CN101085536B - Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete - Google Patents

Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete Download PDF

Info

Publication number
CN101085536B
CN101085536B CN2006100275442A CN200610027544A CN101085536B CN 101085536 B CN101085536 B CN 101085536B CN 2006100275442 A CN2006100275442 A CN 2006100275442A CN 200610027544 A CN200610027544 A CN 200610027544A CN 101085536 B CN101085536 B CN 101085536B
Authority
CN
China
Prior art keywords
concrete
steel pipe
thin
wall steel
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2006100275442A
Other languages
Chinese (zh)
Other versions
CN101085536A (en
Inventor
邰元
左广兴
黄波
谢运青
刘军
吕庆霞
孙树友
张鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI NO 20 METALLURGICAL CONCRETE COMPONENT CO Ltd
Original Assignee
SHANGHAI NO 20 METALLURGICAL CONCRETE COMPONENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI NO 20 METALLURGICAL CONCRETE COMPONENT CO Ltd filed Critical SHANGHAI NO 20 METALLURGICAL CONCRETE COMPONENT CO Ltd
Priority to CN2006100275442A priority Critical patent/CN101085536B/en
Publication of CN101085536A publication Critical patent/CN101085536A/en
Application granted granted Critical
Publication of CN101085536B publication Critical patent/CN101085536B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to the concrete thin wall steel tube centrifugal tube plug. It comprises the concrete blender, one end sealed thin wall steel tube, a casting table cart, blending the concrete material, selecting delivery pump car with output connected to a delivery pipe, setting the thin wall steel tube on the table cart to send steel tube to the inner cavity, blended concrete delivered to the thin wall steel tube inner cavity through the steel tube pump, casting the table car according to the casting direction of the concrete, till the opening of the steel tube to stop the delivery pump car, to the centrifugal forming of the thin wall steel tube. It is reduced in labor, and improved in efficiency.

