CN102563201B - Device for eliminating leakage risk of gas gate valve online - Google Patents
Device for eliminating leakage risk of gas gate valve online Download PDFInfo
- Publication number
- CN102563201B CN102563201B CN2012100334126A CN201210033412A CN102563201B CN 102563201 B CN102563201 B CN 102563201B CN 2012100334126 A CN2012100334126 A CN 2012100334126A CN 201210033412 A CN201210033412 A CN 201210033412A CN 102563201 B CN102563201 B CN 102563201B
- Authority
- CN
- China
- Prior art keywords
- valve
- valves
- gas
- gate valve
- pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000007789 gas Substances 0.000 claims abstract description 55
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 claims abstract description 54
- 229910052757 nitrogen Inorganic materials 0.000 claims abstract description 27
- 238000012360 testing method Methods 0.000 claims abstract description 14
- 230000008030 elimination Effects 0.000 claims description 6
- 238000003379 elimination reaction Methods 0.000 claims description 6
- 238000007789 sealing Methods 0.000 claims description 6
- 238000012546 transfer Methods 0.000 claims description 4
- 230000008676 import Effects 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 2
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- UHOVQNZJYSORNB-UHFFFAOYSA-N Benzene Chemical compound C1=CC=CC=C1 UHOVQNZJYSORNB-UHFFFAOYSA-N 0.000 description 6
- 239000003034 coal gas Substances 0.000 description 5
- 230000006378 damage Effects 0.000 description 4
- 101710089042 Demethyl-4-deoxygadusol synthase Proteins 0.000 description 1
- RWSOTUBLDIXVET-UHFFFAOYSA-N Dihydrogen sulfide Chemical compound S RWSOTUBLDIXVET-UHFFFAOYSA-N 0.000 description 1
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 230000000711 cancerogenic effect Effects 0.000 description 1
- 231100000315 carcinogenic Toxicity 0.000 description 1
- 238000004939 coking Methods 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 229910000037 hydrogen sulfide Inorganic materials 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005272 metallurgy Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 231100000572 poisoning Toxicity 0.000 description 1
- 230000000607 poisoning effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Examining Or Testing Airtightness (AREA)
Abstract
The invention relates to a device for eliminating leakage risk of a gas gate valve online. A nitrogen pipeline is connected on a pressure test port of the gas gate valve, and a three-valve group and a pressure gage are arranged on the nitrogen pipeline. The three-valve group consists of three valves, wherein the first valve is connected with the third valve in series; the second valve is connected between the first valve and the third valve through a three-way pipe; an inlet of the first valve is connected with the nitrogen pipeline; an outlet of the first valve is connected with the inlets of the second valve and the third valve; the outlet of the second valve is connected with the outside; the outlet of the third valve is connected with the pressure test port of the gas gate valve; and the pressure gage is connected between the first valve and the third valve through the three-way pipe. The invention has the beneficial effects that the device has simple structure, is convenient to use and is safe and reliable and as the pressure of the nitrogen is 0.2 Mpa, the device is 8000pa to 12000pa higher than gas pressure and is higher than the atmospheric pressure. If nitrogen is leaked to the direction of an opened device by a city gas fast opening-closing gate valve, employees cannot be harmed, and if the nitrogen is leaked to the direction where the gas comes by the city gas fast opening-closing gate valve, the gas cannot be damaged too much.
Description
Technical field
The invention belongs to the chemical industry equipment field, relate to a kind of device of online elimination leakage risk of gas gate valve.
Background technique
The MZ series " town gas fast opening and closing gate valve " that Yangquan Valves Co., Ltd. produces is the town gas special valve that develops with the unit consolidation such as Shanghai Gas Company, to fill up the blank new product of country, be the scientific and technological achievement that State Scientific and Technological Commission and former national Machinery Ministry are promoted to the whole nation, its technical performance is on the leading domestic level.
This series of valves is applicable to: the various dirty coal gas such as blast furnace gas, coke-stove gas, producer gas, water gas, oil gas reach the clean gas such as liquid gas, rock gas, mine gas.Be mainly used on the gas processed and City Gas Distribution pipe network of the industries such as coal gas, metallurgy, coking.The national market occupancy is more than 80%.
What but this product was carried out is the GB13027-92 standard, and gas allows leakage rate 30 * Dn mm3/s, and leakage rate is very important concerning the Large Diameter Pipeline valve, can be carcinogenic or poisoning because containing benzene, benzene DDGS, BaP and hydrogen sulfide etc. in coal gas.When the equipment on-line that is connected with this valve is uncapped oil removing or maintenance, can cause personal injury to the worker.
Summary of the invention
The present invention is in order to make up the deficiencies in the prior art, and a kind of device of online elimination leakage risk of gas gate valve simple in structure, esy to use, safe and reliable is provided.
The present invention is achieved through the following technical solutions:
The device of online elimination leakage risk of gas gate valve of the present invention, its special way is: the pressure testing mouth at gas gate valve connects nitrogen pipeline, three valve group and pressure gauges are installed on nitrogen pipeline, the valve group that three valve groups are comprised of three valves, wherein a valve is connected with three valves, two valves are connected between a valve and three valves by three-way pipe, one valve inlet connects nitrogen pipeline, one valve outlet port connects the entrance of two valves and three valves, two valve outlet ports connect extraneous, three valve outlet ports connect gas gate valve pressure testing mouth, and pressure gauge is connected between a valve and three valves by three-way pipe.
The invention has the beneficial effects as follows, simple in structure, esy to use, safe and reliable, because of nitrogen pressure 0.2 Mpa, higher than gas pressure 8000pa-12000pa and barometric pressure, if the town gas fast opening and closing gate valve leaks nitrogen to the device orientation of uncapping and can not damage the worker, if town gas fast opening and closing gate valve always coal gas direction leaks nitrogen and also can not cause much harm to coal gas, because of short leakage rate of time limited.
Description of drawings
Fig. 1 is structural representation of the present invention.
In figure, 1 one valves, 2 two valves, 3 three valves, 4 pressure gauges, 5 pressure testing mouths, 6 gas gate valves, 7 coke-stove gas imports, 8 coke-stove gas outlets, 9 double-flashboards, 10 nitrogen pipelines.
Embodiment
Accompanying drawing is a kind of specific embodiment of the present invention.
The device of online elimination leakage risk of gas gate valve of the present invention, pressure testing mouth 5 at gas gate valve 6 connects nitrogen pipeline 10, three valve groups and pressure gauge 4 are installed on nitrogen pipeline, the valve group that three valve groups are comprised of three valves, wherein a valve 1 is connected with three valves 3, two valves 2 are connected between a valve and three valves by three-way pipe, one valve 1 entrance connects nitrogen pipeline 10, one valve outlet port connects the entrance of two valves 2 and three valves 3, two valve 2 outlets connect extraneous, three valve 3 outlets connect the pressure testing mouth 5 of gas gate valve 6, and pressure gauge 4 is connected between a valve and three valves by three-way pipe.
Generally gas pressure is 8000pa-12000pa; Factory's nitrogen pressure is generally 0.7Mpa; The flashboard of MZ series town gas fast opening and closing gate valve and the sealing between valve body are that (one of them flashboard is controlled coke-stove gas import 7 in double-flashboard 9 sealings, another flashboard is controlled coke-stove gas outlet 8), during the valve leak test, gas is inputted from the pressure testing mouth 5 between two flashboards, detected both sides sealing place and whether leak gas.
Pressure testing mouth at gate valve connects three valve group and pressure gauges, and three valve groups connect factory's nitrogen pipeline again, see accompanying drawing.
In three valve groups, valve 1 and valve 3 are normally closed, and valve 2 is often opened.
