CN118324007B - Building material lifting device - Google Patents
Building material lifting device Download PDFInfo
- Publication number
- CN118324007B CN118324007B CN202410761001.1A CN202410761001A CN118324007B CN 118324007 B CN118324007 B CN 118324007B CN 202410761001 A CN202410761001 A CN 202410761001A CN 118324007 B CN118324007 B CN 118324007B
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- plate
- hanging
- rod
- sliding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004566 building material Substances 0.000 title claims abstract description 20
- 230000000712 assembly Effects 0.000 claims abstract description 7
- 238000000429 assembly Methods 0.000 claims abstract description 7
- 229910000831 Steel Inorganic materials 0.000 claims description 28
- 239000010959 steel Substances 0.000 claims description 28
- 238000000034 method Methods 0.000 description 14
- 239000000463 material Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 241000252254 Catostomidae Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/14—Slings with hooks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/10—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for preventing cable slack
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/167—Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention belongs to the technical field of hoisting equipment, in particular to building material hoisting equipment, which comprises hoisting equipment; the hoisting equipment comprises a hanger; pulling plates are arranged on two sides of the four cross beams; the bottom of the pulling plate is fixedly connected with a hanging plate; the hoisting assembly comprises two mounting plates; two rotating shafts are rotatably connected between the two mounting plates; the two rotating shafts are fixedly connected with first gears; the end faces of the two sides, close to the two mounting plates, of the two first gears are fixedly connected with side plates; a boom is fixedly connected to one side of the two side plates on the two first gears, which are opposite to each other; a T-shaped rod is connected in a sliding way in the sliding groove; a cross rod is fixedly connected with two opposite T-shaped rods on the two hoisting assemblies; two hooks are arranged on the cross rod; the invention is mainly used for solving the problem that when a floor slab is lifted, a hand is needed to limit the hook in the circular groove, and the prefabricated floor slab can fall off on the side of the circular groove.
Description
Technical Field
The invention belongs to the technical field of hoisting equipment, and particularly relates to building material hoisting equipment.
Background
Building materials refer to a generic term for various materials and products thereof used in construction engineering. It is the material foundation of all building engineering; specifically, materials used for foundation, bearing members, floors, walls, supporting beam bodies and roof waterproofing all belong to the category of building materials;
when the building material is hoisted, a tool for hoisting the building material is mainly used; the most commonly used lifting appliances refer to lifting hooks and slings, as well as lifting rings, steel wire ropes, chains, lifting suckers, clamps, forks and the like;
At present, when hoisting plate building materials, such as hoisting precast floor slabs, a commonly used tool is to hoist the precast floor slabs by using a steel wire rope, and when hoisting, the steel wire rope is required to be installed on a lifting hook of a crane, and then a hook connected with the steel wire rope is inserted into a circular groove of the precast floor slabs to be hoisted;
In order to facilitate the insertion of the lifting hook into the circular groove of the precast floor slab, the lifting hook is generally required to be moved downwards to the lower part of the circular groove, then the lifting hook is inserted into the circular groove, then the crane gradually pulls the steel wire rope to tighten, and when the steel wire rope is completely tightened, the precast floor slab can be lifted;
However, because the couple is only placed in the circular slot, at wire rope tightening's in-process, can drive the couple and remove at the circular slot to make the couple shift out from the circular slot easily, lead to the area of contact of couple and circular slot to reduce, thereby the risk that drops when the increase lifts up prefabricated floor, consequently when lifting up the floor, need the staff to spacing the couple in the circular slot, nevertheless utilize the staff to carry out spacing when the couple, the condition of tong appears easily.
Disclosure of Invention
In order to make up the defects of the prior art and solve the technical problems, the invention provides building material hoisting equipment, which can avoid the problem that the prior hooks are driven to move in the circular grooves when the prefabricated floor slab is hoisted by using a steel wire rope, so that the hooks are easily moved out of the circular grooves, the contact area between the hooks and the circular grooves is reduced, and the falling risk when the prefabricated floor slab is hoisted is increased; the invention has the following specific structure:
A building material lifting device, comprising a lifting device; the hoisting equipment comprises a hanger; steel cables are connected to the four right-angle sides of the hanger; one end of the steel cable, which is far away from the hanger, is arranged on a lifting hook of the crane, and the lifting device is used for lifting plate building materials;
the hanging bracket is shaped like a Chinese character kou; a vertical beam is fixedly arranged in the middle of the hanging bracket; two sides of the vertical beam are provided with two cross beams which are fixedly arranged on the hanging frame;
The two sides of the four cross beams are respectively provided with a pulling plate, and the bottoms of the pulling plates extend to the lower part of the hanging bracket; the top positions of the pull plates on the two sides of the cross beam are connected through a connecting shaft;
The bottom of the pulling plate is fixedly connected with a hanging plate; two groups of hoisting components are arranged at the positions of the bottom of the hanging plate, which are positioned on two sides of the hanging plate; the hoisting assembly comprises two mounting plates; two rotating shafts are rotatably connected between the two mounting plates;
The two rotating shafts are fixedly connected with first gears, and the two first gears are meshed with each other; the end faces of the two sides, close to the two mounting plates, of the two first gears are fixedly connected with side plates;
A boom is fixedly connected to one side of the two side plates on the two first gears, which are opposite to each other; the end faces of one side of the two suspenders, which are opposite, are fixedly connected with first springs, the other ends of the first springs are fixedly connected to the bottom of the suspending board, and the initial state of the suspenders is vertically downward;
A chute is formed in the suspender; the T-shaped rod is connected in a sliding manner in the sliding groove, and cannot slide out of the sliding groove; the T-shaped rod is fixedly connected with a second spring, and the other end of the second spring is fixedly connected in the chute; the second spring is contracted in the initial state, and the T-shaped rod part extends out of the hanging rod;
A cross rod is fixedly connected with two opposite T-shaped rods on the two hoisting assemblies; two hooks are arranged on the cross rod.
Preferably, the four cross beams are fixedly connected with a sliding table; the top surface of the sliding table is V-shaped;
The connecting shaft is rotationally connected with the pull plate and is positioned at the lowest part of the sliding table in an initial state; the two sides of the sliding table are fixedly connected with a stop block;
Preferably, rollers which are uniformly arranged are rotationally connected to the end surfaces of one side of the pull plate, which is close to the cross beam and the sliding table;
preferably, a first slideway is arranged in the middle of the sliding table; two sides of the first slideway are positioned in the inner wall of the sliding table, and second slideways are respectively arranged on the two sides of the first slideway;
The first slideway is connected with a V-shaped plate in a sliding way; the two sides of the V-shaped plate, which are close to the second slideway, are fixedly connected with sliding blocks, and the sliding blocks slide in the second slideway;
The bottom of the V-shaped plate is fixedly connected with a third spring, and the other end of the third spring is fixedly connected to the bottom of the first slideway; the bottom of the V-shaped plate is fixedly connected with a support column, and the support column is positioned at the inner ring of the third spring;
the V-shaped plate is flush with the upper surface of the sliding table under the action of the third spring in the initial state of the sliding block, and the supporting column is not contacted with the bottom of the first sliding way.
Preferably, the bottom of the hanging plate is fixedly connected with two arc-shaped rods;
the arc rods pass through the two suspenders on the two hoisting assemblies and are connected with the suspenders in a sliding manner, and the suspenders rotate along the arc rods when rotating; the arc-shaped rod penetrates through the first spring inner ring;
preferably, a second gear is rotatably connected in the inner wall of the hanging plate above the first gear through a rotating rod, and the second gear is meshed with the first gear below; and a coil spring is arranged on the rotating rod of the second gear.
Preferably, the cross rod is connected with two lantern rings in a sliding way; the hook rotates on the lantern ring;
preferably, the opposite sides of the two collars on each cross bar are fixedly connected with a fourth spring.
The beneficial effects of the invention are as follows:
1. according to the building material hoisting equipment, the first spring and the second spring can drive the hanging rod and the T-shaped rod to recover the initial state, so that the hanging hook can be clamped in the circular groove of the precast floor slab, the conventional phenomenon that the hanging hook is driven to move in the circular groove when the precast floor slab is hoisted by using the steel wire rope can be avoided, the hanging hook is easily moved out of the circular groove, the contact area between the hanging hook and the circular groove is reduced, the risk of falling when the precast floor slab is hoisted is increased, meanwhile, the hanging hook is not required to be limited by a human hand, the condition of clamping is avoided, meanwhile, due to the fact that the two first gears which are close to each other are meshed with each other, when the hanging rod rotates, the adjacent hanging rods are driven to rotate by the same angle, so that the adjacent hanging rods and the precast floor slab form an isosceles triangle, the stability of the hoisted precast floor slab can be improved, the condition that the hoisted precast floor slab is prevented from inclining can be avoided, and the winding condition between the conventional steel wire ropes can be avoided.
2. According to the building material hoisting equipment, the movable hanging plate and the hoisting assembly are arranged, so that the positions of the hanging plate and the hoisting assembly can be adjusted according to the positions of the precast floor slabs, the hoisting assembly is ensured to be positioned right above the precast floor slabs, and the situation that when the precast floor slabs are hoisted by using the steel wire ropes in the prior art, if the hooks are not positioned right above the precast floor slabs, one sides of the steel wire ropes are in a tensioning state, and the other sides of the steel wire ropes are in a loosening state is avoided, and when the precast floor slabs are hoisted, hooks on the steel wire ropes in the loosening state slide in circular grooves of the precast floor slabs, and even are separated from the circular grooves of the precast floor slabs.
Drawings
The invention is further described below with reference to the accompanying drawings.
FIG. 1 is a perspective view of a lifting apparatus of the present invention;
FIG. 2 is a perspective view of another view of the lifting device of the present invention;
FIG. 3 is an exploded view of the hoisting apparatus of the present invention;
FIG. 4 is an enlarged view of a portion of FIG. 3A in accordance with the present invention;
FIG. 5 is an enlarged view of a portion of the invention at B in FIG. 3;
FIG. 6 is a side view of the lifting apparatus of the present invention;
FIG. 7 is a stepped cross-sectional view at C-C of FIG. 6 in accordance with the present invention;
FIG. 8 is an enlarged view of a portion of the invention at D in FIG. 7;
Fig. 9 is an enlarged view of a portion of fig. 7 at E in accordance with the present invention.
In the figure: 1. a hanging bracket; 11. a wire rope; 12. a lifting hook; 13. a vertical beam; 14. a cross beam; 2. pulling a plate; 21. a connecting shaft; 22. a sliding table; 23. a first slideway; 24. a second slideway; 25. v-shaped plates; 26. a slide block; 27. a third spring; 28. a support column; 3. a hanger plate; 31. a mounting plate; 32. a rotating shaft; 33. a first gear; 331. a second gear; 34. a side plate; 35. a boom; 351. an arc-shaped rod; 36. a first spring; 37. a T-shaped rod; 38. a second spring; 4. a cross bar; 41. a hook; 42. a collar; 43. and a fourth spring.
Detailed Description
The invention is further described in connection with the following detailed description in order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the invention easy to understand.
Embodiment one:
As shown in fig. 1 to 9, a construction material lifting apparatus according to the present invention; comprises hoisting equipment; the hoisting equipment comprises a hanger 1; the four right-angle sides of the hanger 1 are connected with steel cables 11; one end of the steel cable 11, which is far away from the hanger 1, is arranged on a lifting hook 12 of a crane, and lifting equipment is used for lifting plate type building materials;
the hanging bracket 1 is shaped like a Chinese character kou; a vertical beam 13 is fixedly arranged in the middle of the hanging frame 1; two cross beams 14 are arranged on two sides of the vertical beam 13, and the cross beams 14 are fixedly arranged on the hanging frame 1;
the two sides of the four cross beams 14 are respectively provided with a pull plate 2, and the bottoms of the pull plates 2 extend to the lower part of the hanging bracket 1; the top positions of the pull plates 2 on the two sides of the cross beam 14 are connected through a connecting shaft 21;
The bottom of the pulling plate 2 is fixedly connected with a hanging plate 3; two groups of hoisting components are arranged at the bottom of the hanging plate 3 and positioned at two sides of the hanging plate 3; the hoisting assembly comprises two mounting plates 31; two rotating shafts 32 are rotatably connected between the two mounting plates 31;
The two rotating shafts 32 are fixedly connected with first gears 33, and the two first gears 33 are meshed with each other; the two side plates 34 are fixedly connected to the end surfaces of the two first gears 33, which are close to the two mounting plates 31;
A boom 35 is fixedly connected to one side of the two side plates 34 on the two first gears 33 opposite to each other; the end faces of one side of the two suspenders 35 opposite to each other are fixedly connected with a first spring 36, the other ends of the first springs 36 are fixedly connected to the bottom of the hanger plate 3, and the initial state of the suspenders 35 is vertically downward;
a chute is arranged in the suspender 35; the T-shaped rod 37 is connected in a sliding manner in the sliding groove, and the T-shaped rod 37 cannot slide out of the sliding groove; the T-shaped rod 37 is fixedly connected with a second spring 38, and the other end of the second spring 38 is fixedly connected in the chute; the second spring 38 is contracted in the initial state, and the T-shaped rod 37 extends partially out of the boom 35;
the two opposite T-shaped rods 37 on the two hoisting assemblies are fixedly connected with a cross rod 4 together; two hooks 41 are arranged on the cross rod 4;
Specifically, when the precast floor slab is hoisted, firstly, the lifting hook 12 on the crane is controlled to move to the position above the precast floor slab, at the moment, the lifting hook 12 drives the whole hoisting equipment to move to the position above the precast floor slab through the steel cable 11, then the crane controls the lifting hook 12 to move downwards, so as to drive the hoisting equipment to move downwards, after the hoisting equipment moves downwards to a proper position, workers on two sides of the precast floor slab hold the cross rod 4 to pull the cross rod 4 to two sides of the precast floor slab, in the process of pulling the cross rod 4, the cross rod 4 drives the T-shaped rod 37 to gradually slide out of the sliding chute, meanwhile, the T-shaped rod 37 stretches the second spring 38, in the process of pulling the cross rod 4, the cross rod 4 drives the T-shaped rod 37, the hanging rod 35 and the side plate 34 fixedly connected with the hanging rod 35 to rotate, meanwhile, the side plate 34 drives the first gear 33 and the rotating shaft 32 to rotate, and as the other side of the first spring 36 fixedly connected with the hanging rod 35 is fixedly connected to the bottom of the hanging plate 3, the first spring 36 is extruded in the process of rotating the hanging rod 35, and as the two first gears 33 are meshed at the same time, in the process of rotating the hanging rod 35, the two first gears 33 are simultaneously, the angle of rotation of the cross rod 35 on the two first gears is the same, and the rotation angle of the cross rod 35 is gradually different, when the two sides of the cross rod 4 is pulled, and the cross rod 4 is inserted into the round groove, and the round groove 4, and can be inserted into the round groove;
More specifically, when the hanger 41 is inserted into the circular groove of the precast floor slab, since the T-shaped bar 37 is pulled out from the chute by the cross bar 4, the T-shaped bar 37 has a restoring tendency under the tension of the second spring 38, so that the hanger 41 is caught in the circular groove of the precast floor slab, and simultaneously, since the rotating hanger rod 35 compresses the first spring 36, the first spring 36 wants to restore to an initial state after the hanger 41 is inserted into the circular groove of the precast floor slab, so that the hanger rod 35 is pushed to want to an initial state, so that the hanger 41 can be further caught in the circular groove on the precast floor slab, and then the precast floor slab can be lifted;
Further, when the precast floor slab is lifted, the crane controls the lifting hook 12 to move upwards, the lifting hook 12 which moves upwards drives the lifting frame 1 to move upwards, the lifting frame 1 which moves upwards drives the lifting plate 3 to move upwards through the connecting shaft 21 and the pull plate 2, the lifting plate 3 drives the lifting assembly to move upwards, the precast floor slab is lifted through the hanging rod 35, the T-shaped rod 37, the cross rod 4 and the hanging hook 41 in the lifting assembly moving upwards, the precast floor slab can be lifted more stably because the hanging hook 41 is clamped in the circular groove of the precast floor slab, the condition that the hanging hook 41 moves in the circular groove of the precast floor slab is avoided, and after the precast floor slab is lifted to a set position, the hanging hook 41 is manually taken out from the circular groove of the precast floor slab;
Therefore, the hanger rod 35 and the T-shaped rod 37 can be driven to recover the initial state through the first spring 36 and the second spring 38, so that the hanger rod 41 can be clamped in the circular groove of the precast floor slab, the conventional method for hoisting the precast floor slab by using the steel wire rope can be avoided, the hanger rod 41 can be driven to move in the circular groove, the hanger rod 41 can be easily moved out of the circular groove, the contact area between the hanger rod 41 and the circular groove is reduced, the risk of dropping when the precast floor slab is hoisted is increased, meanwhile, the hanger rod 41 is limited by hands of no people, the condition of clamping is avoided, meanwhile, due to the fact that the two first gears 33 which are close to each other are meshed with each other, when the hanger rod 35 rotates, the adjacent hanger rods 35 and the precast floor slab are driven to rotate by the same angle, the stability of the precast floor slab can be improved when the precast floor slab is hoisted, the condition that the hoisted precast floor slab is inclined is prevented, and meanwhile, the winding condition between the conventional steel wire rope can be avoided.
Embodiment two:
The four cross beams 14 are fixedly connected with sliding tables 22; the top surface of the sliding table 22 is V-shaped;
the connecting shaft 21 is rotationally connected with the pull plate 2 and is positioned at the lowest part of the sliding table 22 in an initial state; both sides of the sliding table 22 are fixedly connected with a stop block;
in the embodiment, rollers which are uniformly arranged are rotationally connected to the end face of one side of the pull plate 2, which is close to the cross beam 14 and the sliding table 22;
in this embodiment, a first slideway 23 is provided in the middle of the sliding table 22; the two sides of the first slideway 23 are positioned in the inner wall of the sliding table 22 and are respectively provided with a second slideway 24;
The first slideway 23 is slidably connected with a V-shaped plate 25; the two sides of the V-shaped plate 25, which are close to the second slideway 24, are fixedly connected with sliding blocks 26, and the sliding blocks 26 slide in the second slideway 24;
The bottom of the V-shaped plate 25 is fixedly connected with a third spring 27, and the other end of the third spring 27 is fixedly connected with the bottom of the first slideway 23; the bottom of the V-shaped plate 25 is fixedly connected with a support column 28, and the support column 28 is positioned at the inner ring of the third spring 27;
the V-shaped plate 25 and the sliding block 26 are flush with the upper surface of the sliding table 22 under the action of the third spring 27 in the initial state, and the supporting column 28 is not contacted with the bottom of the first sliding way 23;
When the precast floor slab is lifted by using the steel wire rope and the hook 41, if the hook 41 on the crane is not moved to the position right above the precast floor slab, the hook 41 is at a different distance from two sides of the precast floor slab, so that the steel wire rope is required to be manually pulled to move to the side far away from the precast floor slab, at the moment, the steel wire rope and the hook 12 on the crane are inclined to the side far away from the precast floor slab, when the hook 41 is pulled to the side far away from the hook 41, the hook 41 is gradually restored to the vertical state under the self gravity after being inserted into the round groove of the precast floor slab, so that the steel wire rope inserted into one side of the round groove of the precast floor slab is tensioned, and after the steel wire rope is tensioned, the hook 12 on the crane is still in an inclined state, and then the steel wire rope and the hook 41 on the side near to the precast floor slab are pulled again and are inserted into the round groove on the other side of the precast floor slab, at the moment, and the hook 41 on the side near to the precast floor slab is in a loose state, so that the hook 41 on the loose state can slide in the round groove of the precast floor slab and even get out of the round groove of the precast floor slab;
Specifically, when the hoisting device moves to the position right above the precast floor slab, if the hoisting device is not located at the position right above the precast floor slab, the cross rod 4 can be pulled to the side far away from the hoisting device, in the moving process of the cross rod 4, the hanging rod 35, the mounting plate 31 and the hanging plate 3 can be driven to move, in the moving process of the hanging plate 3, the hanging plate 2 can be driven to move along the cross beam 14 and the sliding table 22, as the balls rotate on the hanging plate 2, the friction force of the hanging plate 2 when moving along the cross beam 14 and the sliding table 22 can be reduced, meanwhile, the connecting shaft 21 can rotate on the sliding table 22 along with the moving of the hanging plate 2, when the hanging plate 3 moves to the position right above the precast floor slab, the hanging rods 35 at the two sides are just located at the positions of round grooves at the two sides of the precast floor slab, then the hanging hooks 41 are inserted into the round grooves at the two sides of the precast floor slab, and after the hanging hooks 41 at the two sides of the precast floor slab are inserted into the round grooves at the moment, the hanging hooks 41 are limited in the round grooves of the precast floor slab, and then the precast floor slab can be hung;
More specifically, when the prefabricated floor slab is lifted, the connecting shaft 21 rotates to the lowest position on the sliding table 22, so that the pull plate 2, the lifting plate 3 and the lifting assembly are driven to move, when the connecting shaft 21 moves to the lower position of the sliding table 22, the connecting shaft 21 is positioned on the V-shaped plate 25, and after the connecting shaft 21 is positioned on the V-shaped plate 25, the V-shaped plate 25 is pressed downwards, so that the V-shaped plate 25 slides downwards in the first sliding way 23, the third spring 27 is compressed, the V-shaped plate 25 drives the sliding block 26 to slide downwards in the second sliding way 24, when the support column 28 fixedly connected with the bottom of the V-shaped plate 25 is attached to the bottom of the first sliding way, the V-shaped plate 25 is not moved downwards, and meanwhile, the connecting shaft 21 is limited in the first sliding way 23, and in the process, the connecting shaft 21 can be prevented from moving on the sliding table 22 when the prefabricated floor slab is lifted, so that the lifting assembly and the prefabricated floor slab are driven to shake;
Further, when the precast floor slab is taken down from the hoisting assembly, the precast floor slab does not bear the weight of the precast floor slab, so that the third spring 27 pushes the V-shaped plate 25 to move upwards and restore to a state of being flush with the surface of the sliding table 22, and the connecting shaft 21 is located above the V-shaped plate 25, and then the next precast floor slab can be hoisted;
In this process, through setting up hanger plate 3 and the hoist and mount subassembly that can remove to can be according to the position adjustment hanger plate 3 of precast floor and hoist and mount subassembly's position, ensure that hoist and mount subassembly is in the precast floor directly over, thereby avoid utilizing wire rope to hoist to precast floor among the prior art, when lifting hook 12 is not in the precast floor directly over, can lead to wire rope one side to be in taut state one side and be in the relaxation state, when lifting to precast floor, the couple 41 on the wire rope of relaxation state can slide in precast floor's circular slot, appears breaking away from precast floor circular slot even.
Embodiment III:
The bottom of the hanger plate 3 is fixedly connected with two arc rods 351;
The arc rods 351 pass through the two suspenders 35 on the two hoisting assemblies and are connected with the suspenders 35 in a sliding manner, and the suspenders 35 rotate along the arc rods 351 when rotating; the arc-shaped rod 351 passes through the inner ring of the first spring 36;
in the present embodiment, a second gear 331 is rotatably connected to the inner wall of the hanger plate 3 above the first gear 33 through a rotating rod, and the second gear 331 is meshed with the first gear 33 below; a coil spring is arranged on the rotating rod of the second gear 331;
Specifically, the arc rod 351 passes through the boom 35 and is in sliding connection with the boom 35, so that the arc rod 351 can rotate along the arc rod 351 in the rotation process of the boom 35, thereby limiting the boom 35 and avoiding the condition that the boom 35 shakes in the rotation process;
more specifically, because the first gear 33 is meshed with the second gear 331, and the coil spring is installed on the rotating rod of the second gear 331, the second gear 331 is driven to rotate in the process of rotating the first gear 33, the coil spring is gradually tightened when the second gear 331 rotates, so after the hook 41 is inserted into the circular groove of the precast floor slab, the coil spring wants to drive the second gear 331 to restore, the second gear 331 wants to drive the first gear 33 to restore, and the first gear 33 wants to drive the hanging rod 35 to restore, so that the force of the hook 41 clamped in the circular groove of the precast floor slab can be increased, and the precast floor slab can be better lifted.
Embodiment four:
Two lantern rings 42 are connected to the cross rod 4 in a sliding manner; the hook 41 rotates on the collar 42;
in this embodiment, a fourth spring 43 is fixedly connected to opposite sides of the two collars 42 on each cross bar 4;
Specifically, in the process of inserting the hooks 41 into the circular grooves of the precast floor slabs, at this time, the two lantern rings 42 are manually controlled to move to the opposite sides, the fourth springs 43 are elongated in the process of moving the two lantern rings 42, when the hooks 41 are opposite to the circular grooves on the precast floor slabs, the hooks 41 are inserted into the circular grooves, and the fourth springs 43 are in the elongated state, so that the hooks 41 want to drive the lantern rings 42 and the hooks 41 to restore to the original state, and because the hooks 41 are already inserted into the circular grooves of the precast floor slabs, the two hooks 41 can be clamped in the circular grooves of the precast floor slabs, so that the effect of clamping the hooks 41 in the circular grooves of the precast floor slabs can be further improved, and the precast floor slabs can be well hoisted.
The foregoing has shown and described the basic principles, principal features and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present invention, and various changes and modifications may be made without departing from the spirit and scope of the invention, which is defined in the appended claims. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (4)
1. A building material hoisting device, comprising a hanger (1); steel cables (11) are connected to the four right-angle edges of the hanging bracket (1); one end of the steel cable (11) far away from the hanger (1) is arranged on a lifting hook (12) of the crane, and the lifting equipment is used for lifting plate building materials;
The hanger is characterized in that the hanger (1) is shaped like a Chinese character kou; a vertical beam (13) is fixedly arranged in the middle of the hanging bracket (1); two sides of the vertical beam (13) are provided with two cross beams (14), and the cross beams (14) are fixedly arranged on the hanging frame (1);
The two sides of the four cross beams (14) are respectively provided with a pulling plate (2), and the bottoms of the pulling plates (2) extend to the lower part of the hanging bracket (1); the top positions of the pull plates (2) on two sides of the cross beam (14) are connected through a connecting shaft (21);
The bottom of the pulling plate (2) is fixedly connected with a hanging plate (3); two groups of hoisting components are arranged at the bottom of the hanging plate (3) and positioned at the two sides of the hanging plate (3); the hoisting assembly comprises two mounting plates (31); two rotating shafts (32) are rotatably connected between the two mounting plates (31);
The two rotating shafts (32) are fixedly connected with first gears (33), and the two first gears (33) are meshed with each other; two side plates (34) are fixedly connected to the end surfaces of the two sides of the first gears (33) close to the two mounting plates (31);
A boom (35) is fixedly connected with one side of the two side plates (34) on the two first gears (33) opposite to each other; the end faces of one side of the two hanging rods (35) opposite to each other are fixedly connected with first springs (36), the other ends of the first springs (36) are fixedly connected to the bottom of the hanging plate (3), and the initial state of the hanging rods (35) is vertically downward;
a chute is formed in the suspender (35); a T-shaped rod (37) is connected in a sliding manner in the sliding groove, and the T-shaped rod (37) cannot slide out of the sliding groove; a second spring (38) is fixedly connected to the T-shaped rod (37), and the other end of the second spring (38) is fixedly connected to the inside of the chute; the second spring (38) is contracted in the initial state, and the T-shaped rod (37) extends out of the hanging rod (35) partially;
A cross rod (4) is fixedly connected to two opposite T-shaped rods (37) on the two hoisting assemblies; two hooks (41) are arranged on the cross rod (4);
the four cross beams (14) are fixedly connected with sliding tables (22); the top surface of the sliding table (22) is V-shaped;
the connecting shaft (21) is rotationally connected with the pull plate (2), and is positioned at the lowest position of the sliding table (22) in an initial state; both sides of the sliding table (22) are fixedly connected with stop blocks;
the end face of one side of the pull plate (2) close to the cross beam (14) and the sliding table (22) is rotationally connected with rollers which are uniformly arranged;
A first slideway (23) is arranged in the middle of the sliding table (22); two sides of the first slideway (23) are positioned in the inner wall of the sliding table (22) and are provided with second slideways (24);
The first slideway (23) is connected with a V-shaped plate (25) in a sliding way; the two sides of the V-shaped plate (25) close to the second slide way (24) are fixedly connected with sliding blocks (26), and the sliding blocks (26) slide in the second slide way (24);
a third spring (27) is fixedly connected to the bottom of the V-shaped plate (25), and the other end of the third spring (27) is fixedly connected to the bottom of the first slideway (23); the bottom of the V-shaped plate (25) is fixedly connected with a support column (28), and the support column (28) is positioned at the inner ring of the third spring (27);
the V-shaped plate (25) is flush with the upper surface of the sliding table (22) under the action of a third spring (27) in the initial state of the sliding block (26), and the supporting column (28) is not contacted with the bottom of the first sliding way (23);
the bottom of the hanging plate (3) is fixedly connected with two arc rods (351);
The arc rods (351) pass through two suspenders (35) on the two hoisting assemblies and are in sliding connection with the suspenders (35), and the suspenders (35) rotate along the arc rods (351) when rotating; the arc-shaped rod (351) penetrates through the inner ring of the first spring (36).
2. A building material lifting device according to claim 1, characterized in that: a second gear (331) is rotatably connected in the inner wall of the hanging plate (3) above the first gear (33) through a rotating rod, and the second gear (331) is meshed with the first gear (33) below; a coil spring is arranged on the rotating rod of the second gear (331).
3. A building material lifting device according to claim 2, characterized in that: two lantern rings (42) are connected to the cross rod (4) in a sliding manner; the hook (41) is rotated on the collar (42).
4. A building material lifting device according to claim 3, wherein: a fourth spring (43) is fixedly connected to the opposite sides of the two lantern rings (42) on each cross rod (4) together.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410761001.1A CN118324007B (en) | 2024-06-13 | 2024-06-13 | Building material lifting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410761001.1A CN118324007B (en) | 2024-06-13 | 2024-06-13 | Building material lifting device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN118324007A CN118324007A (en) | 2024-07-12 |
CN118324007B true CN118324007B (en) | 2024-08-16 |
Family
ID=91766415
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202410761001.1A Active CN118324007B (en) | 2024-06-13 | 2024-06-13 | Building material lifting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN118324007B (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113089894A (en) * | 2021-04-28 | 2021-07-09 | 江苏建科工程咨询有限公司 | Method for installing prefabricated wall board of prefabricated building |
CN113443568A (en) * | 2021-05-11 | 2021-09-28 | 余北京 | Building construction crane |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07323989A (en) * | 1994-06-02 | 1995-12-12 | Yamakawa Eng Kk | Balancing device for crane work |
CN110342393B (en) * | 2019-08-02 | 2021-05-07 | 广东广桥重工有限公司 | Steel plate hoisting clamp in steel structure assembly |
WO2021203303A1 (en) * | 2020-04-08 | 2021-10-14 | 苗林展 | Novel container hoisting apparatus |
CN214326872U (en) * | 2020-11-30 | 2021-10-01 | 中国建筑第七工程局有限公司 | Hoist device for construction |
CN115285828B (en) * | 2022-02-11 | 2024-08-16 | 武昌工学院 | Hoisting system of assembled building |
CN115028054B (en) * | 2022-08-11 | 2022-11-11 | 湖南鹏翔星通汽车有限公司 | Hanging equipment for constructional engineering |
CN220664718U (en) * | 2023-05-26 | 2024-03-26 | 辽宁锦烨装饰装修有限公司 | Limiting protective type construction engineering crane |
CN117585569A (en) * | 2023-10-23 | 2024-02-23 | 中交建筑集团有限公司 | Lifting appliance and lifting method for prefabricated part of assembled building |
CN117303196A (en) * | 2023-11-14 | 2023-12-29 | 安徽协瑞电气工程有限公司 | Lifting equipment for building construction |
-
2024
- 2024-06-13 CN CN202410761001.1A patent/CN118324007B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113089894A (en) * | 2021-04-28 | 2021-07-09 | 江苏建科工程咨询有限公司 | Method for installing prefabricated wall board of prefabricated building |
CN113443568A (en) * | 2021-05-11 | 2021-09-28 | 余北京 | Building construction crane |
Also Published As
Publication number | Publication date |
---|---|
CN118324007A (en) | 2024-07-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4606527A (en) | Theatre scenery hoisting mechanism | |
CN114314307B (en) | Concrete prefabricated part hoisting equipment with multipoint fixing function | |
CN118324007B (en) | Building material lifting device | |
US6357810B1 (en) | Hoist assembly | |
CN114620593A (en) | Hoisting clamp | |
JPWO2020035930A1 (en) | How to extend the lift of a construction elevator and a rope unloading jig for an elevator | |
AU2004209463B2 (en) | Hoist for construction material | |
CN213622880U (en) | Hoisting and demolding equipment for manufacturing prefabricated laminated slab | |
CN211201155U (en) | Movable track hoisting device | |
CN112047250A (en) | Lifting device for constructional engineering | |
CN221165726U (en) | House construction lifting device | |
CN220116020U (en) | Overhead layer prefabricated plate hoisting tool | |
CN217676575U (en) | Mounting support and hanger for aerated concrete batten | |
CN112813838B (en) | Integral concrete vibrating device for viaduct pier body and construction method thereof | |
CN218320524U (en) | Hoisting tool for building steel structure | |
CN217972381U (en) | Pulley assembly of hoister | |
CN117819369B (en) | Crane for building construction | |
CN220056040U (en) | Hoisting device for prefabricated T beam | |
CN220432049U (en) | Building lifting equipment | |
CN219546454U (en) | Hoisting device for H steel production | |
JP3029500B2 (en) | All-weather building automatic construction method | |
CN118205999B (en) | Automobile crane for hoisting precast slabs | |
CN219823585U (en) | Lifting type construction platform for house construction engineering | |
CN221370274U (en) | Prefabricated component hoist | |
CN117088236B (en) | Steel construction lifting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |