CN101967974B - 一种竖井反掘延深和探采工程交叉作业的方法 - Google Patents
一种竖井反掘延深和探采工程交叉作业的方法 Download PDFInfo
- Publication number
- CN101967974B CN101967974B CN2010102796366A CN201010279636A CN101967974B CN 101967974 B CN101967974 B CN 101967974B CN 2010102796366 A CN2010102796366 A CN 2010102796366A CN 201010279636 A CN201010279636 A CN 201010279636A CN 101967974 B CN101967974 B CN 101967974B
- Authority
- CN
- China
- Prior art keywords
- vertical shaft
- shaft
- stage casing
- engineering
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
本发明属于采矿技术领域,公开了一种竖井反掘延深和探采工程交叉作业的方法。首先从采矿工程中段、探矿工程中段分别施工穿脉工程至原竖井井底,然后分别由下至上从探矿工程中段、采矿工程中段反掘施工竖井与原竖井相通,最后安装成井;在整个施工过程中,原探采工程正常生产,各中段施工所产生的矿岩及竖井掘进中产生的废石从相应中段斜井运至原竖井最低标高处的中段后,提至井外。本发明方法既可以保证竖井顺利延深,还可保证选矿厂正常运转,达到了边技改边生产,技改不影响生产的目的;采用本发明方法进行竖井延深时,既没有新增加工程量,也没有增加工程成本,同时带来了间接经济效益。
Description
技术领域
本发明属于采矿技术领域,具体涉及了一种竖井反掘延深和探采工程交叉作业的方法。
背景技术
随着探采工程的逐步深入,矿区竖井的采矿工作面与探矿工程面逐步下降且集中,采矿工作中段与探矿工程中段间各沿脉工程主要靠斜井连接提升,生产能力大受影响,并且严重影响以后的深部探矿工程布置。所以对竖井进行延深,提高生产能力已成为当务之急。为解决此问题,大多数本领域技术人员的做法基本相同:即将竖井停产,按照传统的竖井掘砌程序,逐步从采矿工作中段施工延深至探矿工程中段,工期历时数月。然而,竖井作为选矿厂的主要供矿矿井,如果停产势必造成选矿厂全线停车,严重影响整个公司的正常生产经营。那么,如何既要保证竖井顺利延深,还要保证选矿厂正常运转,已是亟待克服的困难。
发明内容
为克服现有技术中存在的不足之处,本发明的目的在于提供一种竖井反掘延深和探采工程交叉作业的方法,既可以保证竖井顺利延深,还可保证选矿厂正常运转。
为实现上述目的,本发明采取的技术方案如下:
一种竖井反掘延深和探采工程交叉作业的方法:首先从采矿工程中段、探矿工程中段分别施工穿脉工程至原竖井井底,然后分别由下至上从探矿工程中段、采矿工程中段反掘施工竖井与原竖井相通,最后安装成井;在整个施工过程中,原探采工程正常生产,各中段施工所产生的矿岩及竖井掘进中产生的废石从相应中段斜井运至原竖井最低标高处的中段后,提至井外。
为确保正常探采提升作业不受反掘施工影响,反掘施工竖井期间,在原竖井最低标高处的中段向下10米范围内对竖井井筒进行封闭。
为了尽量减少损失,保证供矿,根据安装人员属高空作业,不宜连续工作的特点,安装成井期间,采用井筒装备安装与探采工程交叉进行。
较好地,反掘施工竖井时,首先从探矿工程中段、采矿工程中段同时或分段施工小断面短天井与上中段贯通,全程贯通后再扩帮至与原竖井直径相当的井筒。为了减小斜井提升压力,保证日常探采作业不受影响,优选分段施工方式。
较好的,施工穿脉工程时,保证穿脉工程规格、坡度、转变半径与施工原竖井的马头门参数一致,以便于以后改造为各中段马头门使用。
本发明方法既可以保证竖井顺利延深,还可保证选矿厂正常运转,达到了边技改边生产,技改不影响生产的目的;采用本发明方法进行竖井延深时,各中段的穿脉工程可作为以后各中段马头门使用,所以没有新增加工程量;竖井延深时,无论采用从上向下施工或从下向上反掘,《黄金工业工程建筑预算定额》所规定的单价是相同的,因此也没有增加工程成本;但是,由于采用本发明方法时探采作业可正常进行,给公司带来了间接经济效益。
附图说明
图1:采用本发明方法施工前,桥上寨矿区结构简图;
图2:采用本发明方法施工穿脉工程时,桥上寨矿区结构简图;
图3:采用本发明方法施工小断面短天井时,桥上寨矿区结构简图;
图4:采用本发明方法进行扩帮时,桥上寨矿区结构简图;
其中,1-竖井,2-400中段,3-340中段,4-290中段,5-260中段,6-230中段,7-井筒中心线,8-斜井,9-小断面短天井。
具体实施方式
以下结合具体实施例对本发明的技术方案做进一地详细介绍,但本发明的保护范围并不局限于此:
施工场地及其基本资料:
桥上寨矿区,隶属申请人,并为西阳平选矿厂提供矿量。采用本发明方法施工前其结构简图如图1所示:竖井1直径约3.8米,开口标高696米,最低标高340米,设400中段2和340中段3两个马头门;随着探采工程的逐步深入,采矿工作面逐步下降且集中,从2008年初至今,80%的采矿工程集中在290中段4,探矿工程集中在260中段5和230中段6;340中段3至230中段6间各沿脉工程主要靠斜井8连接提升,生产能力大受影响,并且严重影响2009年以后的深部探矿工程布置。
采用本发明方法施工的具体步骤:
(1)、工程测量:首先对原测量成果进行全面复核,在此基础上对现有竖井1井底、290中段4、260中段5、230中段6进行全面测量定位,准确锁定竖井1井筒中心线7在各中段的具体位置。
(2)、如图2所示施工穿脉工程:在290中段4、260中段5、230中段6各施工穿脉工程至井筒中心线7位置,穿脉工程规格、坡度、转变半径等参数与施工竖井1马头门参数要求一致,以便于以后改造为各中段马头门使用。
(3)、如图3所示施工小断面短天井:分别从230中段6、260中段5、290中段4井筒中心线7位置向上施工小断面短天井9(2米×2米)与上中段贯通,施工顺序可同时进行,亦可分段施工。本次施工过程中,为了减小斜井8提升压力,保证日常探采作业不受影响,采用了分段施工方式。另外,在施工290中段4至340中段3最后10米天井时,为了保证340中段3各岗位工作人员安全,在进行放炮作业时暂将340中段3马头门封闭、竖井1暂停提升,待爆破作业完毕后继续正常作业。各阶段施工过程中产生的废石,先运至各中段斜井8井底,与生产矿岩编组后提升至340中段3马头门,由竖井1提升至坑外。
(4)、小断面短天井9全程贯通后,再次复核竖井1井筒中心线7。
(5)、如图4所示进行扩帮:以竖井1井筒中心线7为圆心,将2米×2米小断面短天井一次性扩帮为直径3.8米的圆形井筒。在此期间用坑木在340中段3向下10米处对竖井1井筒进行封闭,确保正常探采提升作业不受扩帮工程影响。
(6)、对竖井1延深段进行喷浆支护及井筒装备安装:井筒装备安装期间,为了保证井下作业人员安全,必需将井口封闭,如此一来,所有探采作业必须停止。为了尽量减少损失,保证供矿,根据安装人员属高空作业,不宜连续工作的特点,采取了井筒装备安装与探采作业交叉进行的方法,即:把安装工作安排在白天作业,井口临时封闭;晚间将井口打开,开始正常探采作业。既保证了正常供矿,又保证了安装作业正常进行。
上述项目于2008年6月开始施工(内部实践,不对外公开),于2009年1月结束投产,整个工期为7个月。桥上寨矿区2008年共采配下山矿量14.97万吨,掘进4822.5米,完成了公司下达的年度责任目标,达到了边技改边生产,技改不影响生产的目的。其中:2008年10、11、12月共采矿37539.94吨,掘进1120.2米,保证了西阳平选矿厂正常运转,间接产生利税1189.63万元。
经济效益计算方法:
采用本发明方法进行竖井延深时,各中段的穿脉工程可作为以后各中段马头门使用,所以没有新增加工程量。竖井延深时,无论采用从上向下施工或从下向上反掘,《黄金工业工程建筑预算定额》所规定的单价是相同的,因此也没有增加工程成本。但是,采用本发明方法施工时,增加了安装工程的施工难度,同时也增加了费用。该增加费用即为总投资额,计算方法为:项目总投资=工日数量×单价×难度系数=1583工日×80元/工日×0.45=5.62万元。
新增产值计算方法:如果采用正常的施工方法(下掘),那么竖井延深(总长大于400米)的掘进及安装需3个月工期,即矿区须停产3个月(2008年10至12月),这3个月中,该竖井向西阳平选矿厂提供矿量的产值应为该项目的间接产值:
产值=3个月采矿量×入选品位×选矿回收率×合质金单价=37539.94吨×3.62克/吨×90%×200元/克=2446.1万元。
新增利税计算方法:新增利税=产值-成本-项目投资=2446.1万元-1250.85万元-5.62万元=1189.63万元。
其中成本=3个月的掘进费用+采矿费用+运、选费用+公司管理费=239.89万元+327.73万元+75元/吨×37539.94吨+107元/吨×37539.94=1250.85万元。
Claims (5)
1.一种竖井反掘延深和探采工程交叉作业的方法,其特征在于:首先从采矿工程中段、探矿工程中段分别施工穿脉工程至原竖井井底,然后分别由下至上从探矿工程中段、采矿工程中段反掘施工竖井与原竖井相通,最后安装成井;在整个施工过程中,原探采工程正常生产,各中段施工所产生的矿岩及竖井掘进中产生的废石从相应中段斜井运至原竖井最低标高处的中段后,提至井外。
