CN109722959A - A kind of Mine haul track laying equipment and its construction method - Google Patents
A kind of Mine haul track laying equipment and its construction method Download PDFInfo
- Publication number
- CN109722959A CN109722959A CN201811454485.6A CN201811454485A CN109722959A CN 109722959 A CN109722959 A CN 109722959A CN 201811454485 A CN201811454485 A CN 201811454485A CN 109722959 A CN109722959 A CN 109722959A
- Authority
- CN
- China
- Prior art keywords
- sleeper
- steel rail
- transport vehicle
- silo
- mine haul
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
The present invention proposes that a kind of Mine haul track laying equipment and its construction method, the equipment include transport vehicle, and the transport vehicle is equipped with tiling system, sleeper paving system, steel rail laying system and silo.The construction method includes the following steps: to utilize tiling system, the dregs of smooth tunnel bottom;Using sleeper paving system, sleeper is laid on the dregs of smooth mistake;Using steel rail laying system, by steel rail laying on sleeper;Using silo, slag charge is backfilled at sleeper, and using tiling system that slag charge is smooth.Advantages of the present invention: changing original form of construction work, innovates a kind of new construction method, reaches construction quickly, process is simple, economic, convenient, efficient purpose.
Description
Technical field
The present invention relates to shovel mountain production and constructions, particularly relate to a kind of Mine haul track laying equipment and its construction method.
Background technique
When existing Underground Metallic Mines rail interrupts track laying construction, mine is in economic consideration, drift section
General smaller, how as early as possible since drift section is smaller, construction space is limited, and large-scale construction machinery cannot be introduced into substantially,
It is laid with track, is the key point for determining quickly to go into operation.Currently, common scheme is the smooth of artificial progress tunnel, use is small-sized
Farm machinery or small handcart, material be transported to formulate position, then by manually carry out sleeper laying, after pass through other
Equipment re-lays rail or direct steel rail laying, after the backfill of ballast aggregate is carried out with flat car again, process is more, large labor intensity,
Construction efficiency is low.
Summary of the invention
The present invention proposes a kind of Mine haul track laying equipment and its construction method, solves artificial paving in the prior art
If the low problem of track large labor intensity, construction efficiency.
The technical scheme of the present invention is realized as follows: a kind of Mine haul track laying equipment, including transport vehicle, it is described
Transport vehicle be equipped with tiling system, sleeper paving system, steel rail laying system and silo.
Control transport vehicle, tiling system, sleeper paving system, steel rail laying system and object are additionally provided on the transport vehicle
The station of hopper.
The tiling system and sleeper paving system is located at the rear portion of transport vehicle, steel rail laying system, silo and behaviour
Make the front that platform is located at transport vehicle.
The transport vehicle includes front truck and rear car, and front truck is connect by linkwork with rear car, the system that tiles and sleeper
Paving system is located in rear car, and steel rail laying system, silo and station are located on front truck.
The transport vehicle is located on track.
The tiling system includes the waste and old scraper bowl of turning lifting.
The steel rail laying system includes suspension telescopic arm.
The silo includes stone bucket and Sha Dou, and stone bucket and Sha Doujun are connected to lower hopper.
The construction method of above-mentioned Mine haul track laying equipment, includes the following steps:
Utilize tiling system, the dregs of smooth tunnel bottom;
Using sleeper paving system, sleeper is laid on the dregs of smooth mistake;
Using steel rail laying system, by steel rail laying on sleeper;
Using silo, slag charge is backfilled at sleeper, and using tiling system that slag charge is smooth.
Advantages of the present invention: changing original form of construction work, innovates a kind of new construction method, reaches construction quickly,
Process is simple, economic, convenient, efficient purpose.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is grading roads schematic diagram of the present invention.
Fig. 2 is that the present invention lays railway sleepers schematic diagram.
Fig. 3 is steel rail laying schematic diagram of the present invention.
Fig. 4 is that slag charge of the present invention backfills schematic diagram.
In figure: 1- transport vehicle, 11- front truck, 12- rear car, 13- linkwork, 14- track, 2- tiling system, 21- dregs,
3- sleeper paving system, 31- sleeper, 4- steel rail laying system, 41- rail, 5- silo, 51- stone bucket, 52- sand bucket, under 53-
Material mouth, 54- slag charge, 6- station, the tunnel 7-.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under that premise of not paying creative labor
Embodiment shall fall within the protection scope of the present invention.
As shown in Figs 1-4, a kind of Mine haul track laying equipment, including transport vehicle 1, the transport vehicle 1 are equipped with
Tiling system 2, sleeper paving system 3, steel rail laying system 4, silo 5 and station 6.
The transport vehicle 1 is walked on track 14, including front truck 11 and rear car 12, front truck 11 by linkwork 13 with
Rear car 12 connects, and the system 2 that tiles and sleeper paving system 3 are located in rear car 12, steel rail laying system 4, silo 5 and station
6 are located on front truck 11.Transport vehicle is mainly the installation foundation of various pieces, and drives various pieces forward or front and back walking.
The tiling system 2 includes the waste and old scraper bowl of turning lifting.Waste and old scraper bowl is that the dress scrap build of waste and old shovel forms,
By cylinder, dipper-arm can take up waste and old scraper bowl lifting, and waste and old scraper bowl dipper-arm can be overturn relatively, to adjust as needed
Smooth height.Tiling system 2 carries out the dregs 21 of 7 bottom of tunnel or the slag charge slid down smooth.
The sleeper paving system 3 transfers the sleeper 31 on transport vehicle 1, and be laid on it is smooth after dregs on.
The steel rail laying system 4 includes suspension telescopic arm.The rail on telescopic arm crawl transport vehicle 1 is hung, and will
Steel rail laying is on sleeper.
The silo 5 includes that stone bucket 51 and Sha Dou 52, Shi Dou 51 and Sha Dou 52 are connected to lower hopper 53.Stone bucket 51
It is interior to be equipped with microlith, it is equipped with fine sand in Shi Dou 52, fine sand and microlith are mixed into slag charge 54 and slip out from lower hopper 53, carry out secondary slag charge
Backfill.
The station 6 controls transport vehicle 1, tiling system 2, sleeper paving system 3, steel rail laying system 4 and material
The working condition of bucket 5.
The construction method of above-mentioned Mine haul track laying equipment, includes the following steps:
A. tiling system, the dregs of smooth tunnel bottom are utilized;
B. sleeper paving system is utilized, sleeper is laid on the dregs of smooth mistake;
C. steel rail laying system is utilized, by steel rail laying on sleeper;
D. silo is utilized, slag charge is backfilled at sleeper, and is using tiling system that slag charge is smooth.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (9)
1. a kind of Mine haul track laying equipment, including transport vehicle (1), it is characterised in that: the transport vehicle (1) is equipped with
Tiling system (2), sleeper paving system (3), steel rail laying system (4) and silo (5).
2. Mine haul track laying equipment according to claim 1, it is characterised in that: on the transport vehicle (1) also
Equipped with control transport vehicle (1), tiling system (2), sleeper paving system (3), steel rail laying system (4) and silo (5) behaviour
Make platform (6).
3. Mine haul track laying equipment according to claim 2, it is characterised in that: the tiling system (2) and
Sleeper paving system (3) is located at the rear portion of transport vehicle (1), and steel rail laying system (4), silo (5) and station (6) are located at fortune
The front of defeated vehicle (1).
4. Mine haul track laying equipment according to claim 2 or 3, it is characterised in that: transport vehicle (1) packet
Front truck (11) and rear car (12) are included, front truck (11) is connect by linkwork (13) with rear car (12), and tile system (2) and sleeper
Paving system (3) is located on rear car (12), and steel rail laying system (4), silo (5) and station (6) are located on front truck (11).
5. Mine haul track laying equipment according to claim 1, it is characterised in that: the transport vehicle (1) is located at
On track (14).
6. Mine haul track laying equipment according to claim 1, it is characterised in that: tiling system (2) packet
Include the waste and old scraper bowl of turning lifting.
7. Mine haul track laying equipment according to claim 1, it is characterised in that: the steel rail laying system
It (4) include suspension telescopic arm.
8. Mine haul track laying equipment according to claim 1, it is characterised in that: the silo (5) includes
Shi Dou (51) He Shadou (52), Shi Dou (51) He Shadou (52) are connected to lower hopper (53).
9. the construction method of Mine haul track laying equipment according to any one of claims 1 to 7, which is characterized in that packet
Include following steps:
A. tiling system, the dregs of smooth tunnel bottom are utilized;
B. sleeper paving system is utilized, sleeper is laid on the dregs of smooth mistake;
C. steel rail laying system is utilized, by steel rail laying on sleeper;
D. silo is utilized, slag charge is backfilled at sleeper, and is using tiling system that slag charge is smooth.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811454485.6A CN109722959A (en) | 2018-11-30 | 2018-11-30 | A kind of Mine haul track laying equipment and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811454485.6A CN109722959A (en) | 2018-11-30 | 2018-11-30 | A kind of Mine haul track laying equipment and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109722959A true CN109722959A (en) | 2019-05-07 |
Family
ID=66295174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811454485.6A Pending CN109722959A (en) | 2018-11-30 | 2018-11-30 | A kind of Mine haul track laying equipment and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109722959A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110745475A (en) * | 2019-10-28 | 2020-02-04 | 攀钢集团矿业有限公司 | Construction method for ascending section of rock dumping machine in mine dump |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1055026A (en) * | 1990-03-21 | 1991-10-02 | 弗朗茨普拉瑟尔铁路机械工业有限公司 | Distribute the machinery of using with grading of ballast |
CN1172187A (en) * | 1996-06-04 | 1998-02-04 | 弗兰茨普拉塞铁路机械工业股份有限公司 | Machine for laying railway track |
CN1313430A (en) * | 1999-12-07 | 2001-09-19 | 弗兰茨普拉塞铁路机械工业股份有限公司 | Method and apparatus for laying rails |
EP1939354A2 (en) * | 2006-12-18 | 2008-07-02 | GSG Knape Gleissanierung GmbH | Method and device for manufacturing or renovation of a scrapped railway track |
CN103015277A (en) * | 2012-12-21 | 2013-04-03 | 中铁科工集团有限公司 | Long steel rail laying unit |
CN108774929A (en) * | 2018-07-04 | 2018-11-09 | 蒲菊清 | A kind of apparatus for leveling for railroad ballast |
-
2018
- 2018-11-30 CN CN201811454485.6A patent/CN109722959A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1055026A (en) * | 1990-03-21 | 1991-10-02 | 弗朗茨普拉瑟尔铁路机械工业有限公司 | Distribute the machinery of using with grading of ballast |
CN1172187A (en) * | 1996-06-04 | 1998-02-04 | 弗兰茨普拉塞铁路机械工业股份有限公司 | Machine for laying railway track |
CN1313430A (en) * | 1999-12-07 | 2001-09-19 | 弗兰茨普拉塞铁路机械工业股份有限公司 | Method and apparatus for laying rails |
EP1939354A2 (en) * | 2006-12-18 | 2008-07-02 | GSG Knape Gleissanierung GmbH | Method and device for manufacturing or renovation of a scrapped railway track |
CN103015277A (en) * | 2012-12-21 | 2013-04-03 | 中铁科工集团有限公司 | Long steel rail laying unit |
CN108774929A (en) * | 2018-07-04 | 2018-11-09 | 蒲菊清 | A kind of apparatus for leveling for railroad ballast |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110745475A (en) * | 2019-10-28 | 2020-02-04 | 攀钢集团矿业有限公司 | Construction method for ascending section of rock dumping machine in mine dump |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101949301B (en) | Unequal-strength bearing roadside filling body for gob-side entry retaining under coal mine | |
CN107725060B (en) | Subway tunnel construction method containing complex geology and without shield originating site | |
CN103470267A (en) | Long tunnel fast construction process | |
CN102071941B (en) | Fully mechanized mining gob-side entry retaining-based concrete block staggered joint longitudinal stacking wall forming method | |
CN106907177B (en) | A kind of girdle gob side entry retaining roadside packing method for protecting support | |
CN203296022U (en) | Sand gritter for channel | |
CN101915100B (en) | Loess-filling coal-mining method in a coal mine | |
CN109882239B (en) | Open-pit end slope coal-pressing radial filling mining method | |
CN105736045B (en) | A kind of the pocket type filling system and its placement method of control gob floor gushing water | |
CN103388478B (en) | Forming method for transportation road of bucket shovel applied to open pit coal mine | |
CN106702912A (en) | Construction method of dismantling old beam top and introducing new bridge on existing railway | |
CN110578532A (en) | Gob-side entry retaining arrangement method | |
CN106917634A (en) | The plant equipment and method of mine worked-out section mud backfill | |
CN109722959A (en) | A kind of Mine haul track laying equipment and its construction method | |
CN109505604B (en) | Slope ramp arrangement method applied to stope adopting upward layered filling mining method | |
CN107419760A (en) | A kind of new construction husky special forklift of sieve | |
CN208456610U (en) | A kind of open cut tunnel composite structure for tunnel portal section complicated geological | |
CN105971605A (en) | A non-waste mining method for underground mines | |
CN211115999U (en) | Rock mining device for penetrating through surrounding rock of broken zone | |
CN205503179U (en) | Pocket type filling system of control collecting space area bottom plate gushing water | |
CN208948162U (en) | Bucket elevator is used in coal ash autoclaved production | |
CN209780954U (en) | Coal face end triangular space filling device | |
US4400897A (en) | Method and railway train for draining a railway track | |
CN111364999A (en) | Replacement method for open pit coal mine end slope coal pressing mining and filling integration | |
CN110821508A (en) | Rock mining device and method for penetrating through surrounding rock of broken zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190507 |