CN114254966B - Method for matching resources by using dimension groups - Google Patents
Method for matching resources by using dimension groups Download PDFInfo
- Publication number
- CN114254966B CN114254966B CN202210197370.3A CN202210197370A CN114254966B CN 114254966 B CN114254966 B CN 114254966B CN 202210197370 A CN202210197370 A CN 202210197370A CN 114254966 B CN114254966 B CN 114254966B
- Authority
- CN
- China
- Prior art keywords
- dimension
- resource
- demand
- unit
- units
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/087—Inventory or stock management, e.g. order filling, procurement or balancing against orders
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/02—Marketing; Price estimation or determination; Fundraising
- G06Q30/0283—Price estimation or determination
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Development Economics (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Accounting & Taxation (AREA)
- Finance (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Educational Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a method for matching resources by using dimension groups, which comprises the following steps: (1) Maintaining the dimension of the resource units, wherein the resource units form resources, and the dimension of the resource units designates specific resource units; (2) Maintaining the matching relationship between the resource unit dimension and the resource unit dimension group, wherein each resource unit dimension group corresponds to one resource; (3) When the demand unit dimension group is matched with the resource unit dimension group, allocating resources corresponding to the resource unit dimension group to the demands corresponding to the demand unit dimension group; the demand units form demands, the demand unit dimensions specify specific demand units, and each demand unit dimension group corresponds to one demand. The method of the invention can shorten the decision period.
Description
Technical Field
The invention relates to the technical field of supply chain intelligent decision. In particular to a method for matching resources by using dimension groups.
Background
In a consumer-centric market environment, the supply chain needs to be customized to meet the customer needs, both in terms of mass production to maintain efficiency and cost advantages. A particular order, forecast, or contract configures a particular bill of materials, with particular sources of supply including inventory, future arrival plans, suppliers, production lines, and places of inventory. For non-standard matching requirements, product structures, bill of materials or material codes need to be redefined; the management and operation costs are greatly increased and the decision cycle is also affected.
Disclosure of Invention
Therefore, the technical problem to be solved by the present invention is to provide a method for matching resources by using dimension groups, which can shorten the decision period.
In order to solve the technical problems, the invention provides the following technical scheme:
the method for matching resources by using the dimension group comprises the following steps:
(1) Maintaining the dimension of the resource units, wherein the resource units form resources, and the dimension of the resource units designates specific resource units;
(2) Maintaining the matching relationship between the resource unit dimension and the resource unit dimension group, wherein each resource unit dimension group corresponds to one resource;
(3) When the demand unit dimension group is matched with the resource unit dimension group, resources corresponding to the resource unit dimension group are allocated to the demands corresponding to the demand unit dimension group; the demand units constitute demands, the demand unit dimensions specify specific demand units, and each demand unit dimension group corresponds to a demand.
The method for matching resources by using dimension groups comprises the following steps of (1): according to the practical conditions (known requirements, production requirements and order requirements), different primary resource dimensions are used for appointing primary resource units in the resource units, and when the resource units have different primary resource dimensions, the resource units correspond to two or more different primary resource dimensions.
The method for matching resources by using dimension groups comprises the following steps of (1): if a certain primary resource dimension designates primary resource units belonging to two or more types according to actual conditions, designating secondary resource units in the primary resource units by using different secondary resource dimensions according to the actual conditions; and repeating the steps until the N-level resource units belong to the same resource unit class (not reclassifiable) according to the actual situation, wherein N is a positive integer larger than 1.
The method for matching resources by using dimension groups comprises the following steps of (2): each resource unit dimension group comprises one or more than one primary resource dimension, a secondary resource dimension corresponding to each primary resource dimension, a secondary resource dimension, and a tertiary resource dimension \8230 \ 8230 \ and N-1 level resource dimensions, and N-1 level resource dimensions corresponding to each N-1 level resource dimension, wherein N is a positive integer greater than 1.
In the method for matching resources by using dimension groups, in step (3): according to the method for maintaining the resource unit dimension, the requirement is converted into a demand unit, a first-level demand unit in the demand unit is specified by the first-level demand dimension, and when the demand unit has different first-level demand dimensions, the demand unit corresponds to two or more different first-level demand dimensions.
In the method for matching resources by using dimension groups, in step (3): if a certain primary demand dimension designates primary demand units belonging to two or more types, designating secondary demand units in the primary demand units by using different secondary demand dimensions; by analogy, until the M-level demand units belong to the same type of demand units [ cannot be reclassified ], M is a positive integer greater than 1.
In the method for matching resources by using dimension groups, in step (3): each demand unit dimension group comprises one or more than one primary demand dimension, a secondary demand dimension corresponding to each primary demand dimension, a secondary demand dimension, and a tertiary demand dimension \8230correspondingto each secondary demand dimension, wherein M is a positive integer larger than 1, and M-level demand dimensions corresponding to M-1 demand dimensions and M-level demand dimensions corresponding to each M-1 demand dimension.
The method for matching resources by using dimension groups comprises the following steps in step (2):
(2-1) finding out the same resource unit dimensions involved in all the resource unit dimension groups, and respectively generating a resource unit dimension and a resource unit dimension corresponding list according to the same resource unit dimensions;
(2-2) judging whether the resource unit dimension groups conflict with each other;
(2-3) if there is a conflict between the resource unit dimension groups, generating a resource unit dimension group conflict list.
The method for matching resources by using dimension groups comprises the following steps of (3): and when the demand unit dimension group is matched with the resource unit dimension group, determining whether the resources corresponding to the resource unit dimension group can be allocated to the demands corresponding to the demand unit dimension group according to the resource unit dimension group priority, the resource unit dimension group conflict list and the demand unit dimension group priority.
The method for matching resources by using dimension groups comprises the following steps of (1): according to the practical conditions (known requirements, production requirements and order requirements), assigning primary resource units in the resource units by using different primary resource dimensions, wherein when the resource units have different primary resource dimensions, the resource units correspond to two or more different primary resource dimensions; if a certain primary resource dimension designates primary resource units belonging to two or more types according to actual conditions, designating secondary resource units in the primary resource units by using different secondary resource dimensions according to the actual conditions; by analogy, until the N-level resource units belong to the same resource unit class (not reclassifiable) according to the actual situation, N is a positive integer greater than 1;
in step (2): each resource unit dimension group comprises one or more than one primary resource dimension, a secondary resource dimension corresponding to each primary resource dimension, a secondary resource dimension, and a tertiary resource dimension \8230correspondingto each secondary resource dimension, \8230, N-1 level resource dimensions, and N-1 level resource dimensions corresponding to each N-1 level resource dimension, wherein N is a positive integer greater than 1;
in step (3): converting the demand into a demand unit according to a resource unit dimension maintenance method, and specifying a primary demand unit in the demand unit by using a primary demand dimension, wherein when the demand unit has different primary demand dimensions, the demand unit corresponds to two or more different primary demand dimensions; if a certain primary demand dimension designates primary demand units belonging to two or more types, designating secondary demand units in the primary demand units by using different secondary demand dimensions; by analogy, until the M-level demand units belong to the same type demand units (cannot be reclassified), M is a positive integer larger than 1; each requirement unit dimension group comprises one or more than one primary requirement dimension, a secondary requirement dimension corresponding to each primary requirement dimension, a secondary requirement dimension, and a tertiary requirement dimension \8230; \ 8230;, an M-1 level requirement dimension, and an M-1 level requirement dimension corresponding to each M-1 level requirement dimension, wherein M is a positive integer greater than 1.
The method for matching resources by using dimension groups comprises the following steps in step (2):
(2-1) finding out the same resource unit dimensions involved in all the resource unit dimension groups, and respectively generating a resource unit dimension and a resource unit dimension corresponding list according to the same resource unit dimensions;
(2-2) judging whether the resource unit dimension groups conflict with each other;
(2-3) if there is a conflict between the resource unit dimension groups, generating a resource unit dimension group conflict list.
The method for matching resources by using dimension groups comprises the following steps of (3): when the demand unit dimension group is matched with the resource unit dimension group, whether the resources corresponding to the resource unit dimension group can be allocated to the demands corresponding to the demand unit dimension group is determined according to the resource unit dimension group priority, the resource unit dimension group conflict list and the demand unit dimension group priority.
The technical scheme of the invention achieves the following beneficial technical effects: the inventive application heuristic artificial intelligence algorithm is widely suitable for complex decision conditions, efficiently understands and controls decision data quantity, can effectively shorten decision period, can effectively meet given constraint conditions and tends to optimal decision.
Drawings
FIG. 1 is a flow chart of a method of the present invention for matching resources using dimension groups.
Detailed Description
Example 1
The method for matching resources by using dimension groups in the embodiment comprises the following steps:
(1) Maintaining the dimension of the resource units, wherein the resource units form resources, and the dimension of the resource units designates specific resource units;
according to the practical conditions (known requirements, production requirements and order requirements), assigning primary resource units in the resource units by using different primary resource dimensions, wherein when the resource units have different primary resource dimensions, the resource units correspond to two or more different primary resource dimensions; if a certain primary resource dimension designates primary resource units belonging to two or more types according to actual conditions, designating secondary resource units in the primary resource units by using different secondary resource dimensions according to the actual conditions; by analogy, until N-level resource units belong to the same resource unit (which cannot be reclassified) according to actual conditions, wherein N is a positive integer greater than 1;
(2) Maintaining the matching relationship between the resource unit dimension and the resource unit dimension group, wherein each resource unit dimension group corresponds to one resource;
each resource unit dimension group comprises one or more than one primary resource dimension, a secondary resource dimension corresponding to each primary resource dimension, a secondary resource dimension, and a tertiary resource dimension \8230correspondingto each secondary resource dimension, \8230, an N-1 level resource dimension, and an N level resource dimension corresponding to each N-1 level resource dimension, wherein N is a positive integer greater than 1;
(3) When the demand unit dimension group is matched with the resource unit dimension group, allocating resources corresponding to the resource unit dimension group to the demands corresponding to the demand unit dimension group; the demand units form demands, the demand unit dimensions specify specific demand units, and each demand unit dimension group corresponds to one demand.
Converting the demand into a demand unit according to a resource unit dimension maintenance method, and designating a primary demand unit in the demand unit by using a primary demand dimension, wherein when the demand unit has different primary demand dimensions, the demand unit corresponds to two or more different primary demand dimensions; if a certain primary demand dimension designates primary demand units belonging to two or more types, designating secondary demand units in the primary demand units by using different secondary demand dimensions; by analogy, until the M-level demand units belong to the same type demand units (cannot be reclassified), M is a positive integer larger than 1; each demand unit dimension group comprises one or more than one primary demand dimension, a secondary demand dimension corresponding to each primary demand dimension, a secondary demand dimension, and a tertiary demand dimension \8230correspondingto each secondary demand dimension, wherein M is a positive integer larger than 1, and M-level demand dimensions corresponding to M-1 demand dimensions and M-level demand dimensions corresponding to each M-1 demand dimension.
The following describes the method of matching resources using dimension groups in example 1 by taking computer production as an example:
the requirements are shown in table 1:
convert the demand into a set of demand unit dimensions, as shown in Table 2:
resources are shown in table 3:
as can be seen from tables 2 and 3: and matching the demand unit dimension group with the resource unit dimension group, and allocating the resources corresponding to the resource unit dimension group to the demands corresponding to the demand unit dimension group.
Assume that the resources are as shown in table 4:
as can be seen from tables 2 and 4: the demand unit dimension group cannot be matched with the resource unit dimension group, and resources cannot be allocated to the demands corresponding to the demand unit dimension group. At this time, the demand belongs to a non-standard demand, and the product structure, the bill of material or the material code does not need to be redefined, and only a 4T secondary resource unit (secondary resource dimension) needs to be added under a primary resource unit (primary resource dimension) of the resource unit of the hard disk (as shown in table 5), so that the management and operation costs are not greatly increased for the non-standard demand, and the decision cycle is shortened.
Example 2
The present example differs from example 1 in that:
the step (2) comprises the following steps:
(2-1) finding the same resource unit dimensions involved in all the resource unit dimension groups, and respectively generating a resource unit dimension and a resource unit dimension corresponding list according to the same resource unit dimensions.
(2-2) judging whether the resource unit dimension groups conflict with each other; the dimension groups of the secondary resource units have conflict with each other, and the low priority cannot be met.
(2-3) if there is a conflict between the resource unit dimension groups, generating a resource unit dimension group conflict list.
In step (3): and when the demand unit dimension group is matched with the resource unit dimension group, determining whether the resources corresponding to the resource unit dimension group can be allocated to the demands corresponding to the demand unit dimension group according to the resource unit dimension group priority, the resource unit dimension group conflict list and the demand unit dimension group priority.
The following describes the method of matching resources using dimension groups in example 2 by taking computer production as an example:
demand one is shown in table 6:
convert the demand into a set of demand cell dimensions, as shown in Table 7:
requirement two is shown in table 8:
convert demand two into a set of demand unit dimensions, as shown in Table 9:
resources are shown in table 10:
since the priority of demand one is higher than that of demand two, it can be seen from tables 7, 9 and 10 that: the resource is allocated to one of the demands, and the second demand can only be partially satisfied.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications derived therefrom are intended to be within the scope of the claims of this patent.
Claims (4)
1. The method for matching resources by using the dimension group is characterized by comprising the following steps:
(1) Maintaining the dimension of the resource units, wherein the resource units form resources, and the dimension of the resource units designates specific resource units;
according to the practical situation, the primary resource units in the resource units are designated by different primary resource dimensions, and when the resource units have different primary resource dimensions, the resource units correspond to two or more different primary resource dimensions;
if a certain primary resource dimension designates primary resource units belonging to two or more types according to actual conditions, designating secondary resource units in the primary resource units by using different secondary resource dimensions according to the actual conditions; in this way, until N-level resource units belong to the same type of resource units according to actual conditions, N is a positive integer greater than 1;
(2) Maintaining the matching relationship between the resource unit dimension and the resource unit dimension group, wherein each resource unit dimension group corresponds to one resource;
(2-1) finding out the same resource unit dimensions related in all the resource unit dimension groups, and respectively generating a resource unit dimension and a resource unit dimension corresponding list according to the same resource unit dimensions;
(2-2) judging whether the resource unit dimension groups conflict with each other;
(2-3) if the resource unit dimension groups conflict with each other, generating a resource unit dimension group conflict list;
(3) When the demand unit dimension group is matched with the resource unit dimension group, allocating resources corresponding to the resource unit dimension group to the demands corresponding to the demand unit dimension group; the demand units form demands, the dimensions of the demand units specify specific demand units, and each demand unit dimension group corresponds to one demand;
converting the demand into a demand unit according to a resource unit dimension maintenance method, and specifying a primary demand unit in the demand unit by using a primary demand dimension, wherein when the demand unit has different primary demand dimensions, the demand unit corresponds to two or more different primary demand dimensions;
and when the demand unit dimension group is matched with the resource unit dimension group, determining whether the resources corresponding to the resource unit dimension group can be allocated to the demands corresponding to the demand unit dimension group according to the resource unit dimension group priority, the resource unit dimension group conflict list and the demand unit dimension group priority.
2. The method for matching resources by using dimension groups according to claim 1, wherein in step (2): each resource unit dimension group comprises one or more than one primary resource dimension, a secondary resource dimension corresponding to each primary resource dimension, a secondary resource dimension, and a tertiary resource dimension \8230 \ 8230 \ and N-1 level resource dimensions, and N-1 level resource dimensions corresponding to each N-1 level resource dimension, wherein N is a positive integer greater than 1.
3. The method for matching resources by using dimension groups according to claim 1, wherein in step (3): if a certain primary demand dimension designates primary demand units belonging to two or more types, designating secondary demand units in the primary demand units by using different secondary demand dimensions; and repeating the steps until the M-level demand units belong to the same type of demand units, wherein M is a positive integer larger than 1.
4. The method for matching resources by using dimension groups according to claim 3, wherein in step (3): each requirement unit dimension group comprises one or more than one primary requirement dimension, a secondary requirement dimension corresponding to each primary requirement dimension, a secondary requirement dimension, and a tertiary requirement dimension \8230; \ 8230;, an M-1 level requirement dimension, and an M-1 level requirement dimension corresponding to each M-1 level requirement dimension, wherein M is a positive integer greater than 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210197370.3A CN114254966B (en) | 2022-03-02 | 2022-03-02 | Method for matching resources by using dimension groups |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210197370.3A CN114254966B (en) | 2022-03-02 | 2022-03-02 | Method for matching resources by using dimension groups |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114254966A CN114254966A (en) | 2022-03-29 |
CN114254966B true CN114254966B (en) | 2022-11-15 |
Family
ID=80797264
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210197370.3A Active CN114254966B (en) | 2022-03-02 | 2022-03-02 | Method for matching resources by using dimension groups |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114254966B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102207869A (en) * | 2011-06-03 | 2011-10-05 | 用友软件股份有限公司 | Strategy matching device and strategy matching method |
CN102932279A (en) * | 2012-10-30 | 2013-02-13 | 北京邮电大学 | Multidimensional resource scheduling system and method for cloud environment data center |
CN108388564A (en) * | 2017-02-03 | 2018-08-10 | 百度在线网络技术(北京)有限公司 | Inquiry processing method, device and its equipment |
CN109064357A (en) * | 2018-08-22 | 2018-12-21 | 潘皓波 | A kind of tour guide's recommender system and method in real time |
CN111597042A (en) * | 2020-05-11 | 2020-08-28 | Oppo广东移动通信有限公司 | Service thread running method and device, storage medium and electronic equipment |
CN112995201A (en) * | 2019-01-11 | 2021-06-18 | 深圳联合产权交易所股份有限公司 | Resource value evaluation processing method based on cloud platform and related device |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10565229B2 (en) * | 2018-05-24 | 2020-02-18 | People.ai, Inc. | Systems and methods for matching electronic activities directly to record objects of systems of record |
CN105630601A (en) * | 2014-11-03 | 2016-06-01 | 阿里巴巴集团控股有限公司 | Resource allocation method and system based on real-time computing |
CN111260322A (en) * | 2020-01-16 | 2020-06-09 | 襄阳航泰动力机器厂 | Discrete manufacturing industry work order scheduling improvement method |
-
2022
- 2022-03-02 CN CN202210197370.3A patent/CN114254966B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102207869A (en) * | 2011-06-03 | 2011-10-05 | 用友软件股份有限公司 | Strategy matching device and strategy matching method |
CN102932279A (en) * | 2012-10-30 | 2013-02-13 | 北京邮电大学 | Multidimensional resource scheduling system and method for cloud environment data center |
CN108388564A (en) * | 2017-02-03 | 2018-08-10 | 百度在线网络技术(北京)有限公司 | Inquiry processing method, device and its equipment |
CN109064357A (en) * | 2018-08-22 | 2018-12-21 | 潘皓波 | A kind of tour guide's recommender system and method in real time |
CN112995201A (en) * | 2019-01-11 | 2021-06-18 | 深圳联合产权交易所股份有限公司 | Resource value evaluation processing method based on cloud platform and related device |
CN111597042A (en) * | 2020-05-11 | 2020-08-28 | Oppo广东移动通信有限公司 | Service thread running method and device, storage medium and electronic equipment |
Also Published As
Publication number | Publication date |
---|---|
CN114254966A (en) | 2022-03-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Hassan et al. | Optimization modeling for dynamic price based demand response in microgrids | |
CN104915407B (en) | A kind of resource regulating method based under Hadoop multi-job environment | |
WO2010024027A1 (en) | Virtual server system and physical server selection method | |
CN102546700A (en) | Resource scheduling and resource migration methods and equipment | |
CN102479336A (en) | Multi-dimensional classification coding method for manufacturing information of aerospace product structural member | |
CN114254966B (en) | Method for matching resources by using dimension groups | |
Guan et al. | Topology and migration-aware energy efficient virtual network embedding for green data centers | |
CN107203421A (en) | A kind of adaptive work in combination stream method in cloud computing environment | |
CN1552019A (en) | Object-oriented framework for generic adaptive control | |
Felling et al. | Flow-based market coupling revised-Part II: Assessing improved price zones in Central Western Europe | |
CN102063329B (en) | Multi-agent coordination based management task dynamic decomposition method and system | |
Thornburg et al. | A tool for assessing demand side management and operating strategies for isolated microgrids | |
WO2017148296A1 (en) | Method of assigning application to assigned service cluster and device | |
Liang et al. | Business value-aware task scheduling for hybrid IaaS cloud | |
CN110942217B (en) | Method and system for constructing zero-carbon green energy system | |
Lutz et al. | Development of operator assignment schedules: a DSS approach | |
Pan et al. | Enhanced Microgrid Energy Optimization: Integrating Load Prioritization and Dynamic Temporal Adaptation | |
CN114003389A (en) | Cloud platform resource allocation method and system based on joint selection and virtual machine placement | |
CN116302575B (en) | Demand resource configuration processing method suitable for multi-element conflict scene | |
CN116865279A (en) | Multi-time space-scale electricity-hydrogen system optimal scheduling method and system | |
Soplop et al. | Manufacturing execution systems for sustainability: Extending the scope of MES to achieve energy efficiency and sustainability goals | |
CN117634838B (en) | Intelligent scheduling management method and system for power supply station resources | |
CN118508441B (en) | Distributed energy scheduling management system of virtual power plant | |
CN110348740B (en) | Multi-flow-domain hydropower station cluster power generation planning system based on big data | |
Schneeweiß et al. | Aggregation of mixed integer production models by shadow prices in supply chain management |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |