[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN114517586A - Method for adjusting position deviation in steel structure lifting process - Google Patents

Method for adjusting position deviation in steel structure lifting process Download PDF

Info

Publication number
CN114517586A
CN114517586A CN202210231921.3A CN202210231921A CN114517586A CN 114517586 A CN114517586 A CN 114517586A CN 202210231921 A CN202210231921 A CN 202210231921A CN 114517586 A CN114517586 A CN 114517586A
Authority
CN
China
Prior art keywords
steel truss
interface
steel
adjusting
lifting process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210231921.3A
Other languages
Chinese (zh)
Inventor
曹雁冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Weihong Steel Structure Group Co ltd
Original Assignee
Anhui Weihong Steel Structure Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Weihong Steel Structure Group Co ltd filed Critical Anhui Weihong Steel Structure Group Co ltd
Priority to CN202210231921.3A priority Critical patent/CN114517586A/en
Publication of CN114517586A publication Critical patent/CN114517586A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the technical field of steel structure construction, and discloses a method for adjusting position deviation in a steel structure lifting process, which comprises the following specific steps: the method comprises the following steps: lifting inspection, wherein before lifting the steel truss to be installed, the interface of the steel truss to be installed is inspected, and then the interface of the installed steel truss is inspected; step two: installing an adjusting puller, wherein the adjusting puller is installed at the bottom of the steel truss to be installed, the length of four pull ropes extending downwards from the adjusting puller is long enough, and the tail ends of the four pull ropes are respectively held by four constructors; step three: and lifting the steel truss, and aligning the interface of the steel truss to be installed with the interface of the installed steel truss after the steel truss is inspected and installed. The method for adjusting the position deviation in the steel structure lifting process is convenient for adjusting the position of the steel truss in multiple directions, improves the efficiency of lifting and butting the steel structure, and ensures the smooth construction of the steel structure.

Description

Method for adjusting position deviation in steel structure lifting process
Technical Field
The invention relates to the technical field of steel structure construction, in particular to a method for adjusting position deviation in a steel structure lifting process.
Background
The installation of the large-span structure usually adopts a hydraulic synchronous lifting construction process, when the lifting is about to be in place, the rod pieces of the supporting structure and the lifted structure need to be aligned, and whether the rod pieces can be aligned smoothly is the key of whether the truss lifting can be closed.
The patent number is CN113503047A, and discloses a method for adjusting high altitude position offset by traction in the lifting process of a steel structure, which comprises the steps of suspending a lifting section steel truss when the lifting section steel truss is to be lifted in place, tightening a chain block to return the lifting section steel truss to a normal position in the air, checking the gaps between a lower chord and the lower chord, and between the lower chord and the lower chord, and judging whether horizontal projection overlapping exists; and the lifter starts to work, and the lifter is alternately matched with the chain block for multiple times, so that the gaps between the lower chord and the lower chord, and between the lower chord and the lower chord meet the lifting requirement until the steel truss at the lifting section is lifted in place.
In the scheme, only a single chain block is adopted, and the position of the steel truss can be changed in the lifting process, so that the chain block can only be pulled towards the direction of one side, and the position of the steel truss can not be adjusted better, thereby reducing the efficiency of steel structure lifting butt joint.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a method for adjusting the position offset in the steel structure lifting process, which is convenient for adjusting the position of a steel truss in multiple directions, improves the efficiency of steel structure lifting butt joint, ensures the smooth proceeding of steel structure construction, and solves the problem that the position of the steel truss can not be well adjusted because the steel truss can be changed in the lifting process, the chain block can only be pulled towards one side, and the position of the steel truss can not be well adjusted, thereby reducing the efficiency of steel structure lifting butt joint.
(II) technical scheme
In order to achieve the purpose, the invention provides the following technical scheme: a method for adjusting position deviation in a steel structure lifting process comprises the following specific steps:
the method comprises the following steps: the method comprises the following steps of (1) lifting inspection, wherein before a steel truss to be installed is lifted, an interface of the steel truss to be installed is inspected, and then an interface of the installed steel truss is inspected, so that the interface of the steel truss to be installed and the interface of the installed steel truss are not damaged;
step two: installing an adjusting puller, wherein the adjusting puller is installed at the bottom of the steel truss to be installed, the length of a pull rope extending downwards from the adjusting puller is long enough, the number of the pull ropes at the bottom of the adjusting puller is four, the four pull ropes are arranged towards four different directions, and the tail ends of the four pull ropes are respectively held by four constructors;
Step three: lifting the steel truss, lifting the steel truss to be installed upwards after the steel truss to be installed is inspected and installed, enabling an interface of the steel truss to be installed to be aligned with an interface of the installed steel truss, when the interface of the steel truss to be installed is close to the interface of the installed steel truss, needing a fifth constructor to stand at the top of the installed steel truss to observe whether the interface of the steel truss to be installed is aligned with the interface of the installed steel truss or not, and informing four constructors on the ground after observing the inclination angle of the interface, enabling the four constructors to apply different external forces and adjust the inclination angle of the steel truss to be installed, enabling the interface of the steel truss to be installed to be aligned with the interface of the installed steel truss, and finally enabling the interface of the steel truss to be installed to be butted with the interface of the installed steel truss;
step four: and finally, checking, and ensuring that the butt joint is correct again by a fifth constructor after the butt joint of the steel truss to be installed and the joint of the installed steel truss is completed.
Preferably, in the first step, if the interface of the steel truss to be installed and the interface of the steel truss to be installed are damaged, a constructor is required to climb up to maintain the steel truss.
Preferably, in the second step, when the four constructors hold the pull rope by hands, the anti-abrasion gloves need to be worn.
Preferably, in the third step, in the lifting process, four constructors at the ends of the four pull ropes need to slightly apply external force, so that the steel truss to be installed is in a balanced state in the lifting process, and meanwhile, the steel truss to be installed can be prevented from colliding with the installed steel truss in the lifting process.
Preferably, in the third step, in the lifting process, when the steel truss to be installed is to reach the highest position, the lifting speed is reduced, and at the moment, the fifth constructor observes whether the connector of the steel truss to be installed is damaged or not, so that the steel truss to be installed is ensured to be not damaged in the lifting process.
Preferably, in the fourth step, when the interface is inspected, an edge of the interface may be warped or worn, and if the edge is warped or the degree of wear is not large, the interface is qualified in docking.
Preferably, the fifth constructor communicates with the other four constructors through interphones.
Preferably, the fifth constructor can be replaced by a camera for monitoring the butt joint process through the eye observation interface.
(III) advantageous effects
Compared with the prior art, the invention provides a method for adjusting the position offset in the lifting process of a steel structure, which has the following beneficial effects:
This method of adjustment offset in steel construction lifting process installs the adjustment through the bottom at waiting to install the steel truss and draws the ware, and the stay cord length that the adjustment drawn ware down-runs is enough long, and the bottom stay cord figure of adjustment drawing ware is four, and the end of four stay cords is handheld through four constructors respectively, can make to wait to install the steel truss and obtain quick effectual adjustment at the in-process position of promotion, can ensure the accurate butt joint of steel construction interface, has ensured going on smoothly of steel construction.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
A method for adjusting position deviation in a steel structure lifting process comprises the following specific steps:
the method comprises the following steps: the lifting inspection, before lifting the steel truss to be installed, the interface of the steel truss to be installed is inspected, and then the interface of the installed steel truss is inspected, so that the interface of the steel truss to be installed and the interface of the installed steel truss are ensured to be free of damage;
Step two: installing an adjusting puller, wherein the adjusting puller is installed at the bottom of the steel truss to be installed, the length of a pull rope extending downwards from the adjusting puller is long enough, the number of the pull ropes at the bottom of the adjusting puller is four, the four pull ropes are arranged towards four different directions, and the tail ends of the four pull ropes are respectively held by four constructors;
step three: lifting the steel truss, lifting the steel truss to be installed upwards after the steel truss to be installed is inspected and installed, enabling the interface of the steel truss to be installed to be aligned with the interface of the installed steel truss, when the interface of the steel truss to be installed is close to the interface of the installed steel truss, needing a fifth constructor to stand at the top of the installed steel truss to observe whether the interface of the steel truss to be installed is aligned with the interface of the installed steel truss or not, and enabling the fifth constructor to apply different external forces and adjust the inclination angles of the steel truss to be installed after observing the inclination angles of the interfaces and inform four constructors on the ground, enabling the interface of the steel truss to be installed to be aligned with the interface of the installed steel truss, and finally enabling the interface of the steel truss to be installed to be in butt joint with the interface of the installed steel truss;
step four: and finally, checking, and ensuring that the butt joint is correct again by a fifth constructor after the butt joint of the steel truss to be installed and the joint of the installed steel truss is completed.
And in the first step, if the interface of the steel truss to be installed and the interface of the steel truss to be installed are damaged, the constructor is required to climb up to maintain.
And in the second step, when the four constructors hold the pull rope by hands, the anti-abrasion gloves need to be worn.
In the lifting process in the third step, four constructors at the tail ends of the four pull ropes need to slightly apply external force, so that the steel truss to be installed is in a balanced state in the lifting process, and meanwhile, the steel truss to be installed can be prevented from colliding with the installed steel truss in the lifting process.
In the third step, in the lifting process, when the steel truss to be installed is to reach the highest position, the lifting speed is reduced, and at the moment, the fifth constructor observes whether the interface of the steel truss to be installed is damaged or not, so that the steel truss to be installed is ensured to be not damaged in the lifting process.
In the fourth step, when the interface is checked, the phenomenon of edge warping or abrasion of the interface can occur, and if the edge warping or the abrasion degree is not large, the interface is qualified in butt joint.
The fifth constructor communicates with the other four constructors through the interphones.
And a fifth constructor can be replaced by a camera for monitoring through the butt joint process of the eye observation interface.
In conclusion, according to the method for adjusting the position deviation in the steel structure lifting process, when the method is used, the adjusting puller is installed at the bottom of the steel truss to be installed, the length of the pull rope extending downwards from the adjusting puller is long enough, the number of the pull ropes at the bottom of the adjusting puller is four, the tail ends of the four pull ropes are respectively held by four constructors, so that the position of the steel truss to be installed in the lifting process can be quickly and effectively adjusted, accurate butt joint of a steel structure interface can be ensured, and smooth steel structure construction is ensured.
It is to be noted that the term "comprises," "comprising," or any other variation thereof is intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in the process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. A method for adjusting position deviation in a steel structure lifting process is characterized by comprising the following specific steps:
the method comprises the following steps: the method comprises the following steps of (1) lifting inspection, wherein before a steel truss to be installed is lifted, an interface of the steel truss to be installed is inspected, and then an interface of the installed steel truss is inspected, so that the interface of the steel truss to be installed and the interface of the installed steel truss are not damaged;
Step two: installing an adjusting puller, wherein the adjusting puller is installed at the bottom of the steel truss to be installed, the length of a pull rope extending downwards from the adjusting puller is long enough, the number of the pull ropes at the bottom of the adjusting puller is four, the four pull ropes are arranged towards four different directions, and the tail ends of the four pull ropes are respectively held by four constructors;
step three: lifting the steel truss, lifting the steel truss to be installed upwards after the steel truss to be installed is inspected and installed, enabling an interface of the steel truss to be installed to be aligned with an interface of the installed steel truss, when the interface of the steel truss to be installed is close to the interface of the installed steel truss, needing a fifth constructor to stand at the top of the installed steel truss to observe whether the interface of the steel truss to be installed is aligned with the interface of the installed steel truss or not, and informing four constructors on the ground after observing the inclination angle of the interface, enabling the four constructors to apply different external forces and adjust the inclination angle of the steel truss to be installed, enabling the interface of the steel truss to be installed to be aligned with the interface of the installed steel truss, and finally enabling the interface of the steel truss to be installed to be butted with the interface of the installed steel truss;
step four: and finally, checking, and ensuring that the butt joint is correct again by a fifth constructor after the butt joint of the interface of the steel truss to be installed and the interface of the installed steel truss is completed.
2. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: and in the first step, if the interface of the steel truss to be installed and the interface of the steel truss to be installed are damaged, the constructor is required to climb up to maintain.
3. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: and in the second step, when the four constructors hold the pull rope by hands, the constructors need to wear the anti-abrasion gloves.
4. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: in the lifting process in the third step, four constructors at the tail ends of the four pull ropes need to slightly apply external force, so that the steel truss to be installed is in a balanced state in the lifting process, and meanwhile, the steel truss to be installed can be prevented from colliding with the installed steel truss in the lifting process.
5. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: in the third step, in the lifting process, when the steel truss to be installed is to reach the highest position, the lifting speed is reduced, and at the moment, a fifth constructor observes whether the connector of the steel truss to be installed is damaged or not, so that the steel truss to be installed is ensured to be not damaged in the lifting process.
6. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: in the fourth step, when the interface is checked, the phenomenon of edge warping or abrasion of the interface can occur, and if the edge warping or the abrasion degree is not large, the interface is qualified in butt joint.
7. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: and the fifth constructor communicates with the other four constructors through the interphones.
8. The method for adjusting the position deviation in the steel structure lifting process according to claim 1, wherein: and the fifth constructor can be replaced by a camera for monitoring through the butt joint process of the eye observation interface.
CN202210231921.3A 2022-03-10 2022-03-10 Method for adjusting position deviation in steel structure lifting process Pending CN114517586A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210231921.3A CN114517586A (en) 2022-03-10 2022-03-10 Method for adjusting position deviation in steel structure lifting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210231921.3A CN114517586A (en) 2022-03-10 2022-03-10 Method for adjusting position deviation in steel structure lifting process

Publications (1)

Publication Number Publication Date
CN114517586A true CN114517586A (en) 2022-05-20

Family

ID=81598965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210231921.3A Pending CN114517586A (en) 2022-03-10 2022-03-10 Method for adjusting position deviation in steel structure lifting process

Country Status (1)

Country Link
CN (1) CN114517586A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008034165A1 (en) * 2006-09-20 2008-03-27 Innovative Construction Techniques Pty Ltd A system for erecting and holding roof trusses
CN102953553A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Method for mounting large-span pipe truss by using boom luffing mechanism
CN107989380A (en) * 2016-10-27 2018-05-04 中交三航局第三工程有限公司 Steel truss gallery hydraulic synchronizing lifting construction technique
CN113503047A (en) * 2021-07-31 2021-10-15 中冶(上海)钢结构科技有限公司 Method for adjusting high-altitude position offset by traction in steel structure lifting process
CN113685040A (en) * 2021-08-25 2021-11-23 中电建十一局工程有限公司 Large-span steel truss hoisting construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008034165A1 (en) * 2006-09-20 2008-03-27 Innovative Construction Techniques Pty Ltd A system for erecting and holding roof trusses
CN102953553A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Method for mounting large-span pipe truss by using boom luffing mechanism
CN107989380A (en) * 2016-10-27 2018-05-04 中交三航局第三工程有限公司 Steel truss gallery hydraulic synchronizing lifting construction technique
CN113503047A (en) * 2021-07-31 2021-10-15 中冶(上海)钢结构科技有限公司 Method for adjusting high-altitude position offset by traction in steel structure lifting process
CN113685040A (en) * 2021-08-25 2021-11-23 中电建十一局工程有限公司 Large-span steel truss hoisting construction method

Similar Documents

Publication Publication Date Title
CN104993422B (en) Line inspection robot on-line and off-line device and line inspection robot on-line and off-line system provided with same
CN104631839B (en) Ultra-high overweight large span aerial vestibule construction method for lifting whole
CN103821372A (en) Method for installing trusses with different heights
CN104389268B (en) A kind of steel tower column with location structure and construction method for hanging thereof
CN111042540A (en) Construction method for aerial butt joint of ground suspension cables of super-large-span prestressed pipe truss
CN108678388B (en) Short mast multi-point integral lifting construction method for large-capacity circular storage tank
CN108756441A (en) A kind of hydraulic lifting flipped device and its hanging method for reducing tower
CN114517586A (en) Method for adjusting position deviation in steel structure lifting process
CN102864915A (en) Construction method for venue large space double-helix air pipes
CN117052138A (en) Sectional construction method of large-span steel girder
CN110552510A (en) construction method of assembled curved surface suspended ceiling
CN110593111B (en) Method for installing beam section of cable tower area
CN210214536U (en) A biasing hoisting structure for installation of giant truss
CN212609006U (en) Hoisting tool for cooling pipeline of flexible direct-current converter valve
CN104088468B (en) A kind of steel work Multi-section column lifting automatic decoupling device
CN212893474U (en) Reinforced concrete pipe installation device
CN218562082U (en) Bridge main body overhaul machine
CN215249037U (en) Assembled outer wall hoist and mount and fixed establishment
CN117513170A (en) Quick and accurate steel beam closure process
CN114673088B (en) Construction method applied to catwalk of space main cable suspension bridge
CN221253694U (en) Novel tool for inspecting 180-degree bent pipe of alumina dissolution device
CN212450267U (en) Large-scale PC component of assembled installation lifts by crane and turns over board frock equipment
CN113979285B (en) Sectional type three-stage two-lifting pipeline installation process and installation equipment
CN204040498U (en) A kind of steel work Multi-section column lifting automatic decoupling device
CN113957805A (en) Installation device and method for hanging water supply and drainage pipeline under bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220520