CN103394658B - A kind of synchronous method of smelting producing cylinder sleeve molten iron - Google Patents

A kind of synchronous method of smelting producing cylinder sleeve molten iron Download PDF

Info

Publication number
CN103394658B
CN103394658B CN201310354277.XA CN201310354277A CN103394658B CN 103394658 B CN103394658 B CN 103394658B CN 201310354277 A CN201310354277 A CN 201310354277A CN 103394658 B CN103394658 B CN 103394658B
Authority
CN
China
Prior art keywords
melting
molten iron
smelting furnace
smelting
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310354277.XA
Other languages
Chinese (zh)
Other versions
CN103394658A (en
Inventor
程雨
陈庆国
杨剑
胡俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anqing TP Goetze Liner Co Ltd
Original Assignee
Anqing TP Goetze Liner Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anqing TP Goetze Liner Co Ltd filed Critical Anqing TP Goetze Liner Co Ltd
Priority to CN201310354277.XA priority Critical patent/CN103394658B/en
Publication of CN103394658A publication Critical patent/CN103394658A/en
Application granted granted Critical
Publication of CN103394658B publication Critical patent/CN103394658B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refinement Of Pig-Iron, Manufacture Of Cast Iron, And Steel Manufacture Other Than In Revolving Furnaces (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The invention discloses a kind of synchronous method of smelting producing cylinder sleeve molten iron, after melting material is divided into 15-25 part in proportion, then part melting material will do not had to carry out smelting and pouring in turn, because the melting material quantity in smelting furnace reduces, the corresponding shortening of smelting time, then melting direct cast after completing, carries out the melting of other part of melting material again after cast, shorten the time of melting, improve production efficiency.

Description

A kind of synchronous method of smelting producing cylinder sleeve molten iron
Technical field
The present invention relates to cylinder sleeve production field, specifically a kind of synchronous method of smelting producing cylinder sleeve molten iron.
Background technology
Cylinder sleeve adopts molten iron cast to form, and molten iron is that after being prepared burden by the pig iron and other components, in smelting furnace, melting forms.The method of smelting of original molten iron is that all melting materials that can be held by smelting furnace add, and then carry out adding hot smelting, after general melting 2-3 hour, melting completes discharging and pours into a mould.This mode smelting time is oversize, and production efficiency is low.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of synchronous method of smelting producing cylinder sleeve molten iron, carries out smelting and pouring in turn, save smelting time, improve production efficiency after melting material being carried out pro rate.
Technical scheme of the present invention is:
Produce a synchronous method of smelting for cylinder sleeve molten iron, include following steps:
(1), prepare melting material by standard before smelting furnace water outlet, the pro rate average of all melting materials is divided into 15-25 part;
(2), smelting furnace first time water outlet after, the power of smelting furnace is adjusted to 150-160KW, and the melting material then prepared by portion adds, and waits for after 2.5-3 minute, measurement molten iron temperature;
(3), when molten iron temperature is higher than the molten iron temperature scope of coming out of the stove of setting, then the rapid power by smelting furnace is adjusted to insulation power, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(4), when molten iron temperature is lower than the molten iron temperature scope of coming out of the stove of setting, then the power of smelting furnace is adjusted to insulation power after second by wait 20-40, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(5), when molten iron temperature is come out of the stove in molten iron temperature critical field what set, then by normal mileometer adjustment speed, the power of smelting furnace is adjusted to insulation power, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(6), according to the method for step (3)-(5), repeat reinforced melting and cast, until 15-25 part melting material all smelting and pouring is complete.
0.5 ton of intermediate frequency furnace selected by described smelting furnace.
Described insulation frequency is 50KW.
The described every melting of melting material also, after pouring into a mould 5-10 time, is analyzed the chemical composition of molten iron in smelting furnace, carries out ratio adjustment according to composition result to prewired melting material.
Advantage of the present invention:
After melting material distributes by the present invention, the melting material quantity in smelting furnace reduces, and the corresponding shortening of smelting time, then melting direct cast after completing, carries out the melting of other part of melting material again, shorten the time of melting, improve production efficiency after cast.
Detailed description of the invention
Produce a synchronous method of smelting for cylinder sleeve molten iron, include following steps:
(1), prepare melting material by standard before 0.5 ton of intermediate frequency furnace water outlet, the pro rate average of all melting materials is divided into 20 parts;
(2), after the first time water outlet of 0.5 ton of intermediate frequency furnace, the power of 0.5 ton of intermediate frequency furnace is adjusted to 150-160KW, and the melting material then prepared by portion adds, and waits for after 2.5-3 minute, measurement molten iron temperature;
(3), when molten iron temperature is higher than the molten iron temperature scope of coming out of the stove of setting, then the rapid power by 0.5 ton of intermediate frequency furnace is adjusted to 50KW, then pour into a mould, after casting complete, second part of melting material added 0.5 ton of intermediate frequency furnace and the power of 0.5 ton of intermediate frequency furnace is adjusted to 150KW, after having fed in raw material, in 0.5 of 150-160KW ton of intermediate frequency furnace, proceeding melting;
(4), when molten iron temperature is lower than the molten iron temperature scope of coming out of the stove of setting, then the power of 0.5 ton of intermediate frequency furnace is adjusted to 50KW after second by wait 20-40, then pour into a mould, after casting complete, second part of melting material added 0.5 ton of intermediate frequency furnace and the power of 0.5 ton of intermediate frequency furnace is adjusted to 150KW, after having fed in raw material, in 0.5 of 150-160KW ton of intermediate frequency furnace, proceeding melting;
(5), when molten iron temperature is come out of the stove in molten iron temperature critical field what set, then by normal mileometer adjustment speed, the power of 0.5 ton of intermediate frequency furnace is adjusted to 50KW, then pour into a mould, after casting complete, second part of melting material added 0.5 ton of intermediate frequency furnace and the power of 0.5 ton of intermediate frequency furnace is adjusted to 150KW, after having fed in raw material, in 0.5 of 150-160KW ton of intermediate frequency furnace, proceeding melting;
(6), according to the method for step (3)-(5), repeat reinforced melting and cast, until 15-25 part melting material all smelting and pouring is complete.
Wherein, the every melting of melting material after pouring into a mould 10 times, the chemical composition of molten iron in 0.5 ton of intermediate frequency furnace is analyzed, according to composition result, ratio adjustment is carried out to prewired melting material.

Claims (4)

1. produce a synchronous method of smelting for cylinder sleeve molten iron, it is characterized in that: include following steps:
(1), prepare melting material by standard before smelting furnace water outlet, the pro rate average of all melting materials is divided into 15-25 part;
(2), smelting furnace first time water outlet after, the power of smelting furnace is adjusted to 150-160KW, and the melting material then prepared by portion adds, and waits for after 2.5-3 minute, measurement molten iron temperature;
(3), when molten iron temperature is higher than the molten iron temperature scope of coming out of the stove of setting, then the rapid power by smelting furnace is adjusted to insulation power, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(4), when molten iron temperature is lower than the molten iron temperature scope of coming out of the stove of setting, then the power of smelting furnace is adjusted to insulation power after second by wait 20-40, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(5), when molten iron temperature is come out of the stove in molten iron temperature critical field what set, then by normal mileometer adjustment speed, the power of smelting furnace is adjusted to insulation power, then pour into a mould, after casting complete, second part of melting material added smelting furnace and the power of smelting furnace is adjusted to 150KW, after having fed in raw material, in the smelting furnace of 150-160KW, proceeding melting;
(6), according to the method for step (3)-(5), repeat reinforced melting and cast, until 15-25 part melting material all smelting and pouring is complete.
2. a kind of synchronous method of smelting producing cylinder sleeve molten iron according to claim 1, is characterized in that: 0.5 ton of intermediate frequency furnace selected by described smelting furnace.
3. a kind of synchronous method of smelting producing cylinder sleeve molten iron according to claim 1, is characterized in that: described insulation power is 50KW.
4. a kind of synchronous method of smelting producing cylinder sleeve molten iron according to claim 1, it is characterized in that: the described every melting of melting material after pouring into a mould 5-10 time, the chemical composition of molten iron in smelting furnace is analyzed, according to composition result, ratio adjustment is carried out to prewired melting material.
CN201310354277.XA 2013-08-15 2013-08-15 A kind of synchronous method of smelting producing cylinder sleeve molten iron Active CN103394658B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310354277.XA CN103394658B (en) 2013-08-15 2013-08-15 A kind of synchronous method of smelting producing cylinder sleeve molten iron

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310354277.XA CN103394658B (en) 2013-08-15 2013-08-15 A kind of synchronous method of smelting producing cylinder sleeve molten iron

Publications (2)

Publication Number Publication Date
CN103394658A CN103394658A (en) 2013-11-20
CN103394658B true CN103394658B (en) 2015-09-02

Family

ID=49558485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310354277.XA Active CN103394658B (en) 2013-08-15 2013-08-15 A kind of synchronous method of smelting producing cylinder sleeve molten iron

Country Status (1)

Country Link
CN (1) CN103394658B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1303286A (en) * 1970-04-29 1973-01-17
CN1251863A (en) * 1998-10-16 2000-05-03 华新集团丰业总公司耐磨材料厂 Efficient energy-saving smelting method for alloy cast iron
CN101934354A (en) * 2010-08-31 2011-01-05 南京飞燕活塞环股份有限公司 Low-alloy gray cast iron piston ring casting process
CN102069153A (en) * 2011-01-30 2011-05-25 江苏中力齿轮有限公司 Casting method of thin-wall ductile iron gear blank
CN103074537A (en) * 2011-10-26 2013-05-01 韦波 Kamaz heavy truck cylinder liner smelting and forming casting process

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0919522A (en) * 1995-07-07 1997-01-21 Daido Steel Co Ltd Production of head for putter golf club

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1303286A (en) * 1970-04-29 1973-01-17
CN1251863A (en) * 1998-10-16 2000-05-03 华新集团丰业总公司耐磨材料厂 Efficient energy-saving smelting method for alloy cast iron
CN101934354A (en) * 2010-08-31 2011-01-05 南京飞燕活塞环股份有限公司 Low-alloy gray cast iron piston ring casting process
CN102069153A (en) * 2011-01-30 2011-05-25 江苏中力齿轮有限公司 Casting method of thin-wall ductile iron gear blank
CN103074537A (en) * 2011-10-26 2013-05-01 韦波 Kamaz heavy truck cylinder liner smelting and forming casting process

Also Published As

Publication number Publication date
CN103394658A (en) 2013-11-20

Similar Documents

Publication Publication Date Title
CN103272993A (en) Molding sand manufactured from quartz sand as main material and manufacturing method thereof
CN103272987A (en) Molding sand manufactured from silica sand as main material and manufacturing method thereof
CN103667855B (en) A kind of method of scratch tape material smelting iron-based amorphous master alloy
CN103272995A (en) Low-gas evolution molding sand and manufacturing method thereof
CN101603142A (en) A kind of high-intensity high-tenacity ductile cast iron casting and preparation method thereof
CN102744373A (en) Casting process for piston shell
CN104674000A (en) Manganese-silicon-carbon ball for steel making and preparation method thereof
CN103394658B (en) A kind of synchronous method of smelting producing cylinder sleeve molten iron
CN103667856A (en) Method for smelting Fe-based nanocrystalline mother alloy by recovering scratch tape
CN102921932A (en) High-temperature shakeout process method of large-scale Bainite steel casting
CN103740884B (en) A kind of floating plug of efficient pushing off the slag
CN104259389A (en) Central casting pipe for single crystal casting and preparation method thereof
CN103755360B (en) Guide rod pouring material of slag blocking plug used for converter tapping slag blocking
CN103272990A (en) Molding sand comprising cyan sand as main material and manufacturing method thereof
CN103086726A (en) Silicon oxide refractory castable and using method thereof
CN103740885A (en) Preparation method of slag blocking plug
CN102416446A (en) Inoculation production process of high-strength cast iron
CN103361538B (en) Cylinder sleeve alloy cast iron medium-frequency induction furnace melting method and centrifugal casting method
CN102049476A (en) Technique method for inoculating and strengthening cylinder liner
CN108033797A (en) A kind of method for producing tundish dry vibratory material
CN103755357B (en) High-performance binder of guide rod flame-retardant coating
CN104311042B (en) KR desulfurization paddle castable refractory
CN102744363B (en) Casting method of high-strength valve cover
CN103736973A (en) Method for pouring gear
CN105272141A (en) Method for producing stone plate by using melting blast furnace slag

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 246005, 3.9 square kilometers Industrial Park, Anqing Development Zone, Anhui Province, No. 24

Applicant after: ANQING TP GOETZE LINER CO., LTD.

Address before: 246005, 3.9 square kilometers Industrial Park, Anqing Development Zone, Anhui Province, No. 24

Applicant before: Anqing TP Goetze Liner Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant