CN110185007A - A kind of two-way water gate structure applied in blast pit - Google Patents

A kind of two-way water gate structure applied in blast pit Download PDF

Info

Publication number
CN110185007A
CN110185007A CN201910609132.7A CN201910609132A CN110185007A CN 110185007 A CN110185007 A CN 110185007A CN 201910609132 A CN201910609132 A CN 201910609132A CN 110185007 A CN110185007 A CN 110185007A
Authority
CN
China
Prior art keywords
gate
blast pit
slot
bulkhead
gate slot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910609132.7A
Other languages
Chinese (zh)
Other versions
CN110185007B (en
Inventor
赵维炜
曹刚
宋立春
陈雷
熊守纯
赵放
高莹
邢传
翟奕菡
白崇宇
刘通
苗宗伟
薛超
李玥
吴泽莽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Water Conservancy And Hydropower Survey And Design Institute (formerly Known As Liaoning Water Conservancy And Hydropower Survey And Design Institute) LLC
Original Assignee
Liaoning Water Conservancy And Hydropower Survey And Design Institute (formerly Known As Liaoning Water Conservancy And Hydropower Survey And Design Institute) LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Water Conservancy And Hydropower Survey And Design Institute (formerly Known As Liaoning Water Conservancy And Hydropower Survey And Design Institute) LLC filed Critical Liaoning Water Conservancy And Hydropower Survey And Design Institute (formerly Known As Liaoning Water Conservancy And Hydropower Survey And Design Institute) LLC
Priority to CN201910609132.7A priority Critical patent/CN110185007B/en
Publication of CN110185007A publication Critical patent/CN110185007A/en
Application granted granted Critical
Publication of CN110185007B publication Critical patent/CN110185007B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Barrages (AREA)

Abstract

The present invention relates to gate structure technical fields, in particular a kind of two-way water gate structure applied in blast pit, including blast pit gate pedestal, main gate and bulkhead gate, the blast pit gate pedestal side is equipped with Huan's benevolence reservoir, the blast pit gate pedestal is equipped with trash rack gate slot at Huan's benevolence reservoir, trash rack door is equipped in the trash rack gate slot, the trash rack gate slot is equipped with 3'# blast pit far from the side of Huan's benevolence reservoir, the 3'# blast pit is equipped with bulkhead gate slot far from the side of trash rack gate slot, bulkhead gate is equipped in the bulkhead gate slot, the bulkhead gate slot is equipped with depressor area far from the side of 3'# blast pit, the depressor area is equipped with main gate slot far from the side of bulkhead gate slot, main gate is equipped in the main gate slot, the main gate slot far from depressor area one Side is equipped with 15'# branch hole, and overall effect is good, and stability and practicability are higher, has certain promotional value.

Description

A kind of two-way water gate structure applied in blast pit
Technical field
The present invention relates to gate structure technical field field, specially a kind of two-way water gate applied in blast pit Structure.
Background technique
Existing reservoir is normally at a certain position in basin, can only realize with the gate of upstream to reservoir filling, use downstream Gate to basin water delivery, gate can only unidirectionally fetch water, and the reservoir that this technology is related to is located at basin middle reaches location, can be by unique Gate water storage and water delivery, if using existing gate structure, due to gate two sides simultaneously by very big hydraulic pressure, starting gate The resistance being subject to is very big, it is therefore desirable to which a kind of two-way water gate structure applied in blast pit, which makes the above problem, to be changed It is kind.
Summary of the invention
The purpose of the present invention is to provide a kind of two-way water gate structures applied in blast pit, to solve above-mentioned back The problem of being proposed in scape technology.
To achieve the above object, the invention provides the following technical scheme:
A kind of two-way water gate structure applied in blast pit, including blast pit gate pedestal, main gate and maintenance Gate, the blast pit gate pedestal side are equipped with Huan's benevolence reservoir, and the blast pit gate pedestal is equipped at Huan's benevolence reservoir Trash rack gate slot, the trash rack gate slot is interior to be equipped with trash rack door, and the trash rack gate slot is equipped with far from the side of Huan's benevolence reservoir 3'# blast pit, the 3'# blast pit are equipped with bulkhead gate slot far from the side of trash rack gate slot, set in the bulkhead gate slot There is bulkhead gate, the bulkhead gate slot is equipped with depressor area far from the side of 3'# blast pit, and the depressor area is far from bulkhead gate The side of slot is equipped with main gate slot, is equipped with main gate in the main gate slot, the main gate slot is far from depressor area Side be equipped with 15'# branch hole, the trash rack gate slot, bulkhead gate slot and main gate slot are at blast pit gate pedestal It is equipped with the second stage of gate slot concrete layer, pre-buried DN steel pipe is equipped at the bulkhead gate slot and main gate slot two sides, it is described Trash rack door, main gate and bulkhead gate top are fixedly installed with hydraulic hoisting device, and 3'# blast pit top is set There is 3'# blast pit to backfill layer.
Preferably, the intake and exhaust well floor elevation of the 3'# blast pit is 277m, and the crest level of the 3'# blast pit is 322m, the sectional dimension of the 3'# blast pit are 13.6m × 18m.
Preferably, 15'# branch hole length is 2675.88m, and 15'# branch hole is connected with the main hole in the tunnel Huan Ji, described The comprehensive gradient in 15'# branch hole is 1.60%, and 15'# branch hole cavitation hole diameter is 6.0m.
Preferably, the 3'# blast pit be Huan collect Tunnel Engineering 3# intake and exhaust well, and the 3'# blast pit level in The preceding estrade of Huan's benevolence reservoir left bank.
Preferably, the trash rack door is having a size of 10m × 10m.
Preferably, the bulkhead gate is having a size of 6m × 6m, and the bulkhead gate using hydraulic hoisting device it is dynamic close it is quiet It opens.
Preferably, the main gate is having a size of 6m × 6m, and the main gate moves water using hydraulic hoisting device and opens It closes.
Preferably, the bulkhead gate uses synchronous open and close with main gate.
Compared with prior art, the beneficial effects of the present invention are:
1, in the present invention, by the main gate and bulkhead gate of setting, since existing reservoir is normally at a certain position in basin It sets, can only realize that with the gate of upstream, with the gate in downstream to basin water delivery, gate can only unidirectionally fetch water to reservoir filling, this The reservoir that technology is related to is located at basin middle reaches location, can be by unique gate water storage and water delivery, if using existing gate knot Structure, since gate two sides are simultaneously by very big hydraulic pressure, the resistance that starting gate is subject to is very big, the main gate of setting and maintenance Gate can be opened and closed simultaneously two sects by hydraulic hoisting device, due to the depressor area space water between two sects Seldom, so that main gate and bulkhead gate are all only sides by larger pressure, the setting pole of one of gate is compared in this way It is big to reduce that open or close gate be the resistance being subject to.
Detailed description of the invention
Fig. 1 is 3'# blast pit sectional structure chart of the present invention;
Fig. 2 is 3'# blast pit overlooking structure figure of the present invention;
Fig. 3 is Huan's benevolence reservoir of the present invention, 3'# blast pit and 15'# branch hole entirety overlooking structure figure.
In figure: Huan's 1- benevolence reservoir, 2- blast pit gate pedestal, 3- trash rack door, 4-3'# blast pit, 5- depressor area, 6- work Make gate, 7-15'# branch hole, 8- bulkhead gate, 9- hydraulic hoisting device, 10-3'# blast pit backfill layer, 11- trash rack gate slot, The pre-buried DN100 steel pipe of 12-, 13- bulkhead gate slot, 14- second phase gate slot concrete layer, 15- main gate slot.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments, is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-3 is please referred to, the present invention provides a kind of technical solution:
A kind of two-way water gate structure applied in blast pit, including blast pit gate pedestal 2, main gate 6 and inspection Gate 8 is repaired, 2 side of blast pit gate pedestal is equipped with Huan's benevolence reservoir 1, and blast pit gate pedestal 2 is equipped at Huan's benevolence reservoir 1 and blocks Dirty fence gate slot 11, trash rack gate slot 11 is interior to be equipped with trash rack door 3, and for trash rack door 3 having a size of 10m × 10m, trash rack gate slot 11 is remote Side from Huan's benevolence reservoir 1 is equipped with 3'# blast pit 4, and the intake and exhaust well floor elevation of 3'# blast pit 4 is 277m, 3'# blast pit 4 Crest level be 322m, the sectional dimension of 3'# blast pit 4 is 13.6m × 18m, 3'# blast pit 4 be Huan collect Tunnel Engineering 3# into Blast pit, and the preceding estrade of 4 level Yu Huanren reservoir left bank of 3'# blast pit, 3'# blast pit 4 far from trash rack gate slot 11 one Side is equipped with bulkhead gate slot 13, is equipped with bulkhead gate 8 in bulkhead gate slot 13, bulkhead gate slot 13 far from 3'# blast pit 4 one Side is equipped with depressor area 5, and depressor area 5 is equipped with main gate slot 15 far from the side of bulkhead gate slot 13, sets in main gate slot 15 There is main gate 6, main gate slot 15 is equipped with 15'# branch hole 7 far from the side of depressor area 5, and 7 length of 15'# branch hole is 2675.88m, 15'# branch hole 7 is connected with the main hole in the tunnel Huan Ji, and the comprehensive gradient in 15'# branch hole 7 is 1.60%, 15'# branch hole, 7 cavitation hole Diameter is 6.0m, and trash rack gate slot 11, bulkhead gate slot 13 and main gate slot 15 are equipped with two at blast pit gate pedestal 2 Qimen slot concrete layer 14, bulkhead gate slot 13 and main gate slot are equipped with pre-buried DN100 steel pipe 12, trash rack at 15 two sides Door 3, main gate 6 and 8 top of bulkhead gate are fixedly installed with hydraulic hoisting device 9, bulkhead gate 8 having a size of 6m × 6m, and bulkhead gate 8 using hydraulic hoisting device 9 it is dynamic close it is quiet open, main gate 6 is having a size of 6m × 6m, and main gate 6 uses Hydraulic hoisting device 9 moves water opening and closing, and bulkhead gate 8 uses synchronous open and close with main gate 6, and 4 top of 3'# blast pit is equipped with 3'# blast pit backfills layer 10.
Workflow of the present invention: 3'# blast pit 4 is the 3# intake and exhaust well that Huan collects Tunnel Engineering, and 3'# blast pit 4 first The preceding estrade of level Yu Huanren reservoir left bank, the intake and exhaust well floor elevation of 3'# blast pit 4 are 277m, the top of 3'# blast pit 4 Elevation is 322m, and the sectional dimension of 3'# blast pit 4 is 13.6m × 18m, and 7 length of 15'# branch hole is 2675.88m, 15'# branch Hole 7 is connected with the main hole in the tunnel Huan Ji, and it is 6.0m that the comprehensive gradient in 15'# branch hole 7, which is 1.60%, 15'# branch hole, 7 cavitation hole diameter, by setting The main gate 6 and bulkhead gate 8 set can only be realized since existing reservoir is normally at a certain position in basin with upstream Gate is to reservoir filling, and with the gate in downstream to basin water delivery, gate can only unidirectionally fetch water, and the reservoir that this technology is related to is located at stream Domain middle reaches location, can by unique gate water storage and water delivery, if using existing gate structure, due to gate two sides simultaneously by To very big hydraulic pressure, the resistance that starting gate is subject to is very big, and the main gate 6 and bulkhead gate 8 of setting can pass through hydraulic switch Equipment 9 opens and closes at two sects simultaneously, since the 5 space water of depressor area between two sects is seldom, so that main gate 6 All be only side by larger pressure with bulkhead gate 8, in this way compared to one of gate setting greatly reduce unlatching or Closed shutter is the resistance being subject to, and overall effect is good, and stability and practicability are higher, has certain promotional value.
Embodiment
3'# blast pit 4 bears 1 head of Huan's benevolence reservoir by bulkhead gate 8, and main gate 6 bears the Huan Ji in 15'# branch hole 7 Tunnel side head, in different water level conditions by the scheduling of gate, it can be achieved that autumn skin River Reservoir is to Feng Ming Reservoir Regulation, Huan Ren Reservoir 1 is to the water delivery of Feng Ming reservoir, autumn skin River Reservoir Xiang Huanren reservoir 1 moisturizing, three kinds of water delivery modes, autumn skin River Reservoir, Feng Ming reservoir With the specific reservoir feature of Huan's benevolence reservoir 1 such as following table 1-1, table 1-2 and table 1-3.
Northwest Liaoning water supply project water supply coverage is wide, water is big, and watering is Huan's benevolence reservoir 1 of Hunjiang Valley, works as Huan Renshui Library 1 encounters low flow year group, or will be unable to that Northwest Liaoning area user's water demand is completely secured, and is connected to engineering using autumn Huan at this time Autumn skin River Reservoir water resource is called in into Huan's benevolence reservoir 1, and then is supplied water to Northwest Liaoning area, connection engineering also can ensure that autumn Huan's water delivery Engineering shuts down the normal diversion under operating condition in the power station Huan Ren, it is contemplated that there may be pollution factors in autumn skin river, if there is water quality dirt Dye situation, the main gate 6 and bulkhead gate 8 of the connection engineering can also improve the ability of water resistant matter pollution risk.
Therefore, after Qiu Huan connection engineering is built up, autumn skin River Reservoir can be become to the alternate source of Northwest Liaoning water supply project, The water supply guaranteed extent of Northwest Liaoning water supply project is greatly improved, the Emergency water supply of two water supply projects of Northwest Liaoning and Dahuofang is improved Supportability makes full use of the water resource of autumn skin River Reservoir, and can improve the ability of water resistant matter pollution risk.
Table Huan's 1-1 benevolence characteristic water level of reservoir
Project Operating condition Water level (m)
1 Check flood level (P=0.01%) 311.94
2 Design flood level (P=0.1%) 309.84
3 Normal high water level (N.H.W.L.) 301.14
4 Level of dead water 265.00
Table 1-2 autumn skin River Reservoir characteristic level of water
Project Operating condition Water level (m)
1 Check flood level (P=0.01%) 320.23
2 Design flood level (P=0.1%) 318.99
3 Normal high water level (N.H.W.L.) 318.48
4 Level of dead water 281.48
Table 1-3 Feng Ming reservoir mark sheet
Project Operating condition Water level (m)
1 Check water level (P=0.2%) 240.74
2 Design water level (P=2%) 237.01
3 Normal high water level (N.H.W.L.) 236.00
4 Level of dead water 235.64
5 2% flood level 236.18
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, it is possible to understand that These embodiments can be carried out with a variety of variations, modification, replacement without departing from the principles and spirit of the present invention and become Type, the scope of the present invention is defined by the appended.

Claims (8)

1. a kind of two-way water gate structure applied in blast pit, including blast pit gate pedestal (2), main gate (6) And bulkhead gate (8), it is characterised in that: the blast pit gate pedestal (2) side is equipped with Huan's benevolence reservoir (1), the exhaust Well gate pedestal (2) is equipped with trash rack gate slot (11) at Huan's benevolence reservoir (1), is equipped in the trash rack gate slot (11) and blocks dirt Fence gate (3), the trash rack gate slot (11) are equipped with 3'# blast pit (4) far from the side of Huan's benevolence reservoir (1), the 3'# blast pit (4) side far from trash rack gate slot (11) is equipped with bulkhead gate slot (13), and maintenance lock is equipped in the bulkhead gate slot (13) Door (8), the bulkhead gate slot (13) are equipped with depressor area (5) far from the side of 3'# blast pit (4), and the depressor area (5) is separate The side of bulkhead gate slot (13) is equipped with main gate slot (15), is equipped with main gate (6) in the main gate slot (15), institute It states main gate slot (15) and is equipped with 15'# branch hole (7), the trash rack gate slot (11), maintenance lock far from the side of depressor area (5) Gate slot (13) and main gate slot (15) are equipped with the second stage of gate slot concrete layer (14), institute at blast pit gate pedestal (2) It states and is equipped with pre-buried DN100 steel pipe (12), the trash rack door at bulkhead gate slot (13) and main gate slot (15) two sides (3), main gate (6) and bulkhead gate (8) top are fixedly installed with hydraulic hoisting device (9), the 3'# blast pit (4) top is equipped with 3'# blast pit backfill layer (10).
2. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described The intake and exhaust well floor elevation of 3'# blast pit (4) is 277m, and the crest level of the 3'# blast pit (4) is 322m, the 3'# row The sectional dimension of gas well (4) is 13.6m × 18m.
3. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described 15'# branch hole (7) length is 2675.88m, and 15'# branch hole (7) is connected with the main hole in the tunnel Huan Ji, and 15'# branch hole (7) is comprehensive Closing the gradient is 1.60%, and 15'# branch hole (7) cavitation hole diameter is 6.0m.
4. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described 3'# blast pit (4) is Huan's collection Tunnel Engineering 3# intake and exhaust well, and before the 3'# blast pit (4) level Yu Huanren reservoir left bank Estrade.
5. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described Trash rack door (3) is having a size of 10m × 10m.
6. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described Bulkhead gate (8) is having a size of 6m × 6m, and the bulkhead gate (8) closes quiet open using hydraulic hoisting device (9) are dynamic.
7. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described Main gate (6) is having a size of 6m × 6m, and the main gate (6) moves water opening and closing using hydraulic hoisting device (9).
8. a kind of two-way water gate structure applied in blast pit according to claim 1, it is characterised in that: described Bulkhead gate (8) uses synchronous open and close with main gate (6).
CN201910609132.7A 2019-07-08 2019-07-08 Reservoir system Active CN110185007B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910609132.7A CN110185007B (en) 2019-07-08 2019-07-08 Reservoir system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910609132.7A CN110185007B (en) 2019-07-08 2019-07-08 Reservoir system

Publications (2)

Publication Number Publication Date
CN110185007A true CN110185007A (en) 2019-08-30
CN110185007B CN110185007B (en) 2024-07-12

Family

ID=67725171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910609132.7A Active CN110185007B (en) 2019-07-08 2019-07-08 Reservoir system

Country Status (1)

Country Link
CN (1) CN110185007B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663562A (en) * 2020-11-19 2021-04-16 见嘉环境科技(苏州)有限公司 Artificial riverbed for river ecological restoration

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4073147A (en) * 1975-09-18 1978-02-14 Takeshi Nomura Water gate control system
JP2002294672A (en) * 2001-03-30 2002-10-09 Tajima Machinery:Kk Automatic water level regulating gate for water channel
JP2002309562A (en) * 2001-04-13 2002-10-23 Mitsubishi Heavy Ind Ltd Watertight mechanism for stream bed of low-water-depth gate
US20030026660A1 (en) * 2001-08-01 2003-02-06 Chun-Ching Wu Automatically opened and closed water gate
CN2727240Y (en) * 2004-06-03 2005-09-21 上海市水利工程设计研究院 Suspension type bidirectional backwater gate
KR20140112726A (en) * 2013-03-14 2014-09-24 주식회사 대한산업기계 Water gate
CN105421313A (en) * 2015-12-28 2016-03-23 中国电建集团贵阳勘测设计研究院有限公司 Method and device for filling water and leveling pressure of ultrahigh water head gate
CN206873406U (en) * 2017-04-10 2018-01-12 吴江林 A kind of type shunting water conservancy gate easy to control
CN108330921A (en) * 2018-04-12 2018-07-27 中国电建集团贵阳勘测设计研究院有限公司 Drainage method and device for high-narrow large-hole inlet gate
CN109356128A (en) * 2018-12-10 2019-02-19 中国电建集团贵阳勘测设计研究院有限公司 Arrangement structure of single diversion tunnel hydroelectric engineering hoist
CN109667247A (en) * 2018-12-21 2019-04-23 中国电建集团贵阳勘测设计研究院有限公司 High dam emptying system
CN208792265U (en) * 2017-12-07 2019-04-26 周越 A kind of hydraulic engineering cylinder iron gate
CN210315430U (en) * 2019-07-08 2020-04-14 辽宁省水利水电勘测设计研究院有限责任公司(原名称为辽宁省水利水电勘测设计研究院) Use two-way water intaking gate structure in exhaust well

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4073147A (en) * 1975-09-18 1978-02-14 Takeshi Nomura Water gate control system
JP2002294672A (en) * 2001-03-30 2002-10-09 Tajima Machinery:Kk Automatic water level regulating gate for water channel
JP2002309562A (en) * 2001-04-13 2002-10-23 Mitsubishi Heavy Ind Ltd Watertight mechanism for stream bed of low-water-depth gate
US20030026660A1 (en) * 2001-08-01 2003-02-06 Chun-Ching Wu Automatically opened and closed water gate
CN2727240Y (en) * 2004-06-03 2005-09-21 上海市水利工程设计研究院 Suspension type bidirectional backwater gate
KR20140112726A (en) * 2013-03-14 2014-09-24 주식회사 대한산업기계 Water gate
CN105421313A (en) * 2015-12-28 2016-03-23 中国电建集团贵阳勘测设计研究院有限公司 Method and device for filling water and leveling pressure of ultrahigh water head gate
CN206873406U (en) * 2017-04-10 2018-01-12 吴江林 A kind of type shunting water conservancy gate easy to control
CN208792265U (en) * 2017-12-07 2019-04-26 周越 A kind of hydraulic engineering cylinder iron gate
CN108330921A (en) * 2018-04-12 2018-07-27 中国电建集团贵阳勘测设计研究院有限公司 Drainage method and device for high-narrow large-hole inlet gate
CN109356128A (en) * 2018-12-10 2019-02-19 中国电建集团贵阳勘测设计研究院有限公司 Arrangement structure of single diversion tunnel hydroelectric engineering hoist
CN109667247A (en) * 2018-12-21 2019-04-23 中国电建集团贵阳勘测设计研究院有限公司 High dam emptying system
CN210315430U (en) * 2019-07-08 2020-04-14 辽宁省水利水电勘测设计研究院有限责任公司(原名称为辽宁省水利水电勘测设计研究院) Use two-way water intaking gate structure in exhaust well

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
华东水利学院: "水电站 供农田水利工程专业用", vol. 1, 黄河水利出版社, pages: 106 - 107 *
程泽斌;王靖欧;: "清江隔河岩大坝泄洪闸门集控系统改造需求与解决方案", 水电站机电技术, vol. 1, no. 03, 15 March 2016 (2016-03-15), pages 106 - 107 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663562A (en) * 2020-11-19 2021-04-16 见嘉环境科技(苏州)有限公司 Artificial riverbed for river ecological restoration
CN112663562B (en) * 2020-11-19 2022-02-18 见嘉环境科技(苏州)有限公司 Artificial riverbed for river ecological restoration

Also Published As

Publication number Publication date
CN110185007B (en) 2024-07-12

Similar Documents

Publication Publication Date Title
CN210342154U (en) Anti-backflow emergency drainage device for underground building
CN104947780A (en) Inflow vertical shaft system connected into deep tunnel drainage system
CA3057187C (en) System for generating power using energy-storage water pipes of multiple high-rise buildings
CN105781613A (en) Local dynamic dry-type waste water pump house for large-scale shield tunnel
CN110185007A (en) A kind of two-way water gate structure applied in blast pit
CN205035779U (en) Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic
CN211473544U (en) Water area rescue simulation training facility
CN111353120A (en) Design method and design device of long-distance high-altitude water transmission line
CN209025188U (en) A kind of prefabricated pumping plant of wisdom
CN206245390U (en) A kind of culvert pipe water channeling type pumping plant
CN210315430U (en) Use two-way water intaking gate structure in exhaust well
CN106013013B (en) Tubular power station separate combination type factory building system
CN204781253U (en) Insert deep tunnel drainage system's inflow shaft system
CN206034619U (en) Bury formula sewage lifting device
CN205714280U (en) A kind of large shield tunnel local dynamic station dry type waste water pump house
CN212896116U (en) Water cushion pond overhauling, draining and refilling system
CN208688720U (en) A kind of pumping plant water lift pipeline water-filling pressure testing multifunction system
CN208933926U (en) A kind of sediment trapping bank structure for power plant building
CN210769127U (en) Pipeline energy storage hydroelectric power station
CN207776075U (en) The trapped well of transformer collection oil pit by through hole
CN109555089A (en) Oblique stand alone type flood discharging tunnel water inlet tower structure and its construction method
Shao et al. The Causes of Floods and Control Measures during the Rainstorm Period in Cities with Flat Terrain
CN209227602U (en) The shell connecting node of assembly concrete bilayer pipe gallery
CN209388827U (en) A kind of aerial transformer oil pit system of substation
CN208167942U (en) Rainfall pumping station with test run function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant