CN102337912A - 煤矿巷道锚杆快速锚固方法 - Google Patents

煤矿巷道锚杆快速锚固方法 Download PDF

Info

Publication number
CN102337912A
CN102337912A CN2011103152040A CN201110315204A CN102337912A CN 102337912 A CN102337912 A CN 102337912A CN 2011103152040 A CN2011103152040 A CN 2011103152040A CN 201110315204 A CN201110315204 A CN 201110315204A CN 102337912 A CN102337912 A CN 102337912A
Authority
CN
China
Prior art keywords
resin
anchor rod
explosive roll
nut
anchor pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103152040A
Other languages
English (en)
Inventor
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAFENG COAL MINE XINWEN MINING INDUSTRY GROUP Co Ltd
Original Assignee
HUAFENG COAL MINE XINWEN MINING INDUSTRY GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAFENG COAL MINE XINWEN MINING INDUSTRY GROUP Co Ltd filed Critical HUAFENG COAL MINE XINWEN MINING INDUSTRY GROUP Co Ltd
Priority to CN2011103152040A priority Critical patent/CN102337912A/zh
Publication of CN102337912A publication Critical patent/CN102337912A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Road Signs Or Road Markings (AREA)

Abstract

本发明公开了一种煤矿巷道锚杆快速锚固方法,它主要是安装锚杆时依次填入两种不同凝固时间的树脂药卷,一种为凝固时间不大于10秒的速凝树脂药卷,另一种为普通树脂药卷;速凝树脂药卷填入眼底位置;用带有专用套筒的钻机卡住锚杆螺帽后,以150N.m的转矩连续不停的推进转动,将两种药卷一次搅拌到底,到底后仍不停转动,直至速凝树脂药卷10秒内凝固,凝固后锚杆虽不转动,而螺帽继续转动,直至打开螺母阻尼塞,撤除钻机;接着再用钻机加扭矩放大器以400N.m的扭矩上紧螺帽,安装完成。本发明将锚杆钻机的搅拌、安装一次完成,缩短安装时间,减小掘进工作面的空顶时间,提高锚杆的安装效率。

Description

煤矿巷道锚杆快速锚固方法
技术领域
本发明涉及煤矿巷道支护技术,尤其是涉及深部矿井高应力破碎软岩巷道支护。
背景技术
目前煤矿巷道支护普遍使用树脂锚固型金属锚杆,其安装工艺是:
1.在巷道围岩上按照设计打锚杆眼,打眼采用MQT-120型气动锚杆钻机或7665型风钻。
2.向锚杆眼中填入1-2普通卷树脂药卷,用锚杆推入眼底;
4.卷到达眼底后,用带有专用套筒的风煤钻卡住锚杆螺帽,开动钻机以120N.m的转矩搅拌药卷30-45秒钟,静待5-10秒后撤除;
5、待树脂药卷凝固10几分钟后,再用风煤钻加扭矩放大器以400N.m的转矩旋紧螺帽,直至打开螺母阻尼塞,此时使锚杆施加上预紧力。
上述安装工艺的不足是,巷道开挖后在围岩变形很小(约在破坏载荷的25%以下)时,脆性特征明显的岩体就出现开裂、离层、滑动、裂纹扩展和松动等现象,由于此时还未安装锚杆,围岩强度大大弱化;如果巷道开挖后立即安装锚杆,但树脂药卷凝固后才能施加预紧力,在这段时间内由于锚杆极限变形量大于围岩极限变形量,又由于各锚杆都有一定的初始滑移量,因而锚杆不能阻止围岩的开裂、滑动和弱化,只有当围岩的开裂位移达到相当的程度(在钢筋混凝土中达到极限载荷的60-75%)以后,锚杆才起到阻止裂纹扩展的作用。这时围岩已几乎丧失抗拉和抗剪的能力,加固体的抗拉和抗剪能力主要依赖于锚杆。这也就是说,这里围岩和锚杆不同步承载,先是围岩受力破坏,达到一定程度,锚材才开始承载。在开采深度不大和非强烈构造应力区,这种矛盾常常不突出,支护的成功掩盖了问题的实质,而开采深度大于800米和构造应力大时,矛盾就特别突出,所以目前的安装工艺不能解决上术矛盾。
发明内容
为了克服上述技术的不足,本发明提出一种煤矿巷道锚杆快速锚固方法。
技术方案是:它包括在煤矿巷道围岩上打锚杆眼和安装树脂锚固型金属锚杆工序,其特征在于:
1.安装锚杆时依次填入两种不同凝固时间的树脂药卷,第一种树脂药卷为凝固时间不大于10秒的速凝树脂药卷,第二种树脂药卷为普通树脂药卷;速凝树脂药卷填入眼底位置;
2.用带有专用套筒的钻机卡住锚杆螺帽后,以150N.m的转矩连续不停的推进转动,将普通树脂药卷和速凝树脂药卷一次搅拌到底,到底后仍不停转动,直至速凝树脂药卷10秒内凝固,凝固后锚杆虽不转动,而螺帽继续转动,直至打开螺母阻尼塞,撤除钻机;接着再用钻机加扭矩放大器以400N.m的扭矩上紧螺帽,安装完成。
本发明的积极效果是:一次性快速安装,将锚杆钻机的搅拌、安装一次完成,由原来安装一根锚杆10-15分钟,缩短到30-40秒,减小掘进工作面的空顶时间,提高锚杆的安装效率。减少了围岩自稳时间,降低围岩破坏程度,提高围岩承载体强度。使用锚杆快速安装工艺能够增加600mm左右的支护承载体厚度(按照锚杆间排距800mm计算,支护承载体厚度由普通安装工艺的50mm增加到679mm,增加量629mm),极大的的提高了围岩承载能力。在安装锚杆的同时施加足够的预拉力,消除锚杆支护系统的初始滑移量,给围岩一定的预压应力,改善围岩的应力环境。对于受拉截面,可以抵消一部分拉应力,从而大大提高抗拉能力;对于受剪截面,由压应力产生的摩擦力大大提高了加固体的抗剪能力。及时施加预拉力直接避免巷道围岩过早出现张开裂缝,可以大大减缓围岩的弱化过程,岩体利用自身强度及时参与承载过程,即形成整体承载结构,限制破碎区的发展,保证了巷道的长期稳定。
附图说明
图1是锚杆安装前的示意图;
图2是锚杆安装后的示意图。
图例说明,1-速凝树脂药卷,2-普通树脂药卷,3-锚杆眼,4-锚杆,5-螺母阻尼塞,6-螺帽。
具体实施方式
参照附图进一步说明技术方案。
1.在巷道围岩上按照设计打锚杆眼3,打眼采用MQT-120型气动锚杆钻机或7665型风钻。
2.向锚杆眼3中依次填入两种不同凝固时间的树脂药卷,第一种树脂药卷为凝固时间不大于10秒的速凝树脂药卷1,第二种树脂药卷为普通树脂药卷2;用锚杆4推入眼底;
3、用带有专用套筒的钻机卡住锚杆螺帽6后,以150N.m的转矩连续不停的推进转动,将普通树脂药卷1和速凝树脂药卷2一次搅拌到底,到底后仍不停转动,直至速凝树脂药卷1在10秒内凝固,凝固后锚杆4虽不转动,而螺帽6继续转动,直至打开螺母阻尼塞5,撤除钻机;接着再用钻机加扭矩放大器以400N.m的扭矩上紧螺帽6,安装完成。

Claims (1)

1.一种煤矿巷道锚杆快速锚固方法,它包括在煤矿巷道围岩上打锚杆眼和安装树脂锚固型金属锚杆工序,其特征在于:
安装锚杆时依次填入两种不同凝固时间的树脂药卷,第一种树脂药卷为凝固时间不大于10秒的速凝树脂药卷,第二种树脂药卷为普通树脂药卷;速凝树脂药卷填入眼底位置;
用带有专用套筒的钻机卡住锚杆螺帽后,以150N.m的转矩连续不停的推进转动,将普通树脂药卷和速凝树脂药卷一次搅拌到底,到底后仍不停转动,直至速凝树脂药卷10秒内凝固,凝固后锚杆虽不转动,而螺帽继续转动,直至打开螺母阻尼塞,撤除钻机;接着再用钻机加扭矩放大器以400N.m的扭矩上紧螺帽,安装完成。
CN2011103152040A 2011-10-17 2011-10-17 煤矿巷道锚杆快速锚固方法 Pending CN102337912A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103152040A CN102337912A (zh) 2011-10-17 2011-10-17 煤矿巷道锚杆快速锚固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103152040A CN102337912A (zh) 2011-10-17 2011-10-17 煤矿巷道锚杆快速锚固方法

Publications (1)

Publication Number Publication Date
CN102337912A true CN102337912A (zh) 2012-02-01

Family

ID=45513835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103152040A Pending CN102337912A (zh) 2011-10-17 2011-10-17 煤矿巷道锚杆快速锚固方法

Country Status (1)

Country Link
CN (1) CN102337912A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678145A (zh) * 2012-04-20 2012-09-19 中钢集团马鞍山矿山研究院有限公司 一种高效的树脂锚杆施工新方法
CN103032086A (zh) * 2012-12-07 2013-04-10 中国矿业大学 一种巷道顶板锚杆钻孔充填树脂药卷的方法
CN103613322A (zh) * 2013-11-22 2014-03-05 新汶矿业集团有限责任公司鄂庄煤矿 组合式树脂锚固剂及其锚固方法
CN104632259A (zh) * 2014-12-31 2015-05-20 中国矿业大学 软弱地层端头自膨胀扩大型锚固方法
WO2019119900A1 (zh) * 2017-12-18 2019-06-27 中国矿业大学 一种降低预应力损失的低张拉锚索施工方法
CN112282807A (zh) * 2020-11-20 2021-01-29 贵州盘江煤电集团技术研究院有限公司 一种用于煤矿锚杆安装的一体装置及其使用方法
CN116181384A (zh) * 2023-03-28 2023-05-30 成都理工大学 一种快速混合锚固预应力锚索及其施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2262599C2 (ru) * 2003-09-03 2005-10-20 ОАО "Севуралбокситруда" Способ установки сталеполимерных анкеров
CN101672191A (zh) * 2009-10-12 2010-03-17 北京科技大学 一种机械化安装树脂锚杆的方法
CN101949294A (zh) * 2010-08-13 2011-01-19 山西潞安环保能源开发股份有限公司常村煤矿 一种预应力全长锚固支护方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2262599C2 (ru) * 2003-09-03 2005-10-20 ОАО "Севуралбокситруда" Способ установки сталеполимерных анкеров
CN101672191A (zh) * 2009-10-12 2010-03-17 北京科技大学 一种机械化安装树脂锚杆的方法
CN101949294A (zh) * 2010-08-13 2011-01-19 山西潞安环保能源开发股份有限公司常村煤矿 一种预应力全长锚固支护方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭建平等: "架设树脂锚杆的作业要点", 《同煤科技》, no. 1, 31 March 2001 (2001-03-31) *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678145A (zh) * 2012-04-20 2012-09-19 中钢集团马鞍山矿山研究院有限公司 一种高效的树脂锚杆施工新方法
CN103032086A (zh) * 2012-12-07 2013-04-10 中国矿业大学 一种巷道顶板锚杆钻孔充填树脂药卷的方法
CN103032086B (zh) * 2012-12-07 2015-04-29 中国矿业大学 一种巷道顶板锚杆钻孔充填树脂药卷的方法
CN103613322A (zh) * 2013-11-22 2014-03-05 新汶矿业集团有限责任公司鄂庄煤矿 组合式树脂锚固剂及其锚固方法
CN103613322B (zh) * 2013-11-22 2015-08-26 新汶矿业集团有限责任公司鄂庄煤矿 组合式树脂锚固剂及其锚固方法
CN104632259A (zh) * 2014-12-31 2015-05-20 中国矿业大学 软弱地层端头自膨胀扩大型锚固方法
WO2019119900A1 (zh) * 2017-12-18 2019-06-27 中国矿业大学 一种降低预应力损失的低张拉锚索施工方法
CN112282807A (zh) * 2020-11-20 2021-01-29 贵州盘江煤电集团技术研究院有限公司 一种用于煤矿锚杆安装的一体装置及其使用方法
CN116181384A (zh) * 2023-03-28 2023-05-30 成都理工大学 一种快速混合锚固预应力锚索及其施工方法
CN116181384B (zh) * 2023-03-28 2023-09-15 成都理工大学 一种快速混合锚固预应力锚索及其施工方法

Similar Documents

Publication Publication Date Title
CN102337912A (zh) 煤矿巷道锚杆快速锚固方法
CA1173674A (en) Force transmission device
CN205477690U (zh) 一种防滑注浆锚杆
CN203756203U (zh) 自钻式全螺纹锚注锚杆
CN104500115B (zh) 一种预应力全长锚固锚杆支护方法
CN103899341B (zh) 承压型端锚高预紧力锚杆支护方法
CN109236337A (zh) 多段式卡紧注浆锚固的箭头锚杆及其使用方法
CN100497887C (zh) 套管涨壳型自钻式中空锚杆
CN110410123B (zh) 一种新型煤矿用高强度锚杆支护设备
CN102704969A (zh) 一种钻锚注可回收锚杆及支护方法
CN203891018U (zh) 自钻式排水锚固土钉
CN101994315B (zh) 全长粘结预应力锚杆及其施工方法
CN211230519U (zh) 一种采矿用边坡锚杆紧固装置
CN102808635B (zh) 一种胀壳式内锚头预应力锚杆及其安装使用方法
CN205532664U (zh) 一种新型柔性锚杆
CN111764940A (zh) 一种软弱围岩隧道双层初期支护结构及其施工方法
CN108343458A (zh) 全长粘结大变形让压锚杆及其施工方法
CN205370613U (zh) 一种利用双液注浆药卷实现高预应力全长锚固的锚杆
CN207526513U (zh) 可控扩大式增阻锚杆
CN207598275U (zh) 一种锚杆锚固构造
CN102900447B (zh) 一种用于软弱围岩加固的锚杆
CN103321222A (zh) 一种可回收式锚杆、承压板式锚桩及锚固方法
CN205840899U (zh) 推压式可快速锚固安装粘结型中空锚杆
CN208605210U (zh) 一种新型注浆锚固系统
CN105484782B (zh) 一种实现高预应力全长锚固的锚杆及其使用方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120201

WD01 Invention patent application deemed withdrawn after publication