2.如权利要求1所述的竖井反掘延深和探采工程交叉作业的方法,其特征在于:反掘施工竖井期间,在原竖井最低标高处的中段向下10米范围内对竖井井筒进行封闭。
3.如权利要求1或2所述的竖井反掘延深和探采工程交叉作业的方法,其特征在于:安装成井期间,井筒装备安装与探采工程交叉进行。
4.如权利要求3所述的竖井反掘延深和探采工程交叉作业的方法,其特征在于:反掘施工竖井时,首先从探矿工程中段、采矿工程中段同时或分段施工小断面短天井与上中段贯通,全程贯通后再扩帮至与原竖井直径相当的井筒。
5.如权利要求4所述的竖井反掘延深和探采工程交叉作业的方法,其特征在于:施工穿脉工程时,保证穿脉工程规格、坡度、转变半径与施工原竖井的马头门参数一致。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102796366A CN101967974B (zh) | 2010-09-13 | 2010-09-13 | 一种竖井反掘延深和探采工程交叉作业的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102796366A CN101967974B (zh) | 2010-09-13 | 2010-09-13 | 一种竖井反掘延深和探采工程交叉作业的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101967974A CN101967974A (zh) | 2011-02-09 |
CN101967974B true CN101967974B (zh) | 2012-07-25 |
Family
ID=43547184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102796366A Active CN101967974B (zh) | 2010-09-13 | 2010-09-13 | 一种竖井反掘延深和探采工程交叉作业的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101967974B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103046931B (zh) * | 2012-12-03 | 2015-01-14 | 云南建工水利水电建设有限公司 | 一种竖井/导井冲击式钻机冲击成孔施工方法 |
CN104110261A (zh) * | 2014-06-13 | 2014-10-22 | 中国水利水电第十二工程局有限公司 | 一种竖井反向一次扩挖施工方法 |
CN104964625B (zh) * | 2015-05-27 | 2016-09-07 | 中钢集团马鞍山矿山研究院有限公司 | 一种竖井延伸时对已有井筒无损害的反掘贯通爆破方法 |
CN112112682B (zh) * | 2020-09-04 | 2025-01-03 | 中国恩菲工程技术有限公司 | 斜坡道与反掘竖井协同的矿山开拓系统及其开拓方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU7003481A (en) * | 1980-05-01 | 1981-11-05 | Ingersoll-Rand Co. | Roof support over mining machine |
CN1176337A (zh) * | 1996-07-13 | 1998-03-18 | 鲁阿科勒股份公司 | 尤其在硬煤层预防和阻止岩石突出的开采盘区的设计方法 |
CN1333858A (zh) * | 1998-11-20 | 2002-01-30 | Cdx天然气有限公司 | 用于从地表面接近地下矿藏的方法和系统 |
CN101749018A (zh) * | 2010-01-31 | 2010-06-23 | 山西晋城无烟煤矿业集团有限责任公司 | 煤柱直接回收采煤法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3750043B2 (ja) * | 1998-06-10 | 2006-03-01 | 清水建設株式会社 | 大断面地下空洞原石採掘場 |
-
2010
- 2010-09-13 CN CN2010102796366A patent/CN101967974B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU7003481A (en) * | 1980-05-01 | 1981-11-05 | Ingersoll-Rand Co. | Roof support over mining machine |
CN1176337A (zh) * | 1996-07-13 | 1998-03-18 | 鲁阿科勒股份公司 | 尤其在硬煤层预防和阻止岩石突出的开采盘区的设计方法 |
CN1333858A (zh) * | 1998-11-20 | 2002-01-30 | Cdx天然气有限公司 | 用于从地表面接近地下矿藏的方法和系统 |
CN101749018A (zh) * | 2010-01-31 | 2010-06-23 | 山西晋城无烟煤矿业集团有限责任公司 | 煤柱直接回收采煤法 |
Also Published As
Publication number | Publication date |
---|---|
CN101967974A (zh) | 2011-02-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102080518B (zh) | 煤层顶板复杂分支井抽采瓦斯方法 | |
CN103615285B (zh) | 一种利于充填接顶的采场进路布置方式及方法 | |
CN101858217B (zh) | 房柱变换式盘区上向分层充填采矿法 | |
CN107916953A (zh) | 基于煤层顶板水平钻孔的瓦斯抽釆系统、抽采方法及施工工艺 | |
CN106761902B (zh) | 一种适用于软岩保护层开采的立体综合卸压瓦斯抽采方法 | |
CN103306714B (zh) | 近距离煤层群底抽巷钻孔一孔三用的瓦斯治理方法 | |
CN108266193A (zh) | Ⅳ、ⅴ级软弱围岩全断面隧道的施工方法 | |
CN106593445A (zh) | 一种老采空区下伏近距离煤层覆岩隔离注浆充填开采方法 | |
CN205638458U (zh) | 一种加快地下溜破系统施工速度的施工结构 | |
CN103696774B (zh) | 井上井下平行施工暗井架开拓方法 | |
CN111075478A (zh) | 采掘工作面构造破碎带地面施工预注浆加固工艺 | |
CN103924975A (zh) | 一种用于采煤过程中的保水方法 | |
CN114294046B (zh) | 一种煤矿区全覆盖井上下立体抽采方法 | |
CN103808633A (zh) | 一种采动破碎岩体水砂运移试验系统及监测方法 | |
CN103835648A (zh) | 一种通过地面注浆改善岩层性能反井钻井工艺 | |
CN101967974B (zh) | 一种竖井反掘延深和探采工程交叉作业的方法 | |
CN106437632A (zh) | 一种煤矿老采空区瓦斯抽采方法 | |
CN105239964A (zh) | 保护层卸压井上下立体化煤与煤层气协调开发方法 | |
CN104790918A (zh) | 复杂地形条件下丛式井与水平井联合地面开采煤层气方法 | |
CN102913249B (zh) | 斜井横向贯通正洞单喇叭挑高施工方法 | |
CN102635359B (zh) | 隧道通风竖井节能快速施工方法 | |
CN207761705U (zh) | 基于煤层顶板水平钻孔的瓦斯抽采系统 | |
CN108533265A (zh) | 利用混凝土构件组装底柱的充填采矿方法 | |
CN109779634B (zh) | 煤矿地面垂直井压裂坚硬顶板位置确定方法 | |
CN114263464B (zh) | 一种迎采动孤岛工作面巷道围岩卸压锚固协同控制方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent for invention or patent application | ||
CB02 | Change of applicant information |
Address after: 472500, Jincheng Road, Lingbao City, Henan Province, No. 20 Applicant after: Lingbao Jinyuan Mining Co.,Ltd. Address before: 472500, Jincheng Road, Lingbao City, Henan Province, No. 20 Applicant before: Lingbao City Jinyuan Mining Co., Ltd. |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: LINGBAO CITY JINYUAN MINING CO., LTD. TO: LINGBAO JINYUAN MINING CO., LTD. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |