Summary of the invention:
The objective of the invention is to overcome the above-mentioned deficiency of prior art; A kind of central air-conditioning refrigeration station energy-saving control system is provided; The linked database model of this system through adopting rolling optimization, directly to the self-optimization method of the whole energy consumption of refrigeration station; Realization improves the overall operation efficiency of system of central air-conditioning refrigeration station to the monitoring and the optimization of central air-condition freezing station system operational parameters, reaches energy-saving and cost-reducing effect.
Another object of the present invention is to provide the control method of a kind of central air-conditioning refrigeration station energy-saving control system.
Above-mentioned purpose of the present invention is achieved through following technical scheme:
A kind of central air-conditioning refrigeration station energy-saving control system comprises linked database, energy consumption self-optimizing control device, rolling optimization controller, signals collecting switch board, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board and plurality of sensors, wherein:
Linked database: carry out the linked database modeling of central air-conditioning refrigeration station; Form the linked database model; And receive the state parameter of signals collecting switch board output in real time, said linked database model parameter and said state parameter are exported to energy consumption self-optimizing control device carry out handling from optimizing; Also said linked database model parameter is exported to the rolling optimization controller simultaneously and carry out real-time rolling optimization computing, and receive the parameters optimization that the rolling optimization controller returns, accomplish the renewal of linked database model;
Energy consumption self-optimizing control device: the linked database model parameter and the state parameter that receive linked database output; Receive the state parameter of cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and the output of each electrically operated valve simultaneously; Carry out handling from optimizing; Obtain best energy consumption operational factor, and said best energy consumption operational factor is exported to rolling optimization controller, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and each electrically operated valve respectively;
Rolling optimization controller: the linked database model parameter that receives linked database output; Receive the best energy consumption operational factor of energy consumption self-optimizing control device output; In each searching process, carry out the rolling optimization computing; And the parameter that will accomplish the rolling optimization computing returns to linked database, the renewal of completion linked database model;
Signals collecting switch board: gather central air-conditioning refrigeration station grey water system operational factor and ambient parameter that plurality of sensors is measured, and said parameter is exported to linked database;
Cooling tower switch board: the cooling tower running state parameter is exported to linked database in real time, and receive the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC cooling tower;
Coolant pump switch board: the coolant pump running state parameter is exported to linked database in real time, and receive the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC coolant pump;
Refrigerating water pump switch board: the refrigerating water pump running state parameter is exported to linked database in real time, and receive the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC refrigerating water pump;
Sensor: be used to measure water system operational factor and ambient parameter in the central air-conditioning refrigeration station; And said parameter exported to the signals collecting switch board; Its grey water system operational factor comprises the terminal pressure reduction of chilled-water flow, chilled water leaving water temperature, chilled water return water temperature, cooling water flow, cooling water leaving water temperature, cooling water return water temperature, handpiece Water Chilling Units power and chilled water, and ambient parameter comprises outdoor wet-bulb temperature.
In above-mentioned central air-conditioning refrigeration station energy-saving control system, in linked database, carry out the linked database modeling, the concrete grammar that forms the linked database model is following:
(1) refrigerating capacity with the output of central air-conditioning refrigeration station disperses in its cold scope, obtains exporting the m of cold
1Item discrete function Q
n:
Wherein:
Q
Min: the minimum refrigerating capacity that refrigeration station exports under typical condition
Q
Max: the specified refrigerating capacity that refrigeration station exports under typical condition
1≤n≤m
1, and n, m
1∈ N, Q
nThe accuracy of value is by m
1Value confirms that its minimum resolution is:
(2) wet-bulb temperature with outdoor environment disperses in the wet-bulb temperature working range of refrigeration station, obtains the m of wet-bulb temperature
2Item discrete function TW
l:
Wherein:
TW
Min: the minimum wet-bulb temperature of the outdoor environment of refrigeration station work
TW
Max: the highest wet-bulb temperature of outdoor environment of refrigeration station work
1≤l≤m
2, and l, m
2∈ N, TW
lThe accuracy of value is by m
2Value confirms that its minimum resolution is:
The discrete function Q of (3) output colds
nDiscrete function TW with an outdoor environment wet-bulb temperature
lCorresponding refrigeration station initial operational parameter array, corresponding m altogether
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l), to m
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l) in the preset initial value of each parameter, form the linked database model.
In above-mentioned central air-conditioning refrigeration station energy-saving control system, energy consumption self-optimizing control device receives the linked database model parameter and each state parameter of linked database output, carries out handling from optimizing, and the concrete grammar that obtains best energy consumption operational factor is following:
(1) calculate the current output cold Q of refrigeration station through the refrigeration station running state parameter,
Q=C·F
CH·ΔT=C·F
CH·(T
CHI-T
CHO)
Wherein, F
CH: chilled-water flow, T
CHI: chilled water return water temperature, T
CHO: chilled water leaving water temperature, C: specific heat of water, Δ T: the temperature difference of chilled water backwater and water outlet;
(2) the ability loss-rate f of central air-conditioning refrigeration station optimizing starting point under the calculating current working
B,
Wherein: P
WCU: handpiece Water Chilling Units power, P
CHB: chilled water pump power, P
CB: cooling water pump power, P
TB: blower fan of cooling tower power;
(3) establishing the optimizing step-length is Δ P, and calculating at chilled water pump power respectively is P
CHB± Δ P, cooling water pump power are P
CB± Δ P, blower fan of cooling tower power are P
TBCentral air-conditioning refrigeration station under the ± Δ P situation can loss-rate f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max, wherein:
(4) with the ability loss-rate f of optimizing starting point
BWith maximum ability loss-rate f
MaxCompare,
If f
Max>f
B, then make f
B=f
Max, searching process is continued in repeating step (3), (4);
Otherwise, set a constant ε, 0<ε<1,
If | f
Max-f
B|>=ε then makes
Searching process is continued in repeating step (3), (4);
If | f
Max-f
B|<ε then makes f
O=f
B, with f
OCorresponding operational factor from the optimizing operational factor, finishes searching process as the energy consumption of the best.
In above-mentioned central air-conditioning refrigeration station energy-saving control system; The rolling optimization controller receives the linked database model parameter of linked database output; Receive the best energy consumption operational factor of energy consumption self-optimizing control device output, the concrete grammar that carries out the rolling optimization computing is following:
(1) the rolling optimization controller receives the linked database model parameter of linked database output: the chilled water pump power P
CHB, the cooling water pump power P
CB, the blower fan of cooling tower power P
TB
(2) the rolling optimization controller receives the best energy consumption operational factor of energy consumption self-optimizing control device output: the chilled water pump power P
CHO, the cooling water pump power P
CO, the blower fan of cooling tower power P
TO
(3) chilled water pump power P
CHX, the cooling water pump power P
CX, the blower fan of cooling tower power P
TXFor accomplishing the parameter of rolling optimization computing, its computational methods are following:
(4) with parameter P
CHX, P
CX, P
TXReturn to linked database, upgrade linked database parameter P respectively
CHB, P
CB, P
TB
In above-mentioned central air-conditioning refrigeration station energy-saving control system, also comprise man-machine interface, be used for operational factor to refrigeration station and component devices thereof and show and manage that wherein operational factor comprises coefficient of energy dissipation parameter and running state parameter etc.
The control method of a kind of central air-conditioning refrigeration station energy-saving control system comprises the steps:
(1) linked database carries out the linked database modeling of central air-conditioning refrigeration station, forms the linked database model;
(2) the signals collecting switch board is gathered central air-conditioning refrigeration station grey water system operational factor and the ambient parameter that plurality of sensors is measured, and said parameter is exported to linked database;
(3) linked database receives the state parameter of signals collecting switch board output in real time, linked database model parameter and said state parameter is exported to energy consumption self-optimizing control device carry out handling from optimizing; Also the linked database model parameter is exported to the rolling optimization controller simultaneously and carry out real-time rolling optimization computing;
(4) energy consumption self-optimizing control device receives the linked database model parameter and the state parameter of linked database output; Receive the state parameter of cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and the output of each electrically operated valve simultaneously; Carry out handling from optimizing; Obtain best energy consumption operational factor, and said best energy consumption operational factor is exported to rolling optimization controller, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and each electrically operated valve respectively;
(5) the cooling tower switch board receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC cooling tower; The coolant pump switch board receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC coolant pump; The refrigerating water pump switch board receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of said best energy consumption operational factor VFC refrigerating water pump;
(6) the rolling optimization controller receives the linked database model parameter of linked database output; Receive the best energy consumption operational factor of energy consumption self-optimizing control device output; In each searching process, carrying out the rolling optimization computing, and the parameter that will accomplish the rolling optimization computing returns to linked database;
(7) linked database receives the parameters optimization that the rolling optimization controller returns, and accomplishes the renewal of linked database model.
In the control method of above-mentioned central air-conditioning refrigeration station energy-saving control system, linked database carries out the linked database modeling of central air-conditioning refrigeration station in the step (1), and the concrete grammar that forms the linked database model is following:
(1) refrigerating capacity with the output of central air-conditioning refrigeration station disperses in its cold scope, obtains exporting the m of cold
1Item discrete function Q
n:
Wherein:
Q
Min: the minimum refrigerating capacity that refrigeration station exports under typical condition
Q
Max: the specified refrigerating capacity that refrigeration station exports under typical condition
1≤n≤m
1, and n, m
1∈ N, Q
nThe accuracy of value is by m
1Value confirms that its minimum resolution is:
(2) wet-bulb temperature with outdoor environment disperses in the wet-bulb temperature working range of refrigeration station, obtains the m of wet-bulb temperature
2Item discrete function TW
l:
Wherein:
TW
Min: the minimum wet-bulb temperature of the outdoor environment of refrigeration station work
TW
Max: the highest wet-bulb temperature of outdoor environment of refrigeration station work
1≤l≤m
2, and l, m
2∈ N, TW
lThe accuracy of value is by m
2Value confirms that its minimum resolution is:
The discrete function Q of (3) output colds
nDiscrete function TW with an outdoor environment wet-bulb temperature
lCorresponding refrigeration station initial operational parameter array, corresponding m altogether
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l), to m
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l) in the preset initial value of each parameter, form the linked database model.
In the control method of above-mentioned central air-conditioning refrigeration station energy-saving control system; Energy consumption self-optimizing control device receives the linked database model parameter and each state parameter of linked database output in the step (4); Carry out handling from optimizing, the concrete grammar that obtains best energy consumption operational factor is following:
(1) calculate the current output cold Q of refrigeration station through the refrigeration station running state parameter,
Q=C·F
CH·ΔT=C·F
CH·(T
CHI-T
CHO)
Wherein, F
CH: chilled-water flow, T
CHI: chilled water return water temperature, T
CHO: chilled water leaving water temperature, C: specific heat of water, Δ T: the temperature difference of chilled water backwater and water outlet;
(2) the ability loss-rate f of central air-conditioning refrigeration station optimizing starting point under the calculating current working
B,
Wherein: P
WCU: handpiece Water Chilling Units power, P
CHB: chilled water pump power, P
CB: cooling water pump power, P
TB: blower fan of cooling tower power;
(3) establishing the optimizing step-length is Δ P, and calculating at chilled water pump power respectively is P
CHB± Δ P, cooling water pump power are P
CB± Δ P, blower fan of cooling tower power are P
TBCentral air-conditioning refrigeration station under the ± Δ P situation can loss-rate f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max, wherein:
(4) with the ability loss-rate f of optimizing starting point
BWith maximum ability loss-rate f
MaxCompare,
If f
Max>f
B, then make f
B=f
Max, searching process is continued in repeating step (3), (4);
Otherwise, set a constant ε, 0<ε<1,
If | f
Max-f
B|>=ε then makes
Searching process is continued in repeating step (3), (4);
If | f
Max-f
B|<ε then makes f
O=f
B, with f
OCorresponding operational factor from the optimizing operational factor, finishes searching process as the energy consumption of the best.
In the control method of above-mentioned central air-conditioning refrigeration station energy-saving control system; The rolling optimization controller receives the linked database model parameter of linked database output in the step (6); Receive the best energy consumption operational factor of energy consumption self-optimizing control device output, the concrete grammar that carries out the rolling optimization computing is following:
(1) the rolling optimization controller receives the linked database model parameter of linked database output: the chilled water pump power P
CHB, the cooling water pump power P
CB, the blower fan of cooling tower power P
TB
(2) the rolling optimization controller receives the best energy consumption operational factor of energy consumption self-optimizing control device output: the chilled water pump power P
CHO, the cooling water pump power P
CO, the blower fan of cooling tower power P
TO
(3) chilled water pump power P
CHX, the cooling water pump power P
CX, the blower fan of cooling tower power P
TXFor accomplishing the parameter of rolling optimization computing, its computational methods are following:
(4) with parameter P
CHX, P
CX, P
TXReturn to linked database, upgrade linked database parameter P respectively
CHB, P
CB, P
TB
The present invention compared with prior art has following advantage:
(1) energy-saving control system of the present invention is through carrying out the linked database modeling to each main current consuming apparatus in the central air-condition freezing station; And adopt energy consumption self-optimizing control device to carry out energy consumption from searching process; Obtain the parameters optimization of refrigeration station equipment operation, adopt the rolling optimization controller that linked database is carried out rolling optimization again, realize dynamically updating of linked database; Make the variation that whole central air-conditioning refrigeration station can adaptation condition, always work in energy-efficient state;
(2) energy-saving control system of the present invention is at first through carrying out parametric optimization to the associated data database data; Confirm the current basic operating conditions of refrigeration station; Through installation power sensor in main current consuming apparatus supply line such as handpiece Water Chilling Units, chilled water pump, cooling water pump, cooling tower, monitor the operation power consumption situation of each main consumer then, and through further online energy consumption from searching process; Operational factor after each equipment energy consumption optimization is transferred to the cooling tower switch board; The cooling water pump switch board, chilled water pump switch board, the control parameter of regulating handpiece Water Chilling Units, chilled water pump, cooling water pump, cooling tower; Reach the minimum purpose of the whole energy consumption of refrigeration station, rather than a certain equipment energy consumption is minimum;
(3) the associated data database data in the central air-conditioning of the present invention refrigeration station control method is a rolling optimization; Be that parameter optimization is not that disposable off-line is accomplished; But online repeatedly carry out; In central air-conditioning refrigeration station running; The measurement data of chilled water flow quantity sensor, cooling water flow quantity sensor, chilled water supply and return water temperature sensor, cooling water supply and return water temperature sensor, outdoor wet bulb temperature sensor, power sensor, differential pressure pickup is through online updating linked database behind the algorithm optimization; Central air-conditioning refrigeration station device performance parameters can be adjusted along with the variation of equipment performance, aging or more behind the exchange device, this control method still can guarantee the energy-efficient operation at whole freezing station when equipment operation;
(4) control method of the present invention is a kind of central air-conditioning refrigeration station energy-saving control method with self-learning function; Realization is to the monitoring and the optimization of central air-condition freezing station system operational parameters; Improve the overall operation efficiency of system of central air-conditioning refrigeration station; Reach energy-saving and cost-reducing effect, have stronger practicality.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the present invention is described in further detail:
Be illustrated in figure 1 as central air-conditioning of the present invention refrigeration station energy-saving control system sketch map, can know that by figure this central air-conditioning refrigeration station energy-saving control system comprises linked database, energy consumption self-optimizing control device, rolling optimization controller, signals collecting switch board, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, plurality of sensors and man-machine interface.Sensor comprises temperature sensor, wet bulb temperature sensor, flow sensor, power sensor, specifically is divided into outdoor wet bulb temperature sensor, cooling water return water temperature sensor, cooling water leaving water temperature sensor; The cooling water flow quantity sensor; Terminal differential pressure pickup, chilled water flow quantity sensor, chilled water leaving water temperature sensor; Chilled water return water temperature sensor etc.; The cooling tower switch board is monitored the blower fan of cooling tower operation of central air-conditioning, and the cooling water pump switch board is monitored the cooling water pump operation of central air-conditioning, and the chilled water pump switch board is monitored the chilled water pump operation of central air-conditioning.
Linked database carries out the linked database modeling of central air-conditioning refrigeration station, forms the linked database model, and concrete grammar is following:
(1) refrigerating capacity with the output of central air-conditioning refrigeration station disperses in its cold scope, obtains exporting the m of cold
1Item discrete function Q
n:
Wherein:
Q
Min: the minimum refrigerating capacity that refrigeration station exports under typical condition
Q
Max: the specified refrigerating capacity that refrigeration station exports under typical condition
1≤n≤m
1, and n, m
1∈ N, Q
nThe accuracy of value is by m
1Value confirms that its minimum resolution is:
(2) wet-bulb temperature with outdoor environment disperses in the wet-bulb temperature working range of refrigeration station, obtains the m of wet-bulb temperature
2Item discrete function TW
l:
Wherein:
TW
Min: the minimum wet-bulb temperature of the outdoor environment of refrigeration station work
TW
Max: the highest wet-bulb temperature of outdoor environment of refrigeration station work
1≤l≤m
2, and l, m
2∈ N, TW
lThe accuracy of value is by m
2Value confirms that its minimum resolution is:
The discrete function Q of (3) output colds
nDiscrete function TW with an outdoor environment wet-bulb temperature
lCorresponding refrigeration station initial operational parameter array, corresponding m altogether
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l), as to set the specified refrigerating capacity of a certain central air-conditioning refrigeration station be Q
Max, minimum refrigerating capacity is 10% of a specified refrigerating capacity, outdoor wet-bulb temperature working range is 23 ℃≤TW
l≤32 ℃, m
1=m
2=10, be that (n l), sets up linked database model such as following table 1 to D with the array representation in the linked database.
Table 1
To m
1* m
2The individual initial operational parameter array (Q of refrigeration station
n, TW
l) in the preset initial value of each parameter, form the linked database model.
Each initial operational parameter array (Q of refrigeration station wherein
n, TW
l) comprise following parameter:
Chilled-water flow F
CH, chilled water return water temperature T
CHI, chilled water leaving water temperature T
CHO, the chilled water pump rotational speed omega
CH, the chilled water pump power P
CH, the terminal pressure differential deltap P of chilled water, cooling water flow F
C, cooling water return water temperature T
CI, cooling water leaving water temperature T
CO, the cooling water pump rotational speed omega
C, the cooling water pump power P
C, the blower fan of cooling tower rotational speed omega
T, the blower fan of cooling tower power P
T, the handpiece Water Chilling Units power P
WCU, the refrigeration station refrigeration efficiency compares COP.
Wherein to the chilled water pump power P
CH, the cooling water pump power P
CWith the blower fan of cooling tower power P
TOperational factor behind the preset initial value is the chilled water pump power P
CHB, the cooling water pump power P
CBWith the blower fan of cooling tower power P
TB
Linked database receives the state parameter of signals collecting switch board output in real time, linked database model parameter and each state parameter is exported to energy consumption self-optimizing control device carry out handling from optimizing; Also the linked database model parameter is exported to the rolling optimization controller simultaneously and carry out real-time rolling optimization computing, and receive the parameters optimization that the rolling optimization controller returns, accomplish the renewal of linked database model.
Energy consumption self-optimizing control device receives the linked database model parameter and each state parameter of linked database output; Receive the state parameter of cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and the output of each electrically operated valve simultaneously; Carry out handling from optimizing; Obtain best energy consumption operational factor, be illustrated in figure 2 as energy consumption self-optimizing control device of the present invention from the optimizing workflow diagram, following from the optimizing detailed process:
(1) calculate the current output cold Q of refrigeration station through the refrigeration station running state parameter,
Q=C·F
CH·ΔT=C·F
CH·(T
CHI-T
CHO) (3)
Wherein, F
CH: chilled-water flow, T
CHI: chilled water return water temperature, T
CHO: chilled water leaving water temperature, C: specific heat of water, Δ T: the temperature difference of chilled water backwater and water outlet;
(2) with the discrete Q that turns to of Q
n, and with parameter array (Q in the linked database
n, TW
l) corresponding operational factor preset value exports to cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and each electrically operated valve respectively.
Calculate (Q
n, TW
l) the ability loss-rate f of corresponding central air-conditioning refrigeration station optimizing starting point
B,
Wherein: P
WCU: handpiece Water Chilling Units power, P
CHB: chilled water pump power, P
CB: cooling water pump power, P
TB: blower fan of cooling tower power;
(3) establishing the optimizing step-length is Δ P, and calculating at chilled water pump power respectively is P
CHB± Δ P, cooling water pump power are P
CB± Δ P, blower fan of cooling tower power are P
TBCentral air-conditioning refrigeration station under the ± Δ P situation can loss-rate f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max, wherein:
(4) with the ability loss-rate f of optimizing starting point
BWith maximum ability loss-rate f
MaxCompare,
If f
Max>f
B, then make f
B=f
Max, searching process is continued in repeating step (3), (4);
Otherwise, set a constant ε, 0<ε<1,
If | f
Max-f
B|>=ε then makes
Searching process is continued in repeating step (3), (4);
If | f
Max-f
B|<ε then makes f
O=f
B, with f
OCorresponding operational factor from the optimizing operational factor, finishes searching process as the energy consumption of the best.
Take a concrete example:
For example maximum is f in first round searching process
5, and f
5>f
B, then make f
B=f
5, promptly
Again get into step (3) and carry out second and take turns optimizing, calculate f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max, at this moment:
If second takes turns f in the optimizing
3Be maximum, and f
3>f
B, then make f
B=f
3, promptly
Again get into step (3) and carry out the third round optimizing, calculate f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max
Make ε=0.5, if f in the third round optimizing
Max≤f
BAnd | f
Max-f
B|>=ε then makes
Repeating step (3) carries out the four-wheel optimizing, calculates f
1, f
2, f
3, f
4, f
5, f
6, and the maximum of getting wherein is labeled as f
Max
If f in the four-wheel optimizing
Max≤f
BAnd | f
Max-f
B|<ε then makes f
O=f
B,
With f
OCorresponding operational factor from the optimizing operational factor, finishes searching process as the energy consumption of the best.
Searching process is exported to rolling optimization controller, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and each electrically operated valve respectively with best energy consumption operational factor after finishing.
The cooling tower switch board is exported to linked database in real time with the cooling tower running state parameter, and receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC cooling tower.
The coolant pump switch board is exported to linked database in real time with the coolant pump running state parameter, and receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC coolant pump.
The refrigerating water pump switch board is exported to linked database in real time with the refrigerating water pump running state parameter, and receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC refrigerating water pump.
The rolling optimization controller receives the linked database model parameter of linked database output; Receive the best energy consumption operational factor of energy consumption self-optimizing control device output; In each searching process, carry out the rolling optimization computing, the concrete grammar that carries out the rolling optimization computing is following:
(1) the rolling optimization controller receives the linked database model parameter of linked database output: the chilled water pump power P
CHB, the cooling water pump power P
CB, the blower fan of cooling tower power P
TB
(2) the rolling optimization controller receives the best energy consumption operational factor of energy consumption self-optimizing control device output: the chilled water pump power P
CHO, the cooling water pump power P
CO, the blower fan of cooling tower power P
TO
(3) chilled water pump power P
CHX, the cooling water pump power P
CX, the blower fan of cooling tower power P
TXFor accomplishing the parameter of rolling optimization computing, its computational methods are following:
(4) with parameter P
CHX, P
CX, P
TXReturn to linked database, upgrade linked database parameter P respectively
CHB, P
CB, P
TB
Water system operational factor and ambient parameter in the sensor measurement central air-conditioning refrigeration station; The above-mentioned parameter that signals collecting switch board pick-up transducers is measured; And above-mentioned parameter exported to linked database; Its grey water system operational factor comprises the terminal pressure reduction of chilled-water flow, chilled water leaving water temperature, chilled water return water temperature, cooling water flow, cooling water leaving water temperature, cooling water return water temperature, handpiece Water Chilling Units power and chilled water, and ambient parameter comprises outdoor wet-bulb temperature.
Man-machine interface is used for operational factor to refrigeration station and component devices thereof and shows and manage that wherein operational factor comprises coefficient of energy dissipation parameter and running state parameter etc.
It is following to adopt above-mentioned central air-conditioning refrigeration station energy-saving control system to carry out the process of Energy Saving Control:
Step 1, linked database carry out the linked database modeling of central air-conditioning refrigeration station, form the linked database model.
Step 2, signals collecting switch board are gathered central air-conditioning refrigeration station grey water system operational factor and the ambient parameter that plurality of sensors is measured, and said parameter is exported to linked database;
Step 3, linked database receive the state parameter of signals collecting switch board output in real time, linked database model parameter and said state parameter are exported to energy consumption self-optimizing control device carry out handling from optimizing; Also the linked database model parameter is exported to the rolling optimization controller simultaneously and carry out real-time rolling optimization computing.
Step 4, energy consumption self-optimizing control device receive linked database model parameter and each state parameter of linked database output; Receive the state parameter of cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and the output of each electrically operated valve simultaneously; Carry out handling from optimizing; Obtain best energy consumption operational factor, and said best energy consumption operational factor is exported to rolling optimization controller, cooling tower switch board, coolant pump switch board, refrigerating water pump switch board, central air-conditioning refrigeration station handpiece Water Chilling Units and each electrically operated valve respectively.
Step 5, cooling tower switch board receive the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC cooling tower; The coolant pump switch board receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC coolant pump; The refrigerating water pump switch board receives the best energy consumption operational factor of energy consumption self-optimizing control device output in real time, according to the operation of best energy consumption operational factor VFC refrigerating water pump.
Step 6, rolling optimization controller receive the linked database model parameter of linked database output; Receive the best energy consumption operational factor of energy consumption self-optimizing control device output; In each searching process, carrying out the rolling optimization computing, and the parameter that will accomplish the rolling optimization computing returns to linked database.
Step 7, linked database receive the parameters optimization that the rolling optimization controller returns, and accomplish the renewal of linked database model.
Through above-mentioned steps existing monitoring and optimization to central air-condition freezing station system operational parameters, improve the overall operation efficiency of system of central air-conditioning refrigeration station, reach energy-saving and cost-reducing effect.
The above; Be merely the best specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, any technical staff who is familiar with the present technique field is in the technical scope that the present invention discloses; The variation that can expect easily or replacement all should be encompassed within protection scope of the present invention.
The content of not doing to describe in detail in the specification of the present invention belongs to this area professional and technical personnel's known technology.