- CN101132620B CN101132620B CN2006101125796A CN200610112579A CN101132620B CN 101132620 B CN101132620 B CN 101132620B CN 2006101125796 A CN2006101125796 A CN 2006101125796A CN 200610112579 A CN200610112579 A CN 200610112579A CN 101132620 B CN101132620 B CN 101132620B
- Authority
- CN
- China
- Prior art keywords
- terminal
- radio
- radio link
- network controller
- radio network
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Mobile Radio Communication Systems (AREA)
Abstract
This invention provides a channel regulation method, which sets up a new radio link for a terminal in the process of setting up service load or increases a radio link for the terminal when resources above the physical layer is not changed and then the terminal communicates via said radio link, in which, activation time is not set any more, interaction messages is reduced in the process of Iub interface interaction to reduce time delay.
Description
Technical field
The present invention relates to the communications field, relate in particular to a kind of channel adjusting method.
Background technology
In mobile communication system, carry accordingly according to the terminal traffic type selecting, wherein in most cases adopt private resource to carry the business of terminal, as voice, data download, multimedia, stream business etc.In the maintenance process of terminal traffic, because the complexity of wireless environment is for the service quality (Qos, Quality of Service) that guarantees that terminal is applied for, usually need the link circuit resource of terminal traffic is adjusted accordingly, to guarantee the Qos of utilization ratio of wireless resources and terminal.
According to the characteristics of 3G communication, when terminal initial inserts, need and Radio Resource control (RRC, Radio Resource Control) connection that network side is set up its signaling of carrying.After the RRC of terminal connection was based upon on the dedicated channel (DCH, Dedicated Channel), this moment, terminal promptly was in the DCH state.Behind the associative operation of finishing authentication to this terminal, service request identification, the type of this requested service of terminal and Qos are clear and definite.In setting up the process of service bearer, be a reconfiguration course to original link.For the Radio Link of this terminal, after reshuffling, should can carry simultaneously the signaling and the business of this terminal, and the Radio Link during with its signaling of carrying is inconsistent.
Because above-mentioned Radio Link there are differences before and after reshuffling, so need aloft to go up, network side and terminal equipment should adopt this configuration simultaneously at some fixed time points, if the time point that both sides use is inconsistent, then must cause out of touch mutually, thereby cause communication disruption.Behind accessing terminal to network, in communication period, because the variation of business datum amount or the variation of wireless quality, Qos for save radio resources or assurance terminal, need carry out the quality adjustment to original Radio Link, also need the Radio Link of terminal is reshuffled, there is identical attribute in the Radio Link characteristic after reshuffling with Radio Link characteristic in the above-mentioned access procedure.
Characteristics of above-mentioned application are exactly that end is a designated cell, under the control of same base station (NodeB), because professional variation, carry out the adjustment of DCH-DCH, need reshuffle existing link layer, maintenance in order to communicate by letter simultaneously, the new link after reshuffling be interface termination equipment and network side use synchronously aloft.
In order to address the above problem, at present in the 3GPP agreement, realize by the method for using synchronized reconfiguration, introduce the notion of activationary time point usually, using new link at the same time simultaneously by activationary time point coordination terminal equipment and network side in the synchronized reconfiguration process.
In concrete wireless network environment, because its complexity and many existence through disturbing, the setting of activationary time point is an important factors.Figure one is the access procedure at certain terminal primary circuit territory of certain designated cell under certain specific base control, it is described in detail in the at present existing scheme, after the RRC of terminal in access procedure connection is based upon DCH, to set up in the process in follow-up business, the adjustment process of DCH-DCH is specific as follows:
101, terminal is when inserting, and network based certain strategy connects the RRC of this terminal and is based upon on the DCH;
102, after RRC connects foundation, terminal high level (layer three) by and core net (CN) alternately, at radio network controller (RNC, Radio Network Controller) and the interface between the CN (Iu interface) the Iu signaling of setting up this terminal connect, and connect in conjunction with the RRC of air interface, finish UE and CN alternately;
103, CN requires RNC to set up corresponding RAB for this terminal equipment again;
104 and 105, RNC sets up this professional Iu interface bearing of carrying according to the requirement of CN at the Iu interface;
106, RNC is according to the requirement of CN, and the interface (Iub interface) by RNC and base station (Node B) requires the Node B existing Radio Link of this terminal of interface synchronized reconfiguration aloft;
107, Node B is according to the requirement of RNC, prepare corresponding resource and carry out pre-configured, finish on request resource pre-configured after, to the RNC success response;
108 and 109, RNC sets up this professional Iub interface carrying of carrying at Iub interface;
110, RNC calculates the activationary time of this link according to certain strategy, at the appointed time puts by order notice NodeB and enables this link;
111, RNC notice terminal equipment is configured according to new requirement, comprises the characterisitic parameter of new bearer and the activationary time point of this link of use in this order;
112 and 113, after UE receives the configuration order of RNC, reply the affirmation information that data are correctly received to RNC, the requirement according to configuration order is configured then; After configuration is finished, judge whether the activationary time point in the configuration order arrives,, then wait for, after activationary time arrives, then switch in the new configuration and reply, and use the new row communication that is configured into to RNC answer configuration successful if activationary time does not arrive;
114 and 115, RNC confirms UE, and carries out success response to CN;
116, UE and CN carried out the mutual of other after carrying was set up and finished.
For after terminal traffic is set up, follow-up increase business, multi-service circumstances discharge a certain business down, or corresponding service is carried out the situation of DCH-DCH adjustment process, its principle is identical with figure one, the message of air interface can be according to the concrete parameter difference of adjusting, adopt different message, so do not repeat them here.
Yet there is following shortcoming in above-mentioned existing scheme:
1, need activationary time to coordinate RNC and UE uses new link simultaneously, because the complexity of wireless environment, the difference of terminal traffic, not of uniform size the causing of air interface institute message transfer, thus the propagation delay time of idle message is inconsistent, causes the activationary time difficult design;
If the design of 2 activationary time points is excessive, then when wireless environment was better, link configuration can not come into force after finishing, and caused call delay to increase; If the design of activationary time point is too small, when wireless environment was abominable, UE may not receive configuration order owing to disturbing, thereby causes communication disruption;
3, in order to carry out the design of activationary time point, RNC need measure the propagation delay time of UE and network, so as the computing activation time, the expense of increase system;
4, when being configured, need the pre-configured resource of Node B, according to the pre-configured time of computing activation as a result, notify Node B activationary time once more, the reciprocal process more complicated;
5, because the complexity of wireless environment, consider that different business can be inconsistent at the number of times of eating dishes without rice or wine to transmit re-transmission, at computing activation during the time, should be according to maximum retransmission and maximum data packet, come the computing activation time, thereby make that as a rule the time delay that continues that causes calling out increases, and reduces the susceptibility of terminal.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of channel adjusting method, can reduce the complexity of network, thereby improves system effectiveness and reliability.
The technical scheme that realizes the object of the invention is as follows:
A kind of channel adjusting method in setting up the process of service bearer, is the newly-built Radio Link of terminal, and terminal communicates by this Radio Link.
Preferably, first Radio Link, the radio network controller of setting up the Radio Resource control connection in the base station is after terminal is set up first interface bearing of bearer service, is the newly-built Radio Link of terminal according to following steps:
A, radio network controller are terminal distribution communication context sign and this terminal traffic, the required Radio Resource of signaling, and informing base station is set up second Radio Link;
B, base station send success response to radio network controller after finishing the foundation of second Radio Link, and radio network controller is set up second interface bearing of bearer service;
C, terminal are enabled the second Radio Link communication after finishing configuration according to the order that includes the second interface bearing characterisitic parameter of radio network controller immediately;
D, radio network controller and base station carry out discharging first Radio Link and first interface bearing alternately.
Preferably, after the newly-built Radio Link, radio network controller is only in the transmitting-receiving of the enterprising line data of first Radio Link.
Preferably, after the newly-built Radio Link, the radio network controller while is in the transmitting-receiving of the enterprising line data of first and second Radio Links.
A kind of channel adjusting method, in setting up the process of service bearer, when the above resource of physical layer remained unchanged, for terminal increases Radio Link, terminal communicated by this Radio Link.
Preferably, first Radio Link, the radio network controller of setting up the Radio Resource control connection in the base station is after terminal is set up first interface bearing of bearer service, is that terminal increases Radio Link according to following steps:
A, radio network controller are that terminal is adjusted physical resource, and informing base station increases by second Radio Link;
After the increase of second Radio Link is finished in B, base station, send success response to radio network controller;
C, terminal are enabled the second Radio Link communication after finishing configuration according to the order that includes physical layer configurations of radio network controller immediately;
D, radio network controller and base station carry out discharging first Radio Link alternately.
Preferably, increase after the Radio Link, radio network controller is only in the transmitting-receiving of the enterprising line data of first Radio Link.
Preferably, increase after the Radio Link, the radio network controller while is in the transmitting-receiving of the enterprising line data of first and second Radio Links.
Preferably, among the described step B, the base station also comprises after radio network controller sends success response: radio network controller is set up second interface bearing of this business of carrying; Among the described step D, discharge after first Radio Link, also comprise: radio network controller discharges first interface bearing of this terminal.
Compared with prior art, technical scheme provided by the invention has following beneficial effect:
1, in the DCH-DCH adjustment process, activationary time no longer is set, in Iub interface reciprocal process, reduce interaction message, make the time delay of whole handshaking procedure shorten; Also can avoid because activationary time
2, owing to be to activate immediately, thereby the current type of service of the layoutprocedure of making and terminal equipment has nothing to do, in case terminal equipment is received configuration order then enabled immediately, avoids disposing the time delay of generation to greatest extent, do not influence the time delay of reshuffling because of the complexity of wireless environment yet;
3, since RNC reshuffle finish before (that is to say old link deletion before), for the control signaling of terminal equipment at former link, new link sends simultaneously, the time point problem that does not exist new former link to use, thereby guarantee that the signaling of terminal before reshuffling can receive in old link, reshuffle finish after, terminal no longer receives the data of old link, can the efficient of reshuffling not exerted an influence too;
4, during reshuffling, descend signaling and data simultaneously on new link, the former link, only be simple copy, a realization easily at network side to identical downlink data.
Below in conjunction with the drawings and specific embodiments the present invention is further described.
Description of drawings
Fig. 1 is the adjustment process schematic diagram of prior art DCH-DCH;
Fig. 2 is the adjustment process schematic diagram of DCH-DCH of the present invention;
Fig. 3 is another embodiment process schematic diagram of adjustment of DCH-DCH of the present invention.
Embodiment
The present invention adopts a kind of new technical scheme, promptly in the adjustment process of DCH-DCH, adopt the mode that activates immediately, that is to say that UE is after receiving configuration order, after finishing configuration according to the requirement of configuration order, enable new configuration immediately and target Node B communicates.
For Node B, according to the requirement of 3GPP25.433 standard, in same Node B, only can there be a Node B communication context in identical terminal, and the present invention controls in the RNC side in order to defer to the requirement of 3GPP25.433 standard.
(such as setting up new business or adjusting terminal present rate etc.) adjudicated the resource in the sub-district by RNC when needs carry out the adjustment of DCH-DCH, under the situation that resource satisfies, for this terminal is distributed a new CRNC communication context in addition; Notify Node B the newly-built wireless links in sub-district under its control then, Node B is according to the newly assigned CRNC communication context of RNC, generate a new Node B communication context and this CRNC communication context correspondence at NodeB, this moment Node B and do not know that this Node B communication context is to be same Terminal Service, therefore, Node B can handle according to different terminals fully, and the differentiation of terminal is controlled in the RNC side.
When the Radio Link of Node B side set up finish after, RNC can be simultaneously in the transmitting-receiving of two enterprising line data of down link, also can be only in the transmitting-receiving of the original enterprising line data of link.
When RNC receive UE finish reply after, the Radio Link of this terminal before discharging DCH-DCH and adjusting, so far whole process is finished.
As shown in Figure 2, the specific implementation process is as follows:
201, terminal RNC when inserting connects the RRC of this terminal and is based upon on the DCH according to certain strategy;
202, after RRC connect to set up, terminal high level (layer 3) by and CN mutual, the Iu signaling of setting up this terminal at the Iu interface connects.And utilize the RRC of air interface to connect, finish the mutual of UE and CN;
203, CN requires RNC to set up corresponding RAB for this UE again;
204,205:RNC sets up this professional Iu interface bearing of carrying according to the requirement of CN at the Iu interface;
206, RNC is according to the requirement of CN, for this UE distributes new CRNC communication context sign and this terminal traffic, the needed Radio Resource of signaling, require then Node B aloft interface set up new Radio Link by this requirement;
207, Node B is according to the requirement of RNC, after the foundation of finishing Radio Link, to the RNC success response;
208 and 209, RNC sets up this professional Iub interface carrying of carrying at Iub interface;
210, RNC notice UE is configured according to new requirement, comprises the characterisitic parameter of new bearer in this order, requires terminal to use this link immediately simultaneously after finishing configuration;
211 and 212, after UE receives the configuration order of RNC, reply the affirmation information that data are correctly received to RNC, the requirement according to configuration order is configured then, after configuration is finished, enables new link immediately and uses the new row communication that is configured into;
213 and 214, RNC confirms UE, and carries out success response to CN;
215 and 216, RNC and Node B carry out alternately, discharge the Radio Link that original this terminal of carrying RRC connects;
217, UE and CN carried out the mutual of other after carrying was set up and finished;
218 and 219, RNC discharges old Iub interface carrying at Iub interface.
When the adjustment that needs DCH-DCH, (wherein the time slot adjustment is applicable to the TDD system as the adjustment of code channel adjustment, time slot adjustment or sub-district intercarrier, the carrier wave adjustment is applicable to the TD-SCDMA system) time, the above resource of physical layer remains unchanged before and after adjusting, the resource that only is physical layer needs to change, then can also adopt another kind of mode to realize: promptly by RNC the resource in the sub-district is adjudicated, under the situation that resource satisfies, the sub-district of notice Node B under its control increases by a wireless links.
When the newly-increased Radio Link of Node B side set up finish after, RNC can be simultaneously in the transmitting-receiving of two enterprising line data of down link, also can be only in the transmitting-receiving of the enterprising line data of former old link.
After RNC receives that finishing of UE replied, discharge the Radio Link that DCH-DCH adjusts preceding this terminal, so far whole process is finished.
As shown in Figure 3, the specific implementation process is as follows:
301, terminal is when inserting, and RNC is a terminal distribution DCH resource according to certain strategy;
302, RNC is according to triggerings such as measurement reports, determines to adjust physical resource (such as shared code channel or used time slot, used frequency etc.) into terminal;
303, RNC is according to the result of decision, is that this UE adjusts physical resource, require then Node B aloft interface by this requirements at the new Radio Link of former sub-district increase;
304, Node B is according to the requirement of RNC, after the increase of finishing Radio Link, to the RNC success response;
305 and 306, RNC can require to set up this professional Iub interface carrying of new carrying or continue to use original carrying at Iub interface;
307, RNC notice UE is configured according to new requirement, comprises new physical layer configurations in this order, requires terminal to use this link immediately simultaneously after finishing configuration;
308 and 309, after UE receives the configuration order of RNC, reply the affirmation information that data are correctly received to RNC, the requirement according to configuration order is configured then, after configuration is finished, enables new link immediately and uses the new row communication that is configured into;
310, RNC confirms UE;
311, UE uses new physical resource to communicate;
312 and 313, RNC and Node B carry out alternately, discharge the Radio Link that original this terminal of carrying RRC connects;
If 314 and 315 have set up new carrying at Iub interface in 305,306 steps, then need RNC to discharge old Iub interface carrying, otherwise this step is omitted at Iub interface.
Above-described embodiment of the present invention does not constitute the qualification to protection range of the present invention.Any any modification of being done within the spirit and principles in the present invention, be equal to and replace and improvement etc., all should be included within the claim protection range of the present invention.
Claims (7)
1. a channel adjusting method is characterized in that, in setting up the process of service bearer, is the newly-built Radio Link of terminal, and terminal communicates by this Radio Link;
Wherein, first Radio Link, the radio network controller of setting up the Radio Resource control connection in the base station is after terminal is set up first interface bearing of bearer service, is the newly-built Radio Link of terminal according to following steps:
A, radio network controller are terminal distribution communication context sign and this terminal traffic, the required Radio Resource of signaling, and informing base station is set up second Radio Link;
B, base station send success response to radio network controller after finishing the foundation of second Radio Link, and radio network controller is set up second interface bearing of bearer service;
C, terminal are enabled the second Radio Link communication after finishing configuration according to the order that includes the second interface bearing characterisitic parameter of radio network controller immediately;
D, radio network controller and base station carry out discharging first Radio Link and first interface bearing alternately.
2. the method for claim 1 is characterized in that, after the newly-built Radio Link, radio network controller is only in the transmitting-receiving of the enterprising line data of first Radio Link.
3. the method for claim 1 is characterized in that, after the newly-built Radio Link, the radio network controller while is in the transmitting-receiving of the enterprising line data of first and second Radio Links.
4. a channel adjusting method is characterized in that, in setting up the process of service bearer, when the above resource of physical layer remained unchanged, for terminal increases Radio Link, terminal communicated by this Radio Link;
Wherein, first Radio Link, the radio network controller of setting up the Radio Resource control connection in the base station is after terminal is set up first interface bearing of bearer service, is that terminal increases Radio Link according to following steps:
A, radio network controller are that terminal is adjusted physical resource, and informing base station increases by second Radio Link;
After the increase of second Radio Link is finished in B, base station, send success response to radio network controller;
C, terminal are enabled the second Radio Link communication after finishing configuration according to the order that includes physical layer configurations of radio network controller immediately;
D, radio network controller and base station carry out discharging first Radio Link alternately.
5. method as claimed in claim 4 is characterized in that, increases after the Radio Link, and radio network controller is only in the transmitting-receiving of the enterprising line data of first Radio Link.
6. method as claimed in claim 4 is characterized in that, increases after the Radio Link, and the radio network controller while is in the transmitting-receiving of the enterprising line data of first and second Radio Links.
7. method as claimed in claim 4 is characterized in that,
Among the described step B, the base station also comprises after radio network controller sends success response: radio network controller is set up second interface bearing of this business of carrying;
Among the described step D, discharge after first Radio Link, also comprise: radio network controller discharges first interface bearing of this terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2006101125796A CN101132620B (en) | 2006-08-23 | 2006-08-23 | Signal channel regulation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2006101125796A CN101132620B (en) | 2006-08-23 | 2006-08-23 | Signal channel regulation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101132620A CN101132620A (en) | 2008-02-27 |
CN101132620B true CN101132620B (en) | 2010-09-08 |
Family
ID=39129702
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2006101125796A Active CN101132620B (en) | 2006-08-23 | 2006-08-23 | Signal channel regulation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101132620B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1568039A (en) * | 2003-06-10 | 2005-01-19 | 大唐移动通信设备有限公司 | Method for implementing cell update or URA update between RNCs in mobile communication system |
CN1658542A (en) * | 2004-02-17 | 2005-08-24 | 华为技术有限公司 | Method for setting wireless access load |
CN1662091A (en) * | 2004-02-26 | 2005-08-31 | 大唐移动通信设备有限公司 | Method for switching users between different subzones implemented within same station |
CN1678115A (en) * | 2004-04-01 | 2005-10-05 | 大唐移动通信设备有限公司 | Relay switch-over method in TD-SCDMA mobile communication system |
-
2006
- 2006-08-23 CN CN2006101125796A patent/CN101132620B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1568039A (en) * | 2003-06-10 | 2005-01-19 | 大唐移动通信设备有限公司 | Method for implementing cell update or URA update between RNCs in mobile communication system |
CN1658542A (en) * | 2004-02-17 | 2005-08-24 | 华为技术有限公司 | Method for setting wireless access load |
CN1662091A (en) * | 2004-02-26 | 2005-08-31 | 大唐移动通信设备有限公司 | Method for switching users between different subzones implemented within same station |
CN1678115A (en) * | 2004-04-01 | 2005-10-05 | 大唐移动通信设备有限公司 | Relay switch-over method in TD-SCDMA mobile communication system |
Non-Patent Citations (3)
Title |
---|
3rd Generation Partnership Project * |
Technical SpecificationGroup Radio Access Network * |
UTRAN Iur Interface RadioNetwork Subsystem Application Part (RNSAP) signalling(Release 6).3GPP TS 25.423 v6.10.0.2006,3(254236100),69-72. * |
Also Published As
Publication number | Publication date |
---|---|
CN101132620A (en) | 2008-02-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101421946B (en) | Method and apparatus for performing uplink timing synchronization procedure upon handover in a mobile communications system | |
EP3328155B1 (en) | Method, base station, and user equipment for implementing carrier aggregation | |
CN103139764B (en) | Business scheduling method and device | |
CN103517355B (en) | Method for adjusting auxiliary primary cells and evolved NodeB | |
CN101010980B (en) | Methods and apparatus for inter-BSC soft handoff | |
CN101203034B (en) | Method, system and equipment for switching grouping switch in downward dual carrying / multi carrying transmission technique | |
CN104270764A (en) | Base station node resource allocating method, system and device | |
CN101064538B (en) | Power control method for time-division synchronous CDMA communication system | |
JP2012507228A (en) | Synchronization method between base stations, radio communication system, and base station | |
US9204491B2 (en) | Method of managing quality of service in a mobile radio system | |
CN101473691A (en) | User device, base station, and method in mobile communication system | |
CN101594274B (en) | Initial access method and transmission method of initial access signaling | |
CN101137198B (en) | Random access probe transmitting method and apparatus | |
CN101257374B (en) | Method and system for realizing parallel transmission of broadcast/multicasting service and special service | |
CN101132620B (en) | Signal channel regulation method | |
CN100417286C (en) | Updating method and device for high speed down shared channel service cell | |
CN106533937B (en) | A kind of distributed message forwarding method of multipath and base station | |
CN100382651C (en) | Method for realizing hard switching | |
CN1997215B (en) | Wireless communication system and its wireless resource management method | |
US20060056395A1 (en) | Handover for packet switched data | |
CN100389632C (en) | Wireless access network system and soft switching method thereof | |
CN101583081B (en) | Method, system and device for establishing synchronous bearing | |
CN107548166A (en) | Configure method, master base station, user equipment and the communication system of multi-link signaling | |
EP2157807A1 (en) | Method of network controller reporting on the cycle period ability of the maximal discontinuous transmission in a cell | |
CN106470448B (en) | Method and device for receiving signaling of base station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |