CN118691056B - A project management system for offshore wind power based on project implementation progress - Google Patents

A project management system for offshore wind power based on project implementation progress Download PDF

Info

Publication number
CN118691056B
CN118691056B CN202411188236.2A CN202411188236A CN118691056B CN 118691056 B CN118691056 B CN 118691056B CN 202411188236 A CN202411188236 A CN 202411188236A CN 118691056 B CN118691056 B CN 118691056B
Authority
CN
China
Prior art keywords
project
data
personnel
information
flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202411188236.2A
Other languages
Chinese (zh)
Other versions
CN118691056A (en
Inventor
赵龙
杨三元
王其标
李甜
陈春
刘超
朱亚洲
陈珂
徐金牛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Haifeng Wind Power Development Co ltd
Original Assignee
Cccc Haifeng Wind Power Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Haifeng Wind Power Development Co ltd filed Critical Cccc Haifeng Wind Power Development Co ltd
Priority to CN202411188236.2A priority Critical patent/CN118691056B/en
Publication of CN118691056A publication Critical patent/CN118691056A/en
Application granted granted Critical
Publication of CN118691056B publication Critical patent/CN118691056B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/101Collaborative creation, e.g. joint development of products or services
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Health & Medical Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project management system for offshore wind power based on project implementation progress, which relates to the field of project management and comprises a project management center, wherein a project data acquisition module, an offshore data acquisition module, a project resource management module, a project collaborative sharing module and a project early warning management module are arranged in the project management center; the project data acquisition module acquires project data information and project personnel data information; the marine data acquisition module acquires implementation project data and weather forecast data; the project resource management module sets project resource nodes and corresponding user authority data according to the project data information and the project personnel data information; the project cooperative sharing module sets corresponding project planning data according to implementation project data and weather forecast data; the project early warning management module analyzes according to project planning data and implementation project data to acquire project early warning information; the invention improves the safety of project management.

Description

一种海上风电基于项目实施进度的项目管理系统A project management system for offshore wind power based on project implementation progress

技术领域Technical Field

本发明涉及项目管理领域,具体是一种海上风电基于项目实施进度的项目管理系统。The present invention relates to the field of project management, and in particular to an offshore wind power project management system based on project implementation progress.

背景技术Background Art

海上风电作为一种清洁、可再生的能源形式,在近年来得到了快速的发展和应用,海上风电的项目实施通常涉及多个环节,包括前期调查、设计、采购、建造、调试和运营等,每个环节都需要进行精细的管理和控制,以确保项目的顺利进行和最终的成功交付;As a clean and renewable energy form, offshore wind power has been rapidly developed and applied in recent years. The implementation of offshore wind power projects usually involves multiple links, including preliminary investigation, design, procurement, construction, commissioning and operation. Each link requires meticulous management and control to ensure the smooth progress of the project and the ultimate successful delivery.

然而,由于海上风电项目涉及的领域广泛,需要协调的各方众多,且各方的需求和利益不同,因此传统的项目管理方式已经无法满足现代海上风电项目的管理需求;对于海上风电项目管理过程中,无法确保对应项目数据信息的安全性,此外,海上风电项目管理过程中,无法有效协调多个流程序列之间的供需关系,从而导致了一定程度上的资源浪费;因此,如何提高项目管理过程中的安全性,并降低资源浪费是我们需要解决的问题,为此,现提供一种海上风电基于项目实施进度的项目管理系统。However, since offshore wind power projects involve a wide range of fields, there are many parties that need to be coordinated, and the needs and interests of each party are different, the traditional project management method can no longer meet the management needs of modern offshore wind power projects; in the process of offshore wind power project management, the security of the corresponding project data information cannot be ensured. In addition, in the process of offshore wind power project management, the supply and demand relationship between multiple process sequences cannot be effectively coordinated, which leads to a certain degree of resource waste; therefore, how to improve the safety of the project management process and reduce resource waste is a problem we need to solve. To this end, a project management system for offshore wind power based on project implementation progress is provided.

发明内容Summary of the invention

为了解决上述技术问题,本发明的目的在于提供一种海上风电基于项目实施进度的项目管理系统。In order to solve the above technical problems, an object of the present invention is to provide an offshore wind power project management system based on project implementation progress.

本发明的目的可以通过以下技术方案实现:一种海上风电基于项目实施进度的项目管理系统,包括项目管理中心,所述项目管理中心内通信连接有项目数据采集模块、海上数据采集模块、项目资源管理模块、项目进度分析模块、项目协同共享模块以及项目预警管理模块;The object of the present invention can be achieved by the following technical solutions: an offshore wind power project management system based on project implementation progress, comprising a project management center, wherein the project management center is communicatively connected with a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project collaborative sharing module and a project early warning management module;

所述项目数据采集模块用于采集相应海上风电项目所对应的项目数据信息和项目人员数据信息;The project data collection module is used to collect project data information and project personnel data information corresponding to the corresponding offshore wind power project;

所述海上数据采集模块用于采集相应海上风电项目所对应的实施项目数据和气象预测数据;The offshore data acquisition module is used to collect implementation project data and meteorological forecast data corresponding to the corresponding offshore wind power project;

所述项目资源管理模块用于根据项目数据信息对海上风电项目进行流程拆分,根据拆分结果设置项目资源节点,将项目人员数据信息与相应的项目资源节点相互匹配,根据匹配结果设置对应用户权限数据;The project resource management module is used to split the process of the offshore wind power project according to the project data information, set the project resource nodes according to the splitting results, match the project personnel data information with the corresponding project resource nodes, and set the corresponding user authority data according to the matching results;

所述项目进度分析模块用于根据项目资源节点对实施项目数据进行拆分,根据拆分结果获取相应项目资源节点内所对应的即时项目进度数据;The project progress analysis module is used to split the implementation project data according to the project resource nodes, and obtain the corresponding real-time project progress data in the corresponding project resource nodes according to the split results;

所述项目协同共享模块用于根据即时项目进度数据和气象预测数据设置对应项目资源节点内的项目规划数据,发送至相应的项目人员账号内,根据用户权限数据进行项目协同共享;The project collaborative sharing module is used to set the project planning data in the corresponding project resource node according to the real-time project progress data and weather forecast data, send it to the corresponding project personnel account, and perform project collaborative sharing according to the user authority data;

所述项目预警管理模块用于根据相应时刻所对应的项目规划数据与实施项目数据进行对比分析,根据对比分析结果生成项目预警信息,根据项目预警信息进行协调管理。The project early warning management module is used to compare and analyze the project planning data and the implementation project data corresponding to the corresponding time, generate project early warning information according to the comparison and analysis results, and perform coordination management according to the project early warning information.

进一步的,所述项目数据采集模块采集相应海上风电项目所对应的项目数据信息和项目人员数据信息的过程包括:Furthermore, the process of the project data collection module collecting project data information and project personnel data information corresponding to the corresponding offshore wind power project includes:

所述项目数据采集模块内设置有项目采集单元和人员采集单元;The project data collection module is provided with a project collection unit and a personnel collection unit;

所述项目采集单元用于采集相应海上风电项目所对应的项目数据信息,所述项目数据信息内包括项目名称、项目地址、项目流程数据和项目资质数据,对所获得的项目数据信息内的项目资质数据进行验证处理,若通过,则对相应的项目数据信息设置准入权限;The project collection unit is used to collect project data information corresponding to the corresponding offshore wind power project, wherein the project data information includes project name, project address, project process data and project qualification data, and to verify the project qualification data in the obtained project data information. If the verification is successful, access rights are set for the corresponding project data information;

所述人员采集单元用于采集相应海上风电项目所对应的项目人员数据信息,所述项目人员数据包括人员组织结构信息、人员身份资质信息和人员工作职责信息,根据其设置项目人员账户。The personnel collection unit is used to collect project personnel data information corresponding to the corresponding offshore wind power project. The project personnel data includes personnel organizational structure information, personnel identity qualification information and personnel job responsibility information, and project personnel accounts are set up based on them.

进一步的,所述海上数据采集模块采集相应海上风电项目所对应的实施项目数据和气象预测数据的过程包括:Furthermore, the process of the offshore data collection module collecting the implementation project data and meteorological forecast data corresponding to the corresponding offshore wind power project includes:

所述海上数据采集模块内设置有项目监测单元和气象预测单元;The marine data acquisition module is provided with a project monitoring unit and a weather forecasting unit;

所述项目监测单元内设置有项目监测设备,所述项目监测设备用于获取对应海上风电项目实施过程中所对应的实施项目数据;The project monitoring unit is provided with a project monitoring device, and the project monitoring device is used to obtain the corresponding implementation project data during the implementation of the corresponding offshore wind power project;

所述气象预测单元根据项目地址获取对应的气象站,并与所获得的气象站相关联,根据所述气象站获取项目地址所在位置的气象预测数据。The weather forecast unit obtains the corresponding weather station according to the project address, associates with the obtained weather station, and obtains weather forecast data of the location of the project address according to the weather station.

进一步的,所述项目资源管理模块设置项目资源节点的过程包括:Furthermore, the process of the project resource management module setting the project resource node includes:

所述项目资源管理模块内设置有资源管理单元;The project resource management module is provided with a resource management unit;

所述资源管理单元用于获取项目数据信息内所包括的项目流程数据,所述项目流程数据为对应海上风电项目实施过程中的施工流程数据和资源管理数据;The resource management unit is used to obtain project process data included in the project data information, wherein the project process data is construction process data and resource management data corresponding to the implementation process of the offshore wind power project;

对项目流程数据进行特征提取,获取项目工艺流程特性,将项目流程数据根据项目工艺流程特性进行拆分,获取相应的流程序列,根据所述流程序列设置项目资源节点,将所述项目流程数据所对应的流程序列进行匹配,根据匹配结果设置项目资源节点对应流程序列内项目流程数据所对应的项目流程评价指标。Perform feature extraction on the project process data to obtain project process flow characteristics, split the project process data according to the project process flow characteristics, obtain the corresponding process sequence, set the project resource node according to the process sequence, match the process sequence corresponding to the project process data, and set the project process evaluation index corresponding to the project process data in the process sequence corresponding to the project resource node according to the matching result.

进一步的,所述项目资源管理模块设置用户权限数据的过程包括:Furthermore, the process of setting user authority data in the project resource management module includes:

所述项目资源管理模块内设置有权限管理单元;The project resource management module is provided with a rights management unit;

所述权限管理单元获取各个项目资源节点内所对应的流程序列和项目人员数据信息,将所述项目人员数据信息内所包含的人员工作职责信息与各个项目资源节点内所对应的流程序列进行匹配分析,根据匹配分析结果获取对应项目资源节点所对应的人员身份资质信息,根据人员身份资质信息设置用户权限数据;The authority management unit obtains the process sequence and project personnel data information corresponding to each project resource node, matches and analyzes the personnel job responsibility information contained in the project personnel data information with the process sequence corresponding to each project resource node, obtains the personnel identity qualification information corresponding to the corresponding project resource node according to the matching analysis result, and sets user authority data according to the personnel identity qualification information;

获取对应项目资源节点内所包含的人员身份资质信息,根据人员身份资质信息的数量设置对应大小的身份队列方阵,对人员身份资质信息进行序列化处理,获取所述人员身份资质信息所对应的字节序列;将所获得的字节序列根据行排列输入至相应的身份队列方阵内,获取权限队列方阵;Obtain the personnel identity qualification information contained in the corresponding project resource node, set an identity queue matrix of corresponding size according to the number of personnel identity qualification information, serialize the personnel identity qualification information, and obtain the byte sequence corresponding to the personnel identity qualification information; input the obtained byte sequence into the corresponding identity queue matrix according to the row arrangement to obtain the authority queue matrix;

将人员身份资质信息所对应的字节序列进行分析处理,获取相应的稀疏矩阵,将所获得的稀疏矩阵与权限队列方阵进行乘积,获取对应项目人员账号的用户权限数据。The byte sequence corresponding to the personnel identity qualification information is analyzed and processed to obtain the corresponding sparse matrix, and the obtained sparse matrix is multiplied with the permission queue matrix to obtain the user permission data of the corresponding project personnel account.

进一步的,所述项目进度分析模块用于获取相应的实施项目数据,将所获得的实施项目数据根据相应的项目资源节点所对应的项目工艺流程特性进行拆分,根据拆分结果将相应的实施项目数据发送至对应的项目资源节点内;所述项目资源节点所获得拆分结果所对应的实施项目数据标记为即时项目进度数据。Furthermore, the project progress analysis module is used to obtain corresponding implementation project data, split the obtained implementation project data according to the project process flow characteristics corresponding to the corresponding project resource nodes, and send the corresponding implementation project data to the corresponding project resource nodes according to the splitting results; the implementation project data corresponding to the splitting results obtained by the project resource nodes are marked as real-time project progress data.

进一步的,所述项目协同共享模块根据即时项目进度数据和气象预测数据设置对应项目资源节点内的项目规划数据的过程包括:Furthermore, the process of the project collaborative sharing module setting the project planning data in the corresponding project resource node according to the real-time project progress data and the weather forecast data includes:

所述项目协同共享模块内设置有项目协同单元和流程协同单元;The project collaboration sharing module is provided with a project collaboration unit and a process collaboration unit;

所述项目协同单元获取各个项目资源节点所对应的流程序列,根据流程序列所对应的项目工艺流程特性进行分析处理,获取各个项目资源节点之间的关联关系,所述关联关系包括导向性关系、反向性关系以及独立关系三种类型,根据关联关系类型的不同,对各个项目资源节点进行协同管理;The project collaboration unit obtains the process sequence corresponding to each project resource node, performs analysis and processing according to the project process flow characteristics corresponding to the process sequence, obtains the association relationship between each project resource node, and the association relationship includes three types: directional relationship, reverse relationship and independent relationship. According to different types of association relationships, collaborative management is performed on each project resource node;

所述流程协同单元用于获取项目资源节点所对应的即时项目进度数据、气象预测数据以及项目资源节点所对应导向性关系和反向性关系所对应的其他项目资源节点;根据项目资源节点设置预警气象数据;The process coordination unit is used to obtain the real-time project progress data and weather forecast data corresponding to the project resource nodes and other project resource nodes corresponding to the directional relationship and reverse relationship corresponding to the project resource nodes; set early warning weather data according to the project resource nodes;

将所获得的气象预测数据与预警气象数据进行对比分析,根据对比分析结果获取相应的项目气象规划时间;Compare and analyze the obtained meteorological forecast data with the early warning meteorological data, and obtain the corresponding project meteorological planning time based on the comparative analysis results;

预设项目规划周期,根据所述项目规划周期获取项目资源节点所对应导向性关系和反向性关系所对应项目资源节点所对应的即时项目进度数据,分别获取所对应的即时项目进度数据在项目规划周期内所对应的导向性项目变化数据和反向性项目变化数据;Preset a project planning cycle, obtain the real-time project progress data corresponding to the project resource nodes corresponding to the directional relationship and the reverse relationship corresponding to the project resource nodes according to the project planning cycle, and respectively obtain the directional project change data and the reverse project change data corresponding to the corresponding real-time project progress data within the project planning cycle;

将所获得的导向性项目变化数据和反向性变化数据结合项目气象规划时间进行分析处理,生成所述项目资源节点所对应的项目规划数据;Analyze and process the obtained directional project change data and reverse change data in combination with the project weather planning time to generate project planning data corresponding to the project resource node;

将所获得的项目规划数据发送至项目资源节点内所对应的项目人员账号,项目人员根据用户权限数据获取项目人员账户内项目规划数据进行项目协同共享。The obtained project planning data is sent to the corresponding project personnel account in the project resource node. The project personnel obtain the project planning data in the project personnel account according to the user authority data for project collaborative sharing.

进一步的,所述项目预警管理模块用于各个项目资源节点获取相应的即时项目进度数据,将所获得的即时项目进度数据进行特征提取,获取即时项目评价数据,将所获得的即时项目评价数据对所述项目资源节点内所对应的项目流程评价指标进行匹配分析,若不符合项目流程评价指标所对应的标准,则生成评价项目预警信息;Further, the project early warning management module is used for each project resource node to obtain corresponding real-time project progress data, perform feature extraction on the obtained real-time project progress data, obtain real-time project evaluation data, match and analyze the obtained real-time project evaluation data with the corresponding project process evaluation index in the project resource node, and generate evaluation project early warning information if it does not meet the standard corresponding to the project process evaluation index;

若符合项目流程评价指标所对应的标准,则将即时项目进度数据与项目规划数据进行对比分析,获取进度偏差值,预设偏差值阈值,将所获得的进度偏差值和偏差值阈值进行对比分析;If the standards corresponding to the project process evaluation indicators are met, the immediate project progress data is compared and analyzed with the project planning data to obtain the progress deviation value, preset the deviation value threshold, and compare and analyze the obtained progress deviation value with the deviation value threshold;

当进度偏差值大于偏差值阈值时,则生成进度项目预警信息,反之则正常;根据所获得的项目预警信息进行协调管理。When the progress deviation value is greater than the deviation value threshold, a progress project warning information is generated, otherwise it is normal; coordination and management are carried out based on the project warning information obtained.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the present invention has the following beneficial effects:

1、通过设置项目资源节点,根据项目人员所对应的人员工作职责信息将相应的项目人员与对应的项目资源节点相互关联,并设置相应的身份队列方阵和稀疏矩阵,从而获取对应项目人员所对应的用户权限数据,通过对项目资源节点内所对应的项目人员账户设置相应的用户权限数据,在一定程度上提高了项目管理过程中项目数据信息的安全性;1. By setting up project resource nodes, the corresponding project personnel are associated with the corresponding project resource nodes according to the corresponding job responsibilities of the project personnel, and the corresponding identity queue matrix and sparse matrix are set, so as to obtain the user authority data corresponding to the corresponding project personnel. By setting the corresponding user authority data for the corresponding project personnel account in the project resource node, the security of project data information in the project management process is improved to a certain extent;

2、通过对项目资源节点之间关联关系将项目资源节点内的即时项目进度数据进行分析处理,在一定程度上提高了各个项目资源节点设置项目规划数据过程中的协同性,从而避免了资源浪费;此外,通过获取气象预测数据,根据气象预测数据获取相应的项目气象规划时间,在结合气象规划时间设置相应的项目规划数据,在一定程度上提高了项目规划过程中的即时性。2. By analyzing and processing the real-time project progress data within the project resource nodes based on the correlation between the project resource nodes, the coordination of the project resource nodes in setting the project planning data is improved to a certain extent, thereby avoiding waste of resources; in addition, by obtaining meteorological forecast data, obtaining the corresponding project meteorological planning time according to the meteorological forecast data, and setting the corresponding project planning data in combination with the meteorological planning time, the immediacy of the project planning process is improved to a certain extent.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本申请实施例一种海上风电基于项目实施进度的项目管理系统的原理图。FIG1 is a schematic diagram of an offshore wind power project management system based on project implementation progress according to an embodiment of the present application.

具体实施方式DETAILED DESCRIPTION

如图1所示,一种海上风电基于项目实施进度的项目管理系统,包括项目管理中心,所述项目管理中心内通信连接有项目数据采集模块、海上数据采集模块、项目资源管理模块、项目进度分析模块、项目协同共享模块以及项目预警管理模块;As shown in FIG1 , an offshore wind power project management system based on project implementation progress includes a project management center, wherein the project management center is communicatively connected with a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project collaborative sharing module, and a project early warning management module;

所述项目数据采集模块用于采集相应海上风电项目所对应的项目数据信息和项目人员数据信息,并将所获得的数据信息发送至项目资源管理模块,其具体实施过程包括:The project data acquisition module is used to collect project data information and project personnel data information corresponding to the corresponding offshore wind power project, and send the obtained data information to the project resource management module. The specific implementation process includes:

所述项目数据采集模块内设置有项目采集单元和人员采集单元;The project data collection module is provided with a project collection unit and a personnel collection unit;

所述项目采集单元用于采集海上风电项目所对应的项目数据信息,其中设置有项目录入窗口,所述项目录入窗口用于相应的工作人员录入相应的项目数据信息,所述项目数据信息包括项目名称、项目地点、项目设计数据、项目流程数据和项目资质数据;The project collection unit is used to collect project data information corresponding to the offshore wind power project, wherein a project entry window is provided, and the project entry window is used for corresponding staff to enter corresponding project data information, and the project data information includes project name, project location, project design data, project process data and project qualification data;

对所采集到的项目数据信息进行分析处理,对所述项目数据信息内所包含的项目名称、项目地点以及项目资质数据进行验证审核,所述项目资质数据内包括项目公司资质信息、设计单位资质信息、施工资质信息以及法律合规资质信息;Analyze and process the collected project data information, and verify and review the project name, project location and project qualification data contained in the project data information. The project qualification data includes project company qualification information, design unit qualification information, construction qualification information and legal compliance qualification information;

将所获得的项目资质数据进行分析处理,判断所获得的项目数据信息是否符合建筑标准,若符合标准,则该项目数据信息通过验证,且对其设置相应的准入权限;Analyze and process the obtained project qualification data to determine whether the obtained project data information meets the construction standards. If it meets the standards, the project data information is verified and the corresponding access rights are set for it;

所述人员采集单元用于采集相应海上风电项目所对应的项目人员数据信息,所述项目人员数据包括人员组织结构信息、人员身份资质信息和人员工作职责信息;The personnel collection unit is used to collect project personnel data information corresponding to the corresponding offshore wind power project, and the project personnel data includes personnel organizational structure information, personnel identity qualification information and personnel job responsibility information;

所述人员组织结构信息包括项目的组织架构图和岗位分工图,所述组织架构图内包括项目对应企业所对应的管理部门,所述岗位分工图内包括不同岗位所对应主要职责任务以及职能领域;The personnel organizational structure information includes the organizational chart and job division chart of the project. The organizational chart includes the management department corresponding to the enterprise corresponding to the project, and the job division chart includes the main duties and responsibilities and functional areas corresponding to different positions;

所述人员身份资质信息包括项目人员所对应的身份数据信息和资质身份信息,所述身份数据信息包括姓名、年龄、性别、身份证号码以及实名认证的手机号码,所述资质身份信息包括相应的资格证书或聘用数据等;The personnel identity qualification information includes the identity data information and qualification identity information corresponding to the project personnel, the identity data information includes name, age, gender, ID card number and real-name authenticated mobile phone number, and the qualification identity information includes corresponding qualification certificates or employment data, etc.;

所述人员工作职责信息包括对应项目人员在相应项目流程中所需要进行的工作数据。The personnel job responsibility information includes the work data that the corresponding project personnel need to perform in the corresponding project process.

所述海上数据采集模块用于采集相应海上风电项目所对应的实施项目数据和气象预测数据,并对所获得的数据发送至项目进度分析模块,其具体实施过程包括:The offshore data acquisition module is used to collect the implementation project data and meteorological forecast data corresponding to the corresponding offshore wind power project, and send the acquired data to the project progress analysis module. The specific implementation process includes:

所述海上数据采集模块内设置有项目监测单元和气象预测单元;The marine data acquisition module is provided with a project monitoring unit and a weather forecasting unit;

所述项目监测单元内设置有项目监测设备,所述项目监测设备用于获取对应海上风电项目实施过程中所对应的实施项目数据,所述实施项目数据包括施工设备数据、材料更新数据和施工进度数据;The project monitoring unit is provided with a project monitoring device, and the project monitoring device is used to obtain the corresponding implementation project data during the implementation of the corresponding offshore wind power project, and the implementation project data includes construction equipment data, material update data and construction progress data;

所述气象预测单元内设置有气象监测设备,所述气象监测设备用于采集项目实施过程中的实时气象数据;The meteorological forecast unit is provided with a meteorological monitoring device, and the meteorological monitoring device is used to collect real-time meteorological data during the project implementation process;

所述气象预测单元与所在项目地址所对应的气象站相关联,根据所述气象站获取项目地址所在位置的气象预测数据。The weather forecast unit is associated with a weather station corresponding to the project address, and obtains weather forecast data of the project address according to the weather station.

所述项目资源管理模块用于根据项目数据信息对海上风电项目进行流程拆分,根据拆分结果设置项目资源节点,将项目人员数据信息与相应的项目资源节点相互匹配,根据匹配结果设置对应用户权限数据,其具体实施过程包括:The project resource management module is used to split the process of the offshore wind power project according to the project data information, set the project resource node according to the split result, match the project personnel data information with the corresponding project resource node, and set the corresponding user authority data according to the matching result. The specific implementation process includes:

所述项目资源管理模块内设置有资源管理单元和权限管理单元;The project resource management module is provided with a resource management unit and a permission management unit;

所述资源管理单元用于获取项目数据信息内所包括的项目流程数据,所述项目流程数据为对应海上风电项目实施过程中的施工流程数据和资源管理数据;The resource management unit is used to obtain project process data included in the project data information, wherein the project process data is construction process data and resource management data corresponding to the implementation process of the offshore wind power project;

对项目流程数据进行特征提取,获取项目工艺流程特性,将项目流程数据根据项目工艺流程特性进行拆分,获取相应的流程序列,根据所述流程序列设置项目资源节点,将所述资源管理数据与项目流程数据所对应的流程序列进行匹配,根据匹配结果将其标记为流程序列数据;Extract features from the project process data to obtain project process characteristics, split the project process data according to the project process characteristics, obtain corresponding process sequences, set project resource nodes according to the process sequences, match the resource management data with the process sequences corresponding to the project process data, and mark them as process sequence data according to the matching results;

获取对应项目资源节点内所包括的流程序列数据和相应的数据评价结果,生成流程序列数据集,对所获得的流程序列数据集进行分析处理,根据分析处理结果生成对应的项目资源节点所对应的项目流程评价指标,所述项目流程评价指标内包括施工流程评价指标和资源流程评价指标;Acquire the process sequence data and corresponding data evaluation results included in the corresponding project resource node, generate a process sequence data set, analyze and process the obtained process sequence data set, and generate a project process evaluation index corresponding to the corresponding project resource node according to the analysis and processing results, wherein the project process evaluation index includes a construction process evaluation index and a resource process evaluation index;

所述权限管理单元获取各个项目资源节点内所对应的流程序列和项目人员数据信息,将所述项目人员数据信息内所包含的人员工作职责信息与各个项目资源节点内所对应的流程序列进行匹配分析,根据匹配分析结果获取对应项目资源节点所对应的人员身份资质信息,根据人员身份资质信息设置用户权限数据;The authority management unit obtains the process sequence and project personnel data information corresponding to each project resource node, matches and analyzes the personnel job responsibility information contained in the project personnel data information with the process sequence corresponding to each project resource node, obtains the personnel identity qualification information corresponding to the corresponding project resource node according to the matching analysis result, and sets user authority data according to the personnel identity qualification information;

获取对应项目资源节点内所包含的人员身份资质信息,根据人员身份资质信息的数量设置对应大小为N的身份队列方阵,对人员身份资质信息进行序列化处理,获取所述人员身份资质信息所对应的字节序列,所述字节序列所对应的位数也为N;将所获得的字节序列根据行排列输入至大小为N的身份列队方阵内,获取权限队列方阵;Obtain the personnel identity qualification information contained in the corresponding project resource node, set the corresponding identity queue square matrix of size N according to the number of personnel identity qualification information, serialize the personnel identity qualification information, and obtain the byte sequence corresponding to the personnel identity qualification information, and the number of bits corresponding to the byte sequence is also N; input the obtained byte sequence into the identity queue square matrix of size N according to the row arrangement to obtain the permission queue square matrix;

将人员身份资质信息所对应的字节序列进行分析处理,获取相应的稀疏矩阵,将所获得的稀疏矩阵与权限队列方阵进行乘积,获取对应项目人员所对应的用户权限数据;Analyze and process the byte sequence corresponding to the personnel identity qualification information to obtain the corresponding sparse matrix, multiply the obtained sparse matrix with the permission queue matrix to obtain the user permission data corresponding to the corresponding project personnel;

需要进一步说明的是,在具体实施过程中,所述用户权限数据为对应项目人员通过其项目人员账号获取对应项目资源节点内相应的数据信息进行身份验证的数据,在一定程度上提高了项目管理过程中的安全性。It should be further explained that, in the specific implementation process, the user authority data is the data for identity authentication obtained by the corresponding project personnel through their project personnel account to obtain the corresponding data information in the corresponding project resource node, which improves the security of the project management process to a certain extent.

所述项目进度分析模块用于根据项目资源节点对实施项目数据进行拆分,根据拆分结果获取相应项目资源节点内所对应的即时项目进度数据,其具体实施过程包括:The project progress analysis module is used to split the implementation project data according to the project resource nodes, and obtain the corresponding real-time project progress data in the corresponding project resource nodes according to the split results. The specific implementation process includes:

所述项目进度分析模块用于获取相应的实施项目数据,将所获得的实施项目数据根据相应的项目资源节点所对应的项目工艺流程特性进行拆分,根据拆分结果将相应的实施项目数据发送至对应的项目资源节点内;所述项目资源节点所获得拆分结果所对应的实施项目数据标记为即时项目进度数据。The project progress analysis module is used to obtain corresponding implementation project data, split the obtained implementation project data according to the project process flow characteristics corresponding to the corresponding project resource nodes, and send the corresponding implementation project data to the corresponding project resource nodes according to the split results; the implementation project data corresponding to the split results obtained by the project resource nodes are marked as real-time project progress data.

所述项目协同共享模块用于根据即时项目进度数据和气象预测数据设置对应项目资源节点内的项目规划数据,并根据用户权限数据发送至相应的用户账号内,进行项目协同共享,其具体实施过程包括:The project collaborative sharing module is used to set the project planning data in the corresponding project resource node according to the real-time project progress data and weather forecast data, and send it to the corresponding user account according to the user authority data to carry out project collaborative sharing. The specific implementation process includes:

所述项目协同共享模块内设置有项目协同单元和流程协同单元;The project collaboration sharing module is provided with a project collaboration unit and a process collaboration unit;

所述项目协同单元获取各个项目资源节点所对应的流程序列,根据流程序列所对应的项目工艺流程特性进行分析处理,获取各个项目资源节点之间的关联关系,所述关联关系包括导向性关系、反向性关系以及独立关系三种类型;The project collaboration unit obtains the process sequence corresponding to each project resource node, performs analysis and processing according to the project process flow characteristics corresponding to the process sequence, and obtains the association relationship between each project resource node, wherein the association relationship includes three types: directional relationship, reverse relationship and independent relationship;

所述导向性关系为其他项目资源节点内的流程序列对该项目资源节点产生影响的关系;The guiding relationship is the relationship in which the process sequence in other project resource nodes affects the project resource node;

所述反向性关系为相应的项目流程序列内的流程序列对其他项目资源结果产生影响的关系;The reverse relationship is the relationship between the process sequence within the corresponding project process sequence and the impact on other project resource results;

所述独立关系为两个项目资源节点之间不存在影响关系;The independent relationship means that there is no influence relationship between the two project resource nodes;

根据关联关系类型的不同,对各个项目资源节点进行协同管理;Collaboratively manage each project resource node according to the different types of association relationships;

所述流程协同单元用于获取项目资源节点所对应的即时项目进度数据、气象预测数据以及项目资源节点所对应导向性关系和反向性关系所对应的其他项目资源节点;The process coordination unit is used to obtain the real-time project progress data and weather forecast data corresponding to the project resource nodes, and other project resource nodes corresponding to the directional relationship and reverse relationship corresponding to the project resource nodes;

根据项目资源节点设置预警气象数据,获取实时气象数据与相应的项目资源节点内所对应的历史实施项目数据,根据对应结果获取相应的气象阈值数据,将所获得的气象阈值数据设置为预警气象数据;Set early warning meteorological data according to the project resource node, obtain real-time meteorological data and the historical implementation project data corresponding to the corresponding project resource node, obtain corresponding meteorological threshold data according to the corresponding results, and set the obtained meteorological threshold data as early warning meteorological data;

将所获得的气象预测数据与预警气象数据进行对比分析,根据对比分析结果获取相应的项目气象规划时间;Compare and analyze the obtained meteorological forecast data with the early warning meteorological data, and obtain the corresponding project meteorological planning time based on the comparative analysis results;

预设项目规划周期,根据所述项目规划周期获取项目资源节点所对应导向性关系和反向性关系所对应项目资源节点所对应的即时项目进度数据,分别获取所对应的即时项目进度数据在项目规划周期内所对应的导向性项目变化数据和反向性项目变化数据;Preset a project planning cycle, obtain the real-time project progress data corresponding to the project resource nodes corresponding to the directional relationship and the reverse relationship corresponding to the project resource nodes according to the project planning cycle, and respectively obtain the directional project change data and the reverse project change data corresponding to the corresponding real-time project progress data within the project planning cycle;

将所获得的导向性项目变化数据和反向性变化数据结合项目气象规划时间进行分析处理,生成所述项目资源节点所对应的项目规划数据;Analyze and process the obtained directional project change data and reverse change data in combination with the project weather planning time to generate project planning data corresponding to the project resource node;

将所获得的项目规划数据发送至项目资源节点内所对应的项目人员账号,项目人员根据用户权限数据获取项目人员账户内项目规划数据进行项目协同共享。The obtained project planning data is sent to the corresponding project personnel account in the project resource node. The project personnel obtain the project planning data in the project personnel account according to the user authority data for project collaborative sharing.

所述项目预警管理模块用于根据相应时刻所对应的项目规划数据与实施项目数据进行对比分析,根据对比分析结果生成项目预警信息,根据项目预警信息进行协调管理,其具体实施过程包括:The project early warning management module is used to compare and analyze the project planning data and the implementation project data corresponding to the corresponding time, generate project early warning information according to the comparison and analysis results, and coordinate management according to the project early warning information. The specific implementation process includes:

所述项目预警管理模块用于各个项目资源节点获取相应的即时项目进度数据,将所获得的即时项目进度数据进行特征提取,获取即时项目评价数据,将所获得的即时项目评价数据对所述项目资源节点内所对应的项目流程评价指标进行匹配分析,若不符合项目流程评价指标所对应的标准,则生成评价项目预警信息;The project early warning management module is used for each project resource node to obtain the corresponding real-time project progress data, perform feature extraction on the obtained real-time project progress data, obtain the real-time project evaluation data, match and analyze the obtained real-time project evaluation data with the corresponding project process evaluation index in the project resource node, and generate evaluation project early warning information if it does not meet the standard corresponding to the project process evaluation index;

若符合项目流程评价指标所对应的标准,则将即时项目进度数据与项目规划数据进行对比分析,获取进度偏差值,预设偏差值阈值,将所获得的进度偏差值和偏差值阈值进行对比分析;If the standards corresponding to the project process evaluation indicators are met, the immediate project progress data is compared and analyzed with the project planning data to obtain the progress deviation value, preset the deviation value threshold, and compare and analyze the obtained progress deviation value with the deviation value threshold;

当进度偏差值大于偏差值阈值时,则生成进度项目预警信息,反之则正常;根据所获得的项目预警信息进行协调管理。When the progress deviation value is greater than the deviation value threshold, a progress project warning information is generated, otherwise it is normal; coordination and management are carried out based on the project warning information obtained.

以上实施例仅用以说明本发明的技术方法而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方法进行修改或等同替换,而不脱离本发明技术方法的精神和范围。The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.

Claims (3)

1. The project management system based on project implementation progress of offshore wind power comprises a project management center, and is characterized in that a project data acquisition module, an offshore data acquisition module, a project resource management module, a project progress analysis module, a project cooperative sharing module and a project early warning management module are in communication connection in the project management center;
The project data acquisition module is used for acquiring project data information and project personnel data information corresponding to the corresponding offshore wind power project, wherein the project data information comprises project names, project addresses, project flow data and project qualification data, and the project personnel data comprises personnel organization structure information, personnel identity qualification information and personnel work responsibility information;
the marine data acquisition module is used for acquiring implementation project data and weather forecast data corresponding to corresponding marine wind power projects;
The project resource management module is used for carrying out flow splitting on offshore wind power projects according to project data information, setting project resource nodes according to splitting results, mutually matching project personnel data information with corresponding project resource nodes, and setting corresponding user permission data according to matching results;
the project progress analysis module is used for splitting implementation project data according to project resource nodes and acquiring corresponding instant project progress data in corresponding project resource nodes according to splitting results;
the process of setting the project resource nodes by the project resource management module comprises the following steps:
a resource management unit is arranged in the project resource management module;
The resource management unit is used for acquiring project flow data included in project data information, wherein the project flow data are construction flow data and resource management data in the implementation process of corresponding offshore wind power projects;
extracting characteristics of the project flow data, acquiring project process flow characteristics, splitting the project flow data according to the project process flow characteristics, acquiring corresponding flow sequences, setting project resource nodes according to the flow sequences, matching the flow sequences corresponding to the project flow data, and setting project flow evaluation indexes corresponding to the project flow data in the flow sequences corresponding to the project resource nodes according to matching results;
The process of setting the user authority data by the project resource management module comprises the following steps:
a right management unit is arranged in the project resource management module;
The authority management unit acquires a corresponding flow sequence and project personnel data information in each project resource node, performs matching analysis on personnel work responsibility information contained in the project personnel data information and the corresponding flow sequence in each project resource node, acquires personnel identity qualification information corresponding to the corresponding project resource node according to a matching analysis result, and sets user authority data according to the personnel identity qualification information;
Acquiring personnel identity qualification information contained in a corresponding project resource node, setting an identity queue square matrix with a corresponding size according to the quantity of the personnel identity qualification information, carrying out serialization processing on the personnel identity qualification information, and acquiring a byte sequence corresponding to the personnel identity qualification information; the obtained byte sequence is input into a corresponding identity queue square matrix according to row arrangement, and a permission queue square matrix is obtained;
analyzing and processing the byte sequence corresponding to the personnel identity qualification information to obtain a corresponding sparse matrix, multiplying the obtained sparse matrix by a permission queue square matrix, and obtaining user permission data of the personnel account of the corresponding project;
The project collaborative sharing module is used for setting project planning data in corresponding project resource nodes according to the instant project progress data and the weather forecast data, sending the project planning data into corresponding project personnel accounts, and carrying out project collaborative sharing according to the user permission data;
the project early warning management module is used for carrying out comparison analysis on project planning data and implementation project data corresponding to corresponding moments, generating project early warning information according to comparison analysis results and carrying out coordination management according to the project early warning information;
The project collaborative sharing module sets project planning data in the corresponding project resource nodes according to the instant project progress data and the weather forecast data, and the process comprises the following steps:
The project cooperative sharing module is internally provided with a project cooperative unit and a flow cooperative unit;
The project cooperation unit acquires a flow sequence corresponding to each project resource node, analyzes and processes the flow sequence according to project process flow characteristics corresponding to the flow sequence, and acquires an association relation among the project resource nodes, wherein the association relation comprises three types of guidance relation, reversibility relation and independent relation;
the guiding relation is a relation that a flow sequence in other project resource nodes affects the project resource nodes;
The reversibility relation is a relation that a flow sequence in a corresponding project flow sequence affects other project resource results;
The independent relationship is that no influence relationship exists between two project resource nodes;
according to the different association relation types, carrying out collaborative management on each project resource node;
The flow collaboration unit is used for acquiring instant project progress data, weather forecast data and other project resource nodes corresponding to the guidance relationship and the reversibility relationship corresponding to the project resource nodes; setting early warning meteorological data according to project resource nodes;
Comparing and analyzing the obtained weather forecast data with early warning weather data, and obtaining corresponding project weather planning time according to a comparison analysis result;
Presetting a project planning period, and acquiring instant project progress data corresponding to project resource nodes corresponding to a guidance relationship and a reversibility relationship corresponding to project resource nodes according to the project planning period, and respectively acquiring guidance project change data and reversibility project change data corresponding to the corresponding instant project progress data in the project planning period;
Analyzing and processing the acquired guidance project change data and reverse change data in combination with project weather planning time to generate project planning data corresponding to the project resource nodes;
The obtained project planning data are sent to corresponding project personnel accounts in project resource nodes, and project personnel acquire project planning data in project personnel accounts according to user authority data to carry out project collaborative sharing;
The project early warning management module is used for acquiring corresponding instant project progress data by each project resource node, extracting features of the acquired instant project progress data to acquire instant project evaluation data, carrying out matching analysis on project flow evaluation indexes corresponding to the project resource nodes by the acquired instant project evaluation data, and generating evaluation project early warning information if the project flow evaluation indexes do not meet the standards corresponding to the project flow evaluation indexes;
If the corresponding standard of the project flow evaluation index is met, comparing and analyzing the instant project progress data with the project planning data to obtain a progress deviation value, presetting a deviation value threshold value, and comparing and analyzing the obtained progress deviation value and the deviation value threshold value;
when the progress deviation value is larger than the deviation value threshold value, generating progress project early warning information, otherwise, normally; and carrying out coordination management according to the obtained project early warning information.
2. The project management system based on project implementation progress according to claim 1, wherein the process of collecting implementation project data and weather forecast data corresponding to a corresponding offshore wind project by the offshore data collection module comprises:
the marine data acquisition module is internally provided with a project monitoring unit and a weather prediction unit;
The project monitoring unit is internally provided with project monitoring equipment, and the project monitoring equipment is used for acquiring implementation project data corresponding to the implementation process of the offshore wind power project;
The weather forecast unit acquires a corresponding weather station according to the project address, associates the weather station with the acquired weather station, and acquires weather forecast data of the position of the project address according to the weather station.
3. The project management system based on project implementation progress according to claim 2, wherein the project progress analysis module is configured to obtain corresponding implementation project data, split the obtained implementation project data according to project process flow characteristics corresponding to corresponding project resource nodes, and send the corresponding implementation project data to the corresponding project resource nodes according to the split result; and marking implementation project data corresponding to the splitting result obtained by the project resource node as instant project progress data.
CN202411188236.2A 2024-08-28 2024-08-28 A project management system for offshore wind power based on project implementation progress Active CN118691056B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411188236.2A CN118691056B (en) 2024-08-28 2024-08-28 A project management system for offshore wind power based on project implementation progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411188236.2A CN118691056B (en) 2024-08-28 2024-08-28 A project management system for offshore wind power based on project implementation progress

Publications (2)

Publication Number Publication Date
CN118691056A CN118691056A (en) 2024-09-24
CN118691056B true CN118691056B (en) 2024-11-05

Family

ID=92775828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411188236.2A Active CN118691056B (en) 2024-08-28 2024-08-28 A project management system for offshore wind power based on project implementation progress

Country Status (1)

Country Link
CN (1) CN118691056B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111126734A (en) * 2018-10-31 2020-05-08 中国能源建设集团广东省电力设计研究院有限公司 Offshore wind farm dispatching management system
CN113112233A (en) * 2021-04-16 2021-07-13 西安热工研究院有限公司 BIM-based intelligent management method and platform for full life cycle of wind power project

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8738414B1 (en) * 2010-12-31 2014-05-27 Ajay R. Nagar Method and system for handling program, project and asset scheduling management
CN113177749A (en) * 2021-06-29 2021-07-27 武汉华信数据系统有限公司 Resource management method and device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111126734A (en) * 2018-10-31 2020-05-08 中国能源建设集团广东省电力设计研究院有限公司 Offshore wind farm dispatching management system
CN113112233A (en) * 2021-04-16 2021-07-13 西安热工研究院有限公司 BIM-based intelligent management method and platform for full life cycle of wind power project

Also Published As

Publication number Publication date
CN118691056A (en) 2024-09-24

Similar Documents

Publication Publication Date Title
CN106940903A (en) Work attendance method, device and system
CN115619134B (en) Engineering service-based mechanic platform construction method and system
CN106485298A (en) A kind of equipment routing inspection maintaining method based on Quick Response Code
CN105809575A (en) Mobile operation system and method for water and electricity production management
CN105894395A (en) Substation equipment state overhaul, operation and maintenance management system based on two-dimensional code mobile Internet technology
CN107545637A (en) The Activiation method and server of a kind of electronic lock
CN107818449A (en) A kind of power transformation fortune inspection management system based on mobile solution platform
CN107977718A (en) Substation equipment maintaining method and system based on BIM models
CN110517123A (en) A kind of unmanned bid evaluation system of AI based on technology of Internet of things and method
CN109726931A (en) Seat manages method, apparatus, computer equipment and storage medium
CN118691056B (en) A project management system for offshore wind power based on project implementation progress
CN112202721A (en) Intelligent safety system of power enterprise internet of things terminal
CN110866705A (en) Power operator examination method and device, computer equipment and storage medium
CN102360485A (en) Software method and system for incremental risk evaluation
CN110083874A (en) A kind of cable system component digitlization designing system
CN110362626A (en) One kind being based on the convenience-for-people inquiry system of block chain network and application method
CN114358746A (en) Software development integrated control system based on block chain
CN206489612U (en) One kind production report work system
CN205721963U (en) A kind of Condition-based Maintenance of Substation Equipment operation management system based on Quick Response Code mobile interchange technology
CN104318739B (en) Electric power safety, quality In-site supervision main website-wireless data terminal management system
CN104216986B (en) The device and method of pre-operation raising efficiency data query is carried out with the data update cycle
CN112085412B (en) Resource optimization distribution system and distribution method
KR102556149B1 (en) Management system for ultilization of research performance and method for managing ultilization of research performance using the same
CN115641003A (en) Method for hierarchical management and control of associated risks and troubleshooting and treatment of hidden dangers
CN110909215A (en) Information acquisition big data analysis system for medium and small enterprises

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant