CN103295100A - Project management progress arranging method and project management progress arranging system - Google Patents
Project management progress arranging method and project management progress arranging system Download PDFInfo
- Publication number
- CN103295100A CN103295100A CN2013102057207A CN201310205720A CN103295100A CN 103295100 A CN103295100 A CN 103295100A CN 2013102057207 A CN2013102057207 A CN 2013102057207A CN 201310205720 A CN201310205720 A CN 201310205720A CN 103295100 A CN103295100 A CN 103295100A
- Authority
- CN
- China
- Prior art keywords
- project
- quantities
- schedule
- resource
- duration
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a project management progress arranging method and a project management progress arranging system which aim at re-optimizing a progress plan to enable resource allocation of a project to be optimal at any time. The project management progress arranging method includes the following steps: (1), generating a project quantity list, namely decomposing a building information model into work packages, reading material information in the work packages and creating the project quantity list according to defined project quantity calculating rules; (2), generating a progress plan, namely calculating labor time and forming the progress plan on the basis of the project quantity list and according to constraint conditions like a logical relationship between labor quotas and processes and total resources; (3), optimizing the progress plan, namely optimizing the progress plan within a reasonable time limit and based on a PSO (particle swarm optimization) algorithm to obtain an optimal progress schedule meeting requirements of optimization of resource allocation.
Description
Technical field
The invention belongs to the engineering management information technique field, particularly project management progress method of combination and system.
Background technology
Along with the raising of the project management level of IT application and applying of project management system, modern Project Management demonstrates extremely strong vitality day by day.Making rapid progress of state-of-art, business environment fast changing, make the corporate operation business possess the characteristic of project day by day, modern Project Management is as a kind of new management mode of enterprise, embodying impayable advantage aspect managing risk and time, the item diversified demand.
Time management is as a key content in the project management, and its purpose is to guarantee finished item, reasonable distribution resource, performance optimum working efficiency on time.Finally finish in order to ensure project on time, need define ordering to concrete activity, the time is estimated, the task layout, and deployment of human resources etc., effectively the time management meeting significantly promotes work efficiency, reduces the task cost.The time management method of using always in the project construction process is simple at present, limitation is big, accuracy is low etc., especially aspect quantities calculating, most of project management software all is artificial input material table, perhaps generate material list automatically according to two-dimentional drawing, workload is big, loaded down with trivial details, time-consuming, visual low, has directly influenced the layout speed of task scheduling.How directly from BIM efficiently and accurately read material information and generate bill of quantities, again according to the work norm information automatic editing task scheduling of bill of quantities and management show more and more important.
In addition, most of project management system lacks the technology of plan being carried out suboptimization again, how according to certain condition reasonable optimizing is carried out in plan, and it is unbalanced to avoid resource to use, and is frequent, and the appearance of serious peak or low ebb phenomenon is also particularly outstanding.Existing some optimization methods and technology, inefficiency, practicality are not high, restrictive condition is strong, are difficult to layout is carried out in the plan of some complexity.
Summary of the invention
The objective of the invention is at above-mentioned the deficiencies in the prior art, propose a kind of project management progress method of combination and system, schedule is optimized again, make the project resource distribution optimum of when phase in office.
Technical scheme of the present invention is achieved in that
A kind of project management progress method of combination may further comprise the steps:
Step 1: generate bill of quantities: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Step 2: generate schedule: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Step 3: optimize schedule: in the rational time limit, based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
Preferably, in the project management progress method of combination, step 1 generates bill of quantities and comprises following steps:
Step 11: on the basis of project construction BIM, according to quantities subitem rule BIM is split as saddlebag;
Step 12: extract the material information of saddlebag, material comprises: door, window, lead, light fixture, place etc., and material information containing type, component names, absolute altitude, width, height etc. are set up material database according to material information;
Step 13: generate bill of quantities, the material database so that step 12 is set up according to the quantities computation rule of definition, generates bill of quantities; Wherein, the quantities computation rule has comprised the definition to Material Takeoff unit, statistic algorithm and materials classification.
Preferably, project management progress method of combination, step 2 generates schedule and comprises following steps:
Step 21: initialization resource distribution: according to user's technical routine construction period and milestone plan, the resources such as input quantity of the manpower that each quantities subitem is dropped into, machinery, resource are carried out initial configuration;
Step 22: calculate and respectively itemize the duration: based on the bill of quantities table, the corresponding work norm of computational engineering amount subitem is chosen the corresponding regular standard of each subitem according to subitem, calculates the duration size of each quantities subitem;
Step 23: generate network planning figure, dispose the dependence of each quantities subitem, with each quantities with duration of each quantities subitem as weight, generate single code name network planning figure; For the project under construction that is provided with the milestone node, be the beginning summit of network planning figure with the project initiation, be the end vertex of network planning figure with the milestone, network planning figure is split into a plurality of sub-network planning charts;
Step 24: the critical path of calculating chart, the network planning figure of the project construction that obtains based on step 23, the activity that can walk abreast in the project construction is merged, the longest path of choosing then from the beginning summit to end vertex is critical path, and the length of this critical path is the duration length of project construction; The activity on the critical path chosen is as critical activity;
Step 25: judge whether the project duration satisfy construction period, judge whether the project duration satisfy construction period, if satisfy construction period, then obtained satisfactory project construction schedule; If do not satisfy construction period, the resource that then progressively increases critical activity drops into, and shortens the project construction duration to reach requirement;
Step 26: judge whether to reach the resource restriction, travel through each critical activity on each bar critical path at first one by one, find out the activity that does not also reach the restriction of resource input, in the activity that these satisfy condition, select to drop into that the highest activity of Energy Efficiency Ratio, as the goal activities of optimizing; If all activities on the critical path have all reached the restrictive condition of resource, show that then project can't finish on schedule, progress layout failure;
Step 27: increase resource and drop into, obtain the goal activities that to optimize by step 26, input unit's resource, shorten the duration of goal activities, and then jump to step 22, regenerate network planning figure, calculate critical path and carry out comparative analysis, till critical path depth both project duration meets the demands.
Preferably, project management progress method of combination, step 3 is optimized schedule and be may further comprise the steps:
Step 31: determine the resource optimization target, fix by supposing the duration, be no more than under the prerequisite of duration, utilize the variance minimum principle that resource distribution is optimized, reach resource allocation equalization;
Step 32: set up and optimize model, set up mathematical model according to the variance minimum principle, the mathematical model formula is as follows:
Wherein, T is the date of engineering discipline, and R (t) is the engineering t resource consumption intensity of all process steps constantly, R
mFor the engineering average resource consumes intensity, R
i(t) sign operation i is in t resource consumption intensity constantly, and N is the sum of operation;
Step 33: use PSO particle swarm optimization model, the project process scheduled resource is optimized, obtain meeting the best schedule diagram of most optimum distribution of resources.
Preferred again, optimize in the schedule R of step 32
i(t) should satisfy following constraint:
max(T
s(k),T
P(i))≤T
s(i)≤T
L(i)
Wherein, T
s(i) the actual start time of expression operation i, the duration of T (i) expression operation i, operation k is the tight preceding operation of operation i, T
P(i) earliest start time of expression operation i, T
L(i) Late Start of expression operation i.
A kind of project process arranging system comprises the following assembly that connects successively:
Bill of quantities generating apparatus: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Schedule generating apparatus: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Schedule Optimization device: based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
By the above-mentioned description of this invention as can be known, compare with prior art, the present invention has following advantage:
The present invention is split as saddlebag according to quantities subitem rule with BIM, the material information in the extraction model, and calculate the quantities of each quantities subitem according to quantities kinds of construction amount computation rule; Adopt the Network Program Method computational item duration, according to project process arrangement and the restriction of milestone node, consideration standard work norm and project manpower, resources supplIes restriction, progressively generate the human resources planning of each quantities subitem of project, on the basis of saddlebag association, generation project construction speed network planning figure, the desirable duration of identifying project; Utilize the PSO algorithm model further to optimize the construction plan scheme of project, when having overcome the legacy network planning optimization, resource is used unbalanced, frequently, serious peak or low ebb phenomenon, this method has improved the speed of layout, save executive cost to greatest extent, realize distributing rationally of resource.
Description of drawings
In order to be illustrated more clearly in the embodiment of the invention or technical scheme of the prior art, to do to introduce simply to the accompanying drawing of required use in embodiment or the description of the Prior Art below, apparently, accompanying drawing in describing below only is some embodiments of the present invention, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is system architecture synoptic diagram of the present invention.
Fig. 2 is the process flow diagram of generation bill of quantities of the present invention.
Fig. 3 is the process flow diagram of generation schedule of the present invention.
The process flow diagram that Fig. 4 is optimized schedule for PSO algorithm of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the invention, the technical scheme in the embodiment of the invention is clearly and completely described, obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that obtains under the creative work prerequisite.
With reference to Fig. 1, a kind of project process arranging system comprises the following assembly that connects successively:
Bill of quantities generating apparatus: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Schedule generating apparatus: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Schedule Optimization device: based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
A kind of project management progress method of combination may further comprise the steps:
Step 1: generate bill of quantities: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Step 2: generate schedule: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Step 3: optimize schedule: in the rational time limit, based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
With reference to Fig. 2, in the project management progress method of combination, step 1 generates bill of quantities and comprises following steps:
Step 11: on the basis of project construction BIM, according to quantities subitem rule BIM is split as saddlebag;
Step 12: extract the material information of saddlebag, material comprises: door, window, lead, light fixture, place etc., and material information containing type, component names, absolute altitude, width, height etc. are set up material database according to material information;
Step 13: generate bill of quantities, the material database so that step 12 is set up according to the quantities computation rule of definition, generates bill of quantities; Wherein, the quantities computation rule has comprised the definition to Material Takeoff unit, statistic algorithm and materials classification.
With reference to Fig. 3, in the project management progress method of combination, step 2 generates schedule and comprises following steps:
Step 21: initialization resource distribution: according to user's technical routine construction period and milestone plan, the resources such as input quantity of the manpower that each quantities subitem is dropped into, machinery, resource are carried out initial configuration;
Step 22: calculate and respectively itemize the duration: based on the bill of quantities table, the corresponding work norm of computational engineering amount subitem is chosen the corresponding regular standard of each subitem according to subitem, calculates the duration size of each quantities subitem;
Step 23: generate network planning figure, dispose the dependence of each quantities subitem, with each quantities with duration of each quantities subitem as weight, generate single code name network planning figure; For the project under construction that is provided with the milestone node, be the beginning summit of network planning figure with the project initiation, be the end vertex of network planning figure with the milestone, network planning figure is split into a plurality of sub-network planning charts;
Step 24: the critical path of calculating chart, the network planning figure of the project construction that obtains based on step 23, the activity that can walk abreast in the project construction is merged, the longest path of choosing then from the beginning summit to end vertex is critical path, and the length of this critical path is the duration length of project construction; The activity on the critical path chosen is as critical activity;
Step 25: judge whether the project duration satisfy construction period, judge whether the project duration satisfy construction period, if satisfy construction period, then obtained satisfactory project construction schedule; If do not satisfy construction period, the resource that then progressively increases critical activity drops into, and shortens the project construction duration to reach requirement;
Step 26: judge whether to reach the resource restriction, travel through each critical activity on each bar critical path at first one by one, find out the activity that does not also reach the restriction of resource input, in the activity that these satisfy condition, select to drop into that the highest activity of Energy Efficiency Ratio, as the goal activities of optimizing; If all activities on the critical path have all reached the restrictive condition of resource, show that then project can't finish on schedule, progress layout failure;
Step 27: increase resource and drop into, obtain the goal activities that to optimize by step 26, input unit's resource, shorten the duration of goal activities, and then jump to step 22, regenerate network planning figure, calculate critical path and carry out comparative analysis, till critical path depth both project duration meets the demands.
In the project management progress method of combination, step 3 is optimized schedule and be may further comprise the steps:
Step 31: determine the resource optimization target, fix by supposing the duration, be no more than under the prerequisite of duration, utilize the variance minimum principle that resource distribution is optimized, reach resource allocation equalization;
Step 32: set up and optimize model, set up mathematical model according to the variance minimum principle, the mathematical model formula is as follows:
Wherein, T is the date of engineering discipline, and R (t) is the engineering t resource consumption intensity of all process steps constantly, R
mFor the engineering average resource consumes intensity, R
i(t) sign operation i is in t resource consumption intensity constantly, and N is the sum of operation; R
i(t) should satisfy following constraint:
max(T
s(k),T
P(i))≤T
s(i)≤T
L(i) (4)
Wherein, T
s(i) the actual start time of expression operation i, the duration of T (i) expression operation i, operation k is the tight preceding operation of operation i, T
P(i) earliest start time of expression operation i, T
L(i) Late Start of expression operation i.
Being less than operation as can be seen has logical relation constraint and time relationship constraint, and the actual start time of per pass operation not only is limited in earliest start time and the Late Start scope, but also is subjected to the influence of tight preceding working procedure states.
Step 33: use PSO particle swarm optimization model, the project process scheduled resource is optimized, obtain meeting the best schedule diagram of most optimum distribution of resources.
The PSO algorithm is that a kind of bionic intelligence is optimized algorithm, the fitness that each particle has an objective function to determine, and this fitness value is used for weighing the superior degree of each particle, and each particle also has a speed to determine direction and the distance of its flight.All particles are initialized as a group random particles, find optimum solution by iteration then.In the iteration, particle upgrades oneself by following the tracks of two " extreme values ": one is the optimum solution that all particles reach in the successive dynasties search procedure in the whole population, is called as globally optimal solution G each time
BestAnother then is the optimum solution that each particle self reaches in the successive dynasties search procedure, and this solution is called as individual optimum solution P
BestEach each particle of iteration upgrades speed and the position of oneself according to following formula:
x
id=x
id+v
id (6)
In the formula (1): v
IdBe the d dimension component of particle i somatotype velocity, x
IdFor the d of particle i position vector is component, r
1, r
2Be the random number between [0,1], c
1, c
2Be acceleration factor, w is inertia weight.
For using PSO particle swarm optimization model, to the main flow process that the project process scheduled resource is optimized, the specific implementation step is as follows with reference to Fig. 4:
Step 1: initialization procedure, input schedule primary data is calculated other data such as speed limit, lower limit and operation total duration etc., in limited range, produce random site and the speed of each particle of population at random, and calculate the adaptive value of each particle correspondence.
Step 2: evolution equation, according to formula (5), (6) evolution equation is evolved to population.
Step 3: evolution postevaluation particle, revise according to above-mentioned formula (4), make its logical relation constraint of satisfying operation and time relationship constraint, and calculate the fitness value of each particle.
Step 4: new particle more, upgrade P according to evaluation rule
Best, G
Best
Step 5: judge whether to meet end condition, if do not reach a default maximum evolutionary generation, then return step 2; If reach then the iteration end output result.
The above only is preferred embodiment of the present invention, and is in order to limit the present invention, within the spirit and principles in the present invention not all, any modification of doing, is equal to replacement, improvement etc., all should be included within protection scope of the present invention.
Claims (6)
1. project management progress method of combination is characterized in that: may further comprise the steps:
Step 1: generate bill of quantities: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Step 2: generate schedule: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Step 3: optimize schedule: in the rational time limit, based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
2. a kind of project management progress method of combination as claimed in claim 1 is characterized in that: in the project process method of combination, step 1 generates bill of quantities and comprises following steps:
Step 11: on the basis of project construction BIM, according to quantities subitem rule BIM is split as saddlebag;
Step 12: extract the material information of saddlebag, material comprises: door, window, lead, light fixture, place etc., and material information containing type, component names, absolute altitude, width, height etc. are set up material database according to material information;
Step 13: generate bill of quantities, the material database so that step 12 is set up according to the quantities computation rule of definition, generates bill of quantities; Wherein, the quantities computation rule has comprised the definition to Material Takeoff unit, statistic algorithm and materials classification.
3. a kind of project management progress method of combination as claimed in claim 1 is characterized in that: in the project process method of combination, step 2 generates schedule and comprises following steps:
Step 21: initialization resource distribution: according to user's technical routine construction period and milestone plan, the resources such as input quantity of the manpower that each quantities subitem is dropped into, machinery, resource are carried out initial configuration;
Step 22: calculate and respectively itemize the duration: based on the bill of quantities table, the corresponding work norm of computational engineering amount subitem is chosen the corresponding regular standard of each subitem according to subitem, calculates the duration size of each quantities subitem;
Step 23: generate network planning figure, dispose the dependence of each quantities subitem, with each quantities with duration of each quantities subitem as weight, generate single code name network planning figure; For the project under construction that is provided with the milestone node, be the beginning summit of network planning figure with the project initiation, be the end vertex of network planning figure with the milestone, network planning figure is split into a plurality of sub-network planning charts;
Step 24: the critical path of calculating chart, the network planning figure of the project construction that obtains based on step 23, the activity that can walk abreast in the project construction is merged, the longest path of choosing then from the beginning summit to end vertex is critical path, and the length of this critical path is the duration length of project construction; The activity on the critical path chosen is as critical activity;
Step 25: judge whether the project duration satisfy construction period, judge whether the project duration satisfy construction period, if satisfy construction period, then obtained satisfactory project construction schedule; If do not satisfy construction period, the resource that then progressively increases critical activity drops into, and shortens the project construction duration to reach requirement;
Step 26: judge whether to reach the resource restriction, travel through each critical activity on each bar critical path at first one by one, find out the activity that does not also reach the restriction of resource input, in the activity that these satisfy condition, select to drop into that the highest activity of Energy Efficiency Ratio, as the goal activities of optimizing; If all activities on the critical path have all reached the restrictive condition of resource, show that then project can't finish on schedule, progress layout failure;
Step 27: increase resource and drop into, obtain the goal activities that to optimize by step 26, input unit's resource, shorten the duration of goal activities, and then jump to step 22, regenerate network planning figure, calculate critical path and carry out comparative analysis, till critical path depth both project duration meets the demands.
4. a kind of project management progress method of combination as claimed in claim 1 is characterized in that: in the project process method of combination, step 3 is optimized schedule and be may further comprise the steps:
Step 31: determine the resource optimization target, fix by supposing the duration, be no more than under the prerequisite of duration, utilize the variance minimum principle that resource distribution is optimized, reach resource allocation equalization;
Step 32: set up and optimize model, set up mathematical model according to the variance minimum principle, the mathematical model formula is as follows:
Wherein, T is the date of engineering discipline, and R (t) is the engineering t resource consumption intensity of all process steps constantly, R
mFor the engineering average resource consumes intensity, R
i(t) sign operation i is in t resource consumption intensity constantly, and N is the sum of operation;
Step 33: use PSO particle swarm optimization model, the project process scheduled resource is optimized, obtain meeting the best schedule diagram of most optimum distribution of resources.
5. a kind of project management progress method of combination as claimed in claim 4 is characterized in that: optimize in the schedule R of step 32
i(t) should satisfy following constraint:
max(T
s(k),T
P(i))≤T
s(i)≤T
L(i)
Wherein, T
s(i) the actual start time of expression operation i, the duration of T (i) expression operation i, operation k is the tight preceding operation of operation i, T
P(i) earliest start time of expression operation i, T
L(i) Late Start of expression operation i.
6. project process arranging system is characterized in that: comprise the following assembly that connects successively:
Bill of quantities generating apparatus: BIM is resolved into saddlebag, read the material information in the saddlebag, according to the quantities computation rule of definition, set up bill of quantities;
Schedule generating apparatus: based on the bill of quantities table that step 1 obtains, calculate working time according to constraint conditions such as the logical relation between work norm, the operation, total resources, set up schedule;
Schedule Optimization device: based on the PSO algorithm schedule is optimized, obtains meeting the best schedule diagram of most optimum distribution of resources.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102057207A CN103295100A (en) | 2013-05-28 | 2013-05-28 | Project management progress arranging method and project management progress arranging system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102057207A CN103295100A (en) | 2013-05-28 | 2013-05-28 | Project management progress arranging method and project management progress arranging system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103295100A true CN103295100A (en) | 2013-09-11 |
Family
ID=49095918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013102057207A Pending CN103295100A (en) | 2013-05-28 | 2013-05-28 | Project management progress arranging method and project management progress arranging system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103295100A (en) |
Cited By (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103440600A (en) * | 2013-09-13 | 2013-12-11 | 成都中铁隆工程集团有限公司 | BIM (Building Information Modeling) risk monitoring system and method of multilayer 4D (4-Dimensional) model |
CN103500371A (en) * | 2013-08-08 | 2014-01-08 | 机械工业第六设计研究院有限公司 | Change control method based on BIM |
CN103699939A (en) * | 2013-11-15 | 2014-04-02 | 中国空间技术研究院 | Component application validation process establishment method for space navigation |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105321042A (en) * | 2015-10-19 | 2016-02-10 | 金航数码科技有限责任公司 | Genetic algorithm-based advanced plan scheduling system and method |
CN105654399A (en) * | 2015-12-31 | 2016-06-08 | 青建集团股份公司 | Foundation pit digging and support construction period planning intelligent system |
CN106506188A (en) * | 2015-09-08 | 2017-03-15 | 阿里巴巴集团控股有限公司 | A kind of method and apparatus for determining key node |
CN107067220A (en) * | 2016-06-20 | 2017-08-18 | 杨玉海 | The full-automatic lateral road figure technical method of project management progress |
CN107909280A (en) * | 2017-11-24 | 2018-04-13 | 国网内蒙古东部电力有限公司 | A kind of electricity power engineering managing and control system and its control method based on bill of quantities |
CN107977785A (en) * | 2017-11-24 | 2018-05-01 | 国网内蒙古东部电力有限公司 | A kind of electricity power engineering project process monitoring method |
CN108170406A (en) * | 2017-12-29 | 2018-06-15 | 中国银行股份有限公司 | A kind of analysis method and device of required by task stock number |
CN108509220A (en) * | 2018-04-02 | 2018-09-07 | 厦门海迈科技股份有限公司 | Revit engineering calculation amounts method for parallel processing, device, terminal and medium |
CN108985604A (en) * | 2018-07-04 | 2018-12-11 | 成都希盟科技有限公司 | Compression of time limit for a project method for construction plan establishment |
CN109034551A (en) * | 2018-07-04 | 2018-12-18 | 成都希盟泰克科技发展有限公司 | Equilibrium of stock method for construction plan establishment |
CN109636616A (en) * | 2018-11-21 | 2019-04-16 | 周剑毅 | A method of realizing project cluster progress and investment master control management |
CN110232465A (en) * | 2019-03-28 | 2019-09-13 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage plans of critical path method resources balance optimization method step by step |
CN110309938A (en) * | 2019-04-14 | 2019-10-08 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage system of planning Key Information methods of critical path method |
CN110322102A (en) * | 2019-03-31 | 2019-10-11 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization plan time resource dynamic reviewing methods of critical path method |
CN110322101A (en) * | 2019-03-31 | 2019-10-11 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage system of planning resource limited optimization methods of critical path method |
CN110334829A (en) * | 2019-03-26 | 2019-10-15 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization ways to draw up the plan of critical path method forms mode |
CN110363324A (en) * | 2019-03-29 | 2019-10-22 | 济南森坤企业管理咨询有限公司 | A kind of any projects combo multistage plan of the critical path method minimum optimization method of resource step by step |
CN110378668A (en) * | 2019-06-28 | 2019-10-25 | 赣州和永软件开发有限责任公司 | The method and system of engineering project information initialization is carried out with item base template library |
CN110503325A (en) * | 2019-08-16 | 2019-11-26 | 清华大学 | A kind of construction speed resource automatic optimization method based on Building Information Model |
CN110717612A (en) * | 2019-04-04 | 2020-01-21 | 济南森坤企业管理咨询有限公司 | Method for comparing multi-level organization plan resource minimum optimization schemes by overall planning method |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111898791A (en) * | 2020-06-05 | 2020-11-06 | 合肥工业大学 | Method and system for determining construction period planning scheme based on multi-level outsourcing mode |
CN112580915A (en) * | 2019-09-30 | 2021-03-30 | 北京国双科技有限公司 | Project milestone determination method and device, storage medium and electronic equipment |
CN112801515A (en) * | 2021-01-29 | 2021-05-14 | 广船国际有限公司 | Project resource allocation method, electronic equipment and computer readable storage medium |
CN113609550A (en) * | 2021-07-05 | 2021-11-05 | 江苏徐工工程机械研究院有限公司 | BIM-based construction process planning management method and system |
CN114282827A (en) * | 2021-12-27 | 2022-04-05 | 中铁建工集团有限公司 | Method and system for scheduling construction period progress |
CN114611749A (en) * | 2022-01-14 | 2022-06-10 | 北京全路通信信号研究设计院集团有限公司 | Optimization method and system for shortening construction period |
CN114880131A (en) * | 2022-07-11 | 2022-08-09 | 中科雨辰科技有限公司 | Dynamic arranging system based on tasks |
CN116051055A (en) * | 2023-02-24 | 2023-05-02 | 中国水利水电第三工程局有限公司 | Digital project management system |
WO2023109269A1 (en) * | 2021-12-15 | 2023-06-22 | 深圳前海微众银行股份有限公司 | Project data processing method and apparatus, device, medium, and program product |
CN116630095A (en) * | 2023-07-24 | 2023-08-22 | 中建西南咨询顾问有限公司 | Overall planning and planning method and system for automatic engineering construction total tasks |
CN117725662A (en) * | 2024-02-07 | 2024-03-19 | 青岛瑞源工程集团有限公司 | Engineering construction simulation method and system based on municipal engineering |
CN118134167A (en) * | 2024-03-05 | 2024-06-04 | 深圳核裕机电工程有限公司 | Nuclear power project installation engineering amount calculating method and system |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20120121634A (en) * | 2011-04-27 | 2012-11-06 | 대림산업 주식회사 | Building Information Modeling System for Cost and Schedule Managing and Operation Method Thereof |
-
2013
- 2013-05-28 CN CN2013102057207A patent/CN103295100A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20120121634A (en) * | 2011-04-27 | 2012-11-06 | 대림산업 주식회사 | Building Information Modeling System for Cost and Schedule Managing and Operation Method Thereof |
Non-Patent Citations (9)
Title |
---|
三项国标起草组: "《网络计划技术三项国家标准应用指南》", 30 November 1992 * |
于颖、李永生、於孝春: "粒子群算法在工程优化设计中的应用", 《机械工程学报 》 * |
何清华;韩翔宇: "基于BIM的进度管理系统框架构建和流程设计", 《项目管理技术》 * |
刘琼: "资源受限下项目进度问题模型构建及其算法实现", 《中国优秀硕士学位论文全文数据库 经济与管理学辑》 * |
唐俊: "《PSO算法原理及应用》", 《计算机技术与发展》 * |
沈志刚: "资源约束下的关键链管理", 《万方数据库》 * |
王仁超; 郝伟峰: "工程项目中网络进度计划编制标准化研究", 《价值工程》 * |
王青薇; 张建平: "基于BIM的工程进度计划编制", 《商场现代化》 * |
赵彬、王友群、牛博生: "基于BIM的4D虚拟建造技术在工程项目进度管理中的应用", 《建筑经济》 * |
Cited By (49)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103500371A (en) * | 2013-08-08 | 2014-01-08 | 机械工业第六设计研究院有限公司 | Change control method based on BIM |
CN103440600A (en) * | 2013-09-13 | 2013-12-11 | 成都中铁隆工程集团有限公司 | BIM (Building Information Modeling) risk monitoring system and method of multilayer 4D (4-Dimensional) model |
CN103699939A (en) * | 2013-11-15 | 2014-04-02 | 中国空间技术研究院 | Component application validation process establishment method for space navigation |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN106506188A (en) * | 2015-09-08 | 2017-03-15 | 阿里巴巴集团控股有限公司 | A kind of method and apparatus for determining key node |
CN106506188B (en) * | 2015-09-08 | 2019-11-08 | 阿里巴巴集团控股有限公司 | A kind of method and apparatus of determining key node |
