CN109629856A - A kind of container house and its installation method using closed corridor - Google Patents
A kind of container house and its installation method using closed corridor Download PDFInfo
- Publication number
- CN109629856A CN109629856A CN201810893796.6A CN201810893796A CN109629856A CN 109629856 A CN109629856 A CN 109629856A CN 201810893796 A CN201810893796 A CN 201810893796A CN 109629856 A CN109629856 A CN 109629856A
- Authority
- CN
- China
- Prior art keywords
- corridor
- plate
- module
- middle layer
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims description 16
- 238000000034 method Methods 0.000 title claims description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 238000009415 formwork Methods 0.000 claims description 3
- 238000010586 diagram Methods 0.000 description 9
- 238000010276 construction Methods 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 5
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005194 fractionation Methods 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 238000003475 lamination Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H1/00—Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
- E04H1/12—Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/343—Structures characterised by movable, separable, or collapsible parts, e.g. for transport
- E04B1/34315—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H1/00—Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
- E04H1/12—Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
- E04H2001/1283—Small buildings of the ISO containers type
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
A kind of container house using closed corridor, including main tank module and corridor box module, corridor box module are made of corridor board group part and corridor structure column assembly;Corridor board group part includes corridor module one, corridor module two, bottom corridor plate, middle layer corridor plate and top layer corridor plate, and corridor structure column assembly includes corridor structural column one and corridor structural column two;Bottom corridor plate is connect by connector with main body tank module, and it is connected between bottom corridor plate and one end of middle layer corridor plate by corridor structural column one, the other end of middle layer corridor plate is connect with main body tank module, and the other end of middle layer corridor plate is connect by corridor structural column two with one end of top layer corridor plate, the other end of top layer corridor plate is connect with main body tank module;Corridor module one and corridor module two are separately connected between bottom corridor plate and middle layer corridor plate, between middle layer corridor plate and top layer corridor plate.The container house entirety reasonable stress, overall stability are high.
Description
Technical field
The invention belongs to steel structure modularization technical field of buildings, are related to a kind of container house using closed corridor
And its installation method.
Background technique
Container house uses modular design concept and production technology, and a room tank module has been made in factory
At on-site hoisting landing can be used alone, and can also form spacious use space and lamination by various combination, extensively
For the office in construction site, meeting room, dining room and toilet etc..
Currently, when the room case group in construction site uses closed corridor, it is general to use Production Office case respectively and walk
Then corridor case carries out the method for assembly connection at the scene.
This method has the following disadvantages:
1, case equipment installation in corridor is few, using simple, is still made of container body, expensive, increases cost.
2, it needs to increase connecting angle pieces using being reliably connected between corridor cabinet and office box body junction and cabinet
Material investment.
3, cabinet is at high cost in factory's production, whole Transporting.
Summary of the invention:
The purpose of the present invention is overcoming above-mentioned the deficiencies in the prior art, and provide a kind of using closed corridor
Container house, the container house entirety reasonable stress, overall stability are high.
It is a further object of the present invention to provide the installation methods of the above-mentioned container house using closed corridor.
As above design, the technical scheme is that a kind of container house using closed corridor, including main box
Module and corridor box module, it is characterised in that: corridor box module is made of corridor board group part and corridor structure column assembly;It walks
Corridor board group part includes corridor module one, corridor module two, bottom corridor plate, middle layer corridor plate and top layer corridor plate, corridor structure
Column assembly includes corridor structural column one and corridor structural column two;Bottom corridor plate is connected by connector and main body tank module
It connects, and is connected between bottom corridor plate and one end of middle layer corridor plate by corridor structural column one, the other end of middle layer corridor plate
It is connect with main body tank module, and the other end of middle layer corridor plate is connect by corridor structural column two with one end of top layer corridor plate,
The other end of top layer corridor plate is connect with main body tank module;Between bottom corridor plate and middle layer corridor plate, middle layer corridor plate and top
It is separately connected corridor module one and corridor module two between the plate of layer corridor, corridor module one is placed in corridor most end bay, corridor module
Two are placed in the middle part of corridor.
Above-mentioned corridor module one includes that the corridor plate that the Vierendeel girder being made of four channel steels, two corner fittings form and two walk
Corridor structural column.
Above-mentioned corridor module two includes the corridor plate and a corridor that the frame being made of four channel steels, a corner fittings form
Structural column.
It is added on the outside of above-mentioned corridor box module and is stably connected with plate.
Above-mentioned corridor structural column one and two both ends of corridor structural column are equipped with column bottom positioning pin.
A kind of installation method of above-mentioned container house using closed corridor, characterized by the following steps:
1. after the installation for completing main body tank module at the scene, bottom corridor plate one end is passed through connector and main body tank module
It is installed;
2. by the column bottom positioning pin at one both ends of corridor structural column by the other end of bottom corridor plate and middle layer corridor plate
One end connection, the other end of middle layer corridor plate are installed by connector and main body tank module, form bottom corridor box body formwork
Block;
3. in bottom corridor, the fast outside of box body formwork, which is added, is stably connected with plate, then by corridor module one and corridor module two into
Row connection;
4. middle layer corridor plate is connect by the column bottom positioning pin by two both ends of corridor structural column with one end of top layer corridor plate,
The other end of top layer corridor plate is installed by connector and main body tank module, forms top layer corridor box module;
5. being added on the outside of the box module of top layer corridor and being stably connected with plate, corridor module one and corridor module two are connected
It connects;
6. last laying floor layer and installation corridor door and window, the closed corridor of container house are completed.
The present invention has the advantage that and good effect:
1, the present invention can be installed on corridor intraoral illumination pipeline in adjacent main tank module, to realize that corridor cabinet is not set
The purpose of pipeline.
2, corridor box module is split into corridor board group part and corridor structural column by the present invention, and corridor board group part includes corridor
Module one, corridor module two, bottom corridor plate, middle layer corridor plate and top layer corridor plate, corridor structural column include corridor structural column
One and corridor structural column two, transport to scene is installed.After the installation for completing main body case, corridor cabinet steel column angle is not used
The connection method of part and main body case corner fittings, and directly realized and connected with main tank module by bolt, and connecting node is both safe
It is reliable and convenient and efficient, construction efficiency is greatly improved, while meeting the requirement of construction precision.
3, the present invention can finally add on the outside of the box module of corridor is stably connected with plate, makes whole reasonable stress, guarantees knot
The overall stability of structure.
4, present invention production is more standardized, and construction production is simple.Compared to the knot that room tank module in corridor saves about 2/3
The cost of structure column and one layer of corridor roof box, and transportation cost substantially reduces after the fractionation of corridor box module.
Detailed description of the invention:
Fig. 1 is the schematic diagram that main tank module is connected with corridor cabinet;
Fig. 2 is the a-a sectional view of Fig. 1;
Fig. 3 is the b-b sectional view of Fig. 1;
Fig. 4 is the schematic diagram of corridor module one;
Fig. 5 is the schematic diagram of corridor module two;
Fig. 6 is the schematic diagram of corridor structural column one;
Fig. 7 is the schematic diagram of corridor structural column two;
Fig. 8 is bottom corridor plate and main body case module connection diagram, wherein Fig. 8-1 is the portion the A enlarged drawing of Fig. 8, figure
8-2 is that a-a sectional view, the 8-3 of Fig. 8-1 are the b-b sectional views of Fig. 8-1;
Fig. 9 is the schematic diagram that corridor structural column one is connect with bottom corridor plate and middle layer corridor plate, wherein Fig. 9-1 is Fig. 9
The portion B enlarged drawing, Fig. 9-2 be that c-c sectional view, the 9-3 of Fig. 9-1 are the d-d sectional views of Fig. 9-1;
Figure 10 is the schematic diagram after being attached corridor module one and corridor module two after connection middle layer corridor plate,
In, Figure 10-1 is the portion the C enlarged drawing of Figure 10;
Figure 11 is the schematic diagram that corridor structural column two is connect with middle layer corridor plate with top layer corridor plate, wherein Figure 11-1 is
The portion D enlarged drawing, Figure 11-2 of Figure 11 is that e-e sectional view, the 11-3 of Figure 11-1 are the f-f sectional views of Figure 11-1;
Figure 12 is after connection after the plate of top layer corridor, then the signal after corridor module one and corridor module two are attached
Figure, wherein Figure 12-1 is the portion E enlarged drawing.
In figure: 1-main body tank module;2-corridor modules one;3-corridor modules two;4-bottom corridor board group parts one;
5-middle layer corridor board group parts two;6-top layer corridor board group parts three;7-corridor structural columns one;8-corridor structural columns two;9,
10-are stably connected with plate.
Specific embodiment:
It is as shown in Figure 1, 2, 3: a kind of container house using closed corridor, including main tank module and corridor cabinet
Module, it is characterised in that: corridor box module is made of corridor board group part and corridor structure column assembly;Corridor board group part includes walking
Corridor module one, corridor module two, bottom corridor plate, middle layer corridor plate and top layer corridor plate, corridor structure column assembly includes corridor
Structural column one and corridor structural column two;Bottom corridor plate is connect by connector with main body tank module, and bottom corridor plate
It is connected between one end of middle layer corridor plate by corridor structural column one, the other end and main body tank module of middle layer corridor plate connect
Connect, and the other end of middle layer corridor plate is connect by corridor structural column two with one end of top layer corridor plate, top layer corridor plate it is another
One end is connect with main body tank module;Divide between bottom corridor plate and middle layer corridor plate, between middle layer corridor plate and top layer corridor plate
Not Lian Jie corridor module one and corridor module two, corridor module one is placed in corridor most end bay, and corridor module two is placed in the middle part of corridor.
The corridor module is divided into two kinds, as shown in Figure 4;Corridor module 1 includes the frame being made of four channel steels
The corridor board group part and two corridor structural columns that beam, two corner fittings form, are used for corridor most end bay.It is as shown in Figure 5: corridor module
23 include the corridor board group part and a corridor structural column that the Vierendeel girder being made of four channel steels, a corner fittings form, and is used for away
Remaining of corridor in addition to most end bay across.
It is as shown in Figure 6,7: for corridor structural column 1 and corridor structural column 28, made according to different layers high request factory,
Containing two newel post's bottom positioning pins.
The installation method of the container house using closed corridor is:
1, as shown in Figure 8;After the installation for completing main body tank module 1 at the scene, plate 4 one end in bottom corridor is passed through into connecting plate
It is installed with bolt and main body tank module;
2, as shown in Figure 9: by the column bottom positioning pin at one 7 both ends of corridor structural column by the other end of bottom corridor plate 4 and
One end of middle layer corridor plate 5 connects, and the other end of middle layer corridor plate 5 is pacified by connector with bolt and main body tank module 1
Dress forms corridor box module;
3, as shown in Figure 10: being added on the outside of the box module of corridor and be stably connected with plate, by corridor module 1 and corridor module
23 are attached, while guaranteeing the overall stability of structure;
4, as shown in figure 11: by the column bottom positioning pin at 28 both ends of corridor structural column by middle layer corridor plate 5 and top layer corridor
One end of plate 6 connects, and the other end of top layer corridor plate 6 is installed by bolt with main body tank module 1, forms top layer corridor case
Module;
5, as shown in figure 12: being added on the outside of the box module of top layer corridor and be stably connected with plate, by corridor module 1 and corridor
Module 23 is attached, while guaranteeing the overall stability of structure.
6, last laying floor layer and installation corridor door and window, the closed corridor of container house are completed.
Claims (6)
1. a kind of container house using closed corridor, including main tank module and corridor box module, it is characterised in that:
Corridor box module is made of corridor board group part and corridor structure column assembly;Corridor board group part includes corridor module one, corridor mould
Block two, bottom corridor plate, middle layer corridor plate and top layer corridor plate, corridor structure column assembly include corridor structural column one and corridor knot
Structure column two;Bottom corridor plate is connect by connector with main body tank module, and the one of bottom corridor plate and middle layer corridor plate
It being connected between end by corridor structural column one, the other end of middle layer corridor plate is connect with main body tank module, and middle layer corridor plate
The other end is connect by corridor structural column two with one end of top layer corridor plate, and the other end and main body tank module of top layer corridor plate connect
It connects;One and of corridor module is separately connected between bottom corridor plate and middle layer corridor plate, between middle layer corridor plate and top layer corridor plate
Corridor module two, corridor module one are placed in corridor most end bay, and corridor module two is placed in the middle part of corridor.
2. a kind of container house using closed corridor according to claim 1, it is characterised in that: the corridor mould
Block one includes the corridor plate and two corridor structural columns that the Vierendeel girder being made of four channel steels, two corner fittings form.
3. a kind of container house using closed corridor according to claim 1, it is characterised in that: the corridor mould
Block two includes the corridor plate and a corridor structural column that the frame being made of four channel steels, a corner fittings form.
4. a kind of container house using closed corridor according to claim 1, it is characterised in that: the corridor case
It is added on the outside of module and is stably connected with plate.
5. a kind of container house using closed corridor according to claim 1, it is characterised in that: the corridor knot
Structure column one and two both ends of corridor structural column are equipped with column bottom positioning pin.
6. a kind of installation method of the container house using closed corridor a kind of according to claim 1, feature exist
In: include the following steps:
1. after the installation for completing main body tank module at the scene, bottom corridor plate one end is carried out by connector and main body tank module
Installation;
2. by the column bottom positioning pin at one both ends of corridor structural column by one end of the other end of bottom corridor plate and middle layer corridor plate
Connection, the other end of middle layer corridor plate are installed by connector and main body tank module, form bottom corridor box module;
3. in bottom corridor, the fast outside of box body formwork, which is added, is stably connected with plate, then corridor module one and corridor module two are connected
It connects;
4. middle layer corridor plate is connect by the column bottom positioning pin by two both ends of corridor structural column with one end of top layer corridor plate, top layer
The other end of corridor plate is installed by connector and main body tank module, forms top layer corridor box module;
5. being added on the outside of the box module of top layer corridor and being stably connected with plate, corridor module one and corridor module two are attached;
6. last laying floor layer and installation corridor door and window, the closed corridor of container house are completed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810893796.6A CN109629856A (en) | 2018-08-08 | 2018-08-08 | A kind of container house and its installation method using closed corridor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810893796.6A CN109629856A (en) | 2018-08-08 | 2018-08-08 | A kind of container house and its installation method using closed corridor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109629856A true CN109629856A (en) | 2019-04-16 |
Family
ID=66066244
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810893796.6A Pending CN109629856A (en) | 2018-08-08 | 2018-08-08 | A kind of container house and its installation method using closed corridor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109629856A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104712150A (en) * | 2013-12-12 | 2015-06-17 | 扬州通利冷藏集装箱有限公司 | Outdoor corridor and transportation method thereof |
CN205024835U (en) * | 2015-08-28 | 2016-02-10 | 中建八局第三建设有限公司 | Box movable board house in built -in corridor |
KR101644921B1 (en) * | 2016-02-01 | 2016-08-03 | 빌드윈 주식회사 | Construction methods of joining two or more container houses along their long sides |
CN206888595U (en) * | 2017-07-13 | 2018-01-16 | 惠州惠集特种装备制造有限公司 | A kind of loose mail transports field assembled house box |
CN109025381A (en) * | 2018-07-25 | 2018-12-18 | 中冶天工集团有限公司 | A kind of container house and its installation method using closed corridor |
-
2018
- 2018-08-08 CN CN201810893796.6A patent/CN109629856A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104712150A (en) * | 2013-12-12 | 2015-06-17 | 扬州通利冷藏集装箱有限公司 | Outdoor corridor and transportation method thereof |
CN205024835U (en) * | 2015-08-28 | 2016-02-10 | 中建八局第三建设有限公司 | Box movable board house in built -in corridor |
KR101644921B1 (en) * | 2016-02-01 | 2016-08-03 | 빌드윈 주식회사 | Construction methods of joining two or more container houses along their long sides |
CN206888595U (en) * | 2017-07-13 | 2018-01-16 | 惠州惠集特种装备制造有限公司 | A kind of loose mail transports field assembled house box |
CN109025381A (en) * | 2018-07-25 | 2018-12-18 | 中冶天工集团有限公司 | A kind of container house and its installation method using closed corridor |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104755678B (en) | Modular building | |
US6651393B2 (en) | Construction system for manufactured housing units | |
CN102216539B (en) | Unitised building system | |
US10947720B2 (en) | Block construction of prefabricated buildings | |
CN204627053U (en) | A kind of multiple field steel work ITS | |
US20070163184A1 (en) | Transportable modular building and method of constructing thereof | |
CN102003082B (en) | Combined box-type house and mounting method thereof | |
HU221798B1 (en) | Prefabricated building systems | |
CN206667479U (en) | A kind of modular combination prefabricated house | |
CN108560725A (en) | A kind of container house column and panel wall system | |
CN106677349A (en) | Modularly combined trailer coach and building method | |
CN110306674A (en) | Adjustable ganglionic layer high modularization steel construction SOHO building system and construction method | |
CN106628012A (en) | Modularized ship cabin and manufacturing and installing method thereof | |
CN109183988A (en) | A kind of profile steel house and construction method | |
CN107905385A (en) | The assembled arthitecutral structure and method of construction that steel construction is combined with concrete structure | |
CN109025381A (en) | A kind of container house and its installation method using closed corridor | |
CN106193402B (en) | Girder truss integrated form flooring module and its installation method | |
CN211622838U (en) | Three-layer modularization fire station | |
CN109629856A (en) | A kind of container house and its installation method using closed corridor | |
CN113863499A (en) | Connecting structure of end frame and member | |
CN103866859A (en) | Multi-layer moving combined house | |
KR102099018B1 (en) | Method for building of modular structure using construction module | |
CN209482473U (en) | A kind of sliceable building block and movable building | |
CN106759853B (en) | Structure and heat preservation integrated assembly type box-type structure system and construction method thereof | |
CN211622837U (en) | Two-layer modular fire station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190416 |
|
RJ01 | Rejection of invention patent application after publication |