CN118691056B - Project management system for offshore wind power based on project implementation progress - Google Patents
Project management system for offshore wind power based on project implementation progress Download PDFInfo
- Publication number
- CN118691056B CN118691056B CN202411188236.2A CN202411188236A CN118691056B CN 118691056 B CN118691056 B CN 118691056B CN 202411188236 A CN202411188236 A CN 202411188236A CN 118691056 B CN118691056 B CN 118691056B
- Authority
- CN
- China
- Prior art keywords
- project
- data
- flow
- personnel
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007726 management method Methods 0.000 claims abstract description 76
- 238000013439 planning Methods 0.000 claims abstract description 45
- 238000000034 method Methods 0.000 claims description 47
- 238000012797 qualification Methods 0.000 claims description 41
- 238000011156 evaluation Methods 0.000 claims description 27
- 239000011159 matrix material Substances 0.000 claims description 18
- 238000012545 processing Methods 0.000 claims description 14
- 238000012544 monitoring process Methods 0.000 claims description 13
- 238000010276 construction Methods 0.000 claims description 8
- 230000008520 organization Effects 0.000 claims description 7
- 238000004891 communication Methods 0.000 claims description 3
- 238000013480 data collection Methods 0.000 claims description 3
- 238000010586 diagram Methods 0.000 description 5
- 238000013461 design Methods 0.000 description 3
- 238000012795 verification Methods 0.000 description 3
- 239000002699 waste material Substances 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011157 data evaluation Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012384 transportation and delivery Methods 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a project management system for offshore wind power based on project implementation progress, which relates to the field of project management and comprises a project management center, wherein a project data acquisition module, an offshore data acquisition module, a project resource management module, a project collaborative sharing module and a project early warning management module are arranged in the project management center; the project data acquisition module acquires project data information and project personnel data information; the marine data acquisition module acquires implementation project data and weather forecast data; the project resource management module sets project resource nodes and corresponding user authority data according to the project data information and the project personnel data information; the project cooperative sharing module sets corresponding project planning data according to implementation project data and weather forecast data; the project early warning management module analyzes according to project planning data and implementation project data to acquire project early warning information; the invention improves the safety of project management.
Description
Technical Field
The invention relates to the field of project management, in particular to a project management system for offshore wind power based on project implementation progress.
Background
Offshore wind power is a clean and renewable energy form, and has been rapidly developed and applied in recent years, and project implementation of offshore wind power generally involves multiple links, including early investigation, design, purchasing, construction, debugging, operation and the like, each of which needs to be carefully managed and controlled to ensure smooth progress and final successful delivery of the project;
However, because the field related to the offshore wind power project is wide, the number of parties needing coordination is large, and the requirements and benefits of the parties are different, the traditional project management mode cannot meet the management requirements of the modern offshore wind power project; in addition, in the offshore wind power project management process, supply and demand relations among a plurality of flow sequences cannot be effectively coordinated, so that resource waste is caused to a certain extent; therefore, how to improve the safety in the project management process and reduce the resource waste is a problem that we need to solve, and for this reason, a project management system based on project implementation progress for offshore wind power is now provided.
Disclosure of Invention
In order to solve the technical problems, the invention aims to provide a project management system for offshore wind power based on project implementation progress.
The aim of the invention can be achieved by the following technical scheme: the project management system based on project implementation progress of offshore wind power comprises a project management center, wherein a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project collaborative sharing module and a project early warning management module are in communication connection in the project management center;
the project data acquisition module is used for acquiring project data information and project personnel data information corresponding to the corresponding offshore wind power project;
the marine data acquisition module is used for acquiring implementation project data and weather forecast data corresponding to corresponding marine wind power projects;
The project resource management module is used for carrying out flow splitting on offshore wind power projects according to project data information, setting project resource nodes according to splitting results, mutually matching project personnel data information with corresponding project resource nodes, and setting corresponding user permission data according to matching results;
the project progress analysis module is used for splitting implementation project data according to project resource nodes and acquiring corresponding instant project progress data in corresponding project resource nodes according to splitting results;
The project collaborative sharing module is used for setting project planning data in corresponding project resource nodes according to the instant project progress data and the weather forecast data, sending the project planning data into corresponding project personnel accounts, and carrying out project collaborative sharing according to the user permission data;
The project early warning management module is used for carrying out comparison analysis on project planning data and implementation project data corresponding to corresponding moments, generating project early warning information according to comparison analysis results and carrying out coordination management according to the project early warning information.
Further, the process of collecting project data information and project personnel data information corresponding to the corresponding offshore wind power project by the project data collection module comprises the following steps:
the project data acquisition module is internally provided with a project acquisition unit and a personnel acquisition unit;
The project acquisition unit is used for acquiring project data information corresponding to a corresponding offshore wind power project, the project data information comprises project names, project addresses, project flow data and project qualification data, the project qualification data in the acquired project data information are subjected to verification processing, and if the project qualification data pass through the verification processing, access permission is set for the corresponding project data information;
The personnel acquisition unit is used for acquiring project personnel data information corresponding to the corresponding offshore wind power project, wherein the project personnel data comprises personnel organization structure information, personnel identity qualification information and personnel work responsibility information, and project personnel accounts are set according to the personnel organization structure information, the personnel identity qualification information and the personnel work responsibility information.
Further, the process of collecting implementation project data and weather forecast data corresponding to the corresponding offshore wind power project by the offshore data collection module comprises the following steps:
the marine data acquisition module is internally provided with a project monitoring unit and a weather prediction unit;
The project monitoring unit is internally provided with project monitoring equipment, and the project monitoring equipment is used for acquiring implementation project data corresponding to the implementation process of the offshore wind power project;
The weather forecast unit acquires a corresponding weather station according to the project address, associates the weather station with the acquired weather station, and acquires weather forecast data of the position of the project address according to the weather station.
Further, the process of setting the project resource nodes by the project resource management module comprises the following steps:
a resource management unit is arranged in the project resource management module;
The resource management unit is used for acquiring project flow data included in project data information, wherein the project flow data are construction flow data and resource management data in the implementation process of corresponding offshore wind power projects;
Extracting characteristics of the project flow data, acquiring project process flow characteristics, splitting the project flow data according to the project process flow characteristics, acquiring corresponding flow sequences, setting project resource nodes according to the flow sequences, matching the flow sequences corresponding to the project flow data, and setting project flow evaluation indexes corresponding to the project flow data in the flow sequences corresponding to the project resource nodes according to matching results.
Further, the process of setting the user permission data by the project resource management module comprises the following steps:
a right management unit is arranged in the project resource management module;
The authority management unit acquires a corresponding flow sequence and project personnel data information in each project resource node, performs matching analysis on personnel work responsibility information contained in the project personnel data information and the corresponding flow sequence in each project resource node, acquires personnel identity qualification information corresponding to the corresponding project resource node according to a matching analysis result, and sets user authority data according to the personnel identity qualification information;
Acquiring personnel identity qualification information contained in a corresponding project resource node, setting an identity queue square matrix with a corresponding size according to the quantity of the personnel identity qualification information, carrying out serialization processing on the personnel identity qualification information, and acquiring a byte sequence corresponding to the personnel identity qualification information; the obtained byte sequence is input into a corresponding identity queue square matrix according to row arrangement, and a permission queue square matrix is obtained;
And analyzing and processing the byte sequence corresponding to the personnel identity qualification information to obtain a corresponding sparse matrix, multiplying the obtained sparse matrix by the authority queue square matrix, and obtaining the user authority data of the corresponding project personnel account.
Further, the project progress analysis module is used for acquiring corresponding implementation project data, splitting the acquired implementation project data according to project process flow characteristics corresponding to corresponding project resource nodes, and sending the corresponding implementation project data into the corresponding project resource nodes according to splitting results; and marking implementation project data corresponding to the splitting result obtained by the project resource node as instant project progress data.
Further, the process of setting project planning data in the corresponding project resource node by the project collaborative sharing module according to the instant project progress data and the weather forecast data comprises the following steps:
The project cooperative sharing module is internally provided with a project cooperative unit and a flow cooperative unit;
The project cooperation unit acquires a flow sequence corresponding to each project resource node, analyzes and processes the flow sequence according to project process flow characteristics corresponding to the flow sequence, acquires an association relation among the project resource nodes, wherein the association relation comprises three types of a guidance relation, a reversibility relation and an independent relation, and performs cooperation management on the project resource nodes according to the difference of the association relation types;
The flow collaboration unit is used for acquiring instant project progress data, weather forecast data and other project resource nodes corresponding to the guidance relationship and the reversibility relationship corresponding to the project resource nodes; setting early warning meteorological data according to project resource nodes;
Comparing and analyzing the obtained weather forecast data with early warning weather data, and obtaining corresponding project weather planning time according to a comparison analysis result;
Presetting a project planning period, and acquiring instant project progress data corresponding to project resource nodes corresponding to a guidance relationship and a reversibility relationship corresponding to project resource nodes according to the project planning period, and respectively acquiring guidance project change data and reversibility project change data corresponding to the corresponding instant project progress data in the project planning period;
Analyzing and processing the acquired guidance project change data and reverse change data in combination with project weather planning time to generate project planning data corresponding to the project resource nodes;
And sending the obtained project planning data to a project personnel account corresponding to the project resource node, and obtaining project planning data in the project personnel account by the project personnel according to the user authority data to carry out project collaborative sharing.
Further, the project early warning management module is used for acquiring corresponding instant project progress data by each project resource node, extracting features of the acquired instant project progress data to acquire instant project evaluation data, carrying out matching analysis on project flow evaluation indexes corresponding to the project resource nodes by the acquired instant project evaluation data, and generating evaluation project early warning information if the project flow evaluation indexes do not meet the standards corresponding to the project flow evaluation indexes;
If the corresponding standard of the project flow evaluation index is met, comparing and analyzing the instant project progress data with the project planning data to obtain a progress deviation value, presetting a deviation value threshold value, and comparing and analyzing the obtained progress deviation value and the deviation value threshold value;
when the progress deviation value is larger than the deviation value threshold value, generating progress project early warning information, otherwise, normally; and carrying out coordination management according to the obtained project early warning information.
Compared with the prior art, the invention has the beneficial effects that:
1. Through setting project resource nodes, corresponding project personnel and corresponding project resource nodes are associated according to personnel work responsibility information corresponding to the project personnel, and corresponding identity queue square matrixes and sparse matrixes are set, so that user permission data corresponding to the project personnel are obtained, and through setting corresponding user permission data for corresponding project personnel accounts in the project resource nodes, the safety of project data information in the project management process is improved to a certain extent;
2. The real-time project progress data in the project resource nodes are analyzed and processed through the association relation among the project resource nodes, so that the synergy of each project resource node in the process of setting the project planning data is improved to a certain extent, and the resource waste is avoided; in addition, by acquiring the weather forecast data and acquiring the corresponding project weather planning time according to the weather forecast data, the corresponding project planning data is set in combination with the weather planning time, and the instantaneity in the project planning process is improved to a certain extent.
Drawings
FIG. 1 is a schematic diagram of a project management system for offshore wind power based on project implementation progress according to an embodiment of the application.
Detailed Description
As shown in FIG. 1, the project management system for the offshore wind power based on project implementation progress comprises a project management center, wherein a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project collaborative sharing module and a project early warning management module are in communication connection in the project management center;
The project data acquisition module is used for acquiring project data information and project personnel data information corresponding to the corresponding offshore wind power project and sending the acquired data information to the project resource management module, and the specific implementation process comprises the following steps:
the project data acquisition module is internally provided with a project acquisition unit and a personnel acquisition unit;
The project acquisition unit is used for acquiring project data information corresponding to offshore wind power projects, wherein a project entry window is arranged, the project entry window is used for corresponding workers to enter corresponding project data information, and the project data information comprises project names, project places, project design data, project flow data and project qualification data;
Analyzing and processing the acquired project data information, and verifying and checking project names, project places and project qualification data contained in the project data information, wherein the project qualification data comprises project company qualification information, design unit qualification information, construction qualification information and legal compliance qualification information;
analyzing and processing the acquired project qualification data, judging whether the acquired project data information accords with the building standard, if so, verifying the project data information, and setting corresponding admittance permission for the project data information;
The personnel acquisition unit is used for acquiring project personnel data information corresponding to a corresponding offshore wind power project, wherein the project personnel data comprises personnel organization structure information, personnel identity qualification information and personnel work responsibility information;
The personnel organization structure information comprises an organization structure diagram of an item and a post division diagram, wherein the organization structure diagram comprises management departments corresponding to enterprises corresponding to the item, and the post division diagram comprises main duty tasks and functional fields corresponding to different posts;
The personnel identity qualification information comprises identity data information and qualification identity information corresponding to project personnel, the identity data information comprises a name, an age, a sex, an identity card number and a real-name authentication mobile phone number, and the qualification identity information comprises a corresponding qualification certificate or application data and the like;
the staff work responsibility information comprises work data required to be carried out by staff of the corresponding project in the corresponding project flow.
The marine data acquisition module is used for acquiring implementation project data and weather forecast data corresponding to a corresponding marine wind power project, and sending the acquired data to the project progress analysis module, and the specific implementation process comprises the following steps:
the marine data acquisition module is internally provided with a project monitoring unit and a weather prediction unit;
The project monitoring unit is internally provided with project monitoring equipment, the project monitoring equipment is used for acquiring implementation project data corresponding to the implementation process of the offshore wind power project, and the implementation project data comprises construction equipment data, material update data and construction progress data;
The weather prediction unit is internally provided with weather monitoring equipment which is used for collecting real-time weather data in the project implementation process;
The weather forecast unit is associated with a weather station corresponding to the project address, and obtains weather forecast data of the position of the project address according to the weather station.
The project resource management module is used for carrying out flow splitting on offshore wind power projects according to project data information, setting project resource nodes according to splitting results, mutually matching project personnel data information with corresponding project resource nodes, and setting corresponding user permission data according to matching results, wherein the specific implementation process comprises the following steps:
A resource management unit and a permission management unit are arranged in the project resource management module;
The resource management unit is used for acquiring project flow data included in project data information, wherein the project flow data are construction flow data and resource management data in the implementation process of corresponding offshore wind power projects;
Extracting characteristics of project flow data, acquiring project process flow characteristics, splitting the project flow data according to the project process flow characteristics, acquiring corresponding flow sequences, setting project resource nodes according to the flow sequences, matching the resource management data with the flow sequences corresponding to the project flow data, and marking the resource management data as flow sequence data according to a matching result;
Acquiring flow sequence data and corresponding data evaluation results included in corresponding project resource nodes, generating a flow sequence data set, analyzing the acquired flow sequence data set, and generating project flow evaluation indexes corresponding to the corresponding project resource nodes according to the analysis processing results, wherein the project flow evaluation indexes comprise construction flow evaluation indexes and resource flow evaluation indexes;
The authority management unit acquires a corresponding flow sequence and project personnel data information in each project resource node, performs matching analysis on personnel work responsibility information contained in the project personnel data information and the corresponding flow sequence in each project resource node, acquires personnel identity qualification information corresponding to the corresponding project resource node according to a matching analysis result, and sets user authority data according to the personnel identity qualification information;
Acquiring personnel identity qualification information contained in corresponding project resource nodes, setting an identity queue square matrix with a corresponding size of N according to the number of the personnel identity qualification information, carrying out serialization processing on the personnel identity qualification information, and acquiring a byte sequence corresponding to the personnel identity qualification information, wherein the number of bits corresponding to the byte sequence is also N; inputting the obtained byte sequence into an identity queue square matrix with the size of N according to row arrangement, and obtaining a permission queue square matrix;
Analyzing and processing the byte sequence corresponding to the personnel identity qualification information to obtain a corresponding sparse matrix, multiplying the obtained sparse matrix by a permission queue square matrix, and obtaining user permission data corresponding to corresponding project personnel;
It should be further noted that, in the implementation process, the user permission data is data for corresponding project personnel to acquire corresponding data information in corresponding project resource nodes through the project personnel account numbers thereof for identity verification, so that the security in the project management process is improved to a certain extent.
The project progress analysis module is used for splitting implementation project data according to project resource nodes, and acquiring corresponding instant project progress data in corresponding project resource nodes according to splitting results, wherein the implementation process comprises the following steps:
The project progress analysis module is used for acquiring corresponding implementation project data, splitting the acquired implementation project data according to project process flow characteristics corresponding to corresponding project resource nodes, and sending the corresponding implementation project data into the corresponding project resource nodes according to splitting results; and marking implementation project data corresponding to the splitting result obtained by the project resource node as instant project progress data.
The project collaborative sharing module is used for setting project planning data in corresponding project resource nodes according to instant project progress data and weather forecast data, and sending the project planning data into corresponding user accounts according to user permission data to perform project collaborative sharing, and the concrete implementation process comprises the following steps:
The project cooperative sharing module is internally provided with a project cooperative unit and a flow cooperative unit;
The project cooperation unit acquires a flow sequence corresponding to each project resource node, analyzes and processes the flow sequence according to project process flow characteristics corresponding to the flow sequence, and acquires an association relation among the project resource nodes, wherein the association relation comprises three types of guidance relation, reversibility relation and independent relation;
the guiding relation is a relation that a flow sequence in other project resource nodes affects the project resource nodes;
The reversibility relation is a relation that a flow sequence in a corresponding project flow sequence affects other project resource results;
The independent relationship is that no influence relationship exists between two project resource nodes;
according to the different association relation types, carrying out collaborative management on each project resource node;
The flow collaboration unit is used for acquiring instant project progress data, weather forecast data and other project resource nodes corresponding to the guidance relationship and the reversibility relationship corresponding to the project resource nodes;
Setting early warning meteorological data according to project resource nodes, acquiring real-time meteorological data and historical implementation project data corresponding to the project resource nodes, acquiring corresponding meteorological threshold data according to corresponding results, and setting the acquired meteorological threshold data as early warning meteorological data;
Comparing and analyzing the obtained weather forecast data with early warning weather data, and obtaining corresponding project weather planning time according to a comparison analysis result;
Presetting a project planning period, and acquiring instant project progress data corresponding to project resource nodes corresponding to a guidance relationship and a reversibility relationship corresponding to project resource nodes according to the project planning period, and respectively acquiring guidance project change data and reversibility project change data corresponding to the corresponding instant project progress data in the project planning period;
Analyzing and processing the acquired guidance project change data and reverse change data in combination with project weather planning time to generate project planning data corresponding to the project resource nodes;
And sending the obtained project planning data to a project personnel account corresponding to the project resource node, and obtaining project planning data in the project personnel account by the project personnel according to the user authority data to carry out project collaborative sharing.
The project early warning management module is used for carrying out comparison analysis on project planning data and implementation project data corresponding to corresponding moments, generating project early warning information according to comparison analysis results, and carrying out coordination management according to the project early warning information, wherein the specific implementation process comprises the following steps:
The project early warning management module is used for acquiring corresponding instant project progress data by each project resource node, extracting features of the acquired instant project progress data to acquire instant project evaluation data, carrying out matching analysis on project flow evaluation indexes corresponding to the project resource nodes by the acquired instant project evaluation data, and generating evaluation project early warning information if the project flow evaluation indexes do not meet the standards corresponding to the project flow evaluation indexes;
If the corresponding standard of the project flow evaluation index is met, comparing and analyzing the instant project progress data with the project planning data to obtain a progress deviation value, presetting a deviation value threshold value, and comparing and analyzing the obtained progress deviation value and the deviation value threshold value;
when the progress deviation value is larger than the deviation value threshold value, generating progress project early warning information, otherwise, normally; and carrying out coordination management according to the obtained project early warning information.
The above embodiments are only for illustrating the technical method of the present invention and not for limiting the same, and it should be understood by those skilled in the art that the technical method of the present invention may be modified or substituted without departing from the spirit and scope of the technical method of the present invention.
Claims (3)
1. The project management system based on project implementation progress of offshore wind power comprises a project management center, and is characterized in that a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project cooperative sharing module and a project early warning management module are in communication connection in the project management center;
The project data acquisition module is used for acquiring project data information and project personnel data information corresponding to the corresponding offshore wind power project, wherein the project data information comprises project names, project addresses, project flow data and project qualification data, and the project personnel data comprises personnel organization structure information, personnel identity qualification information and personnel work responsibility information;
the marine data acquisition module is used for acquiring implementation project data and weather forecast data corresponding to corresponding marine wind power projects;
The project resource management module is used for carrying out flow splitting on offshore wind power projects according to project data information, setting project resource nodes according to splitting results, mutually matching project personnel data information with corresponding project resource nodes, and setting corresponding user permission data according to matching results;
the project progress analysis module is used for splitting implementation project data according to project resource nodes and acquiring corresponding instant project progress data in corresponding project resource nodes according to splitting results;
the process of setting the project resource nodes by the project resource management module comprises the following steps:
a resource management unit is arranged in the project resource management module;
The resource management unit is used for acquiring project flow data included in project data information, wherein the project flow data are construction flow data and resource management data in the implementation process of corresponding offshore wind power projects;
extracting characteristics of the project flow data, acquiring project process flow characteristics, splitting the project flow data according to the project process flow characteristics, acquiring corresponding flow sequences, setting project resource nodes according to the flow sequences, matching the flow sequences corresponding to the project flow data, and setting project flow evaluation indexes corresponding to the project flow data in the flow sequences corresponding to the project resource nodes according to matching results;
The process of setting the user authority data by the project resource management module comprises the following steps:
a right management unit is arranged in the project resource management module;
The authority management unit acquires a corresponding flow sequence and project personnel data information in each project resource node, performs matching analysis on personnel work responsibility information contained in the project personnel data information and the corresponding flow sequence in each project resource node, acquires personnel identity qualification information corresponding to the corresponding project resource node according to a matching analysis result, and sets user authority data according to the personnel identity qualification information;
Acquiring personnel identity qualification information contained in a corresponding project resource node, setting an identity queue square matrix with a corresponding size according to the quantity of the personnel identity qualification information, carrying out serialization processing on the personnel identity qualification information, and acquiring a byte sequence corresponding to the personnel identity qualification information; the obtained byte sequence is input into a corresponding identity queue square matrix according to row arrangement, and a permission queue square matrix is obtained;
analyzing and processing the byte sequence corresponding to the personnel identity qualification information to obtain a corresponding sparse matrix, multiplying the obtained sparse matrix by a permission queue square matrix, and obtaining user permission data of the personnel account of the corresponding project;
The project collaborative sharing module is used for setting project planning data in corresponding project resource nodes according to the instant project progress data and the weather forecast data, sending the project planning data into corresponding project personnel accounts, and carrying out project collaborative sharing according to the user permission data;
the project early warning management module is used for carrying out comparison analysis on project planning data and implementation project data corresponding to corresponding moments, generating project early warning information according to comparison analysis results and carrying out coordination management according to the project early warning information;
The project collaborative sharing module sets project planning data in the corresponding project resource nodes according to the instant project progress data and the weather forecast data, and the process comprises the following steps:
The project cooperative sharing module is internally provided with a project cooperative unit and a flow cooperative unit;
The project cooperation unit acquires a flow sequence corresponding to each project resource node, analyzes and processes the flow sequence according to project process flow characteristics corresponding to the flow sequence, and acquires an association relation among the project resource nodes, wherein the association relation comprises three types of guidance relation, reversibility relation and independent relation;
the guiding relation is a relation that a flow sequence in other project resource nodes affects the project resource nodes;
The reversibility relation is a relation that a flow sequence in a corresponding project flow sequence affects other project resource results;
The independent relationship is that no influence relationship exists between two project resource nodes;
according to the different association relation types, carrying out collaborative management on each project resource node;
The flow collaboration unit is used for acquiring instant project progress data, weather forecast data and other project resource nodes corresponding to the guidance relationship and the reversibility relationship corresponding to the project resource nodes; setting early warning meteorological data according to project resource nodes;
Comparing and analyzing the obtained weather forecast data with early warning weather data, and obtaining corresponding project weather planning time according to a comparison analysis result;
Presetting a project planning period, and acquiring instant project progress data corresponding to project resource nodes corresponding to a guidance relationship and a reversibility relationship corresponding to project resource nodes according to the project planning period, and respectively acquiring guidance project change data and reversibility project change data corresponding to the corresponding instant project progress data in the project planning period;
Analyzing and processing the acquired guidance project change data and reverse change data in combination with project weather planning time to generate project planning data corresponding to the project resource nodes;
The obtained project planning data are sent to corresponding project personnel accounts in project resource nodes, and project personnel acquire project planning data in project personnel accounts according to user authority data to carry out project collaborative sharing;
The project early warning management module is used for acquiring corresponding instant project progress data by each project resource node, extracting features of the acquired instant project progress data to acquire instant project evaluation data, carrying out matching analysis on project flow evaluation indexes corresponding to the project resource nodes by the acquired instant project evaluation data, and generating evaluation project early warning information if the project flow evaluation indexes do not meet the standards corresponding to the project flow evaluation indexes;
If the corresponding standard of the project flow evaluation index is met, comparing and analyzing the instant project progress data with the project planning data to obtain a progress deviation value, presetting a deviation value threshold value, and comparing and analyzing the obtained progress deviation value and the deviation value threshold value;
when the progress deviation value is larger than the deviation value threshold value, generating progress project early warning information, otherwise, normally; and carrying out coordination management according to the obtained project early warning information.
2. The project management system based on project implementation progress according to claim 1, wherein the process of collecting implementation project data and weather forecast data corresponding to a corresponding offshore wind project by the offshore data collection module comprises:
the marine data acquisition module is internally provided with a project monitoring unit and a weather prediction unit;
The project monitoring unit is internally provided with project monitoring equipment, and the project monitoring equipment is used for acquiring implementation project data corresponding to the implementation process of the offshore wind power project;
The weather forecast unit acquires a corresponding weather station according to the project address, associates the weather station with the acquired weather station, and acquires weather forecast data of the position of the project address according to the weather station.
3. The project management system based on project implementation progress according to claim 2, wherein the project progress analysis module is configured to obtain corresponding implementation project data, split the obtained implementation project data according to project process flow characteristics corresponding to corresponding project resource nodes, and send the corresponding implementation project data to the corresponding project resource nodes according to the split result; and marking implementation project data corresponding to the splitting result obtained by the project resource node as instant project progress data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202411188236.2A CN118691056B (en) | 2024-08-28 | 2024-08-28 | Project management system for offshore wind power based on project implementation progress |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202411188236.2A CN118691056B (en) | 2024-08-28 | 2024-08-28 | Project management system for offshore wind power based on project implementation progress |
Publications (2)
Publication Number | Publication Date |
---|---|
CN118691056A CN118691056A (en) | 2024-09-24 |
CN118691056B true CN118691056B (en) | 2024-11-05 |
Family
ID=92775828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202411188236.2A Active CN118691056B (en) | 2024-08-28 | 2024-08-28 | Project management system for offshore wind power based on project implementation progress |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN118691056B (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111126734A (en) * | 2018-10-31 | 2020-05-08 | 中国能源建设集团广东省电力设计研究院有限公司 | Offshore wind farm dispatching management system |
CN113112233A (en) * | 2021-04-16 | 2021-07-13 | 西安热工研究院有限公司 | BIM-based intelligent management method and platform for full life cycle of wind power project |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8738414B1 (en) * | 2010-12-31 | 2014-05-27 | Ajay R. Nagar | Method and system for handling program, project and asset scheduling management |
CN113177749A (en) * | 2021-06-29 | 2021-07-27 | 武汉华信数据系统有限公司 | Resource management method and device |
-
2024
- 2024-08-28 CN CN202411188236.2A patent/CN118691056B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111126734A (en) * | 2018-10-31 | 2020-05-08 | 中国能源建设集团广东省电力设计研究院有限公司 | Offshore wind farm dispatching management system |
CN113112233A (en) * | 2021-04-16 | 2021-07-13 | 西安热工研究院有限公司 | BIM-based intelligent management method and platform for full life cycle of wind power project |
Also Published As
Publication number | Publication date |
---|---|
CN118691056A (en) | 2024-09-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110852601B (en) | Big data application method and system for environmental monitoring law enforcement decision | |
CN110401692B (en) | Integrated automatic checking and accepting system and method for monitoring information of transformer substation | |
CN110647567B (en) | Power failure plan auxiliary decision system based on end data fusion | |
CN106940903A (en) | Work attendance method, device and system | |
CN104463439A (en) | Highway engineering project managing system and method | |
CN115619134B (en) | Engineering service-based mechanic platform construction method and system | |
CN107798489A (en) | A kind of electric network operation site safety management method based on wechat platform | |
CN106447156A (en) | Attendance management method and system | |
CN104463297A (en) | Asset two-dimensional code identification application method and device structure | |
CN111488999A (en) | Be applied to wind-powered electricity generation field safety production information-based management system | |
CN104732345A (en) | Supervision and management information system used for field management in power transmission and transformation engineering | |
CN105225071A (en) | Based on the power communication identity management method of Quick Response Code | |
CN102142108A (en) | Information processing method of corresponding relationship among materials and equipment suitable for power system | |
CN105447631A (en) | Subway engineering tri-network intelligent control system and method thereof | |
CN107423826A (en) | A kind of method for inspecting of multi-reservoir, device and system | |
CN103136634A (en) | Region certified property intelligent task management system | |
CN118691056B (en) | Project management system for offshore wind power based on project implementation progress | |
CN109360291A (en) | A kind of construction machinery equipment inspection service system | |
CN104318739B (en) | Electric power safety, quality In-site supervision main website-wireless data terminal management system | |
CN102360485A (en) | Software method and system for incremental risk evaluation | |
CN105976092A (en) | Method of generating power distribution room patrol project based on power distribution equipment structure and system thereof | |
CN115314288B (en) | Data tracing system and method based on encryption verification technology | |
CN111221802A (en) | Digital asset risk management and control system and method based on big data | |
CN112085412B (en) | Resource optimization distribution system and distribution method | |
CN112785276B (en) | Engineering consultation management system and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant |