[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN109652603A - Half pouring type blast funnace hot blast stove pipeline of one kind and its construction method - Google Patents

Half pouring type blast funnace hot blast stove pipeline of one kind and its construction method Download PDF

Info

Publication number
CN109652603A
CN109652603A CN201910086611.5A CN201910086611A CN109652603A CN 109652603 A CN109652603 A CN 109652603A CN 201910086611 A CN201910086611 A CN 201910086611A CN 109652603 A CN109652603 A CN 109652603A
Authority
CN
China
Prior art keywords
steel shell
layer
pouring
hot blast
blast stove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910086611.5A
Other languages
Chinese (zh)
Other versions
CN109652603B (en
Inventor
丛培源
刘会永
项冰
彭云涛
宛若峰
薛海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC WUHAN METALLURGICAL BUILDING RESEARCH INSTITUTE Co Ltd
Original Assignee
MCC WUHAN METALLURGICAL BUILDING RESEARCH INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC WUHAN METALLURGICAL BUILDING RESEARCH INSTITUTE Co Ltd filed Critical MCC WUHAN METALLURGICAL BUILDING RESEARCH INSTITUTE Co Ltd
Priority to CN201910086611.5A priority Critical patent/CN109652603B/en
Publication of CN109652603A publication Critical patent/CN109652603A/en
Application granted granted Critical
Publication of CN109652603B publication Critical patent/CN109652603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B9/00Stoves for heating the blast in blast furnaces
    • C21B9/10Other details, e.g. blast mains

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Blast Furnaces (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The invention discloses a kind of half pouring type blast funnace hot blast stove pipelines, including steel shell, steel shell to be made of upper steel shell and lower steel shell;It is equipped with masonry construction layer in lower steel shell, the cast bed of material of formed by integrally casting is equipped in the upper steel shell.The invention also discloses a kind of half pouring type blast funnace hot blast stove pipeline construction methods, including reserved pouring hole integral spray;Fibre felt layer, insulating brick-layer, working lining brick layer are successively laid in the sprayed coating surface of lower steel shell;Fibre felt layer is successively laid in the sprayed coating surface of upper steel shell;Install steel shell formwork for placing;Dilatation joint template is installed;Pouring construction etc..The invention has the benefit that pipeline of hot air furnace its underpart of the present invention liner uses traditional building materials and masonry way, upper inner liner uses castable one-time cast-forming, the gap in conventional pipelines structure can be reduced, the generation of weakness zone is avoided, can effectively avoid the top bricking often occurred in pipeline of hot air furnace use process from sinking, be broken phenomena such as even collapsing.

Description

Half pouring type blast funnace hot blast stove pipeline of one kind and its construction method
Technical field
The present invention relates to blast furnace corollary equipment technical fields, and in particular to a kind of half pouring type blast funnace hot blast stove pipeline and its Construction method.
Background technique
Blast furnace corollary equipment hot-blast stove is a kind of high-temperature high-pressure apparatus, and projected life is generally 20~30 years.With blast furnace The progress of ironmaking technology, Gao Fengwen, high wind pressure, high oxygen-enriched, big blowing operation system are used and are promoted more and more, hot wind Phenomena such as damaging problem of conduit upper liner is more and more frequent, deforms, ruptures often, falling brick, even collapse, causes heat Air piping top, which generates, alters the dangerous hidden danger such as wind gas leakage, hot-spot, rubescent deformation, or even occurs to burn the pernicious things such as explosion Therefore the safety in production of smelting iron and steel enterprise and the service life of hot-blast stove are seriously affected, have become restriction ironmaking development at present One of key factor.
Hot air duct damaging problem takes place frequently other than quality of materials and masonry quality, mainly by being influenced in structure, Traditional hot air pipe pipe lining brick ring is built, and structural gap is had between ring and ring, this gap is the weakness of hot air duct Region, and the connecting portions such as hot-blast outlet, junctions, using combination brick masonry, modular tile production technology is complicated, it is time-consuming and laborious, And the overall structure for building formation, often appearance contracting brick is not tight under the effect of various thermal stress, top modular tile loosens causes Situations such as altering wind, collapsing appearance.
Summary of the invention
It is an object of the present invention in view of the deficiencies of the prior art, it is high provide half stable pouring type of a kind of overall structure Furnace pipeline of hot air furnace and its construction method.
The technical solution adopted by the present invention are as follows: a kind of half pouring type blast funnace hot blast stove pipeline, including steel shell, steel shell is by setting up separately The upper steel shell of two sides and lower steel shell form above and below face in level;Masonry construction layer, the upper steel are equipped in the lower steel shell The cast bed of material of formed by integrally casting is equipped in shell.
According to the above scheme, it between cast bed of material and upper steel shell inner wall, has been sequentially arranged along steel shell radially outward direction Fibre felt layer and spray coating, that is, cast bed of material, fibre felt layer, spray coating and upper steel shell are set gradually.
According to the above scheme, it between masonry construction layer and lower steel shell inner wall, is sequentially arranged along steel shell radially outward direction There are fibre felt layer and spray coating.
According to the above scheme, the masonry construction layer includes the insulating brick-layer being close to fibre felt layer, and is layed in heat preservation The working lining brick layer on brick layer surface.
The invention discloses a kind of half pouring type blast funnace hot blast stove pipeline construction methods, comprising the following steps:
Step 1: reserving pouring hole after steel shell lifting welding, and in steel shell inner wall integral spray;
Step 2: the sprayed coating surface in lower steel shell is successively laid with fibre felt layer, insulating brick-layer, working lining brick layer;
Step 3: the sprayed coating surface in upper steel shell is successively laid with fibre felt layer;
Step 4: installing steel shell formwork for placing, is formed between formwork for placing and the inner wall of upper steel shell and pour chamber;
Step 5: installing dilatation joint template inside upper steel shell;
Step 6: pouring construction: intracavitary pouring castable from reserved pouring hole to pouring;
Step 7: sealing pouring hole after the completion of pouring;
Step 8: opening up gas vent exhaust, be in the milk seal vents.
According to the above scheme, in step 1, several anchoring pieces for being used to hang fibrofelt are set in steel shell inner wall, wherein upper steel The anchoring piece height of shell inner wall welding should exceed 20~40mm of spray coating, and staggered floor arranges.
According to the above scheme, in step 3, anchoring piece flattens after penetrating fibre felt layer, make fibre felt layer in steel shell with Spray coating is in close contact.
According to the above scheme, in step 4, the erection method of upper steel shell formwork for placing are as follows: set up in pipeline using flitch Rice font falsework, falsework top are laid with three-ply board, are formed between three-ply board and upper steel shell inner wall and closed pour chamber.
According to the above scheme, axial at interval of the reserved ㄣ font dilatation joint of 6~8m along steel shell.
According to the above scheme, in step 8, a gas vent is reserved at interval of 4~6m in the axial direction at the top of steel shell, And high-temperature resistant ball valve is installed.
The invention has the benefit that
1. pipeline of hot air furnace its underpart of the present invention liner uses traditional building materials and masonry way, upper inner liner Using castable one-time cast-forming, pipeline of hot air furnace structure is simplified, reduces the gap in conventional pipelines structure, avoids The generation of weakness zone can effectively solve the problem that the top bricking often occurred in pipeline of hot air furnace use process is sunk, is broken very To phenomena such as collapsing;
2. the group that pipeline of hot air furnace of the present invention can reduce the positions such as junctions, hot-blast outlet on pipeline of hot air furnace The use for closing brick, is greatly lowered difficulty of construction and material cost;
3. the present invention is separated hot air duct castable liner with furnace shell using fibrofelt, it still is able to ensure that furnace shell heat expansion is cold The deformation of contracting does not influence the overall structure of hot air duct under high temperature;
4. structure of the invention design is rationally, easy for construction.
Detailed description of the invention
Fig. 1 is the configuration schematic diagram of pipeline of hot air furnace.
Fig. 2 is the structural schematic diagram of a specific embodiment of the invention.
Fig. 3 is the sectional schematic diagram of the present embodiment.
Fig. 4 is the formwork for placing scheme of installation of the present embodiment.
Wherein: 1, upper steel shell;2, fibre felt layer;3, spray coating;4, insulating brick-layer;5, working lining brick layer;6, cast bed of material; 7, lower steel shell;8, pouring hole;9, expansion joint;10, dilatation joint;11, falsework;12, three-ply board.
Specific embodiment
For a better understanding of the present invention, the present invention is further described in the following with reference to the drawings and specific embodiments.
Pipeline of hot air furnace is connected to hot-blast stove, and configuration is as shown in Figure 1.Half pouring type blast furnace of one kind as shown in Figures 2 and 3 Pipeline of hot air furnace, including steel shell, steel shell are formed by being divided into level the upper steel shell 1 of two sides and lower steel shell 7 above and below face;Under described It is equipped with masonry construction layer in steel shell 7, the cast bed of material 6 of formed by integrally casting is equipped in the upper steel shell 1.
Preferably, between 1 inner wall of cast bed of material 6 and upper steel shell, fibre has been sequentially arranged along steel shell radially outward direction Carpet veneer 2 and spray coating 3 are tieed up, that is, cast bed of material 6, fibre felt layer 2, spray coating 3 and upper steel shell 1 are set gradually.
Preferably, between masonry construction layer and lower 7 inner wall of steel shell, fibre has been sequentially arranged along steel shell radially outward direction Tie up carpet veneer 2 and spray coating 3;The masonry construction layer includes the insulating brick-layer 4 (for light structures) being close to fibre felt layer 2, with And it is layed in the working lining brick layer 5 (for heavy structure) on 4 surface of insulating brick-layer, that is, working lining brick layer 5, insulating brick-layer 4, fibre Dimension carpet veneer 2, spray coating 3 and lower steel shell 7 are set gradually.
In the present invention, after the completion of pipeline of hot air furnace steel shell erecting and welding, face in the level of steel shell (namely steel shell is horizontal Horizontal plane where orient diameter) it is used as line of demarcation, lower 7 liner of steel shell uses traditional building materials and masonry way, by outer It inwardly (radially inwardly from steel shell) include spray coating 3, fibre felt layer 2, insulating brick-layer 4, working lining brick layer 5 etc.;Lower steel 7 liner of shell replaces light-weight insulating brick and heavy working lining brick using castable, and integrated poured molding, ecto-entad is (from steel shell diameter To inward direction) it include spray coating 3, fibre felt layer 2, cast bed of material 6.
A kind of half pouring type blast funnace hot blast stove pipeline construction method, comprising the following steps:
Step 1: reserving pouring hole 8 after steel shell lifting welding, and several anchoring pieces and integral spray are set in steel shell inner wall: Anchoring piece is welded in steel shell inner wall and mostly V-shaped structure, wherein the anchoring piece height of upper 1 inner wall of steel shell welding should be beyond spraying 3 20~40mm of surface of layer, staggered floor arranges (400~500mm of interlamellar spacing), for hanging fibrofelt;
Step 2: 3 surface of spray coating in lower steel shell 7 is successively laid with fibre felt layer 2, insulating brick-layer 4, working lining brick layer 5;
Step 3: 3 surface of spray coating in upper steel shell 1 is successively laid with fibre felt layer 2;After anchoring piece penetrates fibre felt layer 2 It flattens, it is ensured that fibre felt layer 2 and spray coating 3 in upper steel shell 1 are in close contact, and reuse thin tied silk connection anchoring element anchoring fiber Felt;
Step 4: installing 1 formwork for placing of steel shell: as shown in figure 4, setting up the mould of meter font in pipeline using flitch etc. Board mount 11,11 top of falsework are laid with three-ply board 12, between 1 inner wall of three-ply board 12 and upper steel shell (specifically and fibrofelt Layer 2 between) formed pour chamber;Ensure that template is solid and compact, not material leakage when castable is poured;
Step 5: installation dilatation joint template: upper 1 liner of steel shell is poured using castable, axial at interval of 6~8m along steel shell Dilatation joint 10 (10 optimum of ㄣ font dilatation joint in actual production) need to be reserved, as shown in Figure 3;Added using 2 blocks of three-ply boards 12 The fibrofelt of 10mm long is set to position and the fixation that need to reserve dilatation joint 10 after being fabricated to dilatation joint template, it is desirable that dilatation joint template Top connects with the fibre felt layer 2 in upper steel shell 1, and dilatation joint template bottom is connected with the formwork for placing set up, and installs swollen The position of expansion joint (E.J.) template will avoid the privileged sites such as expansion joint for pipeline 9, junctions, can be provided with plug hole position;
Step 6: pouring construction: using colloidal sol combination mullite pouring material, poured from the reserved upward steel shell 1 of pouring hole 8 It builds;Colloidal sol combination mullite pouring material has the characteristics that medium temperature intensity is high, thermal shock resistance is excellent, exempts from baking;
Step 7: after the completion of pouring, welded seal pouring hole 8;
Step 8: opening up gas vent and mounting ball valve: in the axial direction at interval of the reserved row of 4~6m at the top of steel shell Stomata installs high-temperature resistant ball valve;Exhaust is closed after the completion of exhaust, and pipeline of hot air furnace after a period of use, is filled as grout hole Slurry sealing.
Finally it should be noted that these are only the preferred embodiment of the present invention, it is not intended to restrict the invention, although Referring to embodiment, invention is explained in detail, for those skilled in the art, still can be to aforementioned Technical solution documented by each embodiment is modified or equivalent replacement of some of the technical features, but it is all Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on should be included in protection of the invention Within the scope of.

Claims (10)

1. a kind of half pouring type blast funnace hot blast stove pipeline, which is characterized in that including steel shell, steel shell is by being divided into level above and below face The upper steel shell of two sides and lower steel shell composition;It is equipped with masonry construction layer in the lower steel shell, is equipped in the upper steel shell and integrally pours The cast bed of material built.
2. half pouring type blast funnace hot blast stove pipeline as described in claim 1, which is characterized in that in cast bed of material and upper steel shell Between wall, be sequentially arranged fibre felt layer and spray coating along steel shell radially outward direction, that is, cast bed of material, fibre felt layer, Spray coating and upper steel shell are set gradually.
3. half pouring type blast funnace hot blast stove pipeline as described in claim 1, which is characterized in that in masonry construction layer and lower steel shell Between inner wall, fibre felt layer and spray coating have been sequentially arranged along steel shell radially outward direction.
4. half pouring type blast funnace hot blast stove pipeline as claimed in claim 3, which is characterized in that the masonry construction layer include with The insulating brick-layer that fibre felt layer is close to, and it is layed in the working lining brick layer on insulating brick-layer surface.
5. a kind of half pouring type blast funnace hot blast stove pipeline construction method, which comprises the following steps:
Step 1: reserving pouring hole after steel shell lifting welding, and in steel shell inner wall integral spray;
Step 2: the sprayed coating surface in lower steel shell is successively laid with fibre felt layer, insulating brick-layer, working lining brick layer;
Step 3: the sprayed coating surface in upper steel shell is successively laid with fibre felt layer;
Step 4: installing steel shell formwork for placing, is formed between formwork for placing and the inner wall of upper steel shell and pour chamber;
Step 5: installing dilatation joint template inside upper steel shell;
Step 6: pouring construction: intracavitary pouring castable from reserved pouring hole to pouring;
Step 7: sealing pouring hole after the completion of pouring;
Step 8: opening up gas vent exhaust, be in the milk seal vents.
6. half pouring type blast funnace hot blast stove pipeline construction method as stated in claim 5, which is characterized in that in step 1, Steel shell inner wall sets several anchoring pieces for being used to hang fibrofelt, wherein the anchoring piece height of upper steel shell inner wall welding should be beyond spraying 20~40mm of layer, and staggered floor arranges.
7. the half pouring type blast funnace hot blast stove pipeline construction method as shown in claim 6, which is characterized in that in step 3, anchor Firmware flattens after penetrating fibre felt layer, is in close contact fibre felt layer and spray coating in steel shell.
8. half pouring type blast funnace hot blast stove pipeline construction method as stated in claim 5, which is characterized in that in step 4, on The erection method of steel shell formwork for placing are as follows: set up a meter font falsework in pipeline using flitch, falsework top is laid with Three-ply board forms between three-ply board and upper steel shell inner wall and closed pours chamber.
9. half pouring type blast funnace hot blast stove pipeline construction method as stated in claim 5, which is characterized in that along steel shell axially every A ㄣ font dilatation joint is reserved every 6~8m.
10. half pouring type blast funnace hot blast stove pipeline construction method as stated in claim 5, which is characterized in that in step 8, A gas vent is reserved at interval of 4~6m in the axial direction at the top of steel shell, and high-temperature resistant ball valve is installed.
CN201910086611.5A 2019-01-29 2019-01-29 Semi-pouring type blast furnace hot blast stove pipeline and construction method thereof Active CN109652603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910086611.5A CN109652603B (en) 2019-01-29 2019-01-29 Semi-pouring type blast furnace hot blast stove pipeline and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910086611.5A CN109652603B (en) 2019-01-29 2019-01-29 Semi-pouring type blast furnace hot blast stove pipeline and construction method thereof

Publications (2)

Publication Number Publication Date
CN109652603A true CN109652603A (en) 2019-04-19
CN109652603B CN109652603B (en) 2021-01-15

Family

ID=66122267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910086611.5A Active CN109652603B (en) 2019-01-29 2019-01-29 Semi-pouring type blast furnace hot blast stove pipeline and construction method thereof

Country Status (1)

Country Link
CN (1) CN109652603B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110791605A (en) * 2019-11-05 2020-02-14 中冶武汉冶金建筑研究院有限公司 Method for preparing pipeline of blast furnace hot blast stove
CN110986591A (en) * 2019-11-22 2020-04-10 柳州钢铁股份有限公司 Masonry repair method with refractory material on the back of suspended cylinder of Maerz kiln
CN114058760A (en) * 2021-11-15 2022-02-18 攀钢集团工程技术有限公司 Method for quickly replacing local hot air pipeline on hot air pipe of blast furnace

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102381869A (en) * 2011-07-22 2012-03-21 郑州京华耐火材料实业有限公司 Integrally-cast blast furnace hot-blast pipeline
CN108193010A (en) * 2018-03-09 2018-06-22 中冶京诚工程技术有限公司 Lining masonry structure of hot-air pipeline and lining masonry structure of three-fork of hot-air pipeline

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102381869A (en) * 2011-07-22 2012-03-21 郑州京华耐火材料实业有限公司 Integrally-cast blast furnace hot-blast pipeline
CN108193010A (en) * 2018-03-09 2018-06-22 中冶京诚工程技术有限公司 Lining masonry structure of hot-air pipeline and lining masonry structure of three-fork of hot-air pipeline

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110791605A (en) * 2019-11-05 2020-02-14 中冶武汉冶金建筑研究院有限公司 Method for preparing pipeline of blast furnace hot blast stove
CN110986591A (en) * 2019-11-22 2020-04-10 柳州钢铁股份有限公司 Masonry repair method with refractory material on the back of suspended cylinder of Maerz kiln
CN114058760A (en) * 2021-11-15 2022-02-18 攀钢集团工程技术有限公司 Method for quickly replacing local hot air pipeline on hot air pipe of blast furnace

Also Published As

Publication number Publication date
CN109652603B (en) 2021-01-15

Similar Documents

Publication Publication Date Title
CN109652603A (en) Half pouring type blast funnace hot blast stove pipeline of one kind and its construction method
CN102424872A (en) Method for repairing damaged blast furnace hot air pipeline lining in thermal state
CN103276130B (en) Maintenance method for air leakage from pipeline of hot-air system of blast furnace
CN100578127C (en) Spherical arch roof of fluidized roaster and its forming method
CN203866244U (en) Dry coke quenching furnace
CN104271774A (en) Structure for tuyere section in blast furnace
CN202730166U (en) Hot air outlet structure of hot-blast stove
CN102183148A (en) Process for repairing thermal insulating layer in a pipeline of heating furnace
CN206330432U (en) It is a kind of to eliminate the process structure that Mialz lime kiln runs wind
CN206328338U (en) A kind of coke dry quenching furnace saliva seal structure
CN110791605A (en) Method for preparing pipeline of blast furnace hot blast stove
CN103788966A (en) A CDQ high temperature resistant expansion joint
CN101851692B (en) Construction method for curing non-aqueous slurry at normal temperature in blast furnace
CN205066457U (en) Inside lining is pour to whole injection
CN114058760B (en) Method for quickly replacing local hot air pipeline on hot air pipe of blast furnace
CN103805723B (en) Blast-furnace hot-air pipeline transposition section refractory brick comes off quick prosthetic appliance and method
CN207316903U (en) Improved Ou Ye stoves coal powder injection steam stove
CN210711606U (en) Blast furnace hot blast stove furnace base leaks out and restores structure
CN206052075U (en) A kind of masonry construction of RH dip pipes steel construction and liner tile
CN212293413U (en) Novel coke oven ascending pipe
CN203866243U (en) High-temperature-resistant expansion joint for dry quenching
CN107782148A (en) Combustion furnace manhole lining masonry structure and masonry method
CN219689759U (en) Top combustion type hot air outlet damage repair structure of hot air furnace
CN110656213A (en) A blast furnace hot blast stove base air leakage repair structure and construction method thereof
CN102003878B (en) Kiln head square tube and manufacturing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant