CN102352685A - Hydraulic lifting construction platform - Google Patents
Hydraulic lifting construction platform Download PDFInfo
- Publication number
- CN102352685A CN102352685A CN2011102158463A CN201110215846A CN102352685A CN 102352685 A CN102352685 A CN 102352685A CN 2011102158463 A CN2011102158463 A CN 2011102158463A CN 201110215846 A CN201110215846 A CN 201110215846A CN 102352685 A CN102352685 A CN 102352685A
- Authority
- CN
- China
- Prior art keywords
- operation platform
- hydraulic
- lifting
- hydraulic cylinder
- construction platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a hydraulic lifting construction platform. A plurality of vertical supports are arranged on a well wall; a plurality of pin roll holes are formed in the vertical supports; the construction platform is provided with a plurality of two-lug plates which are connected with the pin roll holes in corresponding vertical supports through pin rolls; lifting hydraulic cylinders are arranged below the two-lug plates; hydraulic cylinder supports of the lifting hydraulic cylinders are connected with the pin roll holes in the vertical supports through the pin rolls; and the lifting hydraulic cylinders are connected with a hydraulic station arranged on the construction platform. The hydraulic lifting construction platform continuously ascends along with the ascent of a surge shaft by adopting a hydraulic self-jacking mode so as to avoid a plurality of problems brought by erecting super high-rise steel pipe scaffolds, such as technical problems that the work amount of erecting and detaching framed bents is large, a line period of a project is prolonged, the construction progress of the project is seriously influenced, safety risks are high and the like.
Description
Technical field
The present invention relates to a kind of liftable operation platform, particularly a kind of hydraulic elevation type operation platform that is used for major diameter and big height steel pressure regulation vertical shaft.
Background technology
The diameter of power station ground type steel pressure regulation vertical shaft and highly all very big; After normally adopting and set up superelevation layer steel pipe scaffold along the medial and lateral of the borehole wall, working operating platform re-lays the method for platform; And constantly rising with the rising of surge shaft; The shortcoming of this way is: not only need use a large amount of scaffoldings; Construction cost is big, and framed bent to set up, remove engineering quantity big, taken the engineering straight line duration; Have a strong impact on the engineering construction progress, security risk is big simultaneously.
Summary of the invention
Technical problem to be solved by this invention provides a kind of hydraulic elevation type operation platform, can constantly rise with the rising of surge shaft, thereby avoid setting up the problems that superelevation layer steel pipe scaffold brings.
For solving the problems of the technologies described above; The technical scheme that the present invention adopted is: a kind of hydraulic elevation type operation platform, the borehole wall are provided with many perpendicular supports, and perpendicular support is provided with a plurality of pin shaft holes; Operation platform is provided with a plurality of ears plates, and the ears plate is through the pin shaft hole connection in bearing pin and the corresponding perpendicular support;
Below the ears plate, also be provided with lifting hydraulic cylinder, the hydraulic cylinder bearing of lifting hydraulic cylinder also is connected with the pin shaft hole that erects on supportting through bearing pin;
Each lifting hydraulic cylinder is connected with the Hydraulic Station of being located at operation platform.
Also be provided with guide rail between the described many perpendicular supports, opposite position is provided with roller on the operation platform, and roller rolls with guide rail and cooperates.
In the described operation platform, its bottom is made up of rack beams, and ears plate, lifting hydraulic cylinder and roller are connected with rack beams.
Described many perpendicular supports are evenly distributed on circumference, and described many guide rails are evenly distributed on circumference.
Described many guide rails are provided with groove, and roller is positioned at groove.
Described perpendicular support is three or four.
A kind of hydraulic elevation type operation platform provided by the invention through adopting the mode of hydraulic pressure from jacking, has been realized that working platform constantly rises with the rising of surge shaft, thereby has been avoided setting up the problems that superelevation layer steel pipe scaffold brings.For example framed bent to set up, remove engineering quantity big, taken the engineering straight line duration, have a strong impact on the engineering construction progress, technical problem such as security risk is big simultaneously.
The height of ground type steel pressure regulation vertical shaft reaches near 100 meters usually, and working platform sometimes also need carry engineering equipment, for example lifting appliance except needs carry construction material and workpiece.Therefore working platform is except easy of rise, and also requirement can load-carrying, requires load-carrying to surpass 30 tons usually.In addition, working platform also requires enough safety.
A kind of hydraulic elevation type operation platform provided by the invention has adopted the bearing pin location, and hydraulic pressure has been realized that working platform constantly rises with the rising of surge shaft, thereby avoided setting up the problems that superelevation layer steel pipe scaffold brings from the mode of jacking.For example framed bent to set up, remove engineering quantity big, taken the engineering straight line duration, have a strong impact on the engineering construction progress, technical problem such as security risk is big simultaneously.Adopt the mode of bearing pin location, simple to operate, and simplified the structure of single unit system, reduced and occurred the link of security incident easily, thereby improved safety.
The present invention has avoided taking repeatedly of operating platform to tear open, has guaranteed the smooth construction of surge shaft, has practiced thrift the engineering time, has saved construction cost, is fit to very much to take the surge shaft construction part of tearing operation platform open repeatedly.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the present invention is described further:
Fig. 1 is an overall structure vertical view of the present invention.
Fig. 2 is the A-A sectional view of Fig. 1.
Fig. 3 is the B-B sectional view of Fig. 2.
The specific embodiment
In Fig. 1-Fig. 3, a kind of hydraulic elevation type operation platform, the borehole wall 9 are provided with many perpendicular supports 4, and perpendicular support 4 is provided with a plurality of pin shaft holes 10, and operation platform 1 is provided with a plurality of ears plates 3, and ears plate 3 is through pin shaft hole 10 connections in bearing pin and the corresponding perpendicular support 4;
Below ears plate 3, also be provided with lifting hydraulic cylinder 5, the hydraulic cylinder bearing 6 of lifting hydraulic cylinder 5 also is connected with the perpendicular pin shaft hole 10 that supports on 4 through bearing pin;
Each lifting hydraulic cylinder 5 is connected with the Hydraulic Station 8 of being located at operation platform 1.
In the scheme of optimizing, also be provided with guide rail 11 between the described many perpendicular supports 4, opposite position is provided with roller 7 on the operation platform 1, and roller 7 rolls with guide rail 11 and cooperates.Described many guide rails 11 are provided with groove, and roller 7 is positioned at groove.Thereby guarantee the stability and safety when operation platform goes up and down.
In the described operation platform 1, its bottom is made up of rack beams 2, and ears plate 3, lifting hydraulic cylinder 5 and roller 7 are connected with rack beams 2.
Described many perpendicular supports 4 are evenly distributed on circumference, and described many guide rails 11 are evenly distributed on circumference.
Described perpendicular support 4 is three or four.
Embodiment:
In Fig. 1-3; Rack beams 2 adopts i iron welding processing in processing factory to form; Treat that the surge shaft fabrication and installation are after exceed the ground certain altitude; In the borehole wall of surge shaft, be symmetrical set four perpendicular supports 4; Integral hoisting rack beams then 2, the ears plate 3 on the rack beams 2 is connected fixing with perpendicular support 4 through pivot pin.After accomplishing the installation of rack beams 2, be laid to operation platform 1 with steel plate thereon.Stability and safety when going up and down for the assurance operation platform also is provided with four guide rails 11 between four perpendicular supports 4, on guide rail 11, be welded with the steel plate of band groove, and roller 7 is embedded in the groove.
With hydraulic cylinder bearing 6 through latch be fixed on the corresponding perpendicular support 4 in ears plate 3 bottoms on, lifting hydraulic cylinder 5 is installed then, in this example, the piston rod of lifting hydraulic cylinder 5 and rack beams 2 are hinged, and cylinder body is installed on the hydraulic cylinder bearing 6.Through Hydraulic Station 8 operation lifting hydraulic cylinders 5, accomplish the up-down of operation platform and in place.During the lifting hydraulic cylinder lifting; Each lifting 1~1.2m in this example; Ears plate 3 is removed with the pivot pin that is connected of perpendicular support 4, made platform and integrally upwards soaring, when lifting puts in place along perpendicular support; Inserting pivot pin again fuses platform and perpendicular support; Extract the bearing pin of hydraulic cylinder bearing 6, the piston rod of lifting hydraulic cylinder 5 is regained, and connects hydraulic cylinder bearing 6 and perpendicular support 4 again with bearing pin again; Circulation so repeatedly can jack-up construction platform 1.The operating procedure that operation platform 1 descends in contrast.
The present invention has avoided taking repeatedly of operating platform to tear open, has guaranteed the smooth construction of surge shaft, has practiced thrift the engineering time, has saved construction cost, is fit to very much to take the surge shaft construction part of tearing operation platform open repeatedly.
Claims (6)
1. hydraulic elevation type operation platform; It is characterized in that: the borehole wall (9) is provided with many perpendicular supports (4); Perpendicular support (4) is provided with a plurality of pin shaft holes (10); Operation platform (1) is provided with a plurality of ears plates (3), and ears plate (3) is through pin shaft hole (10) connection in bearing pin and the corresponding perpendicular support (4);
Also be provided with lifting hydraulic cylinder (5) in the below of ears plate (3), the hydraulic cylinder bearing (6) of lifting hydraulic cylinder (5) also is connected with the perpendicular pin shaft hole (10) that supports on (4) through bearing pin;
Each lifting hydraulic cylinder (5) is connected with the Hydraulic Station of being located at operation platform (1) (8).
2. a kind of hydraulic elevation type operation platform according to claim 1; It is characterized in that: also be provided with guide rail (11) between the described many perpendicular supports (4); Operation platform (1) is gone up opposite position and is provided with roller (7), and roller (7) rolls with guide rail (11) and cooperates.
3. a kind of hydraulic elevation type operation platform according to claim 2; It is characterized in that: in the described operation platform (1); Its bottom is made up of rack beams (2), and ears plate (3), lifting hydraulic cylinder (5) and roller (7) are connected with rack beams (2).
4. a kind of hydraulic elevation type operation platform according to claim 2 is characterized in that: described many perpendicular supports (4) are evenly distributed on circumference, and described many guide rails (11) are evenly distributed on circumference.
5. a kind of hydraulic elevation type operation platform according to claim 2 is characterized in that: described many guide rails (11) are provided with groove, and roller (7) is positioned at groove.
6. a kind of hydraulic elevation type operation platform according to claim 1 is characterized in that: described perpendicular support (4) is three or four.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102158463A CN102352685A (en) | 2011-07-29 | 2011-07-29 | Hydraulic lifting construction platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102158463A CN102352685A (en) | 2011-07-29 | 2011-07-29 | Hydraulic lifting construction platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102352685A true CN102352685A (en) | 2012-02-15 |
Family
ID=45576316
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102158463A Pending CN102352685A (en) | 2011-07-29 | 2011-07-29 | Hydraulic lifting construction platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102352685A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104564084A (en) * | 2015-01-16 | 2015-04-29 | 郑州煤炭工业(集团)工程有限公司 | Steel strand jack lifting construction device for vertical shaft sliding die and grouting platform |
CN113955638A (en) * | 2021-09-26 | 2022-01-21 | 中国华电科工集团有限公司 | Large-scale barrel steel construction hoisting platform device |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090146041A1 (en) * | 2005-06-29 | 2009-06-11 | Artur Schwoerer | Devisible Climbing Shoe of a Climbing Formwork |
CN201268569Y (en) * | 2008-07-08 | 2009-07-08 | 上海建工(集团)总公司 | Double-acting integral hydraulic automatic jacking platform system |
CN202164810U (en) * | 2011-07-29 | 2012-03-14 | 中国葛洲坝集团股份有限公司 | Hydraulic lifting type construction platform |
-
2011
- 2011-07-29 CN CN2011102158463A patent/CN102352685A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090146041A1 (en) * | 2005-06-29 | 2009-06-11 | Artur Schwoerer | Devisible Climbing Shoe of a Climbing Formwork |
CN201268569Y (en) * | 2008-07-08 | 2009-07-08 | 上海建工(集团)总公司 | Double-acting integral hydraulic automatic jacking platform system |
CN202164810U (en) * | 2011-07-29 | 2012-03-14 | 中国葛洲坝集团股份有限公司 | Hydraulic lifting type construction platform |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104564084A (en) * | 2015-01-16 | 2015-04-29 | 郑州煤炭工业(集团)工程有限公司 | Steel strand jack lifting construction device for vertical shaft sliding die and grouting platform |
CN104564084B (en) * | 2015-01-16 | 2016-05-18 | 河南锦源建设有限公司 | Vertical shaft sliding formwork and grouting platform steel strand wires jack lifting construction equipment |
CN113955638A (en) * | 2021-09-26 | 2022-01-21 | 中国华电科工集团有限公司 | Large-scale barrel steel construction hoisting platform device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102677889B (en) | System for alternatively supporting whole lifting steel platform formwork by steel column casing rack and construction method | |
CN204875552U (en) | Frame bridge crane vertical lift structure | |
CN102305076B (en) | Hydraulic step type vertical shaft template supporting device | |
CN104310165A (en) | Guide rail type adhesion construction lifter and construction method thereof | |
CN103967284B (en) | The steel column installation method of reserved stigma docking | |
CN102080357A (en) | Integrated beam-falling device and method for steel pipe pier bailey beam cast-in-place bracket | |
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN108411922A (en) | The method for dismounting of bracing members | |
CN202658590U (en) | Integral assembled drilling platform | |
CN202481956U (en) | Attached climbing type conventionalized dual-purpose platform | |
CN104989111B (en) | Steel construction high level construction method for hanging | |
CN107142954B (en) | Steel hanging box lifting system for integral lifting and lifting method thereof | |
CN202164810U (en) | Hydraulic lifting type construction platform | |
CN102352685A (en) | Hydraulic lifting construction platform | |
CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
CN103342321A (en) | Integral replacing and hoisting method of steam generator of in-service nuclear power plant | |
CN101580214A (en) | Hydraulic lifting method for large-scale equipment | |
CN203486787U (en) | Integral lifting device for cabinet top of Wiggins coal gas cabinet | |
CN104416352B (en) | Installed using radial type, remove the method that the constructing device of straddle truck is constructed | |
CN204524596U (en) | A kind of dismountable self-locking overhead welding operating platform | |
CN110697581B (en) | Bridge crane dismounting and mounting construction method in factory building bridge crane updating project | |
CN204225503U (en) | Large span steel truss high altitude bulk conversion beam moulding bed | |
CN203855324U (en) | Lifting device for installing and removing underground coal mine working face | |
CN113738156A (en) | Temporary support structure in limited space and dismantling method thereof | |
CN112320630A (en) | Supporting beam for hoisting heat absorber |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120215 |