CN110230497A - A kind of positive barrel double -side approach construction method in threaded list road - Google Patents

A kind of positive barrel double -side approach construction method in threaded list road Download PDF

Info

Publication number
CN110230497A
CN110230497A CN201910547662.3A CN201910547662A CN110230497A CN 110230497 A CN110230497 A CN 110230497A CN 201910547662 A CN201910547662 A CN 201910547662A CN 110230497 A CN110230497 A CN 110230497A
Authority
CN
China
Prior art keywords
pilot tunnel
tunnel
side wall
construction
wall pilot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910547662.3A
Other languages
Chinese (zh)
Inventor
张兵
赵海雷
陈桥
杨延栋
杨振兴
秦银平
高会中
任颖莹
周振建
韩伟锋
陈瑞祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Key Laboratory of Shield Machine and Boring Technology, China Railway Tunnel Group Co Ltd CRTG filed Critical State Key Laboratory of Shield Machine and Boring Technology
Priority to CN201910547662.3A priority Critical patent/CN110230497A/en
Publication of CN110230497A publication Critical patent/CN110230497A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of positive barrel double -side approach construction methods in threaded list road, method includes the following steps: Step 1: preparing before construction: carrying out advance geologic prediction, cleaning face, surveying setting-out, and carry out advance support slip casting, are monitored measurement;The Tunnel of institute's construction tunnel is divided into centrally located middle drift, and is symmetrically positioned in the left side wall pilot tunnel and right side wall pilot tunnel of the middle drift two sides;Step 2: preliminary excavate;Step 3: middle drift excavates;Step 4: applying inverted arch;Step 5: secondary lining.Construction portion of the present invention number is few, construction efficiency is high, saving of work and time, working security are high.

