CN102434098B - Hydraulic five-arm anchor drill for coal mine - Google Patents
Hydraulic five-arm anchor drill for coal mine Download PDFInfo
- Publication number
- CN102434098B CN102434098B CN201110423973.2A CN201110423973A CN102434098B CN 102434098 B CN102434098 B CN 102434098B CN 201110423973 A CN201110423973 A CN 201110423973A CN 102434098 B CN102434098 B CN 102434098B
- Authority
- CN
- China
- Prior art keywords
- dust
- anchor
- hydraulic
- drill
- cleaning case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Earth Drilling (AREA)
- Percussive Tools And Related Accessories (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The invention belongs to the technical field of anchor drills for underground excavation roadway support in coal mines, in particular relating to a hydraulic five-arm anchor drill for the coal mine. With the adoption of the hydraulic five-arm anchor drill provided by the invention, the problem of low supporting efficiency caused by that the traditional four-arm anchor drill for the coal mine cannot be applicable to roadway support in the need of five-anchor-rod support can be solved. The hydraulic five-arm anchor drill comprises an anchor drilling system, wherein the anchor drilling system comprises five drilling arms; three drilling arms are mounted on a fixed sliding rail; and two drilling arms are respectively mounted on a left-sliding sliding rail and a right-sliding sliding rail. The hydraulic five-arm anchor drill provided by the invention has the advantages of being more suitable for the roadway supported by using the five anchor rods, being more common in application, and better meeting requirements for efficiently and rapidly tunneling mine coal faces with high yield. The hydraulic five-arm anchor drill provided by the invention can be used with a continuous miner so that the driving speed can be increased to 1.7 times that of the four-arm anchor drill used with the continuous miner. Therefore, the contradiction between excavating and supporting can be solved and the hydraulic five-arm anchor drill provided by the invention has a wide market prospect.
Description
Technical field
The invention belongs to the technical field of colliery down-hole mining tunnel supporting anchor rod drill carriage, be specifically related to a kind of coal mining hydraulic five arm roofboltiers.
Background technology
Existing roofboltier, the Chinese patent 200410012344.0 that for example applicant has applied for and obtained the authorization, it discloses a kind of crawler-type traveling roofboltier, this drill carriage adopts Explosion-proof Design, rational in infrastructure, bearing capacity large, walking is mobile freely reliably, anchor drilling speed degree is fast, efficiency is high, quality good, safety factor is high, can adapt to work under adverse circumstances, very good down-hole mining safety support equipment, make roofboltier have home-made model, the exploitation supporting anchor that this drill carriage also can be used for other mineral bores operation.
Along with the degree of depth increase of digging laneway and the deterioration of back condition, need to adopt at present the tunnel of five bolt supports more and more, the contradiction of support speed and driving speed highlights day by day.But four arm roofboltiers single need more than 5 meters wide are made a call in the tunnel of 5 anchor poles and needed secondary supporting, supporting efficiency is low.The most effective way of supporting problem that solves such tunnel is exactly a kind of disposable roofboltier of making a call to 5 anchor poles of exploitation.
If directly increase by one group of drill boom on four arm roofboltiers, must cause complete machine width to increase, affect the compliance of complete machine, how 5 drill booms are reasonably arranged side by side in to complete machine front constant in the situation that maintaining complete machine width, and Rational Matching dust pelletizing system etc., be all the difficult point of complete machine structure design.
Summary of the invention
The present invention can not meet the needs of the supporting in the tunnel of five anchor poles of supporting in order to solve existing colliery four arm roofboltiers, cause the inefficient problem of supporting, and a kind of coal mining hydraulic five arm roofboltiers are provided.
The present invention adopts following technical scheme to realize:
Coal mining hydraulic five arm roofboltiers, comprise workbench, anchor drill system, dust pelletizing system, slide track component, the anterior connecting sliding rail assembly of workbench, mooring anchor drill system on slide track component, described slide track component comprises the fixed rack being connected with workbench by tie-beam, one side on fixed rack top is provided with the left slip slide rail of its slip relatively, the opposite side of fixed rack bottom is provided with the right slip slide rail of its slip relatively, described anchor drill system comprises five drill booms, three drill booms are installed on fixed rack, on left slip slide rail and right slip slide rail, be separately installed with a drill boom.
Another preferred version of the present invention: the corresponding five groups of drill booms of described dust pelletizing system arrange five groups, be installed on fixed rack, one group of dust pelletizing system comprises dust cleaning case, power set, cyclone, filter core, cyclone is installed on a side at dust cleaning case top, the opposite side at dust cleaning case top is established depression, recess is installed power set, the blower fan that power set comprise hydraulic motor and are connected by belt gear with hydraulic motor, the suction opeing of blower fan and dust cleaning case internal communication; Dust cleaning case inside is divided into three dedusting area by kicker baffle, comprise rotational flow dust-removing district, gravitational dust collection district, filter core dedusting area, rotational flow dust-removing district and other mutual seal isolation in twoth districts, the top in gravitational dust collection district arranges air intake and is connected with the air outlet of cyclone, filter core dedusting area is arranged at the middle and lower part in gravitational dust collection district, on the kicker baffle between filter core dedusting area and gravitational dust collection district, has some through holes; The inner gray area that falls that also has exhaust zone and bottom of dust cleaning case; Exhaust zone is hermetically-sealed construction, is provided with fresh air inlet and exhaust vent, and fresh air inlet is connected with the centre bore portion of filter core, and exhaust vent is connected with the suction opeing of blower fan; The bottom of rotational flow dust-removing district, gravitational dust collection district, filter core dedusting area is all communicated with the gray area that falls, the fall bottom of gray area is bottom, one end and the dust cleaning case of bottom are hinged, the tailpiece of the piston rod of the other end connecting fluid compressing cylinder of bottom, the cylinder barrel end of hydraulic jack is articulated with dust cleaning case, and the air intake of cyclone connects the air outlet of the anchor case of anchor drill system.
The present invention has following beneficial effect: to adopting the tunnel of five bolt supports to have stronger compliance, apply more generally, more can adapt to the requirement of highly efficient and productive speedy drivage mine working face.The present invention and continuous miner support the use, and Ke Jiangcheng lane speed is increased to matching used 1.7 times of four arm roofboltiers and continuous miner, solve digging and supporting contradiction, have wide market prospects.Specifically:
1, five independent drill boom parallel operations, supporting efficiency is high.
2, adopt highly integrated dust pelletizing system, reduce windage, improved efficiency of dust collection, effectively reduce noise, dedust power device changes belt transmission into by shaft coupling, and assembly process process is good.
3, the weight of complete machine increases (being about 43 tons) to some extent, little but the walking parameter of complete machine changes compared with four arm roofboltiers.
4, complete machine width is the same with wall roofboltier, strong adaptability.
Accompanying drawing explanation
Fig. 1 is main TV structure schematic diagram of the present invention,
Fig. 2 is the top view of Fig. 1,
Fig. 3 is that the master of dust pelletizing system looks schematic diagram,
Fig. 4 is that the back of the body of dust pelletizing system is looked schematic diagram,
Fig. 5 is the schematic internal view of dust pelletizing system,
In figure: 1-chassis, 2-temporary lining assembly, 3-tie-beam, 4-drill boom, 5-workbench, 6-ceiling, 7-fixed rack, the left slip slide rail of 8-, the right slip slide rail of 9-, 10-dust pelletizing system, 11-front rod, 12-back link, 13-electrical system, 14-hopper component, 15-nearside tank, 16-offside tank, 17-worktable lifting oil cylinder, 18-hydraulic system, 19-label assembly, 20-cover plate assembly;
21-hydraulic motor, 22-blower fan, 23-hydraulic jack, 24-bottom, 25-cyclone, 26-dust cleaning case, 27-Qianmen, 28-belt wheel, 29-belt, 30-power set, 31-kicker baffle I, 32-filter core, 33-rotational flow dust-removing district, 34-gravitational dust collection district, 35-filter core dedusting area, 36-exhaust zone, the 37-gray area that falls, 38-kicker baffle II.
The specific embodiment
By reference to the accompanying drawings the specific embodiment of the present invention is described further.
Colliery is mainly made up of frame, workbench, temporary lining, ceiling, linkage, slide rail, volume cable, hydraulic system, electrical system, anchor drill system, dust pelletizing system etc. with hydraulic anchor rod drill carriage.Its important technological parameters is as follows:
Adapt to head-room (mm): 3200~5100;
Adapt to span length (mm): 5000~5500;
Maximum transfer speed (m/min): 25;
Formation hardness: comprehensive rock stratum, f≤7;
Adapt to tunnel inclination angle (°) :≤16 °;
Minimum ground clearance (mm): 300mm;
Installed power (kW): 2 × 55;
Drill boom quantity: 5;
Maximum drilling depth (mm): 2600;
Line voltage grade (V): 1140/660.
1, the layout of five drill booms.
Five drill booms are arranged side by side in body front, drill boom spacing is 555mm, 950mm, 950mm and 555mm, middle three drill booms are fixed on fixed rack, can swing 5 ° all around, outside two drill booms are fixed on movable slide rail, can be with movable slide rail mobile 545mm laterally, maximum spacing reaches 1100mm, swing angle is 5 °, inwardly puts 5 °, outwards puts 95 °.
Five drill booms one are arranged and are put, and can disposablely make a call to 5 anchor poles, and the secondary supporting time of saving four arm roofboltiers and making a call to 5 anchor poles, in the time that 5 meters to the 6 meters single need in wide tunnel are made a call to 5 anchor poles, support speed is 1.7 times of four arm roofboltiers, has improved operating efficiency.
The present invention guarantees that the 3400mm of complete machine width and four arm roofboltiers is constant, the operating valve group of outside two drill booms is arranged on workbench, the permanent position of valve group on workbench is optimized, and simulate at four arm roofboltiers, guarantee operating space and the comfortableness of personnel in the time beating anchor pole.When work, two outside drill booms move outward, disposablely make a call to 5 anchor poles, and when equipment is transferred, two outside drill booms are regained, and guarantee that walking width is 3400mm.
2, dust pelletizing system.
The corresponding five groups of drill booms of dust pelletizing system arrange five groups, be installed on fixed rack? on, one group of dust pelletizing system comprises dust cleaning case, power set, cyclone, filter core, cyclone is installed on a side at dust cleaning case top, the opposite side at dust cleaning case top is established depression, recess is installed power set, the blower fan that power set comprise hydraulic motor and are connected by belt gear with hydraulic motor, the suction opeing of blower fan and dust cleaning case internal communication; Dust cleaning case inside is divided into three dedusting area by kicker baffle, comprise rotational flow dust-removing district, gravitational dust collection district, filter core dedusting area, rotational flow dust-removing district and other mutual seal isolation in twoth districts, the top in gravitational dust collection district arranges air intake and is connected with the air outlet of cyclone, filter core dedusting area is arranged at the middle and lower part in gravitational dust collection district, on the kicker baffle between filter core dedusting area and gravitational dust collection district, has some through holes; The inner gray area that falls that also has exhaust zone and bottom of dust cleaning case; Exhaust zone is hermetically-sealed construction, is provided with fresh air inlet and exhaust vent, and fresh air inlet is connected with the centre bore portion of filter core, and exhaust vent is connected with the suction opeing of blower fan; The bottom of rotational flow dust-removing district, gravitational dust collection district, filter core dedusting area is all communicated with the gray area that falls, the fall bottom of gray area is bottom, one end and the dust cleaning case of bottom are hinged, the tailpiece of the piston rod of the other end connecting fluid compressing cylinder of bottom, the cylinder barrel end of hydraulic jack is articulated with dust cleaning case, and the air intake of cyclone connects the air outlet of the anchor case of anchor drill system.
The present invention becomes one dust cleaning case and cyclone, is arranged on car load foremost.Dust pelletizing system height is integrated, has reduced length of pipe, reduces negative pressure and damages formula, improves efficiency of dust collection; When opening at every turn, cyclone the dust of dust-removing box can be discharged outside machine together; Dust cleaning case bottom initial position and horizontal sextant angle are greater than the angle of repose of coal, and at the bottom of dust cleaning case, this unlatching is manually to control, and bottom is difficult for dust stratification, has improved dust pelletizing system functional reliability; Dust pelletizing system is improved noise-reducing structure first, reducing noise 10dB(A) left and right.Both guarantee dust removing effects, improved again the safety of operating personnel in the time of work.Relatively the situation of labor cleaning's dust of Chinese patent 200410012344.0 crawler-type traveling roofboltiers, has also improved production efficiency when having reduced maintenance rate.
Claims (1)
1. coal mining hydraulic five arm roofboltiers, comprise workbench (5), anchor drill system, dust pelletizing system (10), slide track component, the anterior connecting sliding rail assembly of workbench (5), mooring anchor drill system on slide track component, described slide track component comprises the fixed rack (7) being connected with workbench (5) by tie-beam (3), one side on fixed rack (7) top is provided with the left slip slide rail (8) of its slip relatively, the opposite side of fixed rack (7) bottom is provided with the right slip slide rail (9) of its slip relatively, it is characterized in that described anchor drill system comprises five drill booms (4), three drill booms of the upper installation of fixed rack (7), on left slip slide rail (8) and right slip slide rail (9), be separately installed with a drill boom, the corresponding five groups of drill booms of described dust pelletizing system arrange five groups, be installed on fixed rack, one group of dust pelletizing system comprises dust cleaning case (26), power set (30), cyclone (25), filter core (32), cyclone (25) is installed on a side at dust cleaning case (26) top, the opposite side at dust cleaning case (26) top is established depression, recess is installed power set (30), the blower fan (22) that power set comprise hydraulic motor (21) and are connected by belt gear with hydraulic motor (21), the suction opeing of blower fan (22) and dust cleaning case (26) internal communication, dust cleaning case (26) is inner is divided into three dedusting area by kicker baffle, comprise rotational flow dust-removing district (33), gravitational dust collection district (34), filter core dedusting area (35), rotational flow dust-removing district (33) and other mutual seal isolation in twoth districts, the top in gravitational dust collection district (34) arranges air intake and is connected with the air outlet of cyclone (25), filter core dedusting area (35) is arranged at the middle and lower part of gravitational dust collection district (34), on the kicker baffle between filter core dedusting area (35) and gravitational dust collection district (34), has some through holes, the inner gray area that falls (37) that also has exhaust zone (36) and bottom of dust cleaning case (26), exhaust zone (36) is hermetically-sealed construction, is provided with fresh air inlet and exhaust vent, and fresh air inlet is connected with the centre bore portion of filter core, and exhaust vent is connected with the suction opeing of blower fan, the bottom of rotational flow dust-removing district (33), gravitational dust collection district (34), filter core dedusting area (35) is all communicated with the gray area that falls (37), the fall bottom of gray area (37) is bottom (24), one end of bottom (24) and dust cleaning case (26) are hinged, the tailpiece of the piston rod of the other end connecting fluid compressing cylinder (23) of bottom (24), the cylinder barrel end of hydraulic jack (23) is articulated with dust cleaning case (26), and the air intake of cyclone (25) connects the air outlet of the anchor case of anchor drill system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110423973.2A CN102434098B (en) | 2011-12-01 | 2011-12-17 | Hydraulic five-arm anchor drill for coal mine |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110397502.9 | 2011-12-01 | ||
CN201110397502 | 2011-12-01 | ||
CN201110423973.2A CN102434098B (en) | 2011-12-01 | 2011-12-17 | Hydraulic five-arm anchor drill for coal mine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102434098A CN102434098A (en) | 2012-05-02 |
CN102434098B true CN102434098B (en) | 2014-05-28 |
Family
ID=45982423
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110423973.2A Active CN102434098B (en) | 2011-12-01 | 2011-12-17 | Hydraulic five-arm anchor drill for coal mine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102434098B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104196446A (en) * | 2014-08-29 | 2014-12-10 | 廊坊景隆重工机械有限公司 | Six-arm full hydraulic anchor rod and anchor cable drill carriage used in cooperation with continuous miner |
CN104265166A (en) * | 2014-09-17 | 2015-01-07 | 北京景隆重工机械有限公司 | Eight-arm fully-hydraulic anchor rod-anchor cable drill carriage used with continuous miner |
CN107939284A (en) * | 2017-12-08 | 2018-04-20 | 中国铁建重工集团有限公司 | A kind of open air drill rig |
CN113565500A (en) * | 2021-07-01 | 2021-10-29 | 中国煤炭科工集团太原研究院有限公司 | Intelligent control dust removal system for coal mine and control method thereof |
CN114033298A (en) * | 2021-10-14 | 2022-02-11 | 中国煤炭科工集团太原研究院有限公司 | Anchor rod drill carriage robot |
CN115788532B (en) * | 2023-02-02 | 2023-04-14 | 江苏中贵重工有限公司 | Fully mechanized coal mining face anchor rod supporting system and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4216998A (en) * | 1979-05-31 | 1980-08-12 | Bowen Ray J | Method of underground mining by pillar extraction |
US5531507A (en) * | 1995-05-09 | 1996-07-02 | Jackson; Daryl L. | Method of removing a minable product from an underground seam and bottom hole tool |
CN1144848A (en) * | 1996-09-13 | 1997-03-12 | 冶金工业部钢铁研究总院 | Whole-dry type dust removing device and method for blast furnace gas |
CN1584292A (en) * | 2004-06-10 | 2005-02-23 | 煤炭科学研究总院太原分院 | Crawler-type walking rockbolt drilling carriages |
CN201614887U (en) * | 2010-02-09 | 2010-10-27 | 煤炭科学研究总院西安研究院 | Crawler-type jumbolter |
-
2011
- 2011-12-17 CN CN201110423973.2A patent/CN102434098B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4216998A (en) * | 1979-05-31 | 1980-08-12 | Bowen Ray J | Method of underground mining by pillar extraction |
US5531507A (en) * | 1995-05-09 | 1996-07-02 | Jackson; Daryl L. | Method of removing a minable product from an underground seam and bottom hole tool |
CN1144848A (en) * | 1996-09-13 | 1997-03-12 | 冶金工业部钢铁研究总院 | Whole-dry type dust removing device and method for blast furnace gas |
CN1584292A (en) * | 2004-06-10 | 2005-02-23 | 煤炭科学研究总院太原分院 | Crawler-type walking rockbolt drilling carriages |
CN201614887U (en) * | 2010-02-09 | 2010-10-27 | 煤炭科学研究总院西安研究院 | Crawler-type jumbolter |
Also Published As
Publication number | Publication date |
---|---|
CN102434098A (en) | 2012-05-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102418540B (en) | Hydraulic eight-arm anchor rod drill carriage for coal mine | |
CN102434098B (en) | Hydraulic five-arm anchor drill for coal mine | |
CN211549680U (en) | High-adaptability tunneling and anchoring all-in-one machine with dual-mode anchor drilling system | |
CN101832102B (en) | Movable two-platform partitioned four-arm hanging wall anchor rod and anchor cable construction drill carriage | |
CN100396882C (en) | Crawler-type walking rockbolt drilling carriages | |
CN111075444A (en) | High-adaptability tunneling and anchoring all-in-one machine with dual-mode anchor drilling system | |
CN101832103B (en) | Movable two-arm hanging wall anchor rod and anchor cable construction drill carriage | |
CN101858213B (en) | Drilling, loading, transporting and anchoring integrated machine with dual platforms and four arms for coal roadway | |
CN102704839B (en) | Hanging carrying type integral hydraulic rock drilling machine | |
CN107130656B (en) | Integrated mining loader with functions of underground drilling, anchoring and rock breaking | |
CN102587959B (en) | Method for draining coal seam gas | |
CN110608060A (en) | Straddle type five-arm drill carriage suitable for large section | |
CN103422862B (en) | Large aperture boring Drilling vertical shaft method | |
CN104564089A (en) | Rock roadway quick tunneling process of impact crushing rock roadway tunneling machine | |
CN110242294A (en) | Digging and anchoring integrated machine is stretched roller cutting mechanism with double drive | |
CN101403302A (en) | Pedrail type liftable anchor bar anchor cable construction drill rig and double-lane fast digging technique | |
CN104712333A (en) | Large-width one-step roadway formation roadway rapid excavation technology | |
CN109139033A (en) | A kind of impact grinding formula rock gangway anchor driving machine | |
CN109538224A (en) | A kind of novel coal lane high-speed driving machine | |
CN104533408A (en) | Large-width comprehensive coal road driving anchor machine with simultaneous drifting function | |
CN109915198A (en) | Coal working face advance borehole full blast presses drawing-off gas method | |
CN202866810U (en) | Multifunctional car for underground coal mine | |
CN204386597U (en) | The coal road comprehensive dig-anchor machine of large width simultaneous drifting | |
CN201696041U (en) | Double-platform four-arm drilling, loading, conveying and anchoring integrated machine for coal roadways | |
CN209494569U (en) | A kind of novel coal lane high-speed driving machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |