[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN114960545B - Green road system constructed on soft foundation permeable dike and construction method thereof - Google Patents

Green road system constructed on soft foundation permeable dike and construction method thereof Download PDF

Info

Publication number
CN114960545B
CN114960545B CN202210641519.2A CN202210641519A CN114960545B CN 114960545 B CN114960545 B CN 114960545B CN 202210641519 A CN202210641519 A CN 202210641519A CN 114960545 B CN114960545 B CN 114960545B
Authority
CN
China
Prior art keywords
layer
embankment
water
permeable
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210641519.2A
Other languages
Chinese (zh)
Other versions
CN114960545A (en
Inventor
曹书龙
徐成剑
张仲伟
黄晓敏
李钢
蔡玉鹏
张芝玲
胡胜利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN202210641519.2A priority Critical patent/CN114960545B/en
Publication of CN114960545A publication Critical patent/CN114960545A/en
Application granted granted Critical
Publication of CN114960545B publication Critical patent/CN114960545B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

本申请涉及一种构建在软基透水堤梗上的绿道系统及其施工方法,包括绿道,所述绿道的底部设置有土工格栅,所述土工格栅铺设在软基透水堤梗顶部并水平延伸至临水侧生态护坡和背水侧培厚区,在土工格栅的上层铺设有黏土填筑层,黏土填筑层的上层铺设透水沥青混凝土路面,所述绿道的临水侧从软基透水堤梗的顶部到底部依次设置有临水侧生态护坡、多功能抗滑桩、滨岸带以及消浪固脚平台,所述绿道的临水侧从软基透水堤梗的顶部到底部依次设置有背水侧培厚区及压浸平台,在临水侧生态护坡的下方设置有堤身防渗体,本申请在满足防洪保安的基础上,实现了生态亲水、便民交通、水土保持、生态修复、环境保护等多种功能,并节省了工程运行费用。

This application relates to a greenway system built on a soft-foundation permeable embankment stem and a construction method thereof. The top extends horizontally to the ecological slope protection on the water side and the thickening area on the backwater side. A clay filling layer is laid on the upper layer of the geogrid, and a permeable asphalt concrete pavement is laid on the upper layer of the clay filling layer. The water side of the greenway From the top to the bottom of the soft-foundation permeable embankment stem, there are water-side ecological slope protection, multi-functional anti-sliding piles, shore zones and wave-absorbing foot-fixing platforms. The water-facing side of the greenway starts from the soft-foundation permeable embankment stem. There are backwater side thickening areas and pressure soaking platforms in sequence from top to bottom, and an embankment anti-seepage body is installed below the ecological slope protection on the waterside side. On the basis of meeting the requirements of flood control and security, this application achieves ecological hydrophilicity and convenient transportation. , water and soil conservation, ecological restoration, environmental protection and other functions, and save project operation costs.

Description

一种构建在软基透水堤梗上的绿道系统及其施工方法A greenway system built on soft foundation permeable embankment stems and its construction method

技术领域Technical field

本申请涉及生态水利工程技术领域,特别涉及一种构建在软基透水堤梗上的绿道系统及其施工方法。This application relates to the technical field of ecological water conservancy engineering, and in particular to a greenway system constructed on a soft-foundation permeable embankment stem and its construction method.

背景技术Background technique

随着城市建设规模的扩大,城市防洪标准不断提高,对防洪堤在防洪保安、生态亲水、便民交通、水土保持、生态修复、环境保护等方面提出了更高的要求。With the expansion of urban construction scale, urban flood control standards continue to improve, which places higher requirements on flood control embankments in terms of flood control security, ecological water affinity, convenient transportation, soil and water conservation, ecological restoration, and environmental protection.

平原河湖区河堤、湖堤、圩垸堤防大多始建于上世纪50年代,为开发利用河道、湖泊,不断围湖造田而围起,堤基为厚层(3~10m)冲洪积层淤泥质土,堤身为人工挑土填筑而成,填土质量较差,历年汛期险情频发,堤身散浸现象严重,局部堤段出现迎水面浪坎、滑坡和堤防背水侧滑坡的情况。Most of the river embankments, lake embankments and polder embankments in the plain river and lake areas were built in the 1950s. They were built for the development and utilization of rivers and lakes and the continuous reclamation of lakes for farmland. The embankment base is a thick layer (3-10m) of alluvial deposits. The embankment body is made of silt soil and is filled with artificial soil. The fill quality is poor. Dangerous situations have occurred frequently during flood seasons over the years. The embankment body is seriously soaked. Some sections of the embankment have faced wave ridges, landslides and landslides on the backwater side of the embankment. Condition.

对现状河湖软基透水堤防进行加固改造,首先需要确保在施工期及完建后运行中软土基础不出现深层滑动,其次应保证在河湖高水位时堤身能正常挡水,且不出现渗透变形。建设时堤外需尽量避免对水体容积的侵占,堤内需考虑减少征迁;完建后需满足市民交通出行及亲水需求,实现滨水景观与城市阳台的有机融合,使堤防具备防洪保安、生态亲水、便民交通、水土保持、生态修复、环境保护等多种功能。To reinforce and transform the existing soft-foundation permeable embankments of rivers and lakes, it is first necessary to ensure that the soft soil foundation does not slip deep during the construction period and during operation after completion. Secondly, it is necessary to ensure that the embankment body can retain water normally when the water level of rivers and lakes is high, and does not Penetration deformation occurs. During construction, it is necessary to avoid encroaching on water volume outside the embankment, and to reduce land acquisition and relocation inside the embankment. After completion, it is necessary to meet the needs of citizens for transportation and water-related activities, and to achieve an organic integration of waterfront landscape and urban balconies, so that the embankment has flood control, security, and ecological It has multiple functions such as being close to water, convenient transportation, water and soil conservation, ecological restoration, and environmental protection.

一般的堤防软基处理方法有换土垫层法、排水固结法、碎石粒料桩法或水泥土复合地基等,均需对现状土堤进行挖除,堤身扰动大;或在临水侧填筑大量土石料进行镇脚压重,湖泊容积侵占多;或通过堤防岸线往背水侧后退、修筑子堤等方式加大基础面积,需征用较多土地;以上方法均涉及对现状堤防大规模改造,水土保持效果差,工期长,造价高。同时一般的堤身仅具有挡水单一功能,需进一步探索适合该条件的堤防加固改造型式。The general soft foundation treatment methods for embankments include soil replacement method, drainage consolidation method, gravel pile method or cement-soil composite foundation, etc. All of them require the excavation of the existing soil embankment, which will cause great disturbance to the embankment body; Filling a large amount of earth and stone materials on the water side for footing and weighing will occupy a lot of lake volume; or increasing the foundation area by retreating the embankment shoreline to the backwater side, building sub-embankments, etc., which will require the acquisition of more land; the above methods all involve the current situation Large-scale reconstruction of embankments has poor soil and water conservation effects, long construction period, and high construction costs. At the same time, the general embankment body only has the single function of retaining water, and it is necessary to further explore the type of embankment reinforcement and transformation suitable for this condition.

发明内容Contents of the invention

本申请实施例的目的在于提供一种构建在软基透水堤梗上的绿道系统及其施工方法,在满足防洪保安的基础上,实现了生态亲水、便民交通、水土保持、生态修复、环境保护等多种功能,并节省了工程运行费用。The purpose of the embodiments of this application is to provide a greenway system and its construction method constructed on a soft foundation permeable embankment stem, which, on the basis of meeting flood control and security requirements, achieves ecological hydrophilicity, convenient transportation, water and soil conservation, ecological restoration, Environmental protection and other functions, and save project operation costs.

为实现上述目的,本申请提供如下技术方案:In order to achieve the above purpose, this application provides the following technical solutions:

第一方面,本申请实施例提供一种构建在软基透水堤梗上的绿道系统,包括铺设在软基透水堤梗上的绿道,所述绿道的底部设置有土工格栅,所述土工格栅铺设在软基透水堤梗顶部并水平延伸至临水侧生态护坡和背水侧培厚区,土工格栅两侧分别与临水侧生态护坡和背水侧培厚区的底部交接,在土工格栅的上层铺设有黏土填筑层,黏土填筑层的上层铺设透水沥青混凝土路面,所述绿道的临水侧从软基透水堤梗的顶部到底部依次设置有临水侧生态护坡、多功能抗滑桩、滨岸带以及消浪固脚平台,所述绿道的临水侧从软基透水堤梗的顶部到底部依次设置有背水侧培厚区及压浸平台,在临水侧生态护坡的下方设置有堤身防渗体,所述堤身防渗体的顶部与延伸到临水侧生态护坡下方的黏土填筑层连接,消浪固脚平台、滨岸带、多功能抗滑桩、临水侧生态护坡、堤身防渗体、绿道、背水侧培厚区以及压浸平台构成构建在软基透水堤梗上的绿道系统。In a first aspect, embodiments of the present application provide a greenway system built on a soft-base permeable embankment, including a greenway laid on a soft-base permeable embankment. The bottom of the greenway is provided with a geogrid. The geogrid is laid on the top of the soft foundation permeable embankment stem and extends horizontally to the ecological slope protection on the waterfront side and the backwater side cultivation area. Both sides of the geogrid are connected to the bottom of the ecological slope protection on the waterfront side and the backwater side cultivation area respectively. A clay filling layer is laid on the upper layer of the geogrid, and a permeable asphalt concrete pavement is laid on the upper layer of the clay filling layer. The water-facing side of the greenway is provided with water-facing side ecology from the top to the bottom of the soft-base permeable embankment stem. Slope protection, multi-functional anti-slide piles, shore zone and wave-absorbing platform. The water side of the greenway is provided with a backwater side thickening area and a pressure soaking platform in sequence from the top to the bottom of the soft foundation permeable embankment stem. An embankment anti-seepage body is provided below the ecological slope protection on the water side. The top of the embankment anti-seepage body is connected to the clay filling layer extending below the ecological slope protection on the water side. The wave-absorbing foot-fixing platform, shore zone, Multifunctional anti-slide piles, ecological slope protection on the waterside, anti-seepage body of the embankment body, greenway, thickening area on the backwater side and pressure soaking platform constitute a greenway system built on the soft foundation permeable embankment stems.

所述透水沥青混凝土路面的旁边还安装有太阳能路灯。Solar street lights are also installed next to the permeable asphalt concrete pavement.

所述透水沥青混凝土路面由上到下铺设有第一沥青混凝土面层、第二沥青混凝土面层、第三沥青混凝土面层、第四沥青混凝土面层共四层沥青混凝土面层,所述第四沥青混凝土面层的底部铺设水泥稳定层,水泥稳定层的下方铺设碎石垫层,碎石垫层铺设在黏土填筑层上,所述透水沥青混凝土路面的两侧还设置有路沿石。The permeable asphalt concrete pavement is paved with a first asphalt concrete surface layer, a second asphalt concrete surface layer, a third asphalt concrete surface layer, and a fourth asphalt concrete surface layer from top to bottom, a total of four asphalt concrete surface layers. A cement stabilizing layer is laid at the bottom of the four asphalt concrete surface layers, and a gravel cushion is laid below the cement stabilizing layer. The gravel cushion is laid on the clay filling layer. Curb stones are also provided on both sides of the permeable asphalt concrete pavement. .

所述堤身防渗体包括第一单元墙和第二单元墙,所述第一单元墙和第二单元墙依次搭接形成堤身防渗体。The embankment body anti-seepage body includes a first unit wall and a second unit wall, and the first unit wall and the second unit wall are overlapped in sequence to form the embankment body anti-seepage body.

所述临水侧生态护坡包括底层与软基透水堤坡面接触的亲环境多孔透水砖,所述亲环境多孔透水砖内种植耐水草本植物,临水侧生态护坡与绿道连接处设置有压顶。The ecological slope protection on the water side includes environmentally friendly porous permeable bricks with bottom layers in contact with the slope surface of the soft-base permeable embankment. Water-resistant herbaceous plants are planted in the environmentally friendly porous permeable bricks. A pressure cap is provided at the connection between the ecological slope protection on the waterfront side and the greenway. .

所述多功能抗滑桩采用预制空心钢筋混凝土管桩,预制空心钢筋混凝土管桩顶部设置钢筋混凝土冠梁,钢筋混凝土冠梁上部设置钢筋混凝土栈桥式亲水平台,钢筋混凝土栈桥式亲水平台临水侧设置防护栏杆。The multi-functional anti-sliding pile adopts prefabricated hollow reinforced concrete pipe piles. A reinforced concrete crown beam is arranged on the top of the prefabricated hollow reinforced concrete pipe pile. A reinforced concrete trestle type hydrophilic platform is arranged on the upper part of the reinforced concrete crown beam. The reinforced concrete trestle type hydrophilic platform is adjacent to the Set up protective railings on the water side.

所述预制空心钢筋混凝土管桩采用两排成品预应力混凝土管桩,排距2.0m,桩径0.4m,壁厚95mm,桩顶高程为常水位,预制空心钢筋混凝土管桩上部1.5m范围内设桩填芯混凝土,桩填芯混凝土底部采用钢托板固定,钢托板尺寸小于预制空心钢筋混凝土管桩内径,The prefabricated hollow reinforced concrete pipe piles use two rows of finished prestressed concrete pipe piles, with a row spacing of 2.0m, a pile diameter of 0.4m, and a wall thickness of 95mm. The pile top elevation is the normal water level, and the upper part of the prefabricated hollow reinforced concrete pipe piles is within 1.5m. The core-filled concrete piles are set up, and the bottom of the pile-core concrete is fixed with a steel pallet. The size of the steel pallet is smaller than the inner diameter of the prefabricated hollow reinforced concrete pipe pile.

所述预制空心钢筋混凝土管桩还包括第一链接钢筋、第二链接钢筋以及第三链接钢筋,所述第一链接钢筋沿着预制空心钢筋混凝土管桩的圆周等间距的竖向设置,第一链接钢筋的底部固定安装在钢托板上,所述第二链接钢筋等间距的焊接在第一链接钢筋的外侧,从而将第一链接钢筋箍住,所述第三链接钢筋径向设置在预制空心钢筋混凝土管桩的端部并与第一链接钢筋的上端焊接。The prefabricated hollow reinforced concrete pipe pile also includes a first link steel bar, a second link steel bar and a third link steel bar. The first link steel bars are arranged vertically at equal intervals along the circumference of the prefabricated hollow reinforced concrete pipe pile. The bottom of the link steel bars is fixedly installed on the steel pallet. The second link steel bars are welded at equal intervals on the outside of the first link steel bars to hoop the first link steel bars. The third link steel bars are radially arranged on the prefabricated steel plate. The end of the hollow reinforced concrete pipe pile is welded to the upper end of the first link steel bar.

所述背水侧培厚区包括培厚区风化料层,在培厚区风化料层的上方铺设培厚区耕植土层,培厚区耕植土层上种植绿化植物;所述压浸平台包括压浸风化料层,压浸风化料层的上方铺设压浸耕植土层,压浸耕植土层上种植防护林,在压浸平台的上方和背水侧培厚区连接处设置有巡检道路,在压浸平台的下方设置有排水沟。The backwater side cultured area includes a cultured area weathered material layer, a cultured area cultivated soil layer is laid above the cultured area weathered material layer, and green plants are planted on the cultivated area cultivated soil layer; the pressure soaking platform It includes a pressure-soaked weathered material layer, a pressure-soaked cultivated soil layer laid above the pressure-soaked weathered material layer, a protective forest planted on the pressure-soaked cultivated soil layer, and an inspection system installed above the pressure-soaked platform and at the connection between the backwater side thickening area. For roads, drainage ditches are provided below the pressure-soaking platform.

第一方面,本申请实施例提供一种构建在软基透水堤梗上的绿道系统施工方法,包括以下具体步骤:In the first aspect, embodiments of the present application provide a construction method for a greenway system built on soft-foundation permeable embankments, including the following specific steps:

在软基透水堤的堤身上进行堤身防渗体施工,桩机就位、调平;钻进下沉至设计加固深度;边喷浆、边搅拌,提升直至预定停浆面;重复搅拌至设计加固深度;边喷浆、边搅拌至预定停浆面,即完成一道第一单元墙施工;纵向移动机械,按照设计要求尺寸搭接、就位及调平进行第二单元墙墙体施工;采用二次成墙方法,先完成第一单元墙,然后完成第二单元墙,依次搭接,完成堤身防渗体施工;Construction of the embankment anti-seepage body is carried out on the embankment body of the soft-foundation permeable embankment. The pile driver is in place and leveled; drilling and sinking to the designed reinforcement depth are carried out; while spraying and stirring, the embankment is lifted until the predetermined grouting stop surface; repeated stirring until Design the reinforcement depth; while spraying and stirring to the predetermined grouting stop surface, the construction of a first unit wall is completed; the machine is moved longitudinally, and the second unit wall construction is carried out according to the size required by the design, overlapping, positioning and leveling; Using the secondary wall forming method, the first unit wall is completed first, then the second unit wall is completed, and they are overlapped in sequence to complete the construction of the anti-seepage body of the embankment body;

完成堤身防渗体施工后,在堤身防渗体的上方铺设土工格栅、土工格栅上铺设黏土填筑层,黏土填筑层上方铺设碎石垫层,碎石垫层上铺设水泥稳定层、水泥稳定层上依次铺设第四沥青混凝土面层、第三沥青混凝土面层、第二沥青混凝土面层、第一沥青混凝土面层,安装路沿石以及太阳能路灯,完成绿道施工;After the construction of the anti-seepage body of the embankment body is completed, a geogrid is laid above the anti-seepage body of the embankment, a clay filling layer is laid on the geogrid, a gravel cushion is laid above the clay filling layer, and cement is laid on the gravel cushion. The fourth asphalt concrete surface layer, the third asphalt concrete surface layer, the second asphalt concrete surface layer, and the first asphalt concrete surface layer are laid on the stable layer and cement stable layer in sequence, and curb stones and solar street lights are installed to complete the greenway construction;

在绿道的临水侧和背水侧分别施工临水侧生态护坡和背水侧培厚区;Construction of ecological slope protection on the waterside and thickening area on the backwater side will be carried out on the waterside and backwater sides of the greenway respectively;

在分别进行消浪固脚平台、滨岸带、多功能抗滑桩以及压浸平台的施工;The construction of the wave-absorbing foot-fixing platform, shore zone, multi-functional anti-slide piles and pressure immersion platform are being carried out respectively;

施工完成后在滨岸带种植挺水植物,在临水侧生态护坡种植耐水草本植物,在背水侧培厚区种植绿化植物,在压浸平台种植防护林,构建形成完整的绿道系统。After the construction is completed, emergent plants will be planted in the coastal zone, water-resistant herbaceous plants will be planted in the ecological slope protection on the waterside, green plants will be planted in the thickened area on the backwater side, and protective forests will be planted on the pressure soaking platform to form a complete greenway system.

与现有技术相比,本申请的有益效果是:Compared with the existing technology, the beneficial effects of this application are:

1、堤基抗滑加固采用多功能抗滑桩结合消浪固脚平台、滨岸带及压浸平台,稳定性强,结构紧凑,减少水体侵占,节约用地,尤其适用座落于河湖混合相的淤泥质土层上的堤防加固。1. The anti-slip reinforcement of the embankment foundation adopts multi-functional anti-slip piles combined with a wave-absorbing foot-fixing platform, shore zone and pressure soaking platform. It has strong stability and compact structure, reduces water encroachment and saves land. It is especially suitable for locations where rivers and lakes are mixed. Embankment reinforcement on the silty soil layer.

2、堤身防渗加固采用现状堤身防渗墙拦截渗水,结合背水侧培厚区降低水位线及压浸快速导出渗水,确保了防洪安全,减少汛期安全巡查工作量。2. The anti-seepage reinforcement of the embankment body uses the existing anti-seepage wall of the embankment body to intercept seepage water, combined with the thickened area on the backwater side to lower the water level and pressure immersion to quickly drain the seepage water, ensuring flood control safety and reducing the workload of safety inspections during the flood season.

3、本发明可利用消浪固脚平台营造低水位时的浪花击水景观,利用滨岸带净化道路初期雨水径流污染,利用多功能抗滑桩形成亲水观景平台,利用堤顶加高区作为市民通行道路及景观绿道,利用背水侧培厚区种植特色植物打造网红打卡点,利用压浸平台营造微地形及带状公园提升滨岸品质。3. This invention can use the wave-absorbing foot-fixing platform to create a landscape of waves hitting the water at low water levels, use the shore zone to purify the initial rainwater runoff pollution on the road, use multi-functional anti-slip piles to form a hydrophilic viewing platform, and use the elevated area on the top of the embankment. As a public road and landscape greenway, the thickened area on the backwater side is used to plant characteristic plants to create an internet celebrity check-in point, and the pressure soaking platform is used to create micro-terrain and linear parks to enhance the quality of the shore.

附图说明Description of the drawings

为了更清楚地说明本申请实施例的技术方案,下面将对本申请实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本申请的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required to be used in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present application, therefore This should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without exerting creative efforts.

图1是本发明实施例整体结构示意图;Figure 1 is a schematic diagram of the overall structure of an embodiment of the present invention;

图2是本发明实施例绿道结构示意图;Figure 2 is a schematic structural diagram of a greenway according to an embodiment of the present invention;

图3是本发明实施例黏土填筑层与堤身防渗体连接结构示意图;Figure 3 is a schematic diagram of the connection structure between the clay filling layer and the embankment anti-seepage body according to the embodiment of the present invention;

图4是本发明实施例堤身防渗体结构示意图;Figure 4 is a schematic structural diagram of the embankment anti-seepage body according to the embodiment of the present invention;

图5是本发明实施例预制空心钢筋混凝土管桩结构示意图;Figure 5 is a schematic structural diagram of the prefabricated hollow reinforced concrete pipe pile according to the embodiment of the present invention;

图6是图5的A-A向剖面示意图;Figure 6 is a schematic cross-sectional view along line A-A in Figure 5;

图7是本发明实施例预制空心钢筋混凝土管桩分布示意图。Figure 7 is a schematic diagram of the distribution of prefabricated hollow reinforced concrete pipe piles according to the embodiment of the present invention.

具体实施方式Detailed ways

下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行描述。应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。The technical solutions in the embodiments of the present application will be described below with reference to the drawings in the embodiments of the present application. It should be noted that similar reference numerals and letters represent similar items in the following figures, therefore, once an item is defined in one figure, it does not need further definition and explanation in subsequent figures.

术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。The terms "comprises," "comprises," or any other variation thereof are intended to cover a non-exclusive inclusion such that a process, method, article or apparatus including a list of elements includes not only those elements but also others not expressly listed elements, or elements inherent to such process, method, article or equipment. Without further limitation, an element defined by the statement "comprises a..." does not exclude the presence of additional identical elements in a process, method, article, or apparatus that includes the stated element.

实施例Example

如图1所示,本发明实施例提供的一种构建在软基透水堤梗上的绿道系统,包括铺设在软基透水堤梗上的绿道6,所述绿道6的底部设置有土工格栅61,所述土工格栅61铺设在软基透水堤梗顶部并水平延伸至临水侧生态护坡4和背水侧培厚区7,土工格栅61两侧分别与临水侧生态护坡4和背水侧培厚区7的底部交接,在土工格栅61的上层铺设有黏土填筑层62,黏土填筑层62的上层铺设透水沥青混凝土路面63,所述绿道6的临水侧从软基透水堤梗的顶部到底部依次设置有临水侧生态护坡4、多功能抗滑桩3、滨岸带2以及消浪固脚平台1,所述绿道6的临水侧从软基透水堤梗的顶部到底部依次设置有背水侧培厚区7及压浸平台8,在临水侧生态护坡4的下方设置有堤身防渗体5,所述堤身防渗体5的顶部与延伸到临水侧生态护坡4下方的黏土填筑层62连接,消浪固脚平台1、滨岸带2、多功能抗滑桩3、临水侧生态护坡4、堤身防渗体5、绿道6、背水侧培厚区7以及压浸平台8构成构建在软基透水堤梗上的绿道系统。As shown in Figure 1, an embodiment of the present invention provides a greenway system built on a soft-base permeable embankment, including a greenway 6 laid on a soft-base permeable embankment. The bottom of the greenway 6 is provided with Geogrid 61, the geogrid 61 is laid on the top of the soft foundation permeable embankment and extends horizontally to the ecological slope protection 4 on the waterfront side and the thickening area 7 on the backwater side. Both sides of the geogrid 61 are connected to the ecological slope protection on the waterfront side respectively. 4 is connected to the bottom of the backwater side thickening area 7, a clay filling layer 62 is laid on the upper layer of the geogrid 61, and a permeable asphalt concrete pavement 63 is laid on the upper layer of the clay filling layer 62. The water side of the greenway 6 From the top to the bottom of the soft-foundation permeable embankment stem, there are water-side ecological slope protection 4, multi-functional anti-sliding piles 3, shore zone 2 and wave-absorbing foot-fixing platform 1. The water-side side of the greenway 6 starts from the soft foundation. The backwater side thickening area 7 and the pressure soaking platform 8 are arranged from the top to the bottom of the base permeable embankment stem. An embankment body anti-seepage body 5 is provided below the waterside ecological slope protection 4. The embankment body anti-seepage body 5 has The top is connected to the clay filling layer 62 extending below the ecological slope protection 4 on the water side, the wave-absorbing foot-fixing platform 1, the shore zone 2, the multi-functional anti-slide pile 3, the ecological slope protection 4 on the water side, and the anti-seepage body of the embankment 5. Greenway 6, backwater side thickening area 7 and pressure soaking platform 8 constitute a greenway system built on soft foundation permeable embankment stems.

消浪固脚平台1位于临水侧坡脚,平台顶需高于枯水位0.5m,顶宽2~3m,两侧以1:1.5~1:2.0的坡度向河底放坡,采用块石,要求石质坚硬,遇水不易破碎或分解,石头强度等级≥MU30,软化系数Kd≥0.75,密度不小于2.65t/m3,粒径为0.15~0.45m,单块重量不得小于10kg/块,抛投时应大小搭配。The wave-absorbing foot-fixing platform 1 is located at the foot of the waterside slope. The top of the platform must be 0.5m higher than the low water level, and the top width should be 2 to 3m. Both sides should be sloped to the river bottom at a slope of 1:1.5 to 1:2.0, using blocks of stone. , the stone is required to be hard and not easily broken or decomposed when exposed to water. The stone strength grade is ≥ MU30, the softening coefficient Kd is ≥ 0.75, the density is not less than 2.65t/m 3 , the particle size is 0.15 to 0.45m, and the weight of a single piece should not be less than 10kg/piece. , size should be matched when throwing.

所述滨岸带2包括底层的抛土基础层21,在抛土基础层21上种植挺水植物22,滨岸带2位于消浪固脚平台1背水侧,抛土基础层21采用附近开挖料,抛填平整后可不压实,直接作为多功能抗滑桩3施工作业平台,多功能抗滑桩3施工完成后对抛土基础层21进行修坡、刨松处理,以利于后期种植挺水植物22,挺水植物22可采用香蒲、再力花等耐久性强、景观效果较好的本地水生植物。所述透水沥青混凝土路面63的旁边还安装有太阳能路灯64。The shore zone 2 includes a bottom soil-thrown foundation layer 21, on which emergent plants 22 are planted. The shore zone 2 is located on the backwater side of the wave-absorbing and foot-fixing platform 1. The excavated material does not need to be compacted after being thrown and filled, and can be directly used as a construction work platform for the multi-functional anti-slide pile 3. After the construction of the multi-functional anti-slide pile 3 is completed, the soil foundation layer 21 will be sloped and planed to facilitate subsequent planting. The emergent plants 22 can be local aquatic plants with strong durability and good landscape effects such as cattails and zaili flowers. Solar street lights 64 are also installed next to the permeable asphalt concrete pavement 63 .

如图2所示,所述透水沥青混凝土路面63由上到下铺设有第一沥青混凝土面层631、第二沥青混凝土面层632、第三沥青混凝土面层633、第四沥青混凝土面层634共四层沥青混凝土面层,所述第四沥青混凝土面层634的底部铺设水泥稳定层635,水泥稳定层635的下方铺设碎石垫层636,碎石垫层636铺设在黏土填筑层62上,所述透水沥青混凝土路面63的两侧还设置有路沿石637。As shown in Figure 2, the permeable asphalt concrete pavement 63 is paved with a first asphalt concrete surface layer 631, a second asphalt concrete surface layer 632, a third asphalt concrete surface layer 633, and a fourth asphalt concrete surface layer 634 from top to bottom. There are four asphalt concrete surface layers in total. A cement stabilizing layer 635 is laid at the bottom of the fourth asphalt concrete surface layer 634. A gravel cushion layer 636 is laid below the cement stable layer 635. The gravel cushion layer 636 is laid on the clay filling layer 62. On both sides of the permeable asphalt concrete pavement 63, curb stones 637 are also provided.

如图3所示,土工格栅61采用双向拉伸塑料土工格栅,标称拉伸强度≥50kN/m,黏土填筑层62需连接堤身防渗体5,渗透系数≤10-4cm/s,采用黏性土料分层碾压,分层厚度不大于30cm,压实度不小于0.93;透水沥青混凝土路面63宽8m,采用彩色沥青混凝土结构。As shown in Figure 3, the geogrid 61 is a biaxially stretched plastic geogrid with a nominal tensile strength of ≥50kN/m. The clay filling layer 62 needs to be connected to the embankment anti-seepage body 5, and the permeability coefficient is ≤10 -4 cm. /s, using sticky soil materials for layering and rolling, with the layer thickness not greater than 30cm and the compaction degree not less than 0.93; the permeable asphalt concrete pavement is 63 meters wide and 8m wide, using colored asphalt concrete structure.

如图4所示,所述堤身防渗体5包括第一单元墙51和第二单元墙52,所述第一单元墙51和第二单元墙52依次搭接形成堤身防渗体5,所述堤身防渗体5采用水泥土搅拌桩连续墙结构,堤身防渗体5厚不小于0.3m,堤身防渗体5的上沿与现有堤防的顶部平齐,堤身防渗体的下部穿过透水堤防的堤身,并延伸至透水堤防的堤基淤泥质土层以下不小于0.5m。As shown in Figure 4, the embankment anti-seepage body 5 includes a first unit wall 51 and a second unit wall 52. The first unit wall 51 and the second unit wall 52 are overlapped in sequence to form the embankment anti-seepage body 5. , the embankment body anti-seepage body 5 adopts a cement-soil mixing pile continuous wall structure, the embankment body anti-seepage body 5 is not less than 0.3m thick, the upper edge of the embankment body anti-seepage body 5 is flush with the top of the existing embankment, and the embankment body anti-seepage body 5 The lower part of the anti-seepage body passes through the body of the permeable embankment and extends to no less than 0.5m below the muddy soil layer of the embankment foundation of the permeable embankment.

所述临水侧生态护坡4包括底层与软基透水堤坡面接触的亲环境多孔透水砖41,所述亲环境多孔透水砖41内种植耐水草本植物42,临水侧生态护坡4与绿道6连接处设置有压顶43。临水侧生态护坡4位于多功能抗滑桩3背水侧,并延伸至堤防顶部,亲环境多孔透水砖41采用12cm厚C25混凝土空心六角块或连锁式植生块结构,耐水草本植物42种植在亲环境多孔透水砖41孔内,采用当地常规草本植物,压顶43设置在环境多孔透水砖41顶部,采用C25混凝土结构,尺寸0.4x0.2m,同时作为堤顶加高区6的路肩。The water-side ecological slope protection 4 includes environmentally friendly porous permeable bricks 41 whose bottom layer is in contact with the slope surface of a soft-base permeable embankment. Water-resistant herbaceous plants 42 are planted in the environmentally friendly porous permeable bricks 41. The water-side ecological slope protection 4 is in contact with the greenway. 6. A pressure top 43 is provided at the connection point. The ecological slope protection 4 on the waterside is located on the backwater side of the multi-functional anti-slide pile 3 and extends to the top of the embankment. The environmentally friendly porous permeable bricks 41 adopt a 12cm thick C25 concrete hollow hexagonal block or interlocking planting block structure. Water-resistant herbaceous plants 42 are planted on the pro-environment. Local conventional herbaceous plants are used in the holes of the environmental porous permeable bricks 41. The pressure cap 43 is set on the top of the environmental porous permeable bricks 41. It adopts a C25 concrete structure with a size of 0.4x0.2m and serves as the road shoulder of the embankment top heightening area 6.

所述多功能抗滑桩3采用预制空心钢筋混凝土管桩31,预制空心钢筋混凝土管桩31顶部设置钢筋混凝土冠梁32,钢筋混凝土冠梁32上部设置钢筋混凝土栈桥式亲水平台33,钢筋混凝土栈桥式亲水平台33临水侧设置防护栏杆34。The multifunctional anti-sliding pile 3 adopts a prefabricated hollow reinforced concrete pipe pile 31. A reinforced concrete crown beam 32 is arranged on the top of the prefabricated hollow reinforced concrete pipe pile 31. A reinforced concrete trestle type hydrophilic platform 33 is arranged on the upper part of the reinforced concrete crown beam 32. The reinforced concrete The trestle-type hydrophilic platform 33 is provided with protective railings 34 on the water side.

如图5-7所示,所述预制空心钢筋混凝土管桩31采用两排成品预应力混凝土管桩,排距2.0m,桩径0.4m,壁厚95mm,桩顶高程为常水位,预制空心钢筋混凝土管桩31上部1.5m范围内设桩填芯混凝土312,桩填芯混凝土312底部采用钢托板311固定,钢托板311尺寸小于预制空心钢筋混凝土管桩31内径,桩长及间距根据抗滑稳定计算确定,采用静力压桩到位;钢筋混凝土冠梁32位于预制空心钢筋混凝土管桩31顶部,采用C30钢筋混凝土结构,尺寸0.6x0.5m,同时作为临水侧生态护坡4下部脚槽;钢筋混凝土栈桥式亲水平台33位于钢筋混凝土冠梁32顶部,宽3m,采用C30钢筋混凝土框架结构;防护栏杆34位于钢筋混凝土栈桥式亲水平台33上部临水侧,高1.2m,采用仿石混凝土或不锈钢结构。As shown in Figure 5-7, the prefabricated hollow reinforced concrete pipe piles 31 use two rows of finished prestressed concrete pipe piles, with a row spacing of 2.0m, a pile diameter of 0.4m, a wall thickness of 95mm, the pile top elevation is the normal water level, and the prefabricated hollow A pile core-filled concrete 312 is provided within the upper 1.5m range of the reinforced concrete pipe pile 31. The bottom of the pile core-filled concrete 312 is fixed with a steel supporting plate 311. The size of the steel supporting plate 311 is smaller than the inner diameter of the prefabricated hollow reinforced concrete pipe pile 31. The pile length and spacing are based on The anti-slip stability calculation is determined, and static pressure piles are in place; the reinforced concrete crown beam 32 is located on the top of the prefabricated hollow reinforced concrete pipe pile 31, using a C30 reinforced concrete structure with a size of 0.6x0.5m, and also serves as the lower foot of the ecological slope protection 4 on the waterside trough; the reinforced concrete trestle-type hydrophilic platform 33 is located on the top of the reinforced concrete crown beam 32, is 3m wide, and adopts a C30 reinforced concrete frame structure; the protective railing 34 is located on the water side of the upper part of the reinforced concrete trestle-type hydrophilic platform 33, is 1.2m high, and adopts Stone-like concrete or stainless steel structure.

如图5所示,所述预制空心钢筋混凝土管桩31还包括第一链接钢筋313、第二链接钢筋314以及第三链接钢筋315,所述第一链接钢筋313沿着预制空心钢筋混凝土管桩31的圆周等间距的竖向设置,第一链接钢筋313的底部固定安装在钢托板311上,所述第二链接钢筋314等间距的焊接在第一链接钢筋313的外侧,从而将第一链接钢筋313箍住,所述第三链接钢筋315径向设置在预制空心钢筋混凝土管桩31的端部并与第一链接钢筋313的上端焊接。As shown in Figure 5, the prefabricated hollow reinforced concrete pipe pile 31 also includes a first link steel bar 313, a second link steel bar 314 and a third link steel bar 315. The first link steel bar 313 is along the prefabricated hollow reinforced concrete pipe pile. 31 are arranged vertically at equal intervals around the circumference of the first link steel bar 313, the bottom of the first link steel bar 313 is fixedly installed on the steel supporting plate 311, and the second link steel bars 314 are equally spaced welded to the outside of the first link steel bar 313, thereby connecting the first The third link steel bar 313 is hooped. The third link steel bar 315 is radially arranged at the end of the prefabricated hollow reinforced concrete pipe pile 31 and is welded to the upper end of the first link steel bar 313 .

所述背水侧培厚区7包括培厚区风化料层71,在培厚区风化料层71的上方铺设培厚区耕植土层72,培厚区耕植土层73上种植绿化植物73。培厚区风化料层71渗透系数≥10- 4cm/s,分层厚度不大于40cm,碾压次数应通过碾压试验确定,压实相对密度不小于0.65;培厚区耕植土层72厚度≥0.3m;绿化植物73可选用紫云英或粉黛乱子草或其他特色草本植物。The backwater side cultivated area 7 includes a cultivated area weathered material layer 71, a cultivated area cultivated soil layer 72 is laid above the cultivated area weathered material layer 71, and green plants 73 are planted on the cultivated area cultivated soil layer 73. . The permeability coefficient of the weathered material layer 71 in the cultivation area is ≥10 - 4 cm/s, the layer thickness is not greater than 40cm, the number of rolling should be determined through the rolling test, and the relative density of compaction is not less than 0.65; the cultivated soil layer 72 in the cultivation area Thickness ≥ 0.3m; greening plants 73 can be made of milkvetch or pink grass or other characteristic herbs.

所述压浸平台8包括压浸风化料层81,压浸风化料层81的上方铺设压浸耕植土层82,压浸耕植土层82上种植防护林84,在压浸平台8的上方和背水侧培厚区7连接处设置有巡检道路83,在压浸平台8的下方设置有排水沟85。压浸平台8位于整体结构背水侧最下层,表面铺设成弧形以利于营造微地形;压浸风化料层81的渗透系数≥10-3cm/s,应与消浪固脚平台1同步实施,以利于堤防双侧受力平衡,填筑速度不得大于0.8m/d;巡检道路83为透水砖或卵石路面,宽2m;防护林84采用本地垂柳或白杨或其他喜湿树种;排水沟85采用浆砌石砌筑。The pressure-soaking platform 8 includes a pressure-soaking weathered material layer 81 . A pressure-soaking soil layer 82 is laid above the pressure-soaking weathered material layer 81 . A protective forest 84 is planted on the pressure-soaking soil layer 82 . Above the pressure-soaking platform 8 An inspection road 83 is provided at the connection with the backwater side thickening area 7 , and a drainage ditch 85 is provided below the pressure soaking platform 8 . The pressure-soaking platform 8 is located at the lowest level on the backwater side of the overall structure, and the surface is laid in an arc shape to facilitate the creation of micro-topography; the pressure-soaking weathering material layer 81 has a permeability coefficient of ≥10 -3 cm/s and should be implemented simultaneously with the wave elimination and foot-fixing platform 1 , to facilitate the balance of stress on both sides of the embankment, the filling speed shall not exceed 0.8m/d; the inspection road 83 is permeable brick or pebble pavement, 2m wide; the protective forest 84 uses local weeping willows, poplars or other moisture-loving tree species; the drainage ditch 85 It is built with mortar stone masonry.

一种构建在软基透水堤梗上的绿道系统施工方法,包括以下具体步骤:A construction method for a greenway system built on soft-foundation permeable embankment stems, including the following specific steps:

在软基透水堤的堤身上进行堤身防渗体5施工,桩机就位、调平;钻进下沉至设计加固深度;边喷浆、边搅拌,提升直至预定停浆面;重复搅拌至设计加固深度;边喷浆、边搅拌至预定停浆面,即完成一道第一单元墙51施工;纵向移动机械,按照设计要求尺寸搭接、就位及调平进行第二单元墙52墙体施工;采用二次成墙方法,先完成第一单元墙51,然后完成第二单元墙52,依次搭接,完成堤身防渗体5施工;Construction of the embankment anti-seepage body 5 is carried out on the embankment body of the soft foundation permeable embankment. The pile driver is in place and leveled; drilling and sinking to the designed reinforcement depth are carried out; while spraying and stirring, the embankment body is lifted until the predetermined grouting stop surface; repeated stirring to the designed reinforcement depth; while spraying and stirring to the predetermined grouting stop surface, the construction of a first unit wall 51 is completed; the machine is moved longitudinally to overlap, position and level the second unit wall 52 according to the design requirements. Body construction; using the secondary wall forming method, first complete the first unit wall 51, then complete the second unit wall 52, and overlap in sequence to complete the construction of the embankment anti-seepage body 5;

完成堤身防渗体5施工后,在堤身防渗体5的上方铺设土工格栅61、土工格栅61上铺设黏土填筑层62,黏土填筑层62上方铺设碎石垫层636,碎石垫层636上铺设水泥稳定层635、水泥稳定层635上依次铺设第四沥青混凝土面层634、第三沥青混凝土面层633、第二沥青混凝土面层632、第一沥青混凝土面层631,安装路沿石637以及太阳能路灯64,完成绿道6施工;After the construction of the embankment body anti-seepage body 5 is completed, a geogrid 61 is laid above the embankment body anti-seepage body 5, a clay filling layer 62 is laid on the geogrid 61, and a gravel cushion layer 636 is laid above the clay filling layer 62. A cement stabilizing layer 635 is laid on the gravel cushion 636, and a fourth asphalt concrete surface layer 634, a third asphalt concrete surface layer 633, a second asphalt concrete surface layer 632, and a first asphalt concrete surface layer 631 are laid in sequence on the cement stable layer 635. , install curb stones 637 and solar street lights 64, and complete the construction of greenway 6;

在绿道6的临水侧和背水侧分别施工临水侧生态护坡4和背水侧培厚区7;On the waterside and backwater sides of greenway 6, construct the waterside ecological slope protection 4 and the backwater side thickening area 7 respectively;

在分别进行消浪固脚平台1、滨岸带2、多功能抗滑桩3以及压浸平台8的施工;The construction of wave-absorbing foot-fixing platform 1, shore zone 2, multi-functional anti-sliding piles 3 and pressure soaking platform 8 are being carried out respectively;

施工完成后在滨岸带2种植挺水植物,在临水侧生态护坡4种植耐水草本植物,在背水侧培厚区7种植绿化植物,在压浸平台8种植防护林,构建形成完整的绿道系统。After the construction is completed, emergent plants will be planted in the shore zone 2, water-resistant herbaceous plants will be planted in the ecological slope protection 4 on the waterside side, green plants will be planted in the thickened area 7 on the backwater side, and a protective forest will be planted in the pressure soaking platform 8 to form a complete greenway. system.

本申请利用消浪固脚平台营造低水位时的浪花击水景观,利用滨岸带净化道路初期雨水径流污染,利用多功能抗滑桩形成亲水观景平台,利用堤顶加高区作为市民通行道路及景观绿道,利用背水侧培厚区种植特色植物打造网红打卡点,利用压浸平台营造微地形及带状公园提升滨岸品质。This application uses a wave-absorbing and foot-fixed platform to create a landscape of waves hitting the water at low water levels, uses the shore zone to purify the initial rainwater runoff pollution on the road, uses multi-functional anti-slip piles to form a water-friendly viewing platform, and uses the elevated area on the top of the embankment as a public passage For roads and landscape greenways, special plants are planted in the thickened area on the backwater side to create internet celebrity check-in points, and pressure soaking platforms are used to create micro-terrain and linear parks to improve the quality of the shore.

以上所述仅为本申请的实施例而已,并不用于限制本申请的保护范围,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above descriptions are only examples of the present application and are not intended to limit the scope of protection of the present application. For those skilled in the art, the present application may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of this application shall be included in the protection scope of this application.

Claims (5)

1. The utility model provides a construct green way system on soft foundation dyke stalk that permeates water, its characterized in that, including lay green way (6) on soft foundation dyke stalk that permeates water, the bottom of green way (6) is provided with geogrid (61), geogrid (61) are laid at soft foundation dyke stalk top and the level extends to face water side ecological bank protection (4) and back water side thick district (7), geogrid (61) both sides respectively with face water side ecological bank protection (4) and back water side thick district (7) bottom handing-over, laid clay filling layer (62) in geogrid (61)'s upper strata, the upper strata of clay filling layer (62) is laid asphalt concrete road surface (63) that permeates water, the ecological bank protection system is characterized in that a waterside of the green channel (6) is sequentially provided with a waterside ecological bank protection (4), a multifunctional slide-resistant pile (3), a coastal zone (2) and a wave-dissipating foot fixing platform (1) from the top to the bottom of the soft foundation permeable dike peduncles, a back water side thickness cultivation area (7) and a pressure soaking platform (8) are sequentially arranged on the waterside of the green channel (6) from the top to the bottom of the soft foundation permeable dike peduncles, a dike body seepage-resistant body (5) is arranged below the waterside ecological bank protection (4), the top of the dike body seepage-resistant body (5) is connected with a clay filling layer (62) extending to the lower part of the waterside ecological bank protection (4), the wave-dissipating foot fixing platform (1), the coastal zone (2) and the multifunctional slide-resistant pile (3), the ecological slope protection (4) at the water side, the dyke body seepage-proofing body (5), the green channel (6), the back water side thickness cultivation area (7) and the pressure impregnation platform (8) form a green channel system constructed on the soft foundation permeable dyke stems;
the permeable asphalt concrete pavement (63) is paved with a first asphalt concrete surface layer (631), a second asphalt concrete surface layer (632), a third asphalt concrete surface layer (633) and a fourth asphalt concrete surface layer (634) from top to bottom, a cement stabilizing layer (635) is paved at the bottom of the fourth asphalt concrete surface layer (634), a broken stone cushion layer (636) is paved below the cement stabilizing layer (635), the broken stone cushion layer (636) is paved on the clay filling layer (62), and road edge stones (637) are arranged at two sides of the permeable asphalt concrete pavement (63);
the embankment body seepage-proofing body (5) comprises a first unit wall (51) and a second unit wall (52), and the first unit wall (51) and the second unit wall (52) are sequentially overlapped to form the embankment body seepage-proofing body (5);
the ecological slope protection (4) at the water side comprises an environmentally-friendly porous permeable brick (41) with a bottom layer in contact with the slope surface of the soft foundation permeable embankment, water-resistant herbaceous plants (42) are planted in the environmentally-friendly porous permeable brick (41), and a pressing roof (43) is arranged at the joint of the ecological slope protection (4) at the water side and the green road (6);
the multifunctional slide-resistant pile (3) adopts a prefabricated hollow reinforced concrete pipe pile (31), a reinforced concrete crown beam (32) is arranged at the top of the prefabricated hollow reinforced concrete pipe pile (31), and a reinforced concrete trestle type is arranged at the upper part of the reinforced concrete crown beam (32)
The reinforced concrete trestle type hydrophilic platform (33) is provided with a protective railing (34) on the water side of the reinforced concrete trestle type hydrophilic platform (33);
the back water side thick cultivation area (7) comprises a thick cultivation area weathered material layer (71), a thick cultivation area cultivated soil layer (72) is paved above the thick cultivation area weathered material layer (71), and greening plants (73) are planted on the thick cultivation area cultivated soil layer (72); the pressure impregnation platform (8) comprises a pressure impregnation weathering layer (81), a pressure impregnation soil planting layer (82) is paved above the pressure impregnation weathering layer (81), a protective forest (84) is planted on the pressure impregnation soil planting layer (82), a patrol road (83) is arranged at the joint of the upper part of the pressure impregnation platform (8) and the back water side thick planting area (7), and a drainage ditch (85) is arranged below the pressure impregnation platform (8).
2. A green road system built on a permeable dike according to claim 1, characterized in that a solar street lamp (64) is also installed beside the permeable asphalt concrete pavement (63).
3. The green road system constructed on the permeable dike stem of the soft foundation according to claim 1, wherein the prefabricated hollow reinforced concrete pipe piles (31) are two rows of finished prestressed concrete pipe piles, the row spacing is 2.0m, the pile diameter is 0.4m, the wall thickness is 95mm, the pile top elevation is the normal water level, pile core filling concrete (312) is arranged in the range of 1.5m at the upper part of the prefabricated hollow reinforced concrete pipe piles (31), the bottom of the pile core filling concrete (312) is fixed by steel supporting plates (311), and the size of the steel supporting plates (311) is smaller than the inner diameter of the prefabricated hollow reinforced concrete pipe piles (31).
4. A green road system constructed on a soft foundation permeable dike stem according to claim 3, characterized in that the prefabricated hollow reinforced concrete pile (31) further comprises a first linking bar (313), a second linking bar (314) and a third linking bar (315), the first linking bar (313) is vertically arranged at equal intervals along the circumference of the prefabricated hollow reinforced concrete pile (31), the bottom of the first linking bar (313) is fixedly arranged on the steel pallet (311), the second linking bar (314) is welded at equal intervals on the outer side of the first linking bar (313) so as to hoop the first linking bar (313), and the third linking bar (315) is radially arranged at the end of the prefabricated hollow reinforced concrete pile (31) and welded with the upper end of the first linking bar (313).
5. A construction method for realizing a green road system constructed on a soft foundation permeable dike according to any one of claims 1-4, characterized by comprising the following specific steps:
the method comprises the steps of constructing a dyke body seepage-proofing body (5) on a dyke body of a soft foundation permeable dyke, positioning and leveling a pile machine; drilling and sinking to the design reinforcement depth; spraying slurry while stirring, and lifting until reaching a preset slurry stopping surface; repeatedly stirring to the designed reinforcement depth; spraying slurry while stirring to a preset slurry stopping surface, thus completing the construction of a first unit wall (51); longitudinally moving the machine, overlapping, positioning and leveling according to the size required by design, and constructing a second unit wall (52) wall body; the secondary wall forming method is adopted, a first unit wall (51) is finished firstly, then a second unit wall (52) is finished, the second unit wall is sequentially overlapped, and the construction of the embankment body seepage-proofing body (5) is finished; after the embankment body seepage-proofing body (5) is constructed, a geogrid (61) is paved above the embankment body seepage-proofing body (5), a clay filling layer (62) is paved on the geogrid (61), a broken stone cushion layer (636) is paved above the clay filling layer (62), a cement stabilizing layer (635) is paved on the broken stone cushion layer (636), a fourth asphalt concrete surface layer (634), a third asphalt concrete surface layer (633), a second asphalt concrete surface layer (632), a first asphalt concrete surface layer (631) are sequentially paved on the cement stabilizing layer (635), and road edge stones (637) and solar street lamps (64) are installed to finish green road (6) construction; respectively constructing an ecological slope protection (4) on the water facing side and a thickness cultivation area (7) on the water facing side and the water carrying side of the green road (6); the construction of the wave-eliminating foot-fixing platform (1), the coastal zone (2), the multifunctional slide-resistant pile (3) and the pressure-immersing platform (8) is respectively carried out; after the construction is completed, emergent aquatic plants are planted in the coastal zone (2), water-resistant herbaceous plants are planted in the waterside ecological slope protection (4), greening plants are planted in the back-water side thick cultivation area (7), and protective forests are planted in the pressure leaching platform (8), so that a complete greenway system is formed.
CN202210641519.2A 2022-06-08 2022-06-08 Green road system constructed on soft foundation permeable dike and construction method thereof Active CN114960545B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210641519.2A CN114960545B (en) 2022-06-08 2022-06-08 Green road system constructed on soft foundation permeable dike and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210641519.2A CN114960545B (en) 2022-06-08 2022-06-08 Green road system constructed on soft foundation permeable dike and construction method thereof

Publications (2)

Publication Number Publication Date
CN114960545A CN114960545A (en) 2022-08-30
CN114960545B true CN114960545B (en) 2023-11-10

Family

ID=82961414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210641519.2A Active CN114960545B (en) 2022-06-08 2022-06-08 Green road system constructed on soft foundation permeable dike and construction method thereof

Country Status (1)

Country Link
CN (1) CN114960545B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115478513A (en) * 2022-09-28 2022-12-16 长江勘测规划设计研究有限责任公司 Structure and method for reinforcement and ecological transformation of soft foundation and slope of rivers and lakes in urban areas
CN115595955A (en) * 2022-11-03 2023-01-13 南水北调江苏生态环境有限公司(Cn) Soil-squeezing-prevention sedimentation-control reinforcing structure for heightening and thickening dyke in ultra-thick soft soil layer area

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014177854A (en) * 2012-06-01 2014-09-25 Nippon Steel & Sumitomo Metal Reinforcement structure of dike
CN105178245A (en) * 2015-08-18 2015-12-23 水利部交通运输部国家能源局南京水利科学研究院 Large filling bag ecological embankment and revetment building method for river lake channel
CN206189340U (en) * 2016-09-22 2017-05-24 上海市水利工程设计研究院有限公司 Structure is reformed transform to ecologization shore protection that grouts a stone barricade
CN213358505U (en) * 2020-07-30 2021-06-04 杭州悦为科技有限公司 Seepage-proofing reinforcing heightening structure for existing diseased river levee
CN214883731U (en) * 2021-01-28 2021-11-26 甘肃省水利水电勘测设计研究院有限责任公司 Light gallery structure for protecting rock-soil mixed slope road
CN114197396A (en) * 2022-01-05 2022-03-18 江苏省太湖水利规划设计研究院有限公司 A load-reducing ecological bank protection structure and construction method for river and lake embankment reinforcement

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014177854A (en) * 2012-06-01 2014-09-25 Nippon Steel & Sumitomo Metal Reinforcement structure of dike
CN105178245A (en) * 2015-08-18 2015-12-23 水利部交通运输部国家能源局南京水利科学研究院 Large filling bag ecological embankment and revetment building method for river lake channel
CN206189340U (en) * 2016-09-22 2017-05-24 上海市水利工程设计研究院有限公司 Structure is reformed transform to ecologization shore protection that grouts a stone barricade
CN213358505U (en) * 2020-07-30 2021-06-04 杭州悦为科技有限公司 Seepage-proofing reinforcing heightening structure for existing diseased river levee
CN214883731U (en) * 2021-01-28 2021-11-26 甘肃省水利水电勘测设计研究院有限责任公司 Light gallery structure for protecting rock-soil mixed slope road
CN114197396A (en) * 2022-01-05 2022-03-18 江苏省太湖水利规划设计研究院有限公司 A load-reducing ecological bank protection structure and construction method for river and lake embankment reinforcement

Also Published As

Publication number Publication date
CN114960545A (en) 2022-08-30

Similar Documents

Publication Publication Date Title
CN106703050A (en) Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN105178245A (en) Large filling bag ecological embankment and revetment building method for river lake channel
CN114960545B (en) Green road system constructed on soft foundation permeable dike and construction method thereof
CN203373705U (en) Ecological slope protection
CN101634143A (en) Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay
CN113445396A (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN106836244A (en) Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN106758623B (en) A kind of dam filling construction of the no muscle lightweight earthen platform back of the body
CN104594288A (en) Novel Taihu Lake bank planting ecological restoration technology
CN106930231A (en) A kind of construction method of the engineering flood bank reinforcing that is applied to pass the flood period
CN110067167B (en) A kind of microbial embankment filling method
CN110144783A (en) A roadbed construction method
CN211113444U (en) Ecological protective structure of riverway bank slope under unfavorable geological conditions
CN110644427B (en) Ecological protection structure of river bank slope under unfavorable geological conditions and dredging method
CN204690780U (en) A kind of inter-embedding type ecological block retaining wall
CN202323960U (en) Shallow foundation pit forming construction structure capable of ensuring slope stability
CN106592565A (en) Dam fixing and protecting construction method using soil stabilizer in land reclamation project
CN213625012U (en) Coastal permeable embankment structure
Keown Literature survey and preliminary evaluation of streambank protection methods
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN208023600U (en) A kind of caisson structure suitable for complex environment
CN217325475U (en) Reinforced structure is restoreed to hydraulic retaining wall that collapses
CN217556828U (en) A multifunctional flood control dyke ecological reinforcement structure for soft foundation permeable dyke
CN206220108U (en) Cut Slopes of Expansive Soil reinforced earth back-pressure antiseepage supporting construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant