CN101250876A - Method for installation of medicine volume anchor bar anchorage agent - Google Patents

Method for installation of medicine volume anchor bar anchorage agent Download PDF

Info

Publication number
CN101250876A
CN101250876A CNA2008100642506A CN200810064250A CN101250876A CN 101250876 A CN101250876 A CN 101250876A CN A2008100642506 A CNA2008100642506 A CN A2008100642506A CN 200810064250 A CN200810064250 A CN 200810064250A CN 101250876 A CN101250876 A CN 101250876A
Authority
CN
China
Prior art keywords
outer tube
anchor bar
mounting method
bar anchorage
medicine volume
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100642506A
Other languages
Chinese (zh)
Other versions
CN100588818C (en
Inventor
赵顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority to CN200810064250A priority Critical patent/CN100588818C/en
Publication of CN101250876A publication Critical patent/CN101250876A/en
Application granted granted Critical
Publication of CN100588818C publication Critical patent/CN100588818C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to an installment method of cartridge bolt anchor agent, which relates to an installment method of anchor agent. The invention aims to solve the problems that when a prior bolt anchor agent is arranged, a crabstick is easy to burst a cartridge, thereby leading a subsequent cartridge not to be sent into the bottom portion of a bolting hole, and not playing a predictive role of full column of a bolt. The method of the invention sends the anchor agent into a plastic outer tube, the plastic outer tube and the anchor agent are sent into the bolting hole together, the plastic outer tube is inserted into the outer tube to support the anchor agent, then the plastic outer tube is extracted from the bolting hole, and the installment finishes. The plastic sleeve of the invention has simple structure, the smooth tube wall of the plastic outer tube overcomes the defects that coarse wall of the bolting hole is easy to lead the cartridge to break, and the quality of the bolt is reliably guaranteed. The operation is simple, the installment speed is rapid, and the construction efficiency is high. The bolt is longer, and the superiority is more obvious. The installment speed of workers is capable of being increased by one time, the labor intensity is greatly reduced, and the safety of constructors is guaranteed.

Description

The mounting method of medicine volume anchor bar anchorage agent
Technical field
The present invention relates to a kind of mounting method of anchoring agent.
Background technology
Existing fixing agent for anchor poles (being commonly called as powder stick) in installation process be with powder stick with clear water soak good after, with waddy pushing tow powder stick with in its bolthole of packing into, but because the soak time of powder stick is difficult to grasp and the roughness of anchor pole hole wall is bigger, waddy is easy to powder stick bursting (particularly arch construction) when installing, cause follow-up powder stick can't send into the bottom of bolthole, do not have the predictive role of anchor pole total length bonding, stayed unsafe factor for follow-up construction.
Summary of the invention
The objective of the invention is for the mounting method that solves existing fixing agent for anchor poles be with powder stick with clear water soak good after, with waddy pushing tow powder stick with in its bolthole of packing into, but because the soak time of powder stick is difficult to grasp, waddy is easy to the powder stick bursting when installing, cause follow-up powder stick can't send into the bottom of bolthole, do not have the predictive role of anchor pole total length bonding, the problem of having stayed unsafe factor for follow-up construction provides a kind of mounting method of medicine volume anchor bar anchorage agent.The mounting method of medicine volume anchor bar anchorage agent of the present invention is realized according to the following steps: one, be that 39~41mm, wall thickness are that the plastic pipe of 1.5~2.5mm is as outer tube with external diameter, with external diameter is that 31~33mm, wall thickness are that the plastic pipe of 1.5~2.5mm is as interior pipe, make outer tube and interior tubular packaged tube, with the fixing upward shutoff of an end of interior pipe; Two, the anchoring agent is sent in the outer tube by volume; Three, the outer tube that the anchoring agent will be housed is sent in the bolthole; Four, interior pipe racks there is an end of shutoff insert in the outer tube and withstands the anchoring agent, extract outer tube out in the bolthole then and promptly install.
Beneficial effect of the present invention: one, plastic bushing is made simple, the convenient and low price of material purchase.Two, the tube wall that plastic pipe is smooth has overcome the coarse shortcoming that powder stick is broken of anchor pole hole wall, and the quality of anchor pole has obtained reliable assurance.Three, simple to operate, installation rate is fast, efficiency of construction is high.Four, long more its superiority of anchor pole is obvious more.Five, workman's installation rate can double and alleviate labour intensity greatly, and is simultaneously reliable because of installation quality, significantly reduced the potential safety hazard that forms because of the artificial origin, thereby guaranteed constructor's safety.
Description of drawings
Fig. 1 is the structural representation of plastic bushing of the present invention, Fig. 2 is the schematic diagram of anchoring agent of packing in outer tube 1, Fig. 3 sends into schematic diagram in the bolthole 5 with outer tube 1 together with anchoring agent 4, and Fig. 4 is the schematic diagrames that outer tube 1 is extracted out in the bolthole 5, and Fig. 5 is the schematic diagram of anchoring agent 4 in bolthole 5.
The specific embodiment
The specific embodiment one: (referring to Fig. 1~Fig. 5) mounting method of present embodiment medicine volume anchor bar anchorage agent is realized according to the following steps: be that 39~41mm, wall thickness are that the pipe of plastic inner pipe 2 of 1.5~2.5mm is as outer tube 1 with external diameter one,, with external diameter is that 31~33mm, wall thickness are that the pipe of plastic inner pipe 2 of 1.5~2.5mm is as interior pipe 2, make outer tube 1 and interior pipe 2 form sleeve pipe, with the fixing upward shutoff 3 of an end of interior pipe 2; Two, anchoring agent 4 is sent in the outer tube 1 by volume; Three, the outer tube 1 that anchoring agent 4 will be housed is sent in the bolthole 5; Four, an end that interior pipe 2 is had a shutoff 3 inserts in the outer tube 1 and withstands anchoring agent 4, extracts outer tubes 1 out in the bolthole 5 then and promptly installs.
The specific embodiment two: the external diameter of present embodiment outer tube 1 is 40mm.
The specific embodiment three: the wall thickness of present embodiment outer tube 1 is 2mm.
The specific embodiment four: the external diameter of pipe 2 is 32mm in the present embodiment.
The specific embodiment five: the wall thickness of pipe 2 is 2mm in the present embodiment.
The specific embodiment six: the length of present embodiment outer tube 1 is greater than 45~55cm of bolthole 5 degree of depth.
The specific embodiment seven: the length of present embodiment outer tube 1 is greater than the 50cm of bolthole 5 degree of depth.
The specific embodiment eight: the length of pipe 2 is greater than 65~75cm of bolthole 5 degree of depth in the present embodiment.
The specific embodiment nine: the length of pipe 2 is greater than the 70cm of bolthole 5 degree of depth in the present embodiment.
Because the diameter of bolthole 5 is generally 42mm in the construction, the diameter of anchoring agent 4 (powder stick) is generally 32mm, the external diameter of selecting plastic outer tube 1 according to the diameter of bolthole 5 is 40mm, the diameter of plastic inner pipe 2 is 32mm, for making plastic bushing sturdy and durable, the thickness of plastic outer tube 1 and plastic inner pipe 2 is 2mm, determine the length of plastic pipe according to the degree of depth of bolthole 5, the length of plastic outer tube 1 is advisable with the 50cm that is slightly larger than bolthole 5 degree of depth, and the length of plastic inner pipe 2 is advisable with the 70cm that is slightly larger than bolthole 5 degree of depth and the sealing of the front end mouth of pipe.The material of described plastic outer tube 1 and plastic inner pipe 2 is polyvinyl chloride (PVC), polyethylene (PE) or polypropylene (PP).

Claims (10)

1. the mounting method of a medicine volume anchor bar anchorage agent, it is characterized in that: the mounting method of medicine volume anchor bar anchorage agent is realized according to the following steps: one, be that 39~41mm, wall thickness are that the plastic pipe of 1.5~2.5mm is as outer tube (1) with external diameter, with external diameter is that 31~33mm, wall thickness are that the plastic pipe of 1.5~2.5mm is as interior pipe (2), make outer tube (1) and interior pipe (2) form sleeve pipe, with the fixing upward shutoff (3) of an end of interior pipe (2); Two, anchoring agent (4) is sent in the outer tube (1) by volume; Three, the outer tube (1) that anchoring agent (4) will be housed is sent in the bolthole (5); Four, an end that interior pipe (2) is had a shutoff (3) inserts in the outer tube (1) and withstands anchoring agent (4), extracts outer tube (1) out in the bolthole (5) then and promptly installs.
2. the mounting method of medicine volume anchor bar anchorage agent according to claim 1, it is characterized in that: the external diameter of outer tube (1) is 40mm.
3. the mounting method of medicine volume anchor bar anchorage agent according to claim 2, it is characterized in that: the wall thickness of outer tube (1) is 2mm.
4. the mounting method of medicine volume anchor bar anchorage agent according to claim 3, it is characterized in that: the external diameter of interior pipe (2) is 32mm.
5. the mounting method of medicine volume anchor bar anchorage agent according to claim 4, it is characterized in that: the wall thickness of interior pipe (2) is 2mm.
6. the mounting method of medicine volume anchor bar anchorage agent according to claim 5, it is characterized in that: the length of outer tube (1) is greater than 45~55cm of bolthole (5) degree of depth.
7. the mounting method of medicine volume anchor bar anchorage agent according to claim 6, it is characterized in that: the length of outer tube (1) is greater than the 50cm of bolthole (5) degree of depth.
8. the mounting method of medicine volume anchor bar anchorage agent according to claim 7, it is characterized in that: the length of interior pipe (2) is greater than 65~75cm of bolthole (5) degree of depth.
9. the mounting method of medicine volume anchor bar anchorage agent according to claim 8, it is characterized in that: the length of interior pipe (2) is greater than the 70cm of bolthole (5) degree of depth.
10. according to the mounting method of the described medicine volume anchor bar anchorage agent of the arbitrary claim of claim 1~9, it is characterized in that: the material of described plastic outer tube (1) and plastic inner pipe (2) is polyvinyl chloride, polyethylene or polypropylene.
CN200810064250A 2008-04-07 2008-04-07 Method for installation of medicine volume anchor bar anchorage agent Active CN100588818C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810064250A CN100588818C (en) 2008-04-07 2008-04-07 Method for installation of medicine volume anchor bar anchorage agent

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810064250A CN100588818C (en) 2008-04-07 2008-04-07 Method for installation of medicine volume anchor bar anchorage agent

Publications (2)

Publication Number Publication Date
CN101250876A true CN101250876A (en) 2008-08-27
CN100588818C CN100588818C (en) 2010-02-10

Family

ID=39954459

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810064250A Active CN100588818C (en) 2008-04-07 2008-04-07 Method for installation of medicine volume anchor bar anchorage agent

Country Status (1)

Country Link
CN (1) CN100588818C (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587943A (en) * 2012-03-19 2012-07-18 河南理工大学 Method for quickly mounting capsule resin on separation area of top plate
CN102678144A (en) * 2012-05-31 2012-09-19 淮南矿业(集团)有限责任公司 Device employed to assist installation of anchoring agent
CN103032086A (en) * 2012-12-07 2013-04-10 中国矿业大学 Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
CN104695990A (en) * 2015-02-13 2015-06-10 中国矿业大学(北京) Integral push-lead type device and method for installation of tunnel anchor cable anchoring agent
CN104806279A (en) * 2015-05-12 2015-07-29 蒲长晏 Combined anchor rod

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587943A (en) * 2012-03-19 2012-07-18 河南理工大学 Method for quickly mounting capsule resin on separation area of top plate
CN102678144A (en) * 2012-05-31 2012-09-19 淮南矿业(集团)有限责任公司 Device employed to assist installation of anchoring agent
CN103032086A (en) * 2012-12-07 2013-04-10 中国矿业大学 Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
WO2014086297A1 (en) * 2012-12-07 2014-06-12 中国矿业大学 Resin cartridge filling method for roadway roof bolt drill hole
CN103032086B (en) * 2012-12-07 2015-04-29 中国矿业大学 Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
CN104695990A (en) * 2015-02-13 2015-06-10 中国矿业大学(北京) Integral push-lead type device and method for installation of tunnel anchor cable anchoring agent
CN104806279A (en) * 2015-05-12 2015-07-29 蒲长晏 Combined anchor rod

Also Published As

Publication number Publication date
CN100588818C (en) 2010-02-10

Similar Documents

Publication Publication Date Title
CN100588818C (en) Method for installation of medicine volume anchor bar anchorage agent
CN203756203U (en) Self-drilling type full-thread bolt grouting anchor rod
CN201180553Y (en) Slip casting anchor bar
CN202544883U (en) Self-boring full thread hollow grouting anchor rod
CN104405423A (en) Mining grouting anchor rope
CN110344867B (en) Early-anchored pipe cable anchor rod suitable for large-deformation stratum and construction method
CN203716999U (en) Self-advancing grouting anchor rod
CN203296186U (en) Blocking plug cap for tension screw reserved hole
CN201065643Y (en) Insert type pull rod formwork device
CN201401179Y (en) Reusable grouting plug for mine and underground water plugging
CN103032043A (en) Special hydraulic orifice sealer by orifice sealed grouting method
CN201991548U (en) Drainage, slag discharge and gas extraction integrated device
CN203515624U (en) Novel automatic grouting connector
ATE476558T1 (en) METHOD FOR SECURING RETAINING WALLS
CN106968247B (en) Expansion pressure-breaking type recyclable anchor rod and construction method thereof
CN210660155U (en) Grouting anchoring device and groutable solid anchor rod composed of same
CN204716265U (en) Anchor Agent pushes conduit and pusher
CN204357460U (en) A kind of hollow slip casting is without vertical rib resin anchor
CN102121495A (en) Mechanical anchor bolt with chemical agent
CN201963326U (en) Reusable underground support anchor rod
CN203928904U (en) A kind of Song Yin mechanism of wet method insertion-igniting machine
CN204435330U (en) The interim ecological bleeder pipe plugging system of a kind of water power hydraulic engineering
CN204174904U (en) Scaffold
CN204358180U (en) A kind of anchor pole check valve assembly
CN204001281U (en) A kind of cast-in-place framework and shear wall construction structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA RAILWAY BRIDGE BUREAU GROUP FOURTH ENGINEERI

Free format text: FORMER NAME: THE FOURTH ENGINEERING COMPANY OF CHINA RAILWAY NO.13 BUREAU GROUP

CP01 Change in the name or title of a patent holder

Address after: 150008 No. 459 Xianfeng Road, Daowai District, Heilongjiang, Harbin

Patentee after: Middle iron is built the 4th Engineering Co., Ltd of group of Bridge Project office

Address before: 150008 No. 459 Xianfeng Road, Daowai District, Heilongjiang, Harbin

Patentee before: The Fourth Engineering Co., Ltd. of China Railway 13 Civil