110331992A true CN110331992A (en) 2019-10-15

Family

ID=68144284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910601404.9A Pending CN110331992A (en) 2019-07-03 2019-07-03 A kind of hole daguanpeng construction method

Country Status (1)

Country Link
CN (1) CN110331992A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778337A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Fabricated steel segment template construction method suitable for rapid lining of circular tunnel
CN111140257A (en) * 2020-01-10 2020-05-12 中国水利水电第四工程局有限公司 Advanced support method and equipment
CN111827879A (en) * 2020-07-03 2020-10-27 北京中煤矿山工程有限公司 Horizontal drilling construction method for large-diameter pipe shed in shallow-earth-covered weak stratum
CN113107539A (en) * 2021-05-11 2021-07-13 青岛理工大学 Optimal thickness calculation method for pipe shed reinforcement area
CN113404517A (en) * 2021-08-03 2021-09-17 福建工程学院 Construction method for mud-bursting and water-flushing of tunnel
CN113700437A (en) * 2021-09-01 2021-11-26 中交第二航务工程局有限公司 Tube-following drilling device for soft rock tunnel tube shed and construction method
CN114635716A (en) * 2022-05-17 2022-06-17 中国建筑第六工程局有限公司 Pipe shed advanced supporting method with built-in section steel and application thereof
CN114658449A (en) * 2022-04-29 2022-06-24 中国一冶集团有限公司 Tunnel underground excavation pipe shed guide pipe drilling construction precision control method
CN114961748A (en) * 2022-06-23 2022-08-30 中铁九局集团第三建设有限公司 Construction method of large pipe shed guide wall at tunnel opening of shallow tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767379A (en) * 2012-08-10 2012-11-07 中国建筑第四工程局有限公司 Shallow-buried unsymmetrical pressure section tunnel drilling construction method
CN104074524A (en) * 2014-06-30 2014-10-01 中南大学 Construction method of shallow beneath highway large-cross-section tunnel
CN108150187A (en) * 2017-12-21 2018-06-12 中铁十八局集团有限公司 A kind of huge loose talus shield encircles the method into hole
CN109268030A (en) * 2018-12-04 2019-01-25 湖南省交通规划勘察设计院有限公司 A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767379A (en) * 2012-08-10 2012-11-07 中国建筑第四工程局有限公司 Shallow-buried unsymmetrical pressure section tunnel drilling construction method
CN104074524A (en) * 2014-06-30 2014-10-01 中南大学 Construction method of shallow beneath highway large-cross-section tunnel
CN108150187A (en) * 2017-12-21 2018-06-12 中铁十八局集团有限公司 A kind of huge loose talus shield encircles the method into hole
CN109268030A (en) * 2018-12-04 2019-01-25 湖南省交通规划勘察设计院有限公司 A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
漫步云霄岁月(用户名): "洞口超前大管棚施工方案", 《百度文库》 *
陈云鹤 等编著: "《公路应急交通保障》", 31 January 2013, 国防工业出版社 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778337B (en) * 2019-11-09 2020-12-25 黄河勘测规划设计研究院有限公司 Fabricated steel segment template construction method suitable for rapid lining of circular tunnel
CN110778337A (en) * 2019-11-09 2020-02-11 黄河勘测规划设计研究院有限公司 Fabricated steel segment template construction method suitable for rapid lining of circular tunnel
CN111140257A (en) * 2020-01-10 2020-05-12 中国水利水电第四工程局有限公司 Advanced support method and equipment
CN111827879A (en) * 2020-07-03 2020-10-27 北京中煤矿山工程有限公司 Horizontal drilling construction method for large-diameter pipe shed in shallow-earth-covered weak stratum
CN111827879B (en) * 2020-07-03 2022-04-08 北京中煤矿山工程有限公司 Horizontal drilling construction method for large-diameter pipe shed in shallow-earth-covered weak stratum
CN113107539B (en) * 2021-05-11 2022-07-26 青岛理工大学 Optimal thickness calculation method for pipe shed reinforcement area
CN113107539A (en) * 2021-05-11 2021-07-13 青岛理工大学 Optimal thickness calculation method for pipe shed reinforcement area
CN113404517A (en) * 2021-08-03 2021-09-17 福建工程学院 Construction method for mud-bursting and water-flushing of tunnel
CN113404517B (en) * 2021-08-03 2023-09-22 福建工程学院 Construction method for tunnel mud bursting and water flushing
CN113700437A (en) * 2021-09-01 2021-11-26 中交第二航务工程局有限公司 Tube-following drilling device for soft rock tunnel tube shed and construction method
CN113700437B (en) * 2021-09-01 2023-12-08 中交第二航务工程局有限公司 Soft rock tunnel pipe shed and pipe following drilling device and construction method
CN114658449A (en) * 2022-04-29 2022-06-24 中国一冶集团有限公司 Tunnel underground excavation pipe shed guide pipe drilling construction precision control method
CN114658449B (en) * 2022-04-29 2024-11-01 中国一冶集团有限公司 Control method for drilling construction precision of guide pipe of tunnel underground excavation pipe shed
CN114635716A (en) * 2022-05-17 2022-06-17 中国建筑第六工程局有限公司 Pipe shed advanced supporting method with built-in section steel and application thereof
WO2023174439A1 (en) * 2022-06-23 2023-09-21 中铁九局集团第三建设有限公司 Construction method for large pipe shed guide wall at shallow tunnel portal
CN114961748B (en) * 2022-06-23 2023-03-10 中铁九局集团第三建设有限公司 Construction method of large pipe shed guide wall at tunnel opening of shallow tunnel
CN114961748A (en) * 2022-06-23 2022-08-30 中铁九局集团第三建设有限公司 Construction method of large pipe shed guide wall at tunnel opening of shallow tunnel

Similar Documents

Publication Publication Date Title
CN110331992A (en) A kind of hole daguanpeng construction method
CN106545005B (en) A kind of reinforcing body and reinforcement means of subway tunnel shield end
CN101122131B (en) Foundation pit supporting pile using pipe casting pile embedding in rock
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
JP6342126B2 (en) Ground injection method
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN110671131A (en) Loess tunnel substrate reinforcing structure and method based on high-pressure jet grouting pile
CN108166483A (en) Bored pile construction method
CN109595004A (en) A kind of tunnel two expands four and digs method
CN104831705A (en) Ultra-deep hole grouting method during underground excavation of tunnel
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN105350988B (en) Tunnel Base reinforcement means
CN110284885A (en) Shield inspection-pit construction method
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110439011A (en) A kind of side slope antiskid supporting construction and its construction method
CN104790982A (en) Enclosed mud for underground excavation tunnel ultra-deep hole grouting
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN112855029B (en) Goaf drilling external pipe expansion construction method
CN108952765B (en) Construction method for advanced support of super-large pipe shed on water-rich sand layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191015

RJ01 Rejection of invention patent application after publication