CN114202260A CN202210148641.6A CN202210148641A CN114202260A CN 114202260 A CN114202260 A CN 114202260A CN 202210148641 A CN202210148641 A CN 202210148641A CN 114202260 A CN114202260 A CN 114202260A
Authority
CN
China
Prior art keywords
milestone
project
milestones
node
aggregation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210148641.6A
Other languages
Chinese (zh)
Inventor
李太友
林剑玮
李博雅
孙硕
王德晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Zhongxin Zhiguan Information Technology Co ltd
Original Assignee
Tianjin Zhongxin Zhiguan Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Zhongxin Zhiguan Information Technology Co ltd filed Critical Tianjin Zhongxin Zhiguan Information Technology Co ltd
Priority to CN202210148641.6A priority Critical patent/CN114202260A/en
Publication of CN114202260A publication Critical patent/CN114202260A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/904Browsing; Visualisation therefor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/906Clustering; Classification
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Databases & Information Systems (AREA)
  • General Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project milestone management system and method, electronic equipment and a storage medium. Wherein the project milestone management system comprises: the project milestone acquisition module is used for acquiring project milestones associated with the current user and milestone information corresponding to the project milestones, wherein the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone; the project milestone aggregation module is used for aggregating project milestones with the same non-project attributes based on the milestone information to obtain aggregated milestones under each non-project attribute; the aggregation milestone display module is used for forming an aggregation milestone interface, rendering and displaying the aggregation milestone interface, and performing aggregation display on the project milestones in non-project attribute dimensions, so that information aggregation and display in cross-project dimensions can be realized, and a manager can easily know work development conditions in different information dimensions.

Description

Project milestone management system and method, electronic equipment and storage medium
Technical Field
The embodiment of the invention relates to the technical field of computers, in particular to a project milestone management system, a project milestone management method, electronic equipment and a storage medium.
Background
For an enterprise, the development of its work is usually done on a project-by-project dimension. Project node setting, task allocation, progress tracking, budget management and other items generally relate to project management, and existing common project management tools include a milestone management tool, that is, a project process is managed by using milestones.
The project planning, development and maintenance stages are generally handled by personnel in different departments, the departments cooperate with each other, and the development process of the project planning, development and maintenance stages involves many pieces of information in dimensions other than the project dimensions.
Disclosure of Invention
The embodiment of the invention provides a project milestone management system, a project milestone management method, electronic equipment and a storage medium, which are used for realizing information aggregation and display in a cross-project dimension.
In a first aspect, an embodiment of the present invention provides a project milestone management system, including:
the project milestone acquisition module is used for acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are established based on projects, and the same project corresponds to at least one project milestone;
the project milestone aggregation module is used for aggregating project milestones with the same non-project attributes based on the milestone information to obtain aggregated milestones under each non-project attribute;
and the aggregation milestone display module is used for forming an aggregation milestone interface based on the non-project attributes, the aggregation milestones and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
In a second aspect, an embodiment of the present invention further provides a project milestone management method, including:
acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone;
based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute;
and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
In a third aspect, an embodiment of the present invention further provides an electronic device, including a memory, a processor, and a computer program stored on the memory and executable on the processor, where the processor executes the computer program to implement the project milestone management method according to any embodiment of the present invention.
In a fourth aspect, the present invention further provides a computer-readable storage medium, on which a computer program is stored, where the computer program is executed by a processor to implement the project milestone management method according to any embodiment of the present invention.
The project milestone management system comprises a project milestone acquisition module, a project milestone aggregation module and an aggregation milestone display module, wherein the project milestone management system acquires project milestones associated with a current user and milestone information corresponding to the project milestones, the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone; based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute; and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface. By performing aggregation display on the project milestones in non-project attribute dimensions, information aggregation and display in cross-project dimensions can be realized, so that a manager can easily know the work development conditions in different information dimensions.
Drawings
FIG. 1 is a schematic structural diagram of a project milestone management system according to an embodiment of the present invention;
FIG. 2 is a schematic illustration of an aggregated milestone interface provided by an embodiment of the invention;
FIG. 3 is a schematic illustration of an aggregated milestone interface provided by an embodiment of the invention;
FIG. 4 is a schematic illustration of an aggregated milestone interface provided by an embodiment of the invention;
FIG. 5 is a schematic diagram of a reorganization milestone display interface according to an embodiment of the present invention;
FIG. 6 is a schematic diagram of a reorganization milestone display interface according to an embodiment of the present invention;
FIG. 7 is a schematic illustration of a reorganization milestone according to an embodiment of the present invention;
FIG. 8 is a schematic illustration of a reorganization milestone according to an embodiment of the present invention;
FIG. 9 is a schematic diagram of a target project milestone two-dimensional display page according to an embodiment of the invention;
FIG. 10 is a diagram illustrating a project milestone display area corresponding to a non-project attribute according to an embodiment of the present invention;
FIG. 11 is a flowchart illustrating a project milestone management method according to an embodiment of the invention;
fig. 12 is a schematic structural diagram of an electronic device according to an embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
Fig. 1 is a schematic structural diagram of a project milestone management system according to an embodiment of the present invention, which includes a project milestone acquisition module 110, a project milestone aggregation module 120, and an aggregated milestone display module 130. The project milestone acquisition module 110 is configured to acquire a project milestone associated with a current user and milestone information corresponding to the project milestone, where the project milestone is a milestone established based on a project, and the same project corresponds to at least one project milestone; a project milestone aggregation module 120, configured to aggregate project milestones with the same non-project attributes based on the milestone information to obtain aggregated milestones under each non-project attribute; and an aggregated milestone display module 130, configured to form an aggregated milestone interface based on the non-project attributes, the aggregated milestones, and the corresponding milestone information, and render and display the aggregated milestone interface.
The items in this embodiment are dynamic processes of corresponding events, and all things are items. For example, if the event is a visit event, the project milestones may include a project milestone a corresponding to the visit event a, a project milestone B corresponding to the visit event B, and a project milestone C corresponding to the visit event C, and the visit attributes are the project attributes of the project milestone a, the project milestone B, and the project milestone C. As another example, if the event is an application iteration event, the project milestones may include a project milestone D corresponding to the application iteration event D, and a project milestone E corresponding to the application iteration event E, and the application iteration attributes are the project attributes corresponding to the project milestones D and the project milestones E. Project milestones are one or more levels of flow architecture created based on the execution flow of the project. The first-stage project milestones only comprise first-stage milestone nodes, the multi-stage project milestones can comprise multi-stage milestone nodes, and the next-stage milestone node is the decomposition of the execution flow of the previous-stage milestone node. For example, the first-level project milestone may include a project name and project-related information, where the project-related information is all information that can be involved in the project execution process, and may be, for example, a start time, an end time, a department to which the project belongs, a project member, a processing priority, and the like of the project. The multi-level project milestones can be three-level flow structures, each three-level flow structure comprises a first-level milestone node, a second-level milestone node and a third-level milestone node, wherein the first-level milestone nodes can comprise a plurality of second-level milestone nodes, and each second-level milestone node can comprise a plurality of third-level milestone nodes. The first-level milestone node, the second-level milestone node and the third-level milestone node respectively comprise related information of the corresponding-level milestone node. It can be understood that the information related to each level of the milestone node is all information that can be involved in the execution process of the milestone node. In some embodiments, the multi-level project milestone may be a two-level flow architecture composed of a first-level milestone node and a second-level milestone node, and in some embodiments, the multi-level project milestone may be a four-level flow structure formed by a first-level milestone node, a second-level milestone node, a third-level milestone node, and a task decomposition step under the third-level milestone node, which is not limited thereto. The milestone information is a set of information related to each milestone node in the project milestone, and illustratively, the milestone information may include a project attribute corresponding to the project milestone, and may also include a non-project attribute corresponding to the project milestone, where the non-project attribute is an attribute other than the project attribute, and illustratively, the non-project attribute may be a company to which the project belongs, a cause to which the project belongs, a functional department to which the project belongs, a person participating in the project, and the like. The non-item attribute can be a one-level non-item attribute or a multi-level non-item attribute, and each level of the multi-level non-item attribute has a dependency relationship. For example, the first-level non-project attribute may be a department of the company, or a division of the company, and the multi-level non-project attribute may be a third-level non-project attribute of a company-division of the company.
The user authority or the participating user identifier may be preferably set in each project milestone, and the project milestone acquisition module 110 may acquire the current user information through the login information or the binding information and determine the project milestone associated with the current user based on the current user information and the user authority or the participating user identifier set in the project milestone. Illustratively, based on the current user information, it is determined whether the current user has user privileges for a project milestone, and if so, the project milestone is determined to be the project milestone associated with the current user. It will be appreciated that if the original project milestone includes a tertiary milestone node, but the current user has only user privileges for a local milestone node (which may be, for example, a secondary milestone node and a tertiary milestone node) within the project milestone, then the local milestone node is preferably considered the project milestone associated with the current user. Or, based on the current user information, determining whether the current user identification matches a participating user identification of the project milestone, and if the matching is successful, determining that the project milestone is a project milestone associated with the current user. By determining the project milestones associated with the current user, interference of irrelevant information can be avoided, and the effectiveness and pertinence of the information are improved. Meanwhile, the searching or editing of the project milestones by irrelevant users is avoided, and the information safety is improved.
In this embodiment, the system is preferably provided with an initial non-project attribute, and the project milestone aggregation module 120 may aggregate project milestones having the same non-project attribute based on the initial non-project attribute. Optionally, the user may also reset the non-project attribute according to the actual need of the user, and the system may also reset the non-project attribute according to the historical operation of the user. An aggregate milestone is a collection of project milestones that have the same non-project attributes.
Taking the non-project attributes as the processing priority, the process of obtaining the aggregated milestones by the project milestone aggregation module 120 will be described in detail: the project milestone aggregation module 120 determines project milestones associated with the current user based on the milestone information, and includes project milestones with processing priorities of emergency, medium and normal, respectively, aggregates the project milestones with processing priorities of emergency according to the processing priorities of the project milestones to obtain an aggregated milestone a, aggregates the project milestones with processing priorities of medium to obtain an aggregated milestone B, and aggregates the project milestones with processing priorities of normal to obtain an aggregated milestone C.
The aggregated milestone display module 130 is convenient for quickly browsing and looking up the related information of the project milestones under the non-project attributes through the milestone interface by displaying the aggregated milestones corresponding to the different non-project attributes, thereby simplifying the information management and query process. The aggregated milestone display module 130 may form an aggregated milestone interface through a preset display layout or a preset display template, and render and display the interface on the device side. In some embodiments, each aggregated milestone display area is included in the aggregated milestone interface for displaying a plurality of project milestones in the aggregated milestone collection, corresponding milestone information, and corresponding non-project attribute information. In some embodiments, the aggregated milestone display area may display only key information in the milestone information, which facilitates a user to quickly view key information of multiple project milestones through the aggregated milestone interface, avoiding interference of a large amount of information. The key information may be preset, for example, the key information may be an execution state of one or more stages of milestone nodes in the project milestone, target data, attribute tags, and the like. The key information can be set according to the user requirements, so that a personalized aggregated milestone interface meeting the user requirements is formed, and the display flexibility and the diversity of the aggregated milestone interface are improved. For example, if the user a compares the progress of the concerned time, the key information may be set as the time information of the one-level or multi-level milestone node, and if the user B compares the completion ratio of the concerned progress, the key information may be set as the progress completion ratio information of the one-level or multi-level milestone node.
Preferably, each project milestone in the aggregated milestone interface can be presented in the form of a card. For example, if the project milestone is a primary flow structure, a card may be displayed in a display area corresponding to the project milestone. If the project milestone is a multi-level flow architecture, cards corresponding to the previous two or more levels of milestone nodes can be displayed in a display area corresponding to the project milestone. Illustratively, referring to fig. 2, fig. 2 is a schematic diagram of an aggregated milestone interface provided by an embodiment of the invention. The aggregated milestone interface of fig. 2 includes a non-project attribute display area corresponding to the aggregated milestone, and an aggregated milestone display area including each project milestone display area, where each project milestone display area may be a one-level project milestone display area or a multi-level project milestone display area. It should be noted that fig. 2 is only a schematic diagram, and in this embodiment, the display form and the display layout of the project milestones are not limited, and the number of the milestone nodes at each level is also not limited. Optionally, the display form of the project milestones may be a table, a calendar, a cross-track chart, a mixed row, etc. besides the cards, and may be selectively set according to the actual needs of the user.
The embodiment provides a project milestone management system, which comprises a project milestone acquisition module, a project milestone aggregation module and an aggregation milestone display module, wherein the project milestone management system acquires project milestones associated with a current user and milestone information corresponding to the project milestones, the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone; based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute; and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface on a preset display interface. By performing aggregation display on the project milestones in non-project attribute dimensions, information aggregation and display in cross-project dimensions can be realized, so that a manager can easily know the work development conditions in different information dimensions.
Based on the foregoing embodiment, further the non-project attributes comprise at least one of a milestone cluster, a milestone group and a milestone subgroup, the milestone cluster comprising at least one milestone group, the milestone group comprising at least one milestone subgroup, wherein the aggregated milestones under the milestone cluster are a set of aggregated milestones under each milestone group, and the aggregated milestones under the milestone group are a set of aggregated milestones under each milestone subgroup.
In order to more finely classify and aggregate the project milestones according to the non-project attributes and meet different classification and aggregation requirements of different users, the non-project attributes may be preferably set to one or more levels, i.e., the non-project attributes may include at least one of a milestone family, a milestone group and a milestone subgroup, and exemplarily, the non-project attributes may be the milestone family, the milestone group, the milestone subgroup, the non-project attributes may also be the milestone family-the milestone group, the milestone group-the milestone subgroup, and the non-project attributes may also be the milestone family-the milestone group-the milestone subgroup. It is to be understood that when the non-project attributes are multi-level, the non-project attributes at any one level can be traced back to the non-project attributes at other levels associated therewith to obtain the aggregated milestone corresponding to the non-project attributes at other levels.
Optionally, when the non-project attribute is a milestone group, the project milestone aggregation module aggregates the project milestones belonging to the same milestone group based on the milestone information to obtain aggregated milestones under each milestone group, and correspondingly, the aggregated milestone display module 130 forms and displays an aggregated milestone interface based on each milestone group, the aggregated milestones under each milestone group, and the corresponding milestone information. For example, referring to fig. 3, fig. 3 is a schematic diagram of an aggregated milestone interface according to an embodiment of the present invention, in fig. 3, the non-project attribute is a milestone group, the milestone group is each functional department under the business department, such as a product department, an operation department, a platform development department, and the like, and accordingly, the aggregated milestones obtained by the project-milestone aggregation module are aggregated milestones under the product department, aggregated milestones under the operation department, and aggregated milestones under the platform development department, respectively, and the aggregated milestone display module forms and displays the aggregated milestone interface based on the non-project attribute-product department and aggregated milestones under the product department, the non-project attribute-operation department and aggregated milestones under the operation department, the non-project attribute-platform development department and aggregated milestones under the platform development department, and corresponding milestone information.
Optionally, when the non-project attributes include a milestone cluster, a milestone group and a milestone group, the project milestone aggregation module aggregates the project milestones belonging to the same milestone cluster-milestone group based on the milestone information to obtain aggregated milestones under each milestone cluster-milestone group, and accordingly, the aggregated milestone display module 130 forms and displays an aggregated milestone interface based on each milestone cluster-milestone group, each milestone cluster-milestone group and the corresponding milestone information. For example, referring to fig. 4, fig. 4 is a schematic diagram of an aggregated milestone interface provided by an embodiment of the present invention, in fig. 4, non-project attributes are a milestone family-a milestone group, where the milestone family is an enterprise, such as enterprise a and enterprise B, the milestone group is each of the departments assigned by the enterprise, such as a market department assigned by enterprise a and a product department assigned by enterprise B, the milestone group is each of the functional departments assigned by the departments, such as a market department extension and a market maintenance department, such as a product development department and a product delivery department, under the product department, and accordingly, the aggregated milestones obtained by the project milestone aggregation module are aggregated milestones respectively for enterprise a-market department, and a-market department-a market department, the aggregation milestone display module 130 forms and displays an aggregation milestone interface based on non-project attributes, namely an enterprise A-marketing division, a market expansion division and an aggregation milestone under the market expansion division, non-project attributes, namely the enterprise A-marketing division, the aggregation milestone under the market maintenance division and the aggregation milestone under the market maintenance division, non-project attributes, namely the enterprise B-marketing division, the aggregation milestone under the product development division and the aggregation milestone under the non-project attributes, namely the enterprise B-marketing division, the product delivery division and the aggregation milestone under the product delivery division, and corresponding milestone information. It is understood that the form of presentation in fig. 4 is only an example, and the present embodiment does not limit the form of presentation of the non-project attributes and the corresponding aggregated milestones.
On the basis of the above embodiment, further comprising a polymerization milestone reorganization module, configured to, in response to a polymerization milestone reorganization operation, reorganize a target polymerization milestone based on a polymerization milestone reorganization rule to obtain a reorganized milestone; the aggregated milestone display module 130 is further configured to form and display a reorganization milestone interface based on the reorganization milestones.
In the above embodiments, after the project milestones are aggregated based on the non-project attributes, the number of the obtained aggregated milestones may be large, and the user cannot find the interested milestone node information at a glance.
Illustratively, the aggregated milestone reorganization operation may be triggered by the user by clicking on the aggregated milestone reorganization button, or by performing a corresponding aggregated milestone reorganization action (e.g., may be a double click or a long press at the current interface blank, etc.). The target aggregated milestone may be an aggregated milestone under multiple selected non-project attributes, or an aggregated milestone under one selected non-project attribute. It is understood that when selecting the target aggregated milestone, the aggregated milestone under each selected non-project attribute may be selected in full, or the aggregated milestone under each selected non-project attribute may be selected in part as needed.
The aggregated milestone recombination rule may be a rule set according to different demand scenarios of the user, for example, the different demand scenarios may be that the user is only interested in a milestone node with a certain execution state, or only interested in a milestone node with a certain execution purpose, or only interested in a milestone node with a certain digital target, or only interested in a milestone node with a certain importance level, or the like.
Optionally, the aggregation milestone recombination rule may be that milestone nodes in the same execution state in each project milestone in the target aggregation milestone are extracted, and the extracted milestone nodes are sequenced to obtain recombined milestones; the aggregation milestone recombination rule can also be used for extracting milestone nodes with the same execution purpose in each project milestone in the target aggregation milestone, and sequencing the extracted milestone nodes to obtain a recombined milestone; the aggregation milestone recombination rule can also be used for extracting the milestone nodes with the same execution number target in each project milestone in the target aggregation milestone, and sequencing the extracted milestone nodes to obtain the recombination milestone. It should be understood that the milestone restructuring rule is only an example, and may also be in other conceivable restructuring rule forms, which is not limited in this embodiment.
Taking the aggregation milestone recombination rule as an example for extracting the milestone nodes in the same execution state in each project milestone in the target aggregation milestone, and sequencing the extracted milestone nodes to obtain the recombination milestone, and concretely explaining the recombination process of the aggregation milestone recombination module:
the aggregation milestone recombination module can extract the milestone nodes in the target aggregation milestone in the ongoing state in each project milestone, and sequence the milestone nodes based on the starting time or the ending time of each milestone node to obtain the ongoing intermediate node recombination milestone, wherein the ongoing intermediate node recombination milestone can enable a user to directly position the milestone nodes in the ongoing state without sequentially clicking on each project milestone for viewing. The aggregated milestone reorganization module can also extract the last milestone node in the completion state of each project milestone in the target aggregated milestone, and sequence the milestone nodes based on the completion time of each milestone node to obtain the completed node reorganization milestone, and the completed node reorganization milestone can enable a user to directly position the milestone node in the latest completion state so as to enable the user to directly obtain the completion progress of each project milestone. The aggregated milestone reorganization module can also be used for extracting the milestone nodes in the pause state in each project milestone in the target aggregated milestone, sequencing the milestone nodes based on the pause action starting time of each milestone node to obtain pause node reorganized milestones, and the pause node reorganization milestones can enable a user to directly position the milestone nodes in the pause state so as to facilitate the user to quickly position each pause node, quickly determine the pause reason of each pause node and facilitate the promotion of subsequent work. It can be understood that, after the milestone nodes of the corresponding execution states are extracted, the corresponding milestone nodes can be sequenced based on the sequence of the project milestones in the target aggregated milestone to obtain recombined milestones; and sequencing can be performed based on the importance level of each milestone node to obtain the recombined milestones.
After the aggregated milestone restructuring module obtains the restructured milestone, the aggregated milestone displaying module 130 may display the restructured milestone on the aggregated milestone interface or display the restructured milestone on a new interface, where the new interface may be a suspension interface suspended on the aggregated milestone interface or an interface skipped from the aggregated milestone interface. Illustratively, referring to fig. 5, fig. 5 is a schematic diagram of a reorganization milestone display interface according to an embodiment of the present invention, and as shown in fig. 5, the aggregation milestone display module 130 displays the reorganization milestones in the aggregation milestone interface above the corresponding target aggregation milestones. Referring to fig. 6, fig. 6 is a schematic diagram of a reorganization milestone display interface according to an embodiment of the present invention, and as shown in fig. 6, the aggregated milestone display module 130 displays the reorganization milestone at a preset position in the aggregated milestone interface, where the preset position is the uppermost position of the aggregated milestone interface. It is understood that the preset position may be any position in the aggregated milestone interface, and is not particularly limited herein.
On the basis of the foregoing embodiment, further, the aggregated milestone reorganization module includes an in-progress node extraction unit and an in-progress node sorting unit, where: the ongoing node extracting unit is used for responding to the aggregation milestone recombination operation and extracting ongoing nodes in the target aggregation milestone, wherein the ongoing nodes are the ongoing milestone nodes in the aggregation milestone and the execution state is the ongoing milestone node; and the in-process node sequencing unit is used for sequencing in-process nodes under each non-project attribute based on a preset sequencing rule to obtain the recombination milestone.
The preset ordering rule in this embodiment may be ordering based on the preset completion time of each in-progress node, or based on the start time of each in-progress node, or based on the importance level of each in-progress node. Illustratively, referring to fig. 7, fig. 7 is a schematic diagram of a reorganization milestone provided by an embodiment of the present invention, and as shown in fig. 7, each ongoing node in the reorganization milestone is ranked based on the importance level.
On the basis of the foregoing embodiment, further, the ongoing node extracting unit is further configured to determine, based on the milestone information, an importance level of an ongoing node in the target aggregated milestone; and extracting the node with the highest importance level in the target aggregation milestone based on the importance level.
In this embodiment, each in-progress node corresponding to the target aggregated milestone may correspond to different importance levels, and the user may only be interested in an in-progress node with a higher or highest importance level. Illustratively, referring to fig. 8, fig. 8 is a schematic diagram of a reorganization milestone provided by an embodiment of the present invention, and as shown in fig. 8, the importance level of each ongoing node in the reorganization milestone is the highest (e.g., importance level five).
Based on the foregoing embodiment, further, the aggregated milestone display module 130 is further configured to, in response to an operation performed on a target milestone node in a reorganization milestone and used for displaying a target project milestone associated with the target milestone node, obtain the target project milestone and related target milestone information, and form a target project milestone display interface; rendering and displaying the target project milestone display interface on an interface where the target project milestone node is located, or rendering and displaying the target project milestone display interface in a suspended page mode, or switching the current page to a target project milestone display page.
Wherein the target milestone node is a milestone node in the recombined milestones. Preferably, the target project milestone may be a project milestone to which the target milestone node belongs, and the target project milestone may also include a project milestone to which the target milestone node belongs, and a project milestone or milestone node associated with the target milestone node. Wherein, a project milestone or milestone node associated with a target milestone node means that the target milestone node and its associated project milestone or milestone node belong to different project milestones. The target milestone node is associated with its associated project milestone or milestone node with an association type of one of: triggering starting, triggering completion, synchronous completion and constraint relation of target data, triggering starting a first preset execution state for a front node to trigger the execution state of a rear node to be changed into starting, triggering completion of a second preset execution state for the front node to trigger the execution state of the rear node to be changed into completion, synchronously completing the execution state of two nodes for triggering the association relation to be changed into completion when the two nodes with the association relation are both in a completion state, and the constraint relation of the target data is that the target data of the front node and the rear node has a size constraint relation. And if the front node is the project milestone or the milestone node associated with the target milestone node, the rear node is the target milestone node.
In this embodiment, the target project milestone display page may be a two-dimensional display page, and in the target project milestone two-dimensional display page, the display form of the target project milestone may be a planar tree structure, or a fishbone structure. Illustratively, referring to fig. 9, fig. 9 is a schematic diagram of a target project milestone two-dimensional display page provided by an embodiment of the present invention, as shown in fig. 9, the target project milestone two-dimensional display page is displayed in the form of a floating page, and in the target project milestone two-dimensional display page, the display form of the target project milestone is a planar tree structure. Preferably, the target project milestone display page may also be a three-dimensional display page, and in the target project milestone three-dimensional display page, the display form of the target project milestone may be a three-dimensional tree structure, a three-dimensional sphere structure, or the like. In the target project milestone three-dimensional display page, each or each level of milestone nodes in the target project milestones can be displayed in a page dragging mode.
Based on the above embodiment, further, the project milestone comprises at least the first two levels of the following three-level nodes: a parent milestone, a plurality of child milestones included in the parent milestone, and a mission critical node included in each of the child milestones.
The project milestone in this embodiment is a secondary process architecture or a tertiary process architecture, for example, the secondary process architecture includes a parent milestone and a child milestone, and the tertiary process architecture includes a parent milestone, a child milestone and a key task node, where the parent milestone is a primary milestone node, the child milestone is a secondary milestone node, the key task node is a tertiary milestone node, the parent milestone may include a plurality of child milestones, and each child milestone may include a plurality of key task nodes.
The multiple child milestones within the same parent milestone may be in a sequential triggering relationship or may be in a simultaneous execution relationship, without limitation. The different sub-milestones can be executed by different departments or different execution objects in the same department, and similarly, the plurality of key task nodes in the same sub-milestone can be executed by different departments or different execution objects in the same department, which is not limited herein.
Each level of architecture in the project milestone is provided with an execution state or an execution progress, the execution state of each node of the next level in the project milestone determines the execution progress and the execution state of the node of the previous level, the execution progress of the node of the previous level is the proportion of the node of which the execution state is finished in each node of the next level, and when the execution progress of the node of the previous level is finished or 100%, the execution state is switched from processing to finishing. And each level of nodes in the project milestone are a father milestone, a child milestone and a key task node in sequence. Specifically, the execution state of each sub-milestone affects the execution progress of the parent milestone, and the execution state of each key task node affects the execution progress of the sub-milestone. By setting the project milestones, the execution state and the execution progress of each level of nodes can be obtained and recorded, and the information of each node in the project can be managed and inquired conveniently.
Based on the foregoing embodiment, further, the aggregated milestone interface includes at least one project milestone display area corresponding to a non-project attribute, and the project milestone display area corresponding to any non-project attribute includes a first display area corresponding to the non-project attribute and a second display area corresponding to the aggregated milestone under the non-project attribute. It will be appreciated that the aggregated milestone interface can also include a non-project property display area for displaying various non-project properties to which project milestones associated with the current user relate. The non-item attribute display form can be a list display form, and if the non-item attribute is a multi-level non-item attribute, the multi-level non-item attribute can be displayed in a progressive expansion mode.
For example, in the second display area, for each project milestone in the aggregated milestones, a complete project milestone may be displayed, and milestone nodes in which the user is interested may also be displayed according to the user's setting, for example, milestone nodes in progress in each project milestone may be displayed. For example, referring to fig. 10, fig. 10 is a schematic diagram of a project milestone display area corresponding to a non-project attribute according to an embodiment of the present invention, and as shown in fig. 10, in an aggregated milestone under the non-project attribute, a project milestone may only show milestone nodes whose execution states are in progress.
A project milestone management method is further provided on the basis of the above embodiments, referring to fig. 11, fig. 11 is a schematic flow chart of the project milestone management method provided in the embodiments of the present invention, and this embodiment is applicable to a case of managing and displaying project milestone information, which may be executed by the project milestone management system provided in the embodiments of the present invention, which may be implemented by software and/or hardware, and which may be configured on an electronic device such as a computer or a server, and specifically includes the following steps:
s210, acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are established based on projects, and the same project corresponds to at least one project milestone;
s220, based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute;
and S230, forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
Based on the foregoing embodiment, further the non-project attributes comprise at least one of a milestone cluster, a milestone group and a milestone subgroup, the milestone cluster comprising at least one milestone group, the milestone group comprising at least one milestone subgroup, wherein the aggregated milestones under the milestone cluster are a set of aggregated milestones under each milestone group, and the aggregated milestones under the milestone group are a set of aggregated milestones under each milestone subgroup.
On the basis of the above embodiment, further, in response to the aggregation milestone recombination operation, recombining the target aggregation milestone based on the aggregation milestone recombination rule to obtain a recombined milestone; a reorganization milestone interface is formed based on the reorganization milestones and displayed.
On the basis of the above embodiment, further, in response to the aggregated milestone reorganization operation, extracting an ongoing node in the target aggregated milestone, where the ongoing node is the aggregated milestone node and the execution state is the ongoing milestone node; and sequencing the nodes in progress under each non-project attribute based on a preset sequencing rule to obtain the recombined milestone.
Based on the above embodiment, further, based on the milestone information, determining the importance level of the node in progress in the target aggregated milestone; and extracting the node with the highest importance level in the target aggregation milestone based on the importance level.
Based on the above embodiment, further, in response to an operation performed on a target milestone node in the reorganization milestones for displaying a target project milestone associated with the target milestone node, obtaining the target project milestone and related target milestone information, and forming a target project milestone display interface; rendering and displaying the target project milestone display interface on an interface where the target project milestone node is located, or rendering and displaying the target project milestone display interface in a suspended page mode, or switching the current page to a target project milestone display page.
Based on the above embodiment, further, the target project milestone includes a project milestone to which the target milestone node belongs, and a project milestone or milestone node associated with the target milestone node.
On the basis of the above embodiment, further, the target project milestone display page is a three-dimensional display page.
Based on the above embodiment, further, the project milestone comprises at least the first two levels of the following three-level nodes: a parent milestone, a plurality of child milestones included in the parent milestone, and a mission critical node included in each of the child milestones.
Based on the foregoing embodiment, further, the aggregated milestone interface includes at least one project milestone display area corresponding to a non-project attribute, and the project milestone display area corresponding to any non-project attribute includes a first display area corresponding to the non-project attribute and a second display area corresponding to the aggregated milestone under the non-project attribute.
The embodiment provides a project milestone management method, which comprises the steps of acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are established based on projects, and the same project corresponds to at least one project milestone; based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute; and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface on a preset display interface. By performing aggregation display on the project milestones in non-project attribute dimensions, information aggregation and display in cross-project dimensions can be realized, so that a manager can easily know the work development conditions in different information dimensions.
Fig. 12 is a schematic structural diagram of an electronic device according to an embodiment of the present invention. FIG. 12 illustrates a block diagram of an electronic device 12 suitable for use in implementing embodiments of the present invention. The electronic device 12 shown in fig. 12 is only an example, and should not bring any limitation to the functions and the scope of use of the embodiment of the present invention. The device 12 is typically an electronic device that undertakes image classification functions.
As shown in FIG. 12, electronic device 12 is embodied in the form of a general purpose computing device. The components of electronic device 12 may include, but are not limited to: one or more processors 16, a memory device 28, and a bus 18 that connects the various system components (including the memory device 28 and the processors 16).
Bus 18 represents one or more of any of several types of bus structures, including a memory bus or memory controller, a peripheral bus, an accelerated graphics port, and a processor or local bus using any of a variety of bus architectures. By way of example, such architectures include, but are not limited to, an Industry Standard Architecture (ISA) bus, a Micro Channel Architecture (MCA) bus, an enhanced ISA bus, a Video Electronics Standards Association (VESA) local bus, and a Peripheral Component Interconnect (PCI) bus.
Electronic device 12 typically includes a variety of computer system readable media. Such media may be any available media that is accessible by electronic device 12 and includes both volatile and nonvolatile media, removable and non-removable media.
Storage 28 may include computer system readable media in the form of volatile Memory, such as Random Access Memory (RAM) 30 and/or cache Memory 32. The electronic device 12 may further include other removable/non-removable, volatile/nonvolatile computer system storage media. By way of example only, storage system 34 may be used to read from and write to non-removable, nonvolatile magnetic media (not shown in FIG. 12, and commonly referred to as a "hard drive"). Although not shown in FIG. 12, a magnetic disk drive for reading from and writing to a removable, nonvolatile magnetic disk (e.g., a "floppy disk") and an optical disk drive for reading from or writing to a removable, nonvolatile optical disk (e.g., a Compact disk-Read Only Memory (CD-ROM), a Digital Video disk (DVD-ROM), or other optical media) may be provided. In these cases, each drive may be connected to bus 18 by one or more data media interfaces. Storage 28 may include at least one program product having a set (e.g., at least one) of program modules that are configured to carry out the functions of embodiments of the invention.
A program 36 having a set (at least one) of program modules 26 may be stored, for example, in storage 28, such program modules 26 including, but not limited to, an operating system, one or more application programs, other program modules, and program data, each of which examples or some combination thereof may include an implementation of a gateway environment. Program modules 26 generally perform the functions and/or methodologies of the described embodiments of the invention.
Electronic device 12 may also communicate with one or more external devices 14 (e.g., keyboard, pointing device, camera, display 24, etc.), with one or more devices that enable a user to interact with electronic device 12, and/or with any devices (e.g., network card, modem, etc.) that enable electronic device 12 to communicate with one or more other computing devices. Such communication may be through an input/output (I/O) interface 22. Also, the electronic device 12 may communicate with one or more gateways (e.g., Local Area Network (LAN), Wide Area Network (WAN), etc.) and/or a public gateway, such as the internet, via the Network adapter 20. As shown, the network adapter 20 communicates with other modules of the electronic device 12 via the bus 18. It should be understood that although not shown in the figures, other hardware and/or software modules may be used in conjunction with electronic device 12, including but not limited to: microcode, device drivers, Redundant processing units, external disk drive Arrays, disk array (RAID) systems, tape drives, and data backup storage systems, to name a few.
The processor 16 executes various functional applications and data processing, such as implementing the milestone project management method provided by the above-described embodiments of the present invention, by running a program stored in the storage device 28.
Embodiments of the present invention further provide a computer-readable storage medium, on which a computer program is stored, where the computer program, when executed by a processor, implements a project milestone management method according to an embodiment of the present invention:
acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone;
based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute;
and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
Of course, the embodiment of the present invention provides a computer-readable storage medium on which a computer program is stored, which is not limited to the method operations described above, and can also perform the project milestone management method provided in any embodiment of the present invention.
Computer storage media for embodiments of the invention may employ any combination of one or more computer-readable media. The computer readable medium may be a computer readable signal medium or a computer readable storage medium. A computer readable storage medium may be, for example, but not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination of the foregoing. More specific examples (a non-exhaustive list) of the computer readable storage medium would include the following: an electrical connection having one or more wires, a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disc read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing. In the context of this document, a computer readable storage medium may be any tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device.
A computer readable signal medium may include a propagated data signal with computer readable source code embodied therein, for example, in baseband or as part of a carrier wave. Such a propagated data signal may take many forms, including, but not limited to, electro-magnetic, optical, or any suitable combination thereof. A computer readable signal medium may also be any computer readable medium that is not a computer readable storage medium and that can communicate, propagate, or transport a program for use by or in connection with an instruction execution system, apparatus, or device.
Source code embodied on a computer-readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wireline, optical fiber cable, RF, etc., or any suitable combination of the foregoing.
Computer source code for carrying out operations for aspects of the present invention may be written in any combination of one or more programming languages, including an object oriented programming language such as Java, Smalltalk, C + +, or the like, as well as conventional procedural programming languages, such as the "C" programming language or similar programming languages. The source code may execute entirely on the user's computer, partly on the user's computer, as a stand-alone software package, partly on the user's computer and partly on a remote computer or entirely on the remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of gateway, including a Local Area Network (LAN) or a Wide Area Network (WAN), or the connection may be made to an external computer (for example, through the Internet using an Internet service provider).
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims (13)

1. A project milestone management system, comprising:
the project milestone acquisition module is used for acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are established based on projects, and the same project corresponds to at least one project milestone;
the project milestone aggregation module is used for aggregating project milestones with the same non-project attributes based on the milestone information to obtain aggregated milestones under each non-project attribute;
and the aggregation milestone display module is used for forming an aggregation milestone interface based on the non-project attributes, the aggregation milestones and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
2. The system of claim 1, wherein the non-project attributes comprise at least one of a milestone cluster, a milestone group, and a milestone subgroup, the milestone cluster comprising at least one milestone group, the milestone group comprising at least one milestone subgroup, wherein the aggregate milestones under the milestone cluster are a set of aggregate milestones under each milestone group, and the aggregate milestones under the milestone group are a set of aggregate milestones under each milestone subgroup.
3. The system of claim 1 or 2, further comprising a polymerization milestone reorganization module for reorganizing the target polymerization milestone based on the polymerization milestone reorganization rule to obtain a reorganized milestone in response to the polymerization milestone reorganization operation;
the polymerization milestone display module is also used for forming and displaying a recombination milestone interface based on the recombination milestone.
4. The system of claim 3, wherein the aggregated milestone reorganization module comprises an in-flight node extraction unit and an in-flight node ranking unit, wherein:
the ongoing node extracting unit is used for responding to the aggregation milestone recombination operation and extracting ongoing nodes in the target aggregation milestone, wherein the ongoing nodes are the ongoing milestone nodes in the aggregation milestone and the execution state is the ongoing milestone node;
and the in-process node sequencing unit is used for sequencing in-process nodes under each non-project attribute based on a preset sequencing rule to obtain the recombination milestone.
5. The system of claim 4, wherein the in-progress node extraction unit is further configured to determine a level of importance of in-progress nodes in the target aggregated milestone based on the milestone information;
and extracting the node with the highest importance level in the target aggregation milestone based on the importance level.
6. The system of claim 4, wherein the aggregated milestone display module is further configured to, in response to an operation performed on a target milestone node of the reorganized milestones for displaying target project milestones associated with the target milestone node, obtain target project milestones and associated target milestone information to form a target project milestone display interface;
rendering and displaying the target project milestone display interface on an interface where the target project milestone node is located, or rendering and displaying the target project milestone display interface in a suspended page mode, or switching the current page to a target project milestone display page.
7. The system of claim 6, wherein a target project milestone comprises a project milestone to which the target milestone node belongs, and a project milestone or milestone node associated with the target milestone node.
8. The system of claim 6, wherein the target project milestone presentation page is a three-dimensional presentation page.
9. The system of claim 8, wherein the project milestones comprise at least the first two of the following three levels of nodes: a parent milestone, a plurality of child milestones included in the parent milestone, and a mission critical node included in each of the child milestones.
10. The system of claim 1 or 2, wherein the aggregated milestone interface comprises at least one project milestone display area corresponding to a non-project attribute, and wherein any of the project milestone display areas corresponding to the non-project attribute comprises a first display area corresponding to the non-project attribute and a second display area corresponding to the aggregated milestone under the non-project attribute.
11. A project milestone management method, comprising:
acquiring project milestones associated with a current user and milestone information corresponding to the project milestones, wherein the project milestones are milestones established based on projects, and the same project corresponds to at least one project milestone;
based on the milestone information, aggregating the project milestones with the same non-project attributes to obtain aggregated milestones under each non-project attribute;
and forming an aggregation milestone interface based on the non-project attributes, the aggregation milestone and the corresponding milestone information, and rendering and displaying the aggregation milestone interface.
12. An electronic device comprising a memory, a processor, and a computer program stored on the memory and executable on the processor, wherein the processor implements the project milestone management method of claim 11 when executing the program.
13. A computer-readable storage medium having stored thereon a computer program, wherein the program, when executed by a processor, implements the project milestone management method according to claim 11.
CN202210148641.6A 2022-02-18 2022-02-18 Project milestone management system and method, electronic equipment and storage medium Pending CN114202260A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210148641.6A CN114202260A (en) 2022-02-18 2022-02-18 Project milestone management system and method, electronic equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210148641.6A CN114202260A (en) 2022-02-18 2022-02-18 Project milestone management system and method, electronic equipment and storage medium

Publications (1)

Publication Number Publication Date
CN114202260A true CN114202260A (en) 2022-03-18

Family

ID=80645638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210148641.6A Pending CN114202260A (en) 2022-02-18 2022-02-18 Project milestone management system and method, electronic equipment and storage medium

Country Status (1)

Country Link
CN (1) CN114202260A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109718547A (en) * 2018-12-26 2019-05-07 网易(杭州)网络有限公司 A kind of game fine arts resource progress display method and apparatus
CN110196937A (en) * 2019-04-21 2019-09-03 合肥廷创致嘉科技服务有限公司 A kind of project information grabs in real time and analysis system
CN111815282A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project guidance management system
CN113190304A (en) * 2021-04-08 2021-07-30 中广核工程有限公司 Archive information display method and device, computer equipment and storage medium
CN113537955A (en) * 2021-09-17 2021-10-22 天津中新智冠信息技术有限公司 Milestone project management device and method, electronic equipment and storage medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109718547A (en) * 2018-12-26 2019-05-07 网易(杭州)网络有限公司 A kind of game fine arts resource progress display method and apparatus
CN110196937A (en) * 2019-04-21 2019-09-03 合肥廷创致嘉科技服务有限公司 A kind of project information grabs in real time and analysis system
CN111815282A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project guidance management system
CN113190304A (en) * 2021-04-08 2021-07-30 中广核工程有限公司 Archive information display method and device, computer equipment and storage medium
CN113537955A (en) * 2021-09-17 2021-10-22 天津中新智冠信息技术有限公司 Milestone project management device and method, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
US10304021B2 (en) Metadata-configurable systems and methods for network services
US12056666B2 (en) Collaborative due diligence review system
EP2192536A2 (en) Integrated design application
US20110313932A1 (en) Model-based project network
TW201405452A (en) Workflow management device and workflow management method
CN111782951A (en) Method and device for determining display page, computer system and medium
CN111309712A (en) Optimized task scheduling method, device, equipment and medium based on data warehouse
KR102560784B1 (en) System and method for providing task tracking
WO2020241331A1 (en) Three-dimensional data management method for building and mobile terminal for implementing same
US20210182754A1 (en) Minimizing unmet demands due to short supply
CN111222166A (en) Method and device for sharing and managing design material in multi-user online collaboration
CN114202260A (en) Project milestone management system and method, electronic equipment and storage medium
US9542457B1 (en) Methods for displaying object history information
US11995587B2 (en) Method and device for managing project by using data merging
CN110222960A (en) Method and system for generating automatic matching task
JP2019101829A (en) Software component management system, computor, and method
US20210304220A1 (en) Complex sourcing system
US20160224926A1 (en) Task Management System
US20130339372A1 (en) System and method for contexual ranking of information facets
KR102315397B1 (en) Method and apparatus for managing project using filtering data
KR102315433B1 (en) Method and apparatus for managing project using setting of cost payment time
CN110399337A (en) File automating method of servicing and system based on data-driven
KR102453579B1 (en) System for providing cooperation solution for collaboration between workers
US20220405678A1 (en) Method and device for managing project by using data pointer
US20160065521A1 (en) Systems and Methods for Organizing the Display of Messages

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220318