CN109898913A - A kind of double loop 500kV straight line, which bores, gets over tower - Google Patents

A kind of double loop 500kV straight line, which bores, gets over tower Download PDF

Info

Publication number
CN109898913A
CN109898913A CN201910090632.4A CN201910090632A CN109898913A CN 109898913 A CN109898913 A CN 109898913A CN 201910090632 A CN201910090632 A CN 201910090632A CN 109898913 A CN109898913 A CN 109898913A
Authority
CN
China
Prior art keywords
arm
conducting wire
tower
wire
cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910090632.4A
Other languages
Chinese (zh)
Inventor
张楷
赵贞欣
李志强
李红旭
李旭
韩斐
张亚龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Hebei Electric Survey And Design Research Institute Co Ltd
Original Assignee
China Electric Power Construction Group Hebei Electric Survey And Design Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Construction Group Hebei Electric Survey And Design Research Institute Co Ltd filed Critical China Electric Power Construction Group Hebei Electric Survey And Design Research Institute Co Ltd
Priority to CN201910090632.4A priority Critical patent/CN109898913A/en
Publication of CN109898913A publication Critical patent/CN109898913A/en
Pending legal-status Critical Current

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

It is bored the present invention relates to a kind of double loop 500kV straight line and gets over tower, belonged to power transmission engineering and bore more tower technology field.It further include being fixed at tower body top and upper cross-arm arranged up and down and lower cross-arm including tower body;The both ends setting ground wire hanging point of upper cross-arm simultaneously hangs ground wire, upper cross-arm both ends correspond to ground wire hanging point and the arm that has a down dip are arranged, the end setting side conducting wire hanging point and Pendent edge conducting wire of the arm that has a down dip, upper cross-arm is symmetrical arranged two insulator chains that lower end is connect with tower body intersection and the arm that has a down dip with upper cross-arm intersection, and two insulator chains are upper conducting wire hanging point and hang upper conducting wire;The both ends setting lower wire hanging point of lower cross-arm simultaneously hangs lower wire;Upper conducting wire, lower wire and side conducting wire are at rounded projections arranged.The present invention, which passes through, hangs conducting wire, lower wire and side conducting wire rounded projections arranged on every group, to reduce tower height on the whole.The sunk type of side conducting wire is hung, the height of ground wire is can reduce, is convenient for route and passes through.

Description

A kind of double loop 500kV straight line, which bores, gets over tower
Technical field
It is bored the present invention relates to a kind of double loop 500kV straight line and gets over tower, belonged to power transmission engineering and bore more tower technology field.
Background technique
With the formation of extra-high voltage rack, between extra-high voltage, between extra-high voltage and super-pressure scissors crossing gradually increase, 500kV route bores the case where getting over higher voltage grade route can be more and more.500kV and above line in most cases Road fails reserved 500kV and bores more channel, when 500kV route bores and gets over voltage levels route, can bring changing for drilled more route It makes, while the power failure of long period being brought to influence, voltage levels track remodelling is on the one hand costly, on the other hand to entire Power grid is affected.When route passes through, tangent tower and anchor support are often used, two kinds of tower effects are different, for tower Overall structure requires also different.The usage amount of tangent tower is more, but bores the height problem for getting over tower for straight line in the prior art And the solution that arrangements of conductors problem is no.
Summary of the invention
Getting over tower the object of the present invention is to provide a kind of double loop 500kV straight line brill to solve above-mentioned technical problem is 500kV double circuit line brill more provides dedicated tangent tower.
To achieve the goals above, the technical solution adopted by the present invention is that:
A kind of double loop 500kV straight line, which bores, gets over tower, including tower body, further includes being fixed at tower body top and arranged up and down Upper cross-arm and lower cross-arm;The both ends setting ground wire hanging point of upper cross-arm simultaneously hangs ground wire, and upper cross-arm both ends correspond to ground wire hanging point The arm that has a down dip is set, and the end setting side conducting wire hanging point of the arm that has a down dip simultaneously passes through insulator chain Pendent edge conducting wire, upper cross-arm and tower Body intersection and have a down dip arm and upper cross-arm intersection be upper conducting wire hanging point and be symmetrical arranged two insulator chains that lower end is connect, two A insulator chain interface point hangs upper conducting wire;The both ends of lower cross-arm are arranged lower wire hanging point and lead under being hung by insulator chain Line;Upper conducting wire, lower wire and side conducting wire are at rounded projections arranged.
Technical solution of the present invention further improvement lies in that: upper cross-arm and lower cross-arm are isosceles trapezoidal structure.
Technical solution of the present invention further improvement lies in that: the length of upper cross-arm is greater than the length of lower cross-arm.
Technical solution of the present invention further improvement lies in that: the both ends of upper cross-arm, the both ends of lower cross-arm and have a down dip The conducting wire hanging point of the end of arm is horn structure.
Technical solution of the present invention further improvement lies in that: upper the distance between cross-arm and lower cross-arm are 11.3m.
Technical solution of the present invention further improvement lies in that: the distance that the arm that has a down dip extends downwardly in vertical direction is 2.6m。
Technical solution of the present invention further improvement lies in that: ground wire hanging point lower than bore get over tower top.
By adopting the above-described technical solution, the technical effect that the present invention obtains has:
The present invention is that double loop straight line bores more tower, and there are two ground wire hanging points for setting to hang ground wire, and there are six conducting wire hanging points for setting To hang double back line conductor.By hanging conducting wire, lower wire and side conducting wire rounded projections arranged on every group, from reducing, steel tower is whole Body height 9.8m;The arrangements of conductors suspension of triangle simultaneously, can guarantee line security.
The present invention realizes the sunk type suspension of side conducting wire, in the case where guaranteeing that ground wire and side conductor spacing are certain, drop The low height of ground wire, to reduce whole tower height 2.6m.It can satisfy conductor spacing requirement simultaneously and grounded-line cooperation wanted It asks.
The present invention, which realizes whole tower height, reduces 12.4m, while whole tower steel consumption reduces by 11.2%.
Double back line conductor suspension arrangement setting of the invention rationally, it is more electric to can satisfy 500kV dual loop transmission line brill Gas gap condition, guarantees the general safety of transmission line of electricity, while avoiding the transformation of voltage levels route, has good economy Benefit and social benefit.
Detailed description of the invention
Fig. 1 is stereoscopic schematic diagram of the present invention;
Fig. 2 is main view of the present invention;
Wherein, 1, upper cross-arm, 2, lower cross-arm, 3, ground wire hanging point, 4, ground wire, 5, have a down dip arm, 6, side conducting wire hanging point, 7, side conducting wire, 8, insulator chain, 9, upper conducting wire hanging point, 10, upper conducting wire, 11, lower wire hanging point, 12, lower wire, 13, tower body.
Specific embodiment
With reference to the accompanying drawing and specific embodiment is described in further details the present invention:
It is bored the invention discloses a kind of double loop 500kV straight line and gets over tower, be that brill used in power transmission engineering gets over tower, it is outstanding which gets over tower It is suitable for 500kV double circuit lines.Here is specific embodiment:
The double loop 500kV straight line of the invention, which bores, gets over tower, specifically a kind of electric power pylon comprising tower body 13.The present invention Mainly the conducting wire suspended portion on 13 top of tower body is improved.It further includes being fixed at 13 top of tower body that the brill, which gets over tower, Upper cross-arm 1 and lower cross-arm 2.Upper cross-arm 1 and the arrangement setting of about 2 lower cross-arm, and upper cross-arm 1 is located at the most top of tower body 13 End.Common, the distance between upper cross-arm 1 and lower cross-arm 2 are 11.3m, and the suspension for upper conducting wire, lower wire and side conducting wire provides Safety and sufficient space.
Using the processing that has a down dip at side conducting wire hanging point of the invention, that is, the arm 5 that has a down dip is set.Preferentially, upper cross-arm 1 and the arm that has a down dip The distance between 5 be 2.6m, that is, the distance that arm 5 extends downwardly in vertical direction that has a down dip is 2.6m, significantly reduces entirety Tower height.
The present invention is arranged ground wire hanging point 3 at the both ends of upper cross-arm 1 and hangs ground wire 4, also corresponding at upper 1 both ends of cross-arm The arm 5 that has a down dip is arranged in ground wire hanging point 3.The arm 5 that has a down dip extends obliquely from the end of upper cross-arm 1.Have a down dip arm 5 end setting side Conducting wire hanging point 6 can reduce the height that the brill gets over tower entirety by 8 Pendent edge conducting wire 7 of insulator chain, the dipping type structure for the arm 5 that has a down dip Degree.The present invention is arranged upper conducting wire hanging point 9 with 13 intersection of tower body in upper cross-arm 1 and is hung with insulator chain 8, while the arm that will have a down dip 5 are also configured as conducting wire hanging point 9 and are hung with insulator chain 8 with upper 1 intersection of cross-arm.Above-mentioned two insulator chain 8 is symmetrically set It sets, and upper end connect lower end handover together with two upper conducting wire hanging points 9 and hangs upper conducting wire 10.Upper cross-arm 1 is located at tower body 13 two sides are respectively arranged with one group of insulator chain 8 and hang upper conducting wire 10.Upper conducting wire 10, lower wire 12 and side conducting wire 7 are logical It crosses insulator chain and bores what more tower was connect with straight line.It is specific as shown in Figure 1.
The present invention is arranged lower wire hanging point 11 at the both ends of lower cross-arm 2 and hangs lower wire 12 by insulator chain 8.This The brill of invention gets over upper conducting wire, the lower wire of upper conducting wire 10, lower wire 12 and the side conducting wire 7 of tower at rounded projections arranged, under the setting With side conducting wire under the premise of meeting electrical safety, the height at the top of tower body can reduce, realize that the brill of route is got over.It is specific such as to scheme 1, shown in Fig. 2.
As shown in Figure 1 and Figure 2, upper cross-arm 1 and lower cross-arm 2 are isosceles trapezoidal structure, and further, upper cross-arm 1 Length is greater than the length of lower cross-arm 2.The distance between upper cross-arm 1 and lower cross-arm 2 are 11.3m, which can satisfy conducting wire Suspension demand and demand for security.
For the present invention in specific implement, the hanging point part as conducting wire is horn structure, i.e., the both ends of upper cross-arm 1 The conducting wire hanging point of the end in portion, the both ends of lower cross-arm 2 and the arm 5 that has a down dip is horn structure.
As shown in Fig. 2, ground wire hanging point can effectively reduce the whole height for boring and getting over tower lower than the top for getting over tower is bored.
The present invention is that double loop straight line bores more tower, and there are two ground wire hanging points for setting to hang ground wire, and there are six conducting wires for setting Hanging point hangs double back line conductor.By hanging conducting wire, lower wire and side conducting wire rounded projections arranged on every group, from reduction iron Tower whole height 9.8m.
The present invention realizes the sunk type suspension of side conducting wire, in the case where guaranteeing that ground wire and side conductor spacing are certain, drop The low height of ground wire, to reduce whole tower height 2.6m.It can satisfy conductor spacing requirement simultaneously and grounded-line cooperation wanted It asks.
The present invention, which realizes whole tower height, reduces 12.4m, while whole tower steel consumption reduces by 11.2%.
The present invention is a kind of two circuit tangent tower, and the brill for route is got over, and improves the knot of cross-arm and lower cross-arm Structure and the hanging point for accordingly devising conducting wire are hung by conducting wire, lower wire and side conducting wire rounded projections arranged on every group of conducting wire, with And the sunk type suspension of side conducting wire, it effectively reduces straight line and bores the tower height for getting over tower, be convenient for passing through for route.
The present invention is that double loop straight line bores more tower, has two groups of conducting wires and two ground wires and at arranged symmetrically.The present invention In tangent tower the vertical direction pulling force of conducting wire is primarily subjected to when hanging conducting wire, upper conducting wire, lower wire and side conducting wire are set as Triangle suspension.The suspension setting of conducting wire and ground wire in the present invention, can make the whole stress of tangent tower more rationally balanced, and And it takes full advantage of straight line and bores the upper space for getting over tower.
Double back line conductor suspension arrangement setting of the invention is reasonable, the brill particularly suitable for 500kV dual loop transmission line More, it can satisfy 500kV dual loop transmission line and bore electric clearance condition of getting over, guarantee electrical safety;High voltage etc. is avoided simultaneously The transformation of grade route, with good economic efficiency and social benefit.

Claims (7)

1. a kind of double loop 500kV straight line, which bores, gets over tower, including tower body (13), it is characterised in that: further include being fixed at tower body (13) top and upper cross-arm arranged up and down (1) and lower cross-arm (2);Both ends setting ground wire hanging point (3) of upper cross-arm (1) is simultaneously It hangs ground wire (4), upper cross-arm (1) both ends correspond to ground wire hanging point (3) setting and have a down dip arm (5), and the end of the arm that has a down dip (5) is set It sets side conducting wire hanging point (6) and by insulator chain (8) Pendent edge conducting wire (7), upper cross-arm (1) and tower body (13) intersection and has a down dip Arm (5) and upper cross-arm (1) intersection be upper conducting wire hanging point (9) and be symmetrical arranged two insulator chains (8) that lower end is connect, two Insulator chain (8) interface point hangs upper conducting wire (10);Both ends setting lower wire hanging point (11) of lower cross-arm (2) simultaneously passes through insulation Substring hangs lower wire (12);Upper conducting wire (10), lower wire (12) and side conducting wire (7) are at rounded projections arranged.
2. a kind of double loop 500kV straight line according to claim 1, which bores, gets over tower, it is characterised in that: upper cross-arm (1) and lower cross Carrying on a shoulder pole (2) is isosceles trapezoidal structure.
3. according to claim 1 or a kind of 2 described in any item double loop 500kV straight lines bore and get over tower, it is characterised in that: upper cross-arm (1) length is greater than the length of lower cross-arm (2).
4. according to claim 1 or a kind of 2 described in any item double loop 500kV straight lines bore and get over tower, it is characterised in that: upper cross-arm (1) conducting wire hanging point of the end at the both ends and arm that has a down dip (5) at both ends, lower cross-arm (2) is horn structure.
5. according to claim 1 or a kind of 2 described in any item double loop 500kV straight lines bore and get over tower, it is characterised in that: upper cross-arm It (1) is 11.3m with the distance between lower cross-arm (2).
6. according to claim 1 or a kind of 2 described in any item double loop 500kV straight lines bore and get over tower, it is characterised in that: have a down dip arm (5) distance extended downwardly in vertical direction is 2.6m.
7. according to claim 1 or a kind of 2 described in any item double loop 500kV straight lines bore and get over tower, it is characterised in that: ground wire is hung Point (3) gets over the top of tower lower than boring.
CN201910090632.4A 2019-01-30 2019-01-30 A kind of double loop 500kV straight line, which bores, gets over tower Pending CN109898913A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910090632.4A CN109898913A (en) 2019-01-30 2019-01-30 A kind of double loop 500kV straight line, which bores, gets over tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910090632.4A CN109898913A (en) 2019-01-30 2019-01-30 A kind of double loop 500kV straight line, which bores, gets over tower

Publications (1)

Publication Number Publication Date
CN109898913A true CN109898913A (en) 2019-06-18

Family

ID=66944467

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910090632.4A Pending CN109898913A (en) 2019-01-30 2019-01-30 A kind of double loop 500kV straight line, which bores, gets over tower

Country Status (1)

Country Link
CN (1) CN109898913A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114301020A (en) * 2022-01-10 2022-04-08 中国能源建设集团山西省电力勘测设计院有限公司 Method for drilling 500kV high-voltage line through 220kV double-circuit transmission line
CN115347520A (en) * 2022-09-23 2022-11-15 福建永福电力设计股份有限公司 Six-loop tower overhead line cable leading-down structure and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201953131U (en) * 2011-01-21 2011-08-31 河北省电力勘测设计研究院 220kV one-tower double-loop straight corner penetrating tower
CN202651735U (en) * 2012-07-19 2013-01-02 安徽华电工程咨询设计有限公司 Asymmetric W-shaped wire jumper string double-circuit drilling tower
CN202882514U (en) * 2012-08-17 2013-04-17 岳阳电力勘测设计院有限公司 220-kilovolt all-angle single-circuit drilling cross tower
CN204552238U (en) * 2015-03-26 2015-08-12 中国能源建设集团安徽省电力设计院有限公司 A kind of wire is the compound cross-arm tangent tower that inverted triangle is arranged
CN204571441U (en) * 2015-04-10 2015-08-19 中国电力工程顾问集团中南电力设计院有限公司 Special superhigh voltage DC is with tower mixed pressure steel tower tower head
DE202015003671U1 (en) * 2015-05-22 2015-11-05 Cteam Consulting & Anlagenbau Gmbh mast
CN106639489A (en) * 2017-01-12 2017-05-10 中国能源建设集团天津电力设计院有限公司 500 kV large-angle ladder type ground wire single circuit penetrating-crossing tower
CN208347417U (en) * 2018-04-23 2019-01-08 国核电力规划设计研究院有限公司 A kind of composite material transmission line tangent tower

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201953131U (en) * 2011-01-21 2011-08-31 河北省电力勘测设计研究院 220kV one-tower double-loop straight corner penetrating tower
CN202651735U (en) * 2012-07-19 2013-01-02 安徽华电工程咨询设计有限公司 Asymmetric W-shaped wire jumper string double-circuit drilling tower
CN202882514U (en) * 2012-08-17 2013-04-17 岳阳电力勘测设计院有限公司 220-kilovolt all-angle single-circuit drilling cross tower
CN204552238U (en) * 2015-03-26 2015-08-12 中国能源建设集团安徽省电力设计院有限公司 A kind of wire is the compound cross-arm tangent tower that inverted triangle is arranged
CN204571441U (en) * 2015-04-10 2015-08-19 中国电力工程顾问集团中南电力设计院有限公司 Special superhigh voltage DC is with tower mixed pressure steel tower tower head
DE202015003671U1 (en) * 2015-05-22 2015-11-05 Cteam Consulting & Anlagenbau Gmbh mast
CN106639489A (en) * 2017-01-12 2017-05-10 中国能源建设集团天津电力设计院有限公司 500 kV large-angle ladder type ground wire single circuit penetrating-crossing tower
CN208347417U (en) * 2018-04-23 2019-01-08 国核电力规划设计研究院有限公司 A kind of composite material transmission line tangent tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114301020A (en) * 2022-01-10 2022-04-08 中国能源建设集团山西省电力勘测设计院有限公司 Method for drilling 500kV high-voltage line through 220kV double-circuit transmission line
CN115347520A (en) * 2022-09-23 2022-11-15 福建永福电力设计股份有限公司 Six-loop tower overhead line cable leading-down structure and method

Similar Documents

Publication Publication Date Title
CN105155908A (en) Heavy icing area alternating current strain tower in shape like Chinese character 'gan'
CN109898913A (en) A kind of double loop 500kV straight line, which bores, gets over tower
CN201953131U (en) 220kV one-tower double-loop straight corner penetrating tower
CN202810314U (en) 220kV T-shaped double-circuit drilling tower
CN207518244U (en) A kind of 220kV double backs overhead transmission line cable cut-offs bar
CN204552238U (en) A kind of wire is the compound cross-arm tangent tower that inverted triangle is arranged
CN206128808U (en) Novel single loop cable dead end tower
CN105155907A (en) Strain tower
CN201821070U (en) Double-circuit compact type angle tower with horizontally-wound and jumped jumper wire of transmission wire
CN208479112U (en) A kind of cable for built single time anchor support draws lower special pole
CN206551900U (en) A kind of electric railway arrangements of electric connection
CN206053502U (en) The pyramidal structure of ± 1100kV extra-high voltage direct-currents and 750kV ultrahigh-voltage alternating-currents circuit with tower
CN110374390A (en) A kind of 500 kilovolts of " non-" font conversion anchor supports for being arranged vertically double-loop compact
CN105155910B (en) A kind of single loop that string is combined using V-shape cut-offs steel pipe tower
CN207620484U (en) A kind of UHV transmission line suitable for Hexi Corridor Region, which bores, gets over tower
CN212614030U (en) Transmission line tangent tower of 500kV double-loop alternating current and +/-500 kV direct current common tower line
CN105735731B (en) A kind of double T connection steel pipe poles in double loop
CN203879087U (en) Extra-high-tension AC double-loop shared iron tower
CN102817489A (en) Double-tower-window double-loop linear tower
CN210768060U (en) Dry-type conversion strain tower for 500kV single-circuit compact line
CN203441149U (en) Double-loop triangle straight line steel pipe pole tower
CN209114954U (en) A kind of anchor support of limit for height area double-circuit line
CN203673897U (en) Suspension insulator string assembling system used for AC extra-high-voltage common-tower double circuit long-span transmission line
CN208473424U (en) A kind of bearing platform type narrow base tower for making somebody a mere figurehead under double-circuit line cable T joint draws
CN204850640U (en) With tower pair return circuits strain insulator tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190618