CN105321042A (en) * | 2015-10-19 | 2016-02-10 | 金航数码科技有限责任公司 | Genetic algorithm-based advanced plan scheduling system and method |
CN105321042B (en) * | 2015-10-19 | 2017-02-22 | 金航数码科技有限责任公司 | Genetic algorithm-based advanced plan scheduling system and method |
CN105654399A (en) * | 2015-12-31 | 2016-06-08 | 青建集团股份公司 | Foundation pit digging and support construction period planning intelligent system |
CN107067220A (en) * | 2016-06-20 | 2017-08-18 | 杨玉海 | The full-automatic lateral road figure technical method of project management progress |
CN107977785A (en) * | 2017-11-24 | 2018-05-01 | 国网内蒙古东部电力有限公司 | A kind of electricity power engineering project process monitoring method |
CN107977785B (en) * | 2017-11-24 | 2022-02-15 | 国网内蒙古东部电力有限公司 | Power grid engineering project progress monitoring method |
CN107909280A (en) * | 2017-11-24 | 2018-04-13 | 国网内蒙古东部电力有限公司 | A kind of electricity power engineering managing and control system and its control method based on bill of quantities |
CN108170406A (en) * | 2017-12-29 | 2018-06-15 | 中国银行股份有限公司 | A kind of analysis method and device of required by task stock number |
CN108509220A (en) * | 2018-04-02 | 2018-09-07 | 厦门海迈科技股份有限公司 | Revit engineering calculation amounts method for parallel processing, device, terminal and medium |
CN108509220B (en) * | 2018-04-02 | 2021-01-22 | 厦门海迈科技股份有限公司 | Revit engineering calculation amount parallel processing method, device, terminal and medium |
CN109034551A (en) * | 2018-07-04 | 2018-12-18 | 成都希盟泰克科技发展有限公司 | Equilibrium of stock method for construction plan establishment |
CN108985604A (en) * | 2018-07-04 | 2018-12-11 | 成都希盟科技有限公司 | Compression of time limit for a project method for construction plan establishment |
CN109034551B (en) * | 2018-07-04 | 2020-10-27 | 成都希盟泰克科技发展有限公司 | Resource balancing method for construction planning |
CN108985604B (en) * | 2018-07-04 | 2021-06-08 | 成都希盟泰克科技发展有限公司 | Construction period compression method for construction planning |
CN109636616A (en) * | 2018-11-21 | 2019-04-16 | 周剑毅 | A method of realizing project cluster progress and investment master control management |
CN109636616B (en) * | 2018-11-21 | 2021-09-14 | 周剑毅 | Method for realizing project group progress master control management |
CN110334829A (en) * | 2019-03-26 | 2019-10-15 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization ways to draw up the plan of critical path method forms mode |
CN110232465A (en) * | 2019-03-28 | 2019-09-13 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage plans of critical path method resources balance optimization method step by step |
CN110363324A (en) * | 2019-03-29 | 2019-10-22 | 济南森坤企业管理咨询有限公司 | A kind of any projects combo multistage plan of the critical path method minimum optimization method of resource step by step |
CN110322101A (en) * | 2019-03-31 | 2019-10-11 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage system of planning resource limited optimization methods of critical path method |
CN110322102A (en) * | 2019-03-31 | 2019-10-11 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization plan time resource dynamic reviewing methods of critical path method |
CN110717612A (en) * | 2019-04-04 | 2020-01-21 | 济南森坤企业管理咨询有限公司 | Method for comparing multi-level organization plan resource minimum optimization schemes by overall planning method |
CN110309938A (en) * | 2019-04-14 | 2019-10-08 | 济南森坤企业管理咨询有限公司 | A kind of all kinds of project organization multistage system of planning Key Information methods of critical path method |
CN110378668A (en) * | 2019-06-28 | 2019-10-25 | 赣州和永软件开发有限责任公司 | The method and system of engineering project information initialization is carried out with item base template library |
CN110503325A (en) * | 2019-08-16 | 2019-11-26 | 清华大学 | A kind of construction speed resource automatic optimization method based on Building Information Model |
CN110503325B (en) * | 2019-08-16 | 2022-04-22 | 清华大学 | Construction progress resource automatic optimization method based on building information model |
WO2021031336A1 (en) * | 2019-08-16 | 2021-02-25 | 清华大学 | Method for automated construction progress resource optimization employing building information model |
CN112580915A (en) * | 2019-09-30 | 2021-03-30 | 北京国双科技有限公司 | Project milestone determination method and device, storage medium and electronic equipment |
CN111783270A (en) * | 2020-03-17 | 2020-10-16 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111783270B (en) * | 2020-03-17 | 2021-09-03 | 江西武大扬帆科技有限公司 | Construction progress digital simulation method based on BIM technology |
CN111898791A (en) * | 2020-06-05 | 2020-11-06 | 合肥工业大学 | Method and system for determining construction period planning scheme based on multi-level outsourcing mode |
CN112801515A (en) * | 2021-01-29 | 2021-05-14 | 广船国际有限公司 | Project resource allocation method, electronic equipment and computer readable storage medium |
CN113609550A (en) * | 2021-07-05 | 2021-11-05 | 江苏徐工工程机械研究院有限公司 | BIM-based construction process planning management method and system |
WO2023109269A1 (en) * | 2021-12-15 | 2023-06-22 | 深圳前海微众银行股份有限公司 | Project data processing method and apparatus, device, medium, and program product |
CN114282827A (en) * | 2021-12-27 | 2022-04-05 | 中铁建工集团有限公司 | Method and system for scheduling construction period progress |
CN114611749A (en) * | 2022-01-14 | 2022-06-10 | 北京全路通信信号研究设计院集团有限公司 | Optimization method and system for shortening construction period |
CN114880131A (en) * | 2022-07-11 | 2022-08-09 | 中科雨辰科技有限公司 | Dynamic arranging system based on tasks |
CN116051055A (en) * | 2023-02-24 | 2023-05-02 | 中国水利水电第三工程局有限公司 | Digital project management system |
CN116630095A (en) * | 2023-07-24 | 2023-08-22 | 中建西南咨询顾问有限公司 | Overall planning and planning method and system for automatic engineering construction total tasks |
CN116630095B (en) * | 2023-07-24 | 2023-09-19 | 中建西南咨询顾问有限公司 | Overall planning and planning method and system for automatic engineering construction total tasks |
CN117725662A (en) * | 2024-02-07 | 2024-03-19 | 青岛瑞源工程集团有限公司 | Engineering construction simulation method and system based on municipal engineering |
CN117725662B (en) * | 2024-02-07 | 2024-04-26 | 青岛瑞源工程集团有限公司 | Engineering construction simulation method and system based on municipal engineering |
CN118134167A (en) * | 2024-03-05 | 2024-06-04 | 深圳核裕机电工程有限公司 | Nuclear power project installation engineering amount calculating method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103295100A (en) | Project management progress arranging method and project management progress arranging system | |
Belsnes et al. | Applying successive linear programming for stochastic short-term hydropower optimization | |
Ferreira et al. | Demand response models with correlated price data: A robust optimization approach | |
CN106155791B (en) | A kind of workflow task dispatching method under distributed environment | |
CN104009494B (en) | A kind of environmental economy power generation dispatching method | |
CN101847228A (en) | Workflow static planning method based on process mode | |
CN107944625A (en) | Single air station flight season time slot optimization method based on history data driving | |
Rasoulzadeh-Gharibdousti et al. | Optimal design and operation of pumping stations using NLP-GA | |
Tiwari et al. | Project scheduling by integration of time cost trade-off and constrained resource scheduling | |
CN104657512A (en) | Method and device for realizing steel truss arch bridge engineering quantity statistics by employing BIM (building information modeling) | |
CN108428114A (en) | Information processing method and device, storage medium, the electronic device of project | |
Brunner et al. | Stabilized branch and price with dynamic parameter updating for discontinuous tour scheduling | |
CN105656026B (en) | Equipment construction resource allocation method and system for renewable energy | |
CN104636834B (en) | A kind of improved joint probability plan model system optimization method | |
Maghsoudlou et al. | A framework for preemptive multi-skilled project scheduling problem with time-of-use energy tariffs | |
CN105205052A (en) | Method and device for mining data | |
CN105869017A (en) | Method and system for predicting ticket prices | |
Mathew et al. | Demand forecasting for economic order quantity in inventory management | |
Bai et al. | Extended neighborhood search algorithm for constrained unit commitment | |
Carlier et al. | The project scheduling problem with production and consumption of resources: A list-scheduling based algorithm | |
CN103117008A (en) | Sector instant capacity assessment method based on controller workload | |
Banjar et al. | Intelligent Scheduling Algorithms for the Enhancement of Drone Based Innovative Logistic Supply Chain Systems | |
Wang et al. | Multi-reservoir system operation theory and practice | |
Krishnamoorthy et al. | Temporal manufacturing query language (tMQL) for domain specific composition, what-if analysis, and optimization of manufacturing processes with inventories | |
Devulapalli et al. | A framework for requirement prioritization for software products |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20130911 |