Description

The method of pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete
Technical field
The present invention relates to the preparation method of building field piling, particularly a kind of method of pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete with the steel pipe pile tube.
Background technology
At present, many industry in coastal area and civil building all select the steel-pipe pile of overlength as the basis.Because the pile foundation consumption is very big, and exist because excavation of foundation pit causes bigger sidesway phenomenon, squeeze into penetration concrete method consolidation process behind the steel pipe pile tube if adopt, steel pipe must guarantee enough wall thickness, otherwise can be because of the excessive generation steel pipe of impact force yield phenomenon when squeezing into steel pipe.Pouring concrete in-situ also can be made troubles to construction simultaneously, raises the cost.Therefore people consider that employing placing concrete in steel pipe is a centrifugal tubular pile with concrete of thin-wall steel pipe through centrifugal forming again, this pile tube has the advantage of steel-pipe pile and concrete tubular pile, in the big ability of resistance that guarantees piling, anti-axial compression ability, counter-bending ability, and reduce material cost greatly.Yet irrigation method can not directly adopt the mold filling irrigation method of concrete tubular pile, in order to using the manual watering, wastes time and energy only.
Summary of the invention
Technical problem to be solved by this invention is big for existing steel pipe pile tube penetration concrete construction method labour intensity, and the time is long, and a kind of method of pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete is provided.The present invention utilizes pump concrete method pouring thin-wall steel tube, reduces labour intensity, enhances productivity.
The present invention utilizes following method to realize: a kind of method of pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete; The thin-wall steel tube that comprises the sealing of a concrete mixer and an end, described irrigation method also comprise a concrete pump truck and the pouring chassis that is made of platform truck and the punching block that is mounted thereon, and implement according to the following step:
A, corresponding concrete mixer is selected in designing requirement for use according to the tube pile structure concrete, so that the concrete material of wishing proportioning is stirred;
B selects the concrete pump truck that contains stationary pump for use according to production capacity, pile tube model, concrete strength, and connects a long carrier pipe at the delivery outlet of carrying pump truck;
C places the thin-wall steel tube level on the punching block of platform truck, and sliding platform makes conveying steel pipe enter its inner chamber from the openend of thin-wall steel tube;
D, to after stirring, enter the conveying pump truck from the mixer feed opening by satisfactory concrete, delivery pump handlebar concrete pours into the steel pipe inner chamber by the conveying steel pipe pump, the concrete slump that enters described delivery pump is 75~125mm, simultaneously synchronously by concrete casting direction walking pouring chassis, leave the thin-wall steel tube openend to conveying steel pipe, delivery pump stops to carry;
E, the thin-wall steel tube centrifugal forming that pouring is finished.
The described concrete pump truck of step B is electronic pulling type fixed pump.
Slurry has certain fluidity during for the assurance pouring, and the ready-mixed concrete time is not less than 120 seconds among the described step D.
For reducing the waste of concrete slurry, the amount of concrete that described step C goes into delivery pump is an every steel pipe pouring consumption.
Described centrifugal thickness of steel pipe 6mm.
The present invention utilizes dedicated pump and the straight delivering concrete slurry of carrier pipe, and mode of movement is carried for being interrupted, and steel pipe places on the punching block of chassis, and chassis is synchronous walking simultaneously, finishes pouring, can not only guarantee to water quality, and water velocity is faster than the manual watering.Owing to utilized special-purpose pump truck to carry slurry, operating personnel reduce 2/3rds; And need discontinuity feeding owing to change steel pipe, can calculate the concrete amount of each pouring, thereby cut the waste the concrete slurry.
The specific embodiment
Further provide the specific embodiment of the present invention below:
A kind of method of pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete; The thin-wall steel tube that comprises the sealing of a concrete mixer and an end, described irrigation method also comprise a concrete pump truck and the pouring chassis that is made of platform truck and the punching block that is mounted thereon, and implement according to the following step:
A, corresponding concrete mixer is selected in designing requirement for use according to the tube pile structure concrete, so that the concrete material of wishing proportioning is stirred;
B selects the concrete that contains stationary pump for use according to production capacity, pile tube model, concrete strength
C places the thin-wall steel tube level on the punching block of platform truck, and sliding platform makes conveying steel pipe enter its inner chamber from the openend of thin-wall steel tube;
D, to after stirring, enter the conveying pump truck from the mixer feed opening by satisfactory concrete, open and carry pump truck, concrete is poured into the steel pipe inner chamber by the conveying steel pipe pump, simultaneously synchronously by concrete casting direction walking pouring chassis, leave the thin-wall steel tube openend to conveying steel pipe, close the conveying pump truck simultaneously, stop slurry and carry;
E, with the thin-wall steel tube centrifugal forming that pouring finishes, described centrifugal thickness of steel pipe 6mm.
The described concrete pump truck of step B is electronic pulling type fixed pump.
Slurry has certain fluid ability to be full of centrifugal steel pipe inner chamber during for the assurance pouring, and the concrete mixing time is not less than 120 seconds among the described step D, and making the slump that enters the concrete slurry of carrying pump truck is 75~125mm.
For reducing the waste of concrete slurry, the amount of concrete that described step C goes into delivery pump is an every steel pipe pouring consumption.

Claims (5)

1. the method for a pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete; Comprise the thin-wall steel tube of a concrete mixer and end sealing, it is characterized in that described irrigation method also comprises a concrete pump truck and the pouring chassis that is made of platform truck and the punching block that is mounted thereon, and implement according to the following step:
A, corresponding concrete mixer is selected in designing requirement for use according to the tube pile structure concrete, so that the concrete material of wishing proportioning is stirred;
B selects the concrete pump truck that contains stationary pump for use according to production capacity, pile tube model, concrete strength, and connects a long carrier pipe at the delivery outlet of carrying pump truck;
C places the thin-wall steel tube level on the punching block of platform truck, and sliding platform makes conveying steel pipe enter its inner chamber from the openend of thin-wall steel tube;
D, to after stirring, enter the conveying pump truck from the mixer feed opening by satisfactory concrete, delivery pump handlebar concrete pours into the steel pipe inner chamber by the conveying steel pipe pump, the concrete slump that enters delivery pump is 75~125mm, simultaneously synchronously by concrete casting direction walking pouring chassis, leave the thin-wall steel tube openend to conveying steel pipe, delivery pump stops to carry;
E, the thin-wall steel tube centrifugal forming that pouring is finished.
2. the method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete according to claim 1 is characterized in that, the described concrete pump truck of step B is electronic pulling type fixed pump.
3. the method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete according to claim 1 and 2 is characterized in that, the ready-mixed concrete time is not less than 120 seconds among the described step D.
4. the method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete according to claim 1 and 2 is characterized in that, the amount of concrete of carrying pump truck that enters of described step C is an every steel pipe pouring consumption.
5. the method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete according to claim 1 and 2 is characterized in that, described centrifugal thickness of steel pipe 6mm.
CN2006100275442A 2006-06-10 2006-06-10 Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete Expired - Fee Related CN101085536B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2006100275442A CN101085536B (en) 2006-06-10 2006-06-10 Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2006100275442A CN101085536B (en) 2006-06-10 2006-06-10 Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete

Publications (2)

Publication Number Publication Date
CN101085536A CN101085536A (en) 2007-12-12
CN101085536B true CN101085536B (en) 2010-06-09

Family

ID=38936793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2006100275442A Expired - Fee Related CN101085536B (en) 2006-06-10 2006-06-10 Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete

Country Status (1)

Country Link
CN (1) CN101085536B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102172984B (en) * 2010-12-23 2013-03-20 上海中技桩业股份有限公司 Novel die assembly distribution system with reducing feed pipe and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87201968U (en) * 1987-02-11 1987-12-26 浙江省电力设计院 Steel pipe constructional element with a concrete layer inside by centrifuge shaping
CN86107082A (en) * 1986-10-10 1988-04-27 查理斯·H·诺伯 Centrifugal casting method, lined mold and casting
CN88101607A (en) * 1987-03-24 1988-10-19 帝国混凝土管株式会社 Concrete compound pipe and manufacture method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86107082A (en) * 1986-10-10 1988-04-27 查理斯·H·诺伯 Centrifugal casting method, lined mold and casting
CN87201968U (en) * 1987-02-11 1987-12-26 浙江省电力设计院 Steel pipe constructional element with a concrete layer inside by centrifuge shaping
CN88101607A (en) * 1987-03-24 1988-10-19 帝国混凝土管株式会社 Concrete compound pipe and manufacture method thereof

Also Published As

Publication number Publication date
CN101085536A (en) 2007-12-12

Similar Documents

Publication Publication Date Title
CN112372797A (en) Pouring device for producing concrete bricks
CN206874291U (en) One kind two serves as a contrast chute and enters modular system by window
CN101085536B (en) Method for pouring thin-wall steel pipe centrifugal concrete pipe pile by pumped concrete
CN211596739U (en) Grouting device for building construction
CN213330062U (en) Cement pouring equipment for building engineering
CN100564698C (en) A kind of cast-in-situ major diameter pipe pile concrete fast pouring device and job practices
CN218019336U (en) Concrete is with joining in marriage thick liquid device
CN209243525U (en) A kind of slip-form machine
CN202517594U (en) Stirring grouting equipment
CN108411740B (en) Concrete road surface casting machine is used in municipal works construction
CN201874242U (en) Quantitative foam concrete pouring machine
CN213088019U (en) Full-automatic two lining platform truck concrete placement systems
CN215442981U (en) Fluorgypsum self-leveling construction equipment
CN211306794U (en) Distributing device for producing concrete prestressed pipe piles
CN211143771U (en) Grouting machine
CN110787682B (en) Automatic configuration equipment for building putty
CN212425816U (en) Industrial sludge innocent treatment device
CN204976997U (en) Slip casting device and prefabricated component battery mould
CN209920206U (en) A concrete mixer for civil engineering
CN214749257U (en) Geotechnical test specimen mould
CN219138391U (en) Pump line export concrete transfer device
CN218878247U (en) Powder storage device is used in production of flow state solidified soil
CN214136640U (en) Building concrete mixing equipment
JPH10110531A (en) Concrete filling method in steel pipe concrete pole
CN217734886U (en) Convenient and fast's concrete mud jacking device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100609

CF01 Termination of patent right due to non-payment of annual fee