Operation is used: when the equipment that is connected when this gate valve will be taken off online lid and overhauls in short-term
A. this gas gate valve is closed;
B. slowly open a valve 1, allow nitrogen through a valve 1 and two valves 2 with pipeline in foreign material blow out, close two valves 2 after clean;
C. transfer a valve 1, make pressure gauge indication 0.2Mpa;
D. slowly open three valves 3;
If pressure drop E., then transfer a valve 1, make pressure gauge indication 0.2Mpa.
If the repair time is very long first by aforesaid operations (filling nitrogen between double-flashboard with), then town gas fast opening and closing gate valve and the 8 word blind plates of uncapping between Awaiting Overhaul equipment are extracted out, touched the pillow and insert and hold flange again.Finally nitrogen is shut.Awaiting Overhaul is over and will resumes production, and at first must extract 8 word blind plates out the insertion of touching the pillow again, for preventing gas leakage harm worker, and also by after aforesaid operations (filling nitrogen between double-flashboard with), the active 8 word blind plates of.
Claims (1)
1. the device of an online elimination leakage risk of gas gate valve, it is characterized in that: the pressure testing mouth at gas gate valve connects nitrogen pipeline, three valve group and pressure gauges are installed on nitrogen pipeline, the valve group that three valve groups are comprised of three valves, wherein a valve is connected with three valves, two valves are connected between a valve and three valves by three-way pipe, one valve inlet connects nitrogen pipeline, one valve outlet port connects the entrance of two valves and three valves, two valve outlet ports connect extraneous, three valve outlet ports connect gas gate valve pressure testing mouth, and pressure gauge is connected between a valve and three valves by three-way pipe;
The flashboard of gas gate valve and the sealing between valve body are the double-flashboard sealings, and one of them flashboard is controlled the coke-stove gas import, and another flashboard is controlled the coke-stove gas outlet;
In three valve groups, a valve and three valves are normally closed, and two valves are often opened;
Be exactly that nitrogen is inputted from the pressure testing mouth between two flashboards during leak test, detect both sides sealing place and whether leak gas;
When the equipment that is connected when this gas gate valve will be taken off online lid and overhauls in short-term, concrete steps were as follows:
A. this gas gate valve is closed;
B. slowly open a valve, allow nitrogen through a valve and two valves with pipeline in foreign material blow out, close two valves after clean;
C. transfer a valve, make pressure gauge indication 0.2MPa;
D. slowly open three valves;
If pressure drop E., then transfer a valve, make pressure gauge indication 0.2MPa.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100334126A CN102563201B (en) | 2012-02-15 | 2012-02-15 | Device for eliminating leakage risk of gas gate valve online |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100334126A CN102563201B (en) | 2012-02-15 | 2012-02-15 | Device for eliminating leakage risk of gas gate valve online |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102563201A CN102563201A (en) | 2012-07-11 |
CN102563201B true CN102563201B (en) | 2013-11-13 |
Family
ID=46409412
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100334126A Active CN102563201B (en) | 2012-02-15 | 2012-02-15 | Device for eliminating leakage risk of gas gate valve online |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102563201B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105674055A (en) * | 2016-01-19 | 2016-06-15 | 康乃尔化学工业股份有限公司 | Nitrogen valve group used for safety protection |
CN107687535A (en) * | 2016-11-10 | 2018-02-13 | 林之铠 | A kind of gate valve for having hydraulic pressure indicator function |
CN112578084B (en) * | 2020-12-09 | 2022-07-26 | 贵州盘江煤电集团技术研究院有限公司 | Detection device is administered to colliery gas in pit |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2727508Y (en) * | 2004-08-30 | 2005-09-21 | 邢台钢铁有限责任公司 | Gas fan sealing device |
CN2844888Y (en) * | 2005-11-04 | 2006-12-06 | 攀枝花新钢钒股份有限公司 | A kind of blast furnace gas dust sampling device |
CN2844860Y (en) * | 2005-10-11 | 2006-12-06 | 济南钢铁股份有限公司 | Online sweeping flowmeter pressure sampling tube device |
CN101550359A (en) * | 2008-12-30 | 2009-10-07 | 湖北宜化化工股份有限公司 | On-line valve pressurization method by steam |
CN202469209U (en) * | 2012-02-15 | 2012-10-03 | 山东洪达化工有限公司 | Device for eliminating harm of leakage of gas gate valve on line |
-
2012
- 2012-02-15 CN CN2012100334126A patent/CN102563201B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2727508Y (en) * | 2004-08-30 | 2005-09-21 | 邢台钢铁有限责任公司 | Gas fan sealing device |
CN2844860Y (en) * | 2005-10-11 | 2006-12-06 | 济南钢铁股份有限公司 | Online sweeping flowmeter pressure sampling tube device |
CN2844888Y (en) * | 2005-11-04 | 2006-12-06 | 攀枝花新钢钒股份有限公司 | A kind of blast furnace gas dust sampling device |
CN101550359A (en) * | 2008-12-30 | 2009-10-07 | 湖北宜化化工股份有限公司 | On-line valve pressurization method by steam |
CN202469209U (en) * | 2012-02-15 | 2012-10-03 | 山东洪达化工有限公司 | Device for eliminating harm of leakage of gas gate valve on line |
Also Published As
Publication number | Publication date |
---|---|
CN102563201A (en) | 2012-07-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102506302B (en) | Device for processing residual gas of pressure container | |
CN206676862U (en) | A kind of portable receiving ball tube device for clearing up pipeline | |
CN103994863A (en) | Air-tight sealing detection method of threaded connection of oil casing tubes | |
CN206019960U (en) | Lift non-return valve work seal detection means | |
CN102563201B (en) | Device for eliminating leakage risk of gas gate valve online | |
CN204085824U (en) | Big-flow high-pressure air supply system | |
CN103867885A (en) | Liquid methane filling-up system | |
CN102735409B (en) | Automatic detecting device for air tightness of liquefied petroleum gas cylinder | |
CN104266807A (en) | Method for detecting valve air tightness through high-flow high-voltage gas source | |
CN104165739A (en) | Method for testing pressure by adoption of vertical and automatic heat collector flow channel pressure test machine | |
CN103994865A (en) | Air-tight sealing detection apparatus of threaded connection of oil casing tubes | |
CN202469209U (en) | Device for eliminating harm of leakage of gas gate valve on line | |
CN104088800A (en) | Sealing leakage detection system | |
CN204459571U (en) | Safety by-pass line structure | |
CN203284418U (en) | Movable leakage detection device for blast furnace cooling stave | |
CN210603769U (en) | Ammonia leakage test device | |
CN202661239U (en) | Automatic detection device for air tightness of liquefied petroleum gas steel bottle | |
CN201892031U (en) | Gas pipeline drainer | |
CN204188501U (en) | Hydrogen induced cracking test unit | |
CN202442924U (en) | Highly-reliable intelligent hydraulic detection system | |
CN203981343U (en) | A kind of for the online combination valve detecting of tensimeter | |
CN109856187B (en) | Online real-time detection method for hydrocarbon dew point of gas pipeline | |
CN206396267U (en) | A kind of blast furnace gas pipeline leakage repairing device | |
CN205424072U (en) | Monitoring system of ball valve with soft or hard is sealed | |
CN206223374U (en) | A kind of pressure-resistant rapid test device of product |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240506 Address after: 274700 Yuncheng Chemical Industry Park, Yuncheng County, Heze City, Shandong Province Patentee after: Yuncheng Xuyang Energy Co.,Ltd. Country or region after: China Address before: 274700 Within the Coal Chemical Industrial Park in Yuncheng County, Heze City, Shandong Province Patentee before: SHANDONG HONGDA CHEMICAL Co.,Ltd. Country or region before: China |
|
TR01 | Transfer of patent right |