Description

A kind of positive barrel double -side approach construction method in threaded list road
Technical field
The present invention relates to technical field of tunnel construction, and in particular to a kind of positive barrel double -side approach construction party in threaded list road Method.
Background technique
Two side-wall pilot tunnel is a kind of mode of tunnel excavation, also known as twin side heading method or glasses working, belongs to new Austria One branch of method, using New Austrian Tunneling Method basic principle as foundation.It is used to open when carrying out tunnel excavation using two side-wall pilot tunnel Wa Mian branch, which is generally in the form of, is divided into four pieces, i.e. left side wall base tunnel (also referred to as left side wall pilot tunnel), right side for tunnel excavation section It wall base tunnel (also referred to as right side wall pilot tunnel), top Core Soil region base tunnel (also referred to as top Core Soil region pilot tunnel) and gets out of a predicament or an embarrassing situation It excavates base tunnel (also referred to as get out of a predicament or an embarrassing situation and excavate pilot tunnel).Field measurement shows that subsidence caused by two side-wall pilot tunnel is only The 1/2 of short benching tunnelling method.But two side-wall pilot tunnel excavation portion number is more, not only increases the disturbance number to country rock, is unfavorable for enclosing The stabilization of rock, and interfering with each other between each process is increased, the life security of worker is seriously threatened, and to a certain extent Affect the progress of construction, cause indirectly build up it is at high cost.
Summary of the invention
In view of this, applying in view of the deficiencies of the prior art, it is an object of the present invention to provide one kind, process is simple, efficiency The positive barrel double -side approach construction method in threaded list road high, security performance is high, stability is good.
In order to achieve the above objectives, the invention adopts the following technical scheme:
A kind of positive barrel double -side approach construction method in threaded list road, method includes the following steps:
Step 1: preparing before construction: carrying out advance geologic prediction, cleaning face, surveying setting-out, and carry out advance support note Slurry, is monitored measurement;
The Tunnel of institute's construction tunnel is divided into centrally located middle drift, and is symmetrically positioned in the middle drift two sides Left side wall pilot tunnel and right side wall pilot tunnel;
Step 2: preliminary excavate: the left side wall pilot tunnel and right side wall pilot tunnel are divided into upper side wall pilot tunnel and downside from top to bottom Wall pilot tunnel, digging process is successively are as follows: first excavates two sides upper side wall pilot tunnel, then applies two sides upper side wall pilot tunnel preliminary bracing;Again Two sides lower wall pilot tunnel is excavated, two sides lower wall pilot tunnel preliminary bracing is applied;
Step 3: middle drift excavates: in the left side wall pilot tunnel and right side wall pilot tunnel propulsion length are not less than starting after 10m Pilot drive;The middle drift is divided into top pilot tunnel, middle part pilot tunnel and lower part pilot tunnel from top to bottom;First in the top pilot tunnel Top driving, then applies pre-grouting advance support, then carries out arranged on left and right sides to top pilot tunnel and interlock in parallel tunneling construction;It Middle part pilot drive is carried out afterwards, and the middle part pilot tunnel lags behind top pilot tunnel 2.5-3.5m, installs I-steel stull later;Finally Lower part pilot drive is carried out, so that the lower part pilot tunnel is lagged behind middle part pilot tunnel 2.5-3.5m, applies lower part pilot tunnel initial stage branch later Shield is allowed to closing cyclization;
Step 4: applying inverted arch: inverted arch and lower part pilot drive work surface first carry out monitoring measurement, then adopt at a distance of from 8-15m It is segmented the preliminary bracing for removing two sides lower wall pilot tunnel bottom with flame-cutting, and pours concrete immediately and carries out Tunnel bottom Filling completes inverted arch and just serves as a contrast construction;
Step 5: secondary lining: removing the preliminary bracing to lining cutting section, utilize trolley one-piece casting secondary lining.
Feature in view of the above technology, left side wall pilot tunnel and right side wall pilot tunnel are divided into upper side wall pilot tunnel and downside from top to bottom Wall pilot tunnel reduces construction portion number, and rationally, construction cost is low for design;Length is promoted in the left side wall pilot tunnel and right side wall pilot tunnel After 10m, starts middle drift and excavate;Construction speed is effectively ensured;Arranged on left and right sides is carried out to top pilot tunnel staggeredly to dig in parallel Into construction, construction efficiency is high, and construction quality is good, and safety is reliable, small to the disturbance of country rock;Top pilot tunnel, middle part pilot tunnel and under 2.5-3.5m is mutually lagged between portion's pilot tunnel can effectively increase working security;Inverted arch and lower part pilot drive work surface are apart From 8-15m, keep entire constructing structure more firm.
Preferably, the preliminary bracing in step 2 and three is made of extension steel mesh, jetting cement and anchor pole, III, IV grade of country rock Increase grid steel frame strengthening supporting within the scope of 120 ° of arch;V grade of country rock location arch wall increases grid steel frame strengthening supporting;It is described Anchor pole includes grouting rock bolt and hollow bolt, and arch uses slip casting hollow bolt, remaining abutment wall uses grouting rock bolt.
Preferably, the form of construction work of the advance support in step 1 is divided into advanced middle pipe canopy and two kinds of advanced tubule Mode.
Preferably, the left side wall pilot tunnel and right side wall pilot tunnel apply mode using micro- benching tunnelling method, staggeredly carry out, adjacent to open Digging face is at a distance of 2-3m.The disturbance to construction surface is reduced, the stability and safety of work progress are increased.
Preferably, the form of construction work that the top pilot tunnel is staggeredly tunneled using two sides, and the spacing constructed is not more than 1m.It applies Work safety is good, and construction efficiency is high.
Preferably, the span of the Tunnel is 20-30m, at a distance of 5- between the left side wall pilot tunnel and right side wall pilot tunnel 7m。
Preferably, it is described it is preliminary excavation and middle drift excavate using circulation apply by the way of, every time it is described it is preliminary excavation with The drilling depth that middle drift excavates is not more than 0.75m;The distance for removing the advance support every time is less than 10m.Avoid a drilling depth too Greatly, construction tunnel receiving does not live, the low problem of stability, is conducive to the stability for increasing Tunnel, to ensure construction peace Quan Xing.
The beneficial effects of the present invention are:
For the present invention by the way that Tunnel is divided into left and right sides wall base tunnel, left and right sides wall base tunnel divides equally two layers of excavation, excavates number It reduces, reduces the disturbance in digging process to peripheral rock, to reduce the landing of peripheral rock, increase working security;It adopts Working security can also be increased with circulation form of construction work;Working efficiency is effectively improved simultaneously, is shortened the construction period.
Detailed description of the invention
Fig. 1 is construction schematic diagram of the invention;
Fig. 2 is pipe roof construction process flow chart in advanced;
Fig. 3 is the construction schematic diagram of grouting rock bolt.
In figure: 1 left side wall pilot tunnel, 2 right side wall pilot tunnels, 3 top pilot tunnels, 4 middle part pilot tunnels, 5 lower part pilot tunnels, 6 exhaust pipes, 7 Stop grouting plug, 8 anchor holes, 9 grouting rock bolts, 10 anchor pole leading trucks, 11 mortars, 12 Grouting Pipes.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and examples.
A kind of positive barrel double -side approach construction method in threaded list road, method includes the following steps:
Step 1: preparing before construction: carrying out advance geologic prediction, cleaning face, surveying setting-out, and carry out advance support note Slurry, is monitored measurement;
It when encountering soft stratum, meets underground water and easily softens and the slight large deformation of soft rockmass occurs, need to lead using small in advance Pipe grouting support mode, advance reinforcement country rock when such as loose or breaking surrounding rock (fault disruption zone location), take note dual slurry shape Formula rapidly solidified rock crusher section in advance.
The form of construction work of the advance support is divided into pipe canopy and advanced tubule two ways in advanced.Pipe canopy is equal in advanced Using set arch guide pipe positioning, the drilling of pipe canopy geological drilling rig, segmentation heads into Guan Peng, then uses grouting pump grouting and reinforcing;Slip casting Slip casting pipe diameter on pump is Ф 60 or Ф 50, and extrapolation angle is 3 °;Fig. 2 is shown in pipe roof construction process flow in advanced.
Advanced tubule uses diameter for φ 42, the hot rolled seamless steel tube of thick 3.5mm, long 3.5m/ root.Between ductule is circumferential The floor projection lap of splice away from 40cm, longitudinally adjacent two rows is not less than 150cm, and outer limb is 5~10 °;Before advanced tubule End processing is tapered, so as to inserting piling, and prevents slurries preshoot;The injected hole of φ 10mm, slip casting are bored in position among advanced tubule Hole is in quincuncial arrangement (preventing slip casting from dead angle occur), is not drilled within the scope of spacing 15mm, tail portion 1m with mortar leakage prevention, end weldering Diameter is the ring-shaped stirrup of 6mm, and cracking ends when to prevent setting advanced tubule influence Grouting Pipe connection.
Construction stage need to reinforce monitoring measurement, adjust excavation plan and supporting parameter according to monitoring data in time, to inhibit Excessive deformation, and guarantee safe construction.
The Tunnel of institute's construction tunnel is divided into centrally located middle drift, and is symmetrically positioned in the middle drift The left side wall pilot tunnel 1 and right side wall pilot tunnel 2 of two sides;
When designing excavated section structure size, the deformation values being likely to occur are considered as, to guarantee after there is large deformation, are reserved The space of secondary set arch supporting measure, guarantees the needs of headroom size in tunnel, carries out changeing steel arch after avoiding the occurrence of large deformation Frame jeopardizes construction safety.
Step 2: preliminary excavate: the left side wall pilot tunnel 1 and right side wall pilot tunnel 2 are divided into upper side wall pilot tunnel from top to bottom With lower wall pilot tunnel, the left side wall pilot tunnel 1 and right side wall pilot tunnel 2 apply mode using micro- benching tunnelling method, staggeredly carry out, adjacent to open Digging face is at a distance of 2-3m.Digging process is successively are as follows: first excavates two sides upper side wall pilot tunnel, then applies two sides upper side wall pilot tunnel initial stage branch Shield;Two sides lower wall pilot tunnel is excavated again, applies two sides lower wall pilot tunnel preliminary bracing;
Step 3: middle drift excavates: promoting length not less than after 10m in the left side wall pilot tunnel 1 and right side wall pilot tunnel 2, start Middle drift excavates;The middle drift is divided into top pilot tunnel 3, middle part pilot tunnel 4 and lower part pilot tunnel 5 from top to bottom;First on the top The top of pilot tunnel 3 is tunneled, the form of construction work that the top pilot tunnel 3 is staggeredly tunneled using two sides, and the spacing constructed is not more than 1m, Then it applies pre-grouting advance support, then arranged on left and right sides is carried out to top pilot tunnel 3 and is interlocked in parallel tunneling construction;In carrying out later Portion's pilot tunnel 4 excavates, and the middle part pilot tunnel 4 lags behind top pilot tunnel 32.5-3.5m, installs I-steel stull later;Finally carry out Lower part pilot tunnel 5 excavates, and so that the lower part pilot tunnel 5 is lagged behind middle part pilot tunnel 42.5-3.5m, applies lower part pilot tunnel 5 initial stage branch later Shield is allowed to closing cyclization;2.5-3.5m is successively lagged respectively between the top pilot tunnel 3, middle part pilot tunnel 4 and lower part pilot tunnel 5.
Step 4: applying inverted arch: inverted arch and lower part pilot tunnel 5 excavate work surface at a distance of from 8-15m, are divided using flame-cutting Section removes the preliminary bracing of two sides lower wall pilot tunnel bottom, and pours concrete immediately and be filled Tunnel bottom, completes inverted arch Just lining construction;
Step 5: secondary lining: removing the preliminary bracing to lining cutting section, utilize trolley one-piece casting secondary lining.Secondary lining To resist the development of later period deformation.
The preliminary bracing of construction stage is to determine supporting parameter according to the principle of " based on anti-, anti-to put combination ", after excavation It should close in time, and take strong supporting measure, to inhibit the occurrence and development of deformation.
Preliminary bracing is made of extension steel mesh, jetting cement and anchor pole, increases grid within the scope of III, IV grade of 120 ° of country rock arch Steelframe strengthening supporting;V grade of country rock location arch wall increases grid steel frame strengthening supporting;The anchor pole includes grouting rock bolt and hollow Anchor pole, arch use slip casting hollow bolt, remaining abutment wall uses grouting rock bolt.
Jetting cement supporting construction program are as follows: advance geologic prediction → excavation → just spray concrete 4cm → construction lofting → installation steel Frame and extension steel mesh → monitoring → apply system anchor bolt → injection to design thickness.
Anchor pole is divided into grouting rock bolt and hollow bolt, the operational procedure of grouting rock bolt are as follows: and it first carries out positioning and does preparation of construction, Using rock bolting jumbo or air rock drill drilling anchor hole 8, after being drilled anchor hole 8, landwaste in anchor hole 8 is blown off with high-pressure blast, and check anchor Then 8 depth of hole will be sent into anchor hole 8,8 bottom of anchor hole of going directly containing the anchor pole of anchor pole leading truck 10, and pay attention to rotating mortar anchor Bar 9 makes 9 tail end of grouting rock bolt expose outside anchor hole mouth 10cm, to be welded with steel mesh;In 9 tail end anchor hole of grouting rock bolt Stop grouting plug 7 is installed in oral area position, is later connect 9 tail end of grouting rock bolt with grouting rock bolt special slip casting pump 12 using Grouting Pipe 12, Arch, abutment wall use the slip casting of dual exhaust method, and by internal diameter 4~5mm of Φ, the flexible plastic exhaust pipe of 1~1.5mm of wall thickness is the same as anchor pole one It rises to be sent into and drill to bottom hole, and stay the excess length of 1m or so outside hole, Grouting Pipe 12 is then fixed on anchor orifice position, and Anchor hole mouth is blocked, after confirmation exhaust pipe is unimpeded, starts to inject mortar 11, when exhaust pipe 6 is not vented or overflows thin pulp Stop, and exhaust pipe 6 is extracted, backing plate tightening nuts are installed after mortar 11 reaches intensity.The construction schematic diagram of grouting rock bolt As shown in Figure 3.The ratio of mud of slurries used in slip casting 1:0.8-1.1 by weight, wherein the intensity of cement is not less than 42.5.
Hollow bolt construction drill is drilled using rock bolting jumbo or air rock drill, makes hole according to design requirement before drilling Position, drilling keep straight line and, bore diameter φ 42mm vertical with place position strata structure face, and drilling depth is greater than Soil Anchor Design Length 10cm.Hollow grouting anchor operational procedure are as follows: after being drilled hole, blow off landwaste in hole with high-pressure blast;By anchor head and anchor pole end Head combination, puts on gasket and nut;The combination body of rod is sent into hole, bottom hole of going directly;Stop grouting plug is penetrated into anchor pole end and aperture It makes even and is fastened with the body of rod;Ensure that slurries fill hole body when slip casting, grouting pressure reaches design or code requirement, overflows to exhaust pipe Stop slip casting when underflow out;After slurry intensity reaches 70%, upper arch backing plate is covered in anchor pole end, is then twisted by prescribed torque Tight nut.The ratio of mud of slurries used in slip casting 1:0.4~0.5 by weight, grouting pressure are 0.3~0.8MPa, cement slurry With mix with.
Grid steel frame presses design machine-shaping outside hole, and progress after just spray concrete is mounted in hole, is welded with anchor pole.Grid Longitudinally connected muscle is set between steelframe, is filled and led up between grid steel frame with spraying concrete, and grid steel frame arch springing is placed in firm foundations, when erection Cushion block is arranged when gap is excessive between grid steel frame and country rock in Vertical tunnel middle line, is filled out with spray concrete spray.
Jetting cement is completed in two times, i.e. just spray and multiple spray.Jetting cement is based on wet shot, and the larger location of water content is using tide spray Technique.Jetting material by hole outside concrete mixing station mix, concrete waggon transport.The jetting cement just sprayed is with a thickness of 4~5cm, early fastly Speed closing country rock bores quick-fried section and uses wheeled wet shot manipulator, and TBM tunnels the wet shot manipulator that section uses TBM to carry.It is sprayed on arch again It is carried out after frame, linked network, anchor pole procedures.Using wet spraying process, constructed by jet robot.
Jetting cement segmentation, fragment, layering carry out, and from bottom to top, concentrate from anhydrous, few location water Xiang Youshui, Duo Shui, more water It places conduit and water is discharged in place.When applying spray spray head with it is substantially vertical by spray plane, distance is maintained at 1.5~2.0m.Grid steel frame, steel When arch, gap between steelframe and scar jetting cement fills closely knit, and injection order gets on, get off symmetrical progress, first sprays steelframe The gap between country rock, rear to spray between steelframe, steelframe should be covered by jetting cement, and protective layer cannot be less than 4cm.It is first levelling before spray Helically slowly uniformly mobile by the recess of spray plane, then by spray head, every circle pressure front half-turn is made every effort to around loop diameter about 30cm The concrete layer face of ejection is smoothly smooth.Jet thickness control is in 6cm hereinafter, every segment length is no more than 6m.
The content of monitoring measurement include the inside and outside observation in hole, headroom horizontal convergence measure, vault it is opposite sink measurement, shallow embedding Section surface subsidence measures, deformation in surrounding rock measures, anchor axial force measures, pressure from surrounding rock measures, support lining stress measures, steel Frame internal force and the load born measure and country rock elastic wave velocity measures.
Secondary lining perform the time should be arranged in country rock and preliminary bracing deformation it is basicly stable, measure monitoring data show When transport ratio obviously slows down, but secondary lining should be applied as early as possible when the breaking surrounding rock for enbrittling or Shallow Section It does.All main hole secondary linings in tunnel all use integral hydraulic lining trolley to construct.Concrete uses the mixing station of automatic gauge Centralizedly supply, agitator truck transport, and concrete transfer pump is pumped into mould.The pre-buried of embedded backfill slip casting in time is paid attention in lining construction The built-in fitting of pvc pipe and other affiliated facilities.
The span of the Tunnel is 20-30m, at a distance of 5-7m between the left side wall pilot tunnel 1 and right side wall pilot tunnel 2.
The preliminary excavation and middle drift excavate in such a way that circulation applies, and the preliminary excavation and middle drift are opened every time The drilling depth of digging is not more than 0.75m;The distance for removing the advance support every time is less than 10m.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, this field is common Other modifications or equivalent replacement that technical staff makes technical solution of the present invention, without departing from technical solution of the present invention Spirit and scope, be intended to be within the scope of the claims of the invention.

Claims (7)

1. a kind of positive barrel double -side approach construction method in threaded list road, which is characterized in that method includes the following steps:
Step 1: preparing before construction: carrying out advance geologic prediction, cleaning face, surveying setting-out, and carry out advance support note Slurry, is monitored measurement;
The Tunnel of institute's construction tunnel is divided into centrally located middle drift, and is symmetrically positioned in the middle drift two sides Left side wall pilot tunnel and right side wall pilot tunnel;
Step 2: preliminary excavate: the left side wall pilot tunnel and right side wall pilot tunnel are divided into upper side wall pilot tunnel and downside from top to bottom Wall pilot tunnel, digging process is successively are as follows: first excavates two sides upper side wall pilot tunnel, then applies two sides upper side wall pilot tunnel preliminary bracing;Again Two sides lower wall pilot tunnel is excavated, two sides lower wall pilot tunnel preliminary bracing is applied;
Step 3: middle drift excavates: in the left side wall pilot tunnel and right side wall pilot tunnel propulsion length are not less than starting after 10m Pilot drive;The middle drift is divided into top pilot tunnel, middle part pilot tunnel and lower part pilot tunnel from top to bottom;First in the top pilot tunnel Top driving, then applies pre-grouting advance support, then carries out arranged on left and right sides to top pilot tunnel and interlock in parallel tunneling construction;It Middle part pilot drive is carried out afterwards, and the middle part pilot tunnel lags behind top pilot tunnel 2.5-3.5m, installs I-steel stull later;Finally Lower part pilot drive is carried out, so that the lower part pilot tunnel is lagged behind middle part pilot tunnel 2.5-3.5m, applies lower part pilot tunnel initial stage branch later Shield is allowed to closing cyclization;
Step 4: applying inverted arch: inverted arch and lower part pilot drive work surface first carry out monitoring measurement, then adopt at a distance of from 8-15m It is segmented the preliminary bracing for removing two sides lower wall pilot tunnel bottom with flame-cutting, and pours concrete immediately and carries out Tunnel bottom Filling completes inverted arch and just serves as a contrast construction;
Step 5: secondary lining: removing the preliminary bracing to lining cutting section, utilize trolley one-piece casting secondary lining.
2. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that step 2 and three In preliminary bracing be made of extension steel mesh, jetting cement and anchor pole, within the scope of III, IV grade of 120 ° of country rock arch increase grid steel frame Strengthening supporting;V grade of country rock location arch wall increases grid steel frame strengthening supporting;The anchor pole includes grouting rock bolt and hollow bolt, Arch uses slip casting hollow bolt, remaining abutment wall uses grouting rock bolt.
3. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that in step 1 The form of construction work of the advance support is divided into pipe canopy and advanced tubule two ways in advanced.
4. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that the left side wall Pilot tunnel and right side wall pilot tunnel apply mode using micro- benching tunnelling method, staggeredly carry out, adjacent excavation face is at a distance of 2-3m.
5. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that the upper guide The form of construction work that hole is staggeredly tunneled using two sides, and the spacing constructed is not more than 1m.
6. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that the Tunnel Span be 20-30m, at a distance of 5-7m between the left side wall pilot tunnel and right side wall pilot tunnel.
7. the positive barrel double -side approach construction method in threaded list road according to claim 1, which is characterized in that described tentatively to open It digs and middle drift excavates in such a way that circulation applies, the drilling depth that the preliminary excavation and middle drift excavate every time is not more than 0.75m;The distance for removing the advance support every time is less than 10m.
CN201910547662.3A 2019-06-24 2019-06-24 A kind of positive barrel double -side approach construction method in threaded list road Pending CN110230497A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910547662.3A CN110230497A (en) 2019-06-24 2019-06-24 A kind of positive barrel double -side approach construction method in threaded list road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910547662.3A CN110230497A (en) 2019-06-24 2019-06-24 A kind of positive barrel double -side approach construction method in threaded list road

Publications (1)

Publication Number Publication Date
CN110230497A true CN110230497A (en) 2019-09-13

Family

ID=67857269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910547662.3A Pending CN110230497A (en) 2019-06-24 2019-06-24 A kind of positive barrel double -side approach construction method in threaded list road

Country Status (1)

Country Link
CN (1) CN110230497A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302662A (en) * 2020-10-29 2021-02-02 中铁上海工程局集团有限公司 Construction method of artificial backfill shallow-buried tunnel passing through highway
CN112484589A (en) * 2020-11-02 2021-03-12 上海宝冶集团有限公司 Method for blasting tunnel under elevated buttress
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113417645A (en) * 2021-06-01 2021-09-21 上海宝冶集团有限公司 Large-section tunnel excavation method based on double-side-wall pit guiding method
CN113464147A (en) * 2021-07-22 2021-10-01 中铁五局集团成都工程有限责任公司 Construction method of soft rock large-span and variable-section tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858220A (en) * 2010-05-28 2010-10-13 深圳市建设(集团)有限公司 Tunnel double upper sidewall heading construction method
CN102071947A (en) * 2011-01-21 2011-05-25 中交四航局第一工程有限公司 Construction method for soft surrounding rock section of large-span tunnel portal
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN104929648A (en) * 2015-06-03 2015-09-23 西华大学 Method for constructing branch guide pits of tunnels
CN108708739A (en) * 2018-04-12 2018-10-26 中铁四局集团有限公司 Shallow-buried exposed construction method suitable for ultra-large section hard rock tunnel
CN109681210A (en) * 2018-12-04 2019-04-26 中铁二十四局集团有限公司 A kind of two side-wall pilot tunnel of section bored tunnel construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858220A (en) * 2010-05-28 2010-10-13 深圳市建设(集团)有限公司 Tunnel double upper sidewall heading construction method
CN102071947A (en) * 2011-01-21 2011-05-25 中交四航局第一工程有限公司 Construction method for soft surrounding rock section of large-span tunnel portal
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN104929648A (en) * 2015-06-03 2015-09-23 西华大学 Method for constructing branch guide pits of tunnels
CN108708739A (en) * 2018-04-12 2018-10-26 中铁四局集团有限公司 Shallow-buried exposed construction method suitable for ultra-large section hard rock tunnel
CN109681210A (en) * 2018-12-04 2019-04-26 中铁二十四局集团有限公司 A kind of two side-wall pilot tunnel of section bored tunnel construction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302662A (en) * 2020-10-29 2021-02-02 中铁上海工程局集团有限公司 Construction method of artificial backfill shallow-buried tunnel passing through highway
CN112302662B (en) * 2020-10-29 2022-10-14 中铁上海工程局集团有限公司 Construction method of artificial backfill shallow-buried tunnel passing through highway
CN112484589A (en) * 2020-11-02 2021-03-12 上海宝冶集团有限公司 Method for blasting tunnel under elevated buttress
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113417645A (en) * 2021-06-01 2021-09-21 上海宝冶集团有限公司 Large-section tunnel excavation method based on double-side-wall pit guiding method
CN113464147A (en) * 2021-07-22 2021-10-01 中铁五局集团成都工程有限责任公司 Construction method of soft rock large-span and variable-section tunnel

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN110230497A (en) A kind of positive barrel double -side approach construction method in threaded list road
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
CN101929340B (en) Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN113833480A (en) Shield initial tunneling and arrival construction method
CN110185457A (en) A kind of flat pilot tunnel body construction method of TBM
CN104612698A (en) Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
CN103527219A (en) Tunnel supporting structure used for large deformation stratum and construction method of tunnel supporting structure
CN110195604A (en) A kind of threaded list road main tunnel TBM driving section constructing method
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN102400694A (en) Method for reinforcing joint of shield tunnel and mine tunnel
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN106437760A (en) Large-section tunnel novel multi-layer lining structure
CN108561156A (en) Separate tunnel changes arch supporting construction and its construction method
CN113137235B (en) Construction method of high-ground-stress soft rock extrusion large-deformation tunnel
CN112922635B (en) Hydraulic tunnel excavation supporting structure and construction method
CN109578035A (en) Steel pipe draining lock foot stake and construction method
CN110439582A (en) Unfavorable geology method of disposal, TBM, which support to tunnel when happening suddenly unfavorable geology at boots, at TBM support boots passes through method
CN114562289A (en) Rapid treatment method for large-scale cavity collapse of soft broken surrounding rock tunnel vault
CN113107501A (en) Initial tunneling construction method for portal extension steel ring
CN209687506U (en) Wear river shallow buried covered excavation electric power tunnel constructing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190913