CN115030510A - Construction method for improving pouring quality of self-compacting concrete of CL board wall - Google Patents

Construction method for improving pouring quality of self-compacting concrete of CL board wall Download PDF

Info

Publication number
CN115030510A
CN115030510A CN202210741949.1A CN202210741949A CN115030510A CN 115030510 A CN115030510 A CN 115030510A CN 202210741949 A CN202210741949 A CN 202210741949A CN 115030510 A CN115030510 A CN 115030510A
Authority
CN
China
Prior art keywords
pouring
concrete
self
board wall
steps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210741949.1A
Other languages
Chinese (zh)
Inventor
徐超
王志敏
周叙伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202210741949.1A priority Critical patent/CN115030510A/en
Publication of CN115030510A publication Critical patent/CN115030510A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a construction method for improving the pouring quality of self-compacting concrete of a CL board wall, which comprises the following steps: manufacturing a template; pouring concrete; carrying out an exhaust operation; carrying out plugging operation; continuously pouring concrete, and repeating the steps; and (5) removing the template and carrying out concrete curing. The invention effectively solves the problems of construction quality, increased cost and labor cost and potential safety hazard in the prior art, and eliminates bubbles generated in the process of pouring self-compacting concrete by reserving vent holes at corresponding positions of the formwork in the process of supporting the CL board wall formwork and then determining the pouring sequence and matching with an auxiliary vibrating method, and the vent holes are blocked and continuously poured by a device for blocking the reserved vent holes. The problem of CL siding wall surface crack and easy aversion is solved, reduce the secondary treatment construction, reduce expense and cost of labor improve construction quality and security.

Description

Construction method for improving pouring quality of self-compacting concrete of CL board wall
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a construction method for improving the pouring quality of self-compacting concrete of a CL board wall.
Background
CL integration heated board presss from both sides behind the heated board by two-layer steel wire welding net with the rack that the three-dimensional oblique steel wire welding formed, together with major structure wall post reinforcement, prop up the wall body that forms in an organic whole that holds in force concurrently, keeps warm after establishing template concreting, forms after the inside and outside both sides concreting, and the outside is self-compaction concrete, and the inboard is ordinary concrete. CL plates are generally formed in a factory. The concrete layer tightly wraps and seals the heat-insulating layer, and the long-term protection effect is achieved.
Because CL siding wall leans on the oblique web muscle to fix, the vibrations stick can't stretch into in the wall, leads to unable adoption ordinary concrete to pour, can only adopt self-compaction concrete placement. Because the self-compacting concrete is in a flowing state and has large slump, slurry leakage can occur along the joint of the template and the joint of the upper layer and the lower layer in the pouring process, so that the slurry leakage of the lower layer of the outer wall surface is serious after pouring. On the other hand, the self-compacting concrete does not use a vibration rod, so that the gas cannot be completely discharged, and the poured outer wall surface forms a large-area honeycomb pitted surface, a cavity and the like. And secondary treatment is needed in the later period, so that the cost is increased, and the potential safety hazard during the secondary treatment is increased.
At present, some projects under construction adopt a method of hanging a flat plate vibrator on the outer surface of a formwork to vibrate aiming at the problem of complaint. Because there is not the coarse aggregate of big particle diameter in the self-compaction concrete, and the aggregate of self-compaction concrete sinks after the vibration, causes the well upper portion aggregate of wall less, because of heated board outside concrete thickness only is 5cm, and is thinner, leads to pouring the completion after, the surface of CL outer wall forms great crack easily. Rainwater (especially in an offshore area with high salt content of rainwater) enters the wall body through the crack and corrodes the reinforcing steel bars of the CL wallboard.
In addition, the plastic fixing buckle of the CL board wall is inaccurate in positioning and is not firmly connected with the shear wall, so that the CL board wall is easy to displace due to the influence of lateral pressure, buoyancy and the like during pouring in the concrete pouring process, only one layer of laitance is arranged on the outer surface of the local CL board wall after the concrete pouring is finished, a protective layer is not arranged, and even the reinforcing mesh is directly exposed outside.
In summary, the problems of the prior art are:
(1) the outer surface of the CL board wall is easy to form large cracks and is easy to be invaded by rainwater, so that the steel bar is corroded, and the construction quality problem is caused;
(2) CL board walls are easy to displace, and a protective layer is lacked after concrete pouring is finished, so that the construction quality and the safety are caused;
(3) the outer wall surface needs to be subjected to secondary treatment after pouring, so that the cost and labor cost are increased, and potential safety hazards are caused.
Disclosure of Invention
The invention aims to solve the problems that (1) in the prior art, large cracks are easily formed on the outer surface of a CL board wall, the CL board wall is easily invaded by rainwater, the reinforcing steel bar is corroded, and the construction quality problem is caused; (2) the CL board wall is easy to shift, and a protective layer is lacked after concrete pouring is finished, so that the construction quality and safety problems are caused; (3) the invention provides a construction method for improving the pouring quality of self-compacting concrete of a CL board wall, which solves the problems that after pouring, the outer wall surface needs to be subjected to secondary treatment, the cost and the labor cost are increased, and potential safety hazards are caused. By the construction method, the problem that the outer wall surface forms a large-area honeycomb pitted surface and a cavity after pouring due to the fact that gas cannot be completely removed is solved, the problems that cracks and displacement are easy to occur on the outer surface of the CL board wall are solved, secondary treatment construction is reduced, cost and labor cost are reduced, and construction quality and safety are improved.
In order to solve the technical problems, the invention adopts the technical scheme that:
a construction method for improving the pouring quality of self-compacting concrete of a CL board wall comprises the following steps:
manufacturing a template;
pouring concrete;
carrying out an exhaust operation;
carrying out plugging operation;
continuously pouring concrete, and repeating the steps;
and (5) removing the template and carrying out concrete curing.
And (5) pouring construction is carried out, and after the construction is finished, mold plugging is carried out.
Further, before the step of making the template, the method also comprises the following steps: and reserving exhaust holes in the pouring wall body.
Furthermore, the exhaust hole is located in the middle of the pouring wall body.
Further, in the concrete pouring step, the height difference of the concrete grout surfaces on the two sides is less than 400 mm.
Further, in the step of performing the air discharging operation, air is discharged by using a hammer tamping method.
Further, in the step of performing the plugging operation, the diameter of the plugging device is larger than that of the vent hole.
Further, the diameter difference between the diameter of the plugging device and the diameter of the vent hole is 1 cm.
The invention discloses a construction method for improving the pouring quality of self-compacting concrete of a CL board wall, which is characterized in that vent holes are reserved at corresponding positions of a template in the supporting process of the CL board wall template, then the pouring sequence is determined and an auxiliary vibrating method is matched, bubbles generated in the pouring process of the self-compacting concrete are eliminated, and the vent holes are blocked by a device for blocking the reserved vent holes for continuous pouring. By the construction method, the problem that the outer wall surface forms a large-area honeycomb pitted surface and a cavity after pouring due to the fact that gas cannot be completely removed is solved, the problems that cracks and displacement are easy to occur on the outer surface of the CL board wall are solved, secondary treatment construction is reduced, cost and labor cost are reduced, and construction quality and safety are improved.
According to the invention, through exhaust matching with CL board wall self-compacting concrete pouring construction, the quality problems that gas cannot be completely discharged due to the fact that the self-compacting concrete does not use a vibration rod, and a large-area honeycomb pitted surface and a cavity are formed on the outer wall surface after pouring are solved, the CL board wall self-compacting concrete pouring construction quality is improved, the construction is simple, the operation is convenient, and the construction period is saved.
Drawings
FIG. 1 is a schematic illustration of concrete placement locations and sequence according to one embodiment of the present invention;
FIG. 2 is a schematic view of a vent blocking device according to an embodiment of the present invention;
fig. 3 is a schematic view of the installation of the vent hole plugging device according to an embodiment of the present invention.
In the figure: 1-a first steel plate, 2-a second steel plate, 3-a connecting section, 4-a fixing bolt and 5-an exhaust hole.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are illustrative and intended to be illustrative of the invention and are not to be construed as limiting the invention.
Referring to fig. 1 to fig. 3, an embodiment of the present invention provides a construction method for improving a pouring quality of a self-compacting concrete of a CL panel wall, including the steps of:
manufacturing a template;
pouring concrete;
carrying out an exhaust operation;
carrying out plugging operation;
continuously pouring concrete, and repeating the steps;
and (5) removing the template and carrying out concrete curing.
Specifically, A, B, C, D in fig. 1 is the casting sequence. And pouring according to the sequence of A-D.
Specifically, the plugging device is manufactured before the template is manufactured, and the plugging device is formed by combining a first steel plate 1, a second steel plate 2, a connecting section 3 and a fixing bolt 4. The first steel plate 1 is a steel plate with the thickness of 1mm, the height of 10cm and the width of 8 cm; the second steel plate 2 is a steel plate with the thickness of 1mm, the height of 10cm and the width of 4 cm; the second steel plate 2 is stretched through the connecting section 3, so that the second steel plate can conveniently go deep into the inner side of the template from the outer side and is fixed; the length of the fixing bolt 4 is 10cm, and the fixing bolt is used for fixing when the exhaust hole 5 is plugged.
Specifically, the method further comprises the following steps before the step of manufacturing the template: and an exhaust hole 5 is reserved in the pouring wall body.
Preferably, the vent 5 is located in the middle of the cast wall.
Preferably, the size of the vent 5 is 10cm x 8 cm.
Preferably, in the concrete pouring step, the height difference of the concrete grout surfaces on the two sides is less than 400 mm.
Specifically, in the step of performing the air discharging operation, air is discharged by using a hammer tamping method. Specifically, during air exhaust, the leather hammer vibrates from bottom to top along with the pouring of concrete, vibration is assisted, and air is exhausted as soon as possible.
Specifically, in the step of performing the plugging operation, the diameter of the plugging device is larger than the diameter of the vent hole 5.
Preferably, the diameter of the blocking means differs from the diameter of the vent 5 by 1 cm.
Specifically, when concrete is poured to the position of the exhaust hole 5, the exhaust hole blocking device is used for blocking, and the second steel plate 2 is stretched to the position of the first steel plate 1 to enable the length to be 8cm and the height to be 10 cm. And (4) holding a fixing bolt 4 by hand, stretching into the inner side of the wood board from the outer side of the template for plugging, stretching the second steel plate 2 after stretching into the template, wherein the relative distance of the bolt position is 12cm, and the bolt position is consistent with the bolt fixing position on the template. The fixing position of the fixing bolt 4 is shown in fig. 3, and the fixing bolt 4 is tightened to be fixed. After the plugging device is unfolded, the diameters of the periphery of the plugging device are larger than the diameters of the exhaust holes 5, the difference value is 1cm, and concrete pouring leakage is prevented.
The invention has the advantages and beneficial effects that:
the invention discloses a construction method for improving the pouring quality of self-compacting concrete of a CL board wall. By the construction method, the problem that the outer wall surface forms a large-area honeycomb pitted surface and a cavity after pouring due to the fact that gas cannot be completely removed is solved, the problems that cracks and displacement are easy to occur on the outer surface of the CL board wall are solved, secondary treatment construction is reduced, cost and labor cost are reduced, and construction quality and safety are improved.
According to the invention, through exhaust matching with CL board wall self-compacting concrete pouring construction, the quality problems that gas cannot be completely discharged due to the fact that the self-compacting concrete does not use a vibration rod, and a large-area honeycomb pitted surface and a cavity are formed on the outer wall surface after pouring are solved, the CL board wall self-compacting concrete pouring construction quality is improved, the construction is simple, the operation is convenient, and the construction period is saved.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundary of the appended claims, or the equivalents of such scope and boundary.

Claims (7)

1. A construction method for improving the pouring quality of self-compacting concrete of a CL board wall is characterized by comprising the following steps:
manufacturing a template;
pouring concrete;
carrying out an exhaust operation;
carrying out plugging operation;
continuously pouring concrete, and repeating the steps;
and (5) removing the template and carrying out concrete curing.
2. The method for improving the pouring quality of the self-compacting concrete of the CL board wall according to claim 1, wherein the method comprises the following steps:
before the step of manufacturing the template, the method also comprises the following steps: and reserving exhaust holes in the pouring wall body.
3. The method for improving the pouring quality of the self-compacting concrete of the CL board wall according to claim 2, wherein the method comprises the following steps:
the exhaust hole is located in the middle of the pouring wall body.
4. The method for improving the pouring quality of the self-compacting concrete of the CL board wall according to claim 1, wherein the method comprises the following steps:
in the concrete pouring step, the height difference of the concrete grout surfaces on the two sides is less than 400 mm.
5. The method for improving the pouring quality of the self-compacting concrete for the CL board wall as claimed in claim 1, wherein the method comprises the following steps:
in the step of performing the air discharging operation, air is discharged by using a leather hammer tamping mode.
6. The method for improving the pouring quality of the self-compacting concrete for the CL board wall according to any one of claims 2 to 5, wherein the method comprises the following steps:
in the step of plugging operation, the diameter of the plugging device is larger than that of the vent hole.
7. The method for improving the pouring quality of the self-compacting concrete of the CL board wall as claimed in claim 6, wherein the method comprises the following steps:
the diameter difference between the plugging device and the vent hole is 1 cm.
CN202210741949.1A 2022-06-28 2022-06-28 Construction method for improving pouring quality of self-compacting concrete of CL board wall Pending CN115030510A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210741949.1A CN115030510A (en) 2022-06-28 2022-06-28 Construction method for improving pouring quality of self-compacting concrete of CL board wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210741949.1A CN115030510A (en) 2022-06-28 2022-06-28 Construction method for improving pouring quality of self-compacting concrete of CL board wall

Publications (1)

Publication Number Publication Date
CN115030510A true CN115030510A (en) 2022-09-09

Family

ID=83126357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210741949.1A Pending CN115030510A (en) 2022-06-28 2022-06-28 Construction method for improving pouring quality of self-compacting concrete of CL board wall

Country Status (1)

Country Link
CN (1) CN115030510A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2221119C1 (en) * 2002-07-17 2004-01-10 Баширов Хамит Закирович Laminated panel of ventilated wall fence
CN108505644A (en) * 2018-03-27 2018-09-07 黄河科技学院 CL compound concrete shear wall construction methods
CN110258848A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of building energy conservation CL composite shear wall
CN112359994A (en) * 2020-11-26 2021-02-12 中国十七冶集团有限公司 CL heat preservation system construction method
CN112609986A (en) * 2020-12-11 2021-04-06 上海宝冶集团有限公司 Method for controlling pouring forming quality of concrete batter post

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2221119C1 (en) * 2002-07-17 2004-01-10 Баширов Хамит Закирович Laminated panel of ventilated wall fence
CN108505644A (en) * 2018-03-27 2018-09-07 黄河科技学院 CL compound concrete shear wall construction methods
CN110258848A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of building energy conservation CL composite shear wall
CN112359994A (en) * 2020-11-26 2021-02-12 中国十七冶集团有限公司 CL heat preservation system construction method
CN112609986A (en) * 2020-12-11 2021-04-06 上海宝冶集团有限公司 Method for controlling pouring forming quality of concrete batter post

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
田敬贤 等: "自密实混凝土在CL结构体系中的施工质量控制", 混凝土, no. 6, pages 111 - 112 *

Similar Documents

Publication Publication Date Title
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN107268878A (en) The fabrication and installation method of prefabricated sandwich wallboard
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN102828468B (en) Construction method for controlling prefabricated crack of high-strength thin-walled box girder under high-temperature dry condition
CN111764522A (en) Anti-leakage building floor post-cast strip structure and pouring method
CN106401041A (en) Cast-in-situ concrete construction method for pseudo-classic architecture slope roof
CN111042010A (en) T-beam bridge widening structure and construction method
CN103938767B (en) Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete
CN111734018A (en) Formwork structure, disassembly-free mold and concrete wall construction method
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
JP7008989B2 (en) Assembly structure for roadbed concrete placement, concrete press-fitting device and roadbed concrete placement method
CN111719869A (en) Masonry engineering construction process
CN214329455U (en) Bealock hole cast-in-situ wall structure
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN115030510A (en) Construction method for improving pouring quality of self-compacting concrete of CL board wall
CN108544655A (en) The curved beam prefabricated construction method of curved bridge
CN107859061A (en) A kind of construction method of box culvert primary concreting
CN110259172B (en) Construction method for transforming original precast slab into cast-in-place slab
CN209620240U (en) Between integrally assembling staircase
CN209620278U (en) Concrete anti-bank template structure with can have enough to meet need reinforcing bar inside lining
CN110777635A (en) Side arch rib construction method and side arch rib
CN114274306A (en) Production process of prefabricated steel structure exterior wall cladding
CN113216008A (en) Concrete pouring method for cantilever box girder
CN210134641U (en) Construction structures is pour to concrete link plate secondary under roof beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination