CN114411564A - Novel guardrail steel bar installation device and construction method - Google Patents
Novel guardrail steel bar installation device and construction method Download PDFInfo
- Publication number
- CN114411564A CN114411564A CN202210182147.1A CN202210182147A CN114411564A CN 114411564 A CN114411564 A CN 114411564A CN 202210182147 A CN202210182147 A CN 202210182147A CN 114411564 A CN114411564 A CN 114411564A
- Authority
- CN
- China
- Prior art keywords
- installation device
- guardrail
- guardrail reinforcement
- new
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 66
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 title abstract description 17
- 239000010959 steel Substances 0.000 title abstract description 17
- 238000013461 design Methods 0.000 claims abstract description 11
- 230000002787 reinforcement Effects 0.000 claims description 71
- 238000000034 method Methods 0.000 claims description 13
- 230000003014 reinforcing effect Effects 0.000 abstract 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/10—Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
- E01D19/103—Parapets, railings ; Guard barriers or road-bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
Description
技术领域technical field
本发明涉及新型护栏钢筋安装装置及施工方法,属于桥梁护栏施工技术领域。The invention relates to a novel guardrail reinforcement installation device and a construction method, and belongs to the technical field of bridge guardrail construction.
背景技术Background technique
随着国家基础建设的大力发展,施工标准化正日益成为主导趋势,同时大跨径桥梁建设日益增多,护栏的安全与质量更是重中之重。但常规的护栏钢筋施工很难满足精准、安全、便捷的要求,同时更难满足规范技术质量和施工标准化的要求,不仅预埋钢筋的位置定位,线型控制以及间距一直难以控制,导致大量施工时间、人员和机械的消耗,同时也使护栏的整体质量得不到保证,容易造成返工的现象。With the vigorous development of national infrastructure, construction standardization is increasingly becoming a dominant trend, and at the same time, the construction of large-span bridges is increasing, and the safety and quality of guardrails are the top priority. However, it is difficult to meet the requirements of precision, safety and convenience in the construction of conventional reinforcement bars for guardrails, and it is even more difficult to meet the requirements of technical quality and construction standardization. The consumption of time, personnel and machinery also makes the overall quality of the guardrail not guaranteed, which is easy to cause rework.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提供新型护栏钢筋安装装置及施工方法,解决了常规护栏钢筋安装作业时间长、线型差、间距控制难等问题,保证了工程质量和施工安全,同时提高了施工效率,加快了施工进度。The purpose of the present invention is to provide a new type of guardrail reinforcement installation device and construction method, which solves the problems of long operation time, poor line shape, and difficult spacing control for conventional guardrail reinforcement installation, ensures engineering quality and construction safety, and simultaneously improves construction efficiency and accelerates. construction progress.
为达到上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:
一种新型护栏钢筋安装装置,包括:A new type of guardrail reinforcement installation device, comprising:
支撑架;support frame;
线型控制架,与所述支撑架连接,所述线型控制架包括主体部和与所述主体部相连的定位块,所述定位块对护栏钢筋的顶部进行定位;a linear control frame, connected with the support frame, the linear control frame includes a main body part and a positioning block connected with the main body part, and the positioning block positions the top of the guardrail reinforcement;
固定架,与所述线型控制架相连,所述固定架控制所述新型护栏钢筋安装装置的稳定性。The fixing frame is connected with the linear control frame, and the fixing frame controls the stability of the new guardrail reinforcement installation device.
进一步地,所述支撑架包括支撑底座和可伸缩底座,所述可伸缩底座调整所述新型护栏钢筋安装装置的垂直度,所述支撑底座和所述可伸缩底座上安装有支撑套。Further, the support frame includes a support base and a retractable base, the retractable base adjusts the verticality of the new guardrail reinforcement installation device, and a support sleeve is installed on the support base and the retractable base.
进一步地,所述支撑套为方形。Further, the support sleeve is square.
进一步地,所述可伸缩底座包括可伸缩部和与所述可伸缩部相连的第一横杆,所述第一横杆与所述主体部相连,所述可伸缩部调节所述伸缩底座的高度。Further, the retractable base includes a retractable part and a first cross bar connected with the retractable part, the first cross bar is connected with the main body part, and the retractable part adjusts the movement of the retractable base. high.
进一步地,所述可伸缩部包括螺杆和与所述螺杆适配的螺孔。Further, the retractable part includes a screw rod and a screw hole adapted to the screw rod.
进一步地,所述主体部位于第一平面内,所述定位块自所述主体部的顶端向垂直于所述第一平面的方向延伸。Further, the main body portion is located in a first plane, and the positioning block extends from a top end of the main body portion in a direction perpendicular to the first plane.
进一步地,所述主体部近似A字型。Further, the main body portion is approximately A-shaped.
进一步地,所述主体部包括第一斜杆和第二斜杆,所述第一斜杆和所述第二斜杆的一端相连,所述第一斜杆和所述第二斜杆之间连接有若干第二横杆,若干第二横杆的长度不同。Further, the main body includes a first inclined rod and a second inclined rod, one end of the first inclined rod and the second inclined rod are connected, and the first inclined rod and the second inclined rod are connected between one end. A plurality of second transverse bars are connected, and the lengths of the plurality of second transverse bars are different.
一种新型护栏钢筋施工方法,所述方法适用于上述任一项所述的新型护栏钢筋安装装置中,所述方法包括:A new type of guardrail reinforcement construction method, the method is applicable to any one of the above-mentioned new type of guardrail reinforcement installation device, and the method comprises:
S1、根据设计图纸加工好新型护栏钢筋安装装置;S1. Process the new guardrail reinforcement installation device according to the design drawings;
S2、对施工部位进行精确放点;S2. Accurately place points on the construction site;
S3、将所述新型护栏钢筋安装装置放置到测量好的点上;S3, placing the new guardrail reinforcement installation device on the measured point;
S4、根据所述新型护栏钢筋安装装置的线型、间距完成护栏钢筋的安装。S4. Complete the installation of the guardrail reinforcement according to the line type and spacing of the new guardrail reinforcement installation device.
进一步地,在步骤S3后,还包括:使用水平仪对所述新型护栏钢筋安装装置进行竖直度调整。Further, after step S3, the method further includes: using a spirit level to adjust the verticality of the new guardrail reinforcement installation device.
本发明的有益效果在于:提供了新型护栏钢筋安装装置及施工方法,该装置包括支撑架、线型控制架和固定架,线型控制架与支撑架连接,线型控制架包括主体部和与主体部相连的定位块,定位块对护栏钢筋的顶部进行定位,固定架与线型控制架相连,用于控制新型护栏钢筋安装装置的稳定性;根据设计图纸提前将新型护栏钢筋安装装置设计好,在需要安装护栏钢筋时,将该装置放置到已测量好的点上,由于该新型护栏钢筋安装装置是按照设计图纸提前设计好的,与护栏钢筋形状相同,因此,可以很容易的通过新型护栏钢筋安装装置将护栏钢筋安装好,解决了常规护栏钢筋安装作业时间长、线型差、间距控制难等问题,保证了工程质量和施工安全,同时提高了施工效率,加快了施工进度。The beneficial effects of the present invention are as follows: a new guardrail reinforcement installation device and construction method are provided, the device includes a support frame, a linear control frame and a fixing frame, the linear control frame is connected with the support frame, and the linear control frame includes a main body part and a The positioning block connected to the main body, the positioning block locates the top of the guardrail steel bar, the fixing frame is connected with the linear control frame, and is used to control the stability of the new guardrail steel bar installation device; the new guardrail steel bar installation device is designed in advance according to the design drawings. , When the guardrail reinforcement needs to be installed, the device should be placed on the measured point. Since the new guardrail reinforcement installation device is designed in advance according to the design drawings and has the same shape as the guardrail reinforcement, it can be easily passed through the new type. The guardrail reinforcement installation device installs the guardrail reinforcement, which solves the problems of long installation time, poor line shape, and difficult spacing control of conventional guardrail reinforcement, ensures the quality of the project and construction safety, while improving the construction efficiency and speeding up the construction progress.
上述说明仅是本发明技术方案的概述,为了能够更清楚了解本发明的技术手段,并可依照说明书的内容予以实施,以下以本发明的较佳实施例并配合附图详细说明如后。The above description is only an overview of the technical solution of the present invention. In order to understand the technical means of the present invention more clearly, and implement it according to the content of the description, the preferred embodiments of the present invention are described in detail below with the accompanying drawings.
附图说明Description of drawings
图1为一种新型护栏钢筋安装装置的主视图;Fig. 1 is a front view of a new type of guardrail reinforcement installation device;
图2为一种新型护栏钢筋安装装置的侧视图;Figure 2 is a side view of a new type of guardrail reinforcement installation device;
图3为一种新型护栏钢筋安装装置的俯视图;Fig. 3 is a top view of a new type of guardrail reinforcement installation device;
图4为一种新型护栏钢筋施工方法的流程图。Fig. 4 is a flow chart of a new construction method of guardrail reinforcement.
100-新型护栏钢筋安装装置,1-支撑架,11-支撑底座,12-可伸缩底座,121-可伸缩部,1211-螺杆,122-第一横杆,13-支撑套,2-线型控制架,21-主体部,211-第一斜杆,212-第二斜杆,213-第二横杆,22-定位块,3-固定架,31-第一杆体,32-第二杆体。100-New type guardrail reinforcement installation device, 1-support frame, 11-support base, 12-retractable base, 121-retractable part, 1211-screw, 122-first cross bar, 13-support sleeve, 2-line type Control frame, 21-main body, 211-first inclined rod, 212-second inclined rod, 213-second cross rod, 22-positioning block, 3-fixed frame, 31-first rod body, 32-second rod body .
具体实施方式Detailed ways
下面结合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments. The following examples are intended to illustrate the present invention, but not to limit the scope of the present invention.
下面结合附图和实施例,对本申请的具体实施方式作进一步详细描述。以下实施例用于说明本申请,但不用来限制本申请的范围。The specific implementations of the present application will be described in further detail below with reference to the accompanying drawings and embodiments. The following examples are used to illustrate the present application, but are not intended to limit the scope of the present application.
在本申请的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请保护范围的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”等的特征可以明示或者隐含地包括一个或者更多个该特征。在本申请创造的描述中,除非另有说明,“多个”的含义是两个或两个以上。In the description of this application, it should be understood that the terms "center", "portrait", "horizontal", "top", "bottom", "front", "rear", "left", "right", " The orientations or positional relationships indicated by vertical, horizontal, top, bottom, inner, and outer are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and The description is simplified rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as limiting the scope of protection of the present application. In addition, the terms "first", "second", etc. are used for descriptive purposes only, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first", "second", etc., may expressly or implicitly include one or more of that feature. In the description created in the present application, unless otherwise specified, "plurality" means two or more.
在本申请的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以通过具体情况理解上述术语在本申请中的具体含义。In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection Connection, or integral connection; can be mechanical connection, can also be electrical connection; can be directly connected, can also be indirectly connected through an intermediate medium, can be internal communication between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood through specific situations.
请参考图1至图3,本申请一较佳实施例提供了一种新型护栏钢筋安装装置100,包括:支撑架1、与支撑架1连接的线型控制架2以及与线型控制架2相连的固定架3。Referring to FIGS. 1 to 3 , a preferred embodiment of the present application provides a novel guardrail
线型控制架2包括主体部21和与主体部21相连的定位块22。在本实施例中,由于护栏钢筋为近似A字型,因此,为了方便安装护栏钢筋,主体部21同样设置成近似A字型。进一步地,主体部21包括第一斜杆211和第二斜杆212,第一斜杆211和第二斜杆212的一端相连,另一端向两个相反方向相离。第一斜杆211和第二斜杆212之间连接有若干第二横杆213,若干第二横杆213的长度不同。如此设置,进一步提高了线型控制架2的稳固性。The
定位块22用于对护栏钢筋的顶部进行定位。具体的,将线型控制架2所在平面定义为第一平面(未图示),主体部21位于第一平面内,定位块22自主体部21的顶端向垂直于第一平面的方向延伸,使得定位块22突出主体部21,在实际安装护栏钢筋时,更加方便对护栏钢筋的定位。The
支撑架1作为整个新型护栏钢筋安装装置100的支撑部位,位于新型护栏钢筋安装装置100的底部。支撑架1包括支撑底座11和可伸缩底座12,当需要安装护栏钢筋时,将支撑底座11安装在预安装护栏钢筋的地面上。为了提高支撑架1的稳固性,在其中一个实施例中,支撑底座11和可伸缩底座12上安装有支撑套13。而为了进一步提高支撑架1的稳固性,将支撑套13设置为方形。The support frame 1 is located at the bottom of the new type of guardrail
可伸缩底座12用于调整新型护栏钢筋安装装置100的垂直度,使得待施工地面不论是否平整,新型护栏钢筋安装装置100的中轴线始终与待施工地面垂直,提高该装置100的适用范围。具体的,可伸缩底座12包括可伸缩部121和与可伸缩部121相连的第一横杆122,第一横杆122与主体部相连,可伸缩部121用于调节伸缩底座12的高度。在本实施例中,可伸缩部121包括螺杆1211和与螺杆1211适配的螺孔(未图示),在实际施工时,螺杆1211的一端与待施工地面抵持,另一端穿过螺孔,当需要调整伸缩底座12的高度时,只需要旋转螺杆1211即可。当然,在其中实施例中,可伸缩部121还可以为其他结构,本申请不对此作限定。The retractable base 12 is used to adjust the verticality of the new guardrail
固定架3用于控制新型护栏钢筋安装装置100的稳定性。在本实施例中,固定架3包括第一杆体31和与第一杆体31相连的第二杆体32,第一杆体31与地面垂直,第二杆体32与地面平行。需要说明的是,固定架3除了可以用于控制该安装装置100的稳定性外,还可以在放置、搬运该装置100时,作为握持部位,以方便工作人员更好的进行施工。The fixing
请参考图4所示,图4为本申请一实施例提供的一种新型护栏钢筋施工方法的流程图,该方法适用于上述新型护栏钢筋安装装置中。该方法包括:S1、根据设计图纸加工好新型护栏钢筋安装装置;S2、对施工部位进行精确放点;S3、将新型护栏钢筋安装装置放置到测量好的点上;S4、根据新型护栏钢筋安装装置的线型、间距完成护栏钢筋的安装。Please refer to FIG. 4 , which is a flowchart of a new construction method for guardrail reinforcement provided by an embodiment of the present application, and the method is applicable to the above-mentioned novel guardrail reinforcement installation device. The method includes: S1, processing a new type of guardrail reinforcement installation device according to the design drawing; S2, accurately placing points on the construction site; S3, placing the new type guardrail reinforcement installation device on the measured point; S4, according to the new type guardrail reinforcement installation The line type and spacing of the device complete the installation of the guardrail reinforcement.
可选地,在步骤S1中,设计图纸主要对护栏钢筋的形状、间距、保护层厚度以及线型进行设计。Optionally, in step S1, the design drawings mainly design the shape, spacing, thickness of protective layer and line type of the reinforcement bars of the guardrail.
可选地,在将新型护栏钢筋安装装置放置到提前测量好的点上后,为了保证该装置的中轴线与地面垂直,避免对后续的护栏钢筋的安装产生影响,在步骤S3后,该方法还包括:使用水平仪对新型护栏钢筋安装装置进行竖直度调整。Optionally, after the new guardrail reinforcement installation device is placed on the point measured in advance, in order to ensure that the central axis of the device is perpendicular to the ground and avoid affecting the subsequent installation of the guardrail reinforcement, after step S3, the method Also includes: using a spirit level to adjust the verticality of the new guardrail reinforcement installation device.
综上,本申请提供了新型护栏钢筋安装装置及施工方法,该装置包括支撑架、线型控制架和固定架,线型控制架与支撑架连接,线型控制架包括主体部和与主体部相连的定位块,定位块对护栏钢筋的顶部进行定位,固定架与线型控制架相连,用于控制新型护栏钢筋安装装置的稳定性;根据设计图纸提前将新型护栏钢筋安装装置设计好,在需要安装护栏钢筋时,将该装置放置到已测量好的点上,由于该新型护栏钢筋安装装置是按照设计图纸提前设计好的,与护栏钢筋形状相同,因此,可以很容易的通过新型护栏钢筋安装装置将护栏钢筋安装好,解决了常规护栏钢筋安装作业时间长、线型差、间距控制难等问题,保证了工程质量和施工安全,同时提高了施工效率,加快了施工进度。To sum up, the present application provides a new guardrail reinforcement installation device and construction method, the device includes a support frame, a linear control frame and a fixing frame, the linear control frame is connected with the support frame, and the linear control frame includes a main body part and a main body part. Connected positioning block, the positioning block locates the top of the guardrail steel bar, and the fixed frame is connected with the linear control frame, which is used to control the stability of the new guardrail steel bar installation device; according to the design drawings, the new guardrail steel bar installation device is designed in advance. When the guardrail reinforcement needs to be installed, place the device on the measured point. Since the new guardrail reinforcement installation device is designed in advance according to the design drawings and has the same shape as the guardrail reinforcement, it can be easily passed through the new guardrail reinforcement. The installation device installs the steel bars of the guardrail, which solves the problems of long installation time, poor line shape and difficult spacing control of conventional guardrail steel bars, ensures the quality of the project and the safety of the construction, and at the same time improves the construction efficiency and accelerates the construction progress.
以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The technical features of the above-described embodiments can be combined arbitrarily. For the sake of brevity, all possible combinations of the technical features in the above-described embodiments are not described. However, as long as there is no contradiction between the combinations of these technical features, All should be regarded as the scope described in this specification.
以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only represent several embodiments of the present invention, and the descriptions thereof are specific and detailed, but should not be construed as a limitation on the scope of the invention patent. It should be pointed out that for those of ordinary skill in the art, without departing from the concept of the present invention, several modifications and improvements can also be made, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention should be subject to the appended claims.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210182147.1A CN114411564A (en) | 2022-02-25 | 2022-02-25 | Novel guardrail steel bar installation device and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210182147.1A CN114411564A (en) | 2022-02-25 | 2022-02-25 | Novel guardrail steel bar installation device and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114411564A true CN114411564A (en) | 2022-04-29 |
Family
ID=81261280
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210182147.1A Pending CN114411564A (en) | 2022-02-25 | 2022-02-25 | Novel guardrail steel bar installation device and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114411564A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN208105045U (en) * | 2018-03-21 | 2018-11-16 | 邳州远通公路工程有限公司 | A kind of Bridge guardrail reinforcing bar integrated positioning device |
KR20190041189A (en) * | 2017-10-12 | 2019-04-22 | 현대건설주식회사 | Modular work platform of a long span bridge main tower rebar and construction method using the same |
CN111270606A (en) * | 2020-02-11 | 2020-06-12 | 山东省交通规划设计院有限公司 | Connecting structure of assembled steel bridge floor concrete anti-collision guardrail and complete construction method thereof |
KR20210017720A (en) * | 2019-08-09 | 2021-02-17 | 한국도로공사 | Vehicle protection wall connecting apparatus and method for constructing vehicle protection wall of bridge using the same |
CN212582432U (en) * | 2020-05-27 | 2021-02-23 | 中国水利水电第十工程局有限公司 | Bridge anticollision barrier reinforcing bar protective layer controlling means |
CN214089463U (en) * | 2020-09-10 | 2021-08-31 | 中交一公局桥隧工程有限公司 | Bridge concrete anticollision barrier steel bar installation bed-jig |
CN113944104A (en) * | 2021-10-26 | 2022-01-18 | 中交路桥建设有限公司 | Hanging bracket convenient for positioning and moving horizontal steel bars of concrete guardrail and construction method |
-
2022
- 2022-02-25 CN CN202210182147.1A patent/CN114411564A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20190041189A (en) * | 2017-10-12 | 2019-04-22 | 현대건설주식회사 | Modular work platform of a long span bridge main tower rebar and construction method using the same |
CN208105045U (en) * | 2018-03-21 | 2018-11-16 | 邳州远通公路工程有限公司 | A kind of Bridge guardrail reinforcing bar integrated positioning device |
KR20210017720A (en) * | 2019-08-09 | 2021-02-17 | 한국도로공사 | Vehicle protection wall connecting apparatus and method for constructing vehicle protection wall of bridge using the same |
CN111270606A (en) * | 2020-02-11 | 2020-06-12 | 山东省交通规划设计院有限公司 | Connecting structure of assembled steel bridge floor concrete anti-collision guardrail and complete construction method thereof |
CN212582432U (en) * | 2020-05-27 | 2021-02-23 | 中国水利水电第十工程局有限公司 | Bridge anticollision barrier reinforcing bar protective layer controlling means |
CN214089463U (en) * | 2020-09-10 | 2021-08-31 | 中交一公局桥隧工程有限公司 | Bridge concrete anticollision barrier steel bar installation bed-jig |
CN113944104A (en) * | 2021-10-26 | 2022-01-18 | 中交路桥建设有限公司 | Hanging bracket convenient for positioning and moving horizontal steel bars of concrete guardrail and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060357A (en) | The bracing device of Assembled wall panels | |
CN205445093U (en) | Buried bolt device in advance | |
CN114411564A (en) | Novel guardrail steel bar installation device and construction method | |
CN112681760A (en) | Construction method of BIM auxiliary inclined structural column | |
CN102505864A (en) | Method for assembling fixed ends of scaffold of large-volume triangular variable-section tubular truss structure | |
CN205745938U (en) | The mounting bracket of a kind of LED display and hoisting structure | |
CN213205009U (en) | Component mounting and positioning guide frame | |
CN216339588U (en) | A foundation pit support beam structure | |
CN214144807U (en) | Large-diameter steel sleeve mounting device | |
CN212516334U (en) | Electric power warning sign convenient to adjust | |
CN203222810U (en) | Steel column and base structure system | |
CN222183920U (en) | A split step structure for spiral staircase | |
KR20100004374U (en) | Walls supporter of a truss type | |
CN218203917U (en) | Positioning fine-adjustment device for installing arch rib sections with dumbbell-shaped cross sections of continuous beam arch bridge | |
CN107860376B (en) | Measuring and positioning method for tripod of large-scale intercooling tower cone section | |
CN216380268U (en) | External reinforcing steel bar positioning device | |
CN112982961B (en) | A kind of quick pre-buried silo structure auxiliary steel structure silo wall | |
CN205637632U (en) | Special instrument holder is rectified in installation of shaped steel post | |
CN218678305U (en) | Adjustable cable tray device | |
CN219298784U (en) | Quick detach formula building engineering template bearing structure | |
CN218479500U (en) | Small-size operation platform of vertical aluminum alloy template | |
CN111335357A (en) | A kind of pipe gallery formwork support system and construction method thereof | |
CN221955700U (en) | Quick mounting structure for tower crane attached wall | |
CN219754011U (en) | Portable tripod leg L-shaped steel supporting structure | |
CN215168042U (en) | Concrete structure beam template fixing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220429 |