CN109607989A - A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge - Google Patents

A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge Download PDF

Info

Publication number
CN109607989A
CN109607989A CN201811533744.4A CN201811533744A CN109607989A CN 109607989 A CN109607989 A CN 109607989A CN 201811533744 A CN201811533744 A CN 201811533744A CN 109607989 A CN109607989 A CN 109607989A
Authority
CN
China
Prior art keywords
sludge
primary
dewatered sludge
level
dewatered
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811533744.4A
Other languages
Chinese (zh)
Inventor
张�浩
李方志
刘新立
刘波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Military Environmental Protection Ltd By Share Ltd
Original Assignee
Hunan Military Environmental Protection Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Military Environmental Protection Ltd By Share Ltd filed Critical Hunan Military Environmental Protection Ltd By Share Ltd
Priority to CN201811533744.4A priority Critical patent/CN109607989A/en
Publication of CN109607989A publication Critical patent/CN109607989A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F11/00Treatment of sludge; Devices therefor
    • C02F11/008Sludge treatment by fixation or solidification

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Treatment Of Sludge (AREA)

Abstract

The invention discloses a kind of methods that collaboration solidifies dewatered sludge Yu primary sludge, include the following steps: S1, are stirred, and carry out primary solidification primary sludge and middle sand, solidification auxiliary material progress level-one, obtain primary solidification sludge;S2, primary solidification sludge is stirred with through broken dewatered sludge progress second level, and carries out collaboration solidification, obtain solidification sludge.The invention also discloses the systems that a kind of collaboration solidifies dewatered sludge Yu primary sludge.Method high treating effect of the invention, is easily promoted, is at low cost simple process, can be used for scale processing, and system structure is simple, at low cost, easy to operate, high treating effect.

Description

A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge
Technical field
The present invention relates to the sides that technical field of sludge treatment more particularly to a kind of collaboration solidify dewatered sludge Yu primary sludge Method and system.
Background technique
Municipal sludge is a kind of biomass relic that municipal sewage plant generates in sewage disposal process, moisture content High, complicated components.If a large amount of municipal sludges do not deal carefully with disposition, environment will be caused seriously to pollute.
It is required according to specific resistance to filtration " four change ", current municipal sludge processing technique mainly includes sanitary landfills, anaerobism Digestion, aerobic compost, anhydration and incineration etc., (minimizing degree is 60% in sludge reduction for " anaerobic digestion+deep dehydration " technology More than), recycling (recycling sludge in biomass energy), innoxious (killing harmful pathogen) and stabilize (generate stablize it is rotten Grow matter) etc. have greater advantage, be one of the sludge treatment technique of current international mainstream, in recent years at home also quickly it is emerging It rises and applies.Sludge anhydration burning technology there are costs of investment it is big, operating cost is high the problems such as;Product after aerobic compost exists The problems such as market space is limited, environmental safety, presently, there are many limitations.Therefore, current municipal sludge disposition is final Whereabouts is still to enter landfill yard after processing to dispose.
If municipal sludge directly adds curing agent and auxiliary material solidification, index of correlation to may conform to the sludge shale mark into landfill yard Standard, but this technique cannot achieve " minimizing, innoxious, stabilisation, recycling " requirement of specific resistance to filtration.
The dehydration equipment type that country's anaerobic digestion project digested sludge uses at present is mainly plate and frame filter press, and sludge is adopted Can be degraded organic matter in sludge, recycling biomass energy with Anaerobic Digestion, after through frame dehydration can greatly reduce dirt Mud volume effectively realizes " minimizing, innoxious, the stabilisation, recycling " of specific resistance to filtration.It needs to be added in dehydration The quenched medicaments such as a certain amount of PAM, coagulant (organic or inorganic), while certain content of organic matter is still remained in dewatered sludge (20% or more) causes dewatered sludge to have elasticity, water imbibition, and dewatered sludge organic matter is higher, PAM dosage is more, which gets over Obviously.After sludge frame dehydration moisture content can be down to 60% hereinafter, but simple physical extrusion dehydration can only reduce sludge volume, nothing Method thoroughly changes sludge quality, when dewatered sludge meet water it is hygroscopic, cause its mechanical index be deteriorated, easily slide, bad stability. Dewatered sludge routine disposal options are to mix to fill out with house refuse into landfill yard, and the dewatered sludge into landfill yard easily absorbs rubbish And surrounding enviroment moisture, cause moisture percentage in sewage sludge increase, mechanical index variation, mobility to become strong, influences landfill yard heap body and stablize Property;Percolate is easily dispersed into after dewatered sludge water suction and leads infiltration system, and Heavy Metals in Sludge and mud granule easily dissolve out after causing It holds percolate processing difficulty to increase, influences intake dust removal rate and discharge index stability, while dewatered sludge is dispersed into rubbish Rubbish heap body easily blocks firedamp drainage gap, causes collecting methane unsmooth and there are security risks.
Volume is still larger (diameter is greater than 10cm) after frame dehydration sludge crushing, if with only surface layer carries out after curing agent mix Hydration and sclerosis reaction, binding force is not strong, causes integrally curing effect poor, and water imbibition and mechanical index do not have clear improvement.And plate In the case of frame dewatered sludge uses a large amount of curing agent, increases cost of disposal, increases sludge weight and volume, economy and the feature of environmental protection Difference.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, a kind of high treating effect, technique letter are provided It is single, easily promote, collaboration at low cost solidifies the method for dewatered sludge Yu primary sludge, also provide a kind of structure it is simple, it is at low cost, The system that collaboration easy to operate, high treating effect solidifies dewatered sludge Yu primary sludge.
In order to solve the above technical problems, the invention adopts the following technical scheme:
A method of collaboration solidification dewatered sludge and primary sludge include the following steps:
S1, primary sludge and middle sand, solidification auxiliary material progress level-one are stirred, and carry out primary solidification, obtain primary solidification Sludge;
S2, primary solidification sludge is stirred with through broken dewatered sludge progress second level, and carries out collaboration solidification, consolidate Change sludge.
The method that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that count in mass ratio, dewatered sludge: former Primary sludge is 1: 0.5~1.5.
The method that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that in the step S1, the solidification is auxiliary Material is cement and curing agent;It counts in mass ratio, primary sludge: middle sand: cement: curing agent 1: 0.1~0.3: 0.1~0.3: 0.02~0.1.
The method that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that described through broken in the step S2 Dewatered sludge partial size < 10cm, the dewatered sludge be the anaerobically digested sludge through frame dehydration.
The method that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that in the step S1, the level-one is stirred The time for mixing mixing is 2~3min;In the step S2, the time that the second level is stirred is 2~5min.
The inventive concept total as one, the present invention also provides what a kind of collaboration solidified dewatered sludge and primary sludge to be System, including second level mixed stirring device, for storing, broken dewatered sludge and convey broken dewatered sludge to second level mixing and stir Mix dewatered sludge storage-broken-conveying mechanism of device and for blending the primary sludge of mix, middle sand and solidifying auxiliary material The feed inlet of level-one mixed stirring device, the discharge port of the level-one mixed stirring device and the second level mixed stirring device connects It connects.
The system that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that dewatered sludge storage-broken- Conveying mechanism includes dewatered sludge warehouse, sludge crusher, the first screw conveyor and the first belt conveyor, and the dehydration is dirty Mud warehouse is connected to the first screw conveyor, and the discharge port of first screw conveyor is located at the charging of the sludge crusher Above mouthful, first belt conveyor is set to below the discharge port of the sludge crusher, first belt conveyor One end far from the sludge crusher extends in the second level mixed stirring device.
The system that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that further include primary warehouse of sludge, middle sand Hopper, solidification auxiliary material storage tank, the second screw conveyor, the second belt conveyor and third screw conveyor, second belt Conveyer is set to the lower section of the middle sand hopper discharge port, and second belt conveyor is extended to far from one end of middle sand hopper In the level-one mixed stirring device, the discharge port of the feed inlet of second screw conveyor and the primary warehouse of sludge connects Logical, the feed inlet of the third screw conveyor is connected to the discharge port for solidifying auxiliary material storage tank, second helical feed The discharge port of machine and third screw conveyor all extends in the level-one mixed stirring device.
The system that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that further include for dirty to the dehydration The spray deodorization device of mud warehouse spray deodorization medicament;
The charging door of the dewatered sludge warehouse is equipped with automatic inductor, and the automatic inductor and spray deodorization device are automatic It is chain.
The system that above-mentioned collaboration solidifies dewatered sludge Yu primary sludge, it is preferable that the dewatered sludge warehouse outer wall The vibrator for being used to eliminate arch formation is respectively arranged in middle part and lower part, and two vibrators are arranged in opposite directions;
First belt conveyor and the second belt conveyor are respectively provided with fender in the two sides along conveying direction, in two belts The conveying end of conveyer is equipped with cleaning shoe.
Compared with the prior art, the advantages of the present invention are as follows:
(1) present invention is by carrying out primary solidification to primary sludge, obtaining having easy mix, viscous viscosity and can further solidifying Primary solidification sludge, and by frame dehydration sludge crushing, the dewatered sludge fritter for the aggregate properties being had mixes the two Solidified after conjunction, since dewatered sludge fritter plays skeleton function in the curing process and the primary sludge being cured wraps up, The dosage for reducing sand in aggregate simultaneously is finally reached the cured effect of collaboration.Primary solidification sludge centainly mix than in the case where, Obtained solidification sludge is able to satisfy into landfill yard shale moisture content and mechanical index requirement.Method high treating effect of the invention, Simple process is easily promoted, is at low cost, can be used for scale processing.
(2) present invention utilizes the aggregate properties of dewatered sludge, cooperates with the dosage that sand in aggregate can be reduced in solidification process, drop Low production cost, while dewatered sludge is added during primary sludge curing secondary mix, avoid consumption curing agent;Utilize original Primary sludge carry out the easy mix in solidification process, viscous viscosity and can further cured property, adequately achieve to dehydration The utilization of sludge, overcome existing for anaerobic digestion dewatered sludge in the prior art it is hygroscopic cause mechanical index be deteriorated, flowing Property the defects of becoming strong, influencing landfill yard heap body stability, leachate collection and collecting methane, also overcome de- using directly solidification The disadvantages of solidification effect existing for sewage sludge is poor, at high cost, the feature of environmental protection is poor.
(3) system of the invention use by level-one mixed stirring device to primary sludge carry out primary solidification subsequently into Second level agitating device, and be delivered to broken dewatered sludge fritter by using dewatered sludge storage, broken and conveying device It is mixed in second level mixed stirring device with the mixture after primary solidification, realizes that the two cooperates with cured effect.This The system structure of invention is simple, at low cost, easy to operate, high treating effect.
(4) system of the invention passes through each material warehouse, sludge crusher and multiple screw conveyors and Belt Conveying The cooperation of machine, whole system high degree of automation can realize material conveying, broken, mixing and solidification automatically, can effectively drop Low labor intensity improves treatment effeciency.
(5) system of the invention sprays the spray deodorization device of deodorization medicament by setting to dewatered sludge warehouse, effectively It reduces foul smell and dissipates and overflow, improve operating condition, by automatic in the charging door setting of dewatered sludge warehouse and spray deodorization device Chain automatic inductor can realize automatic spray according to the folding of door, further improve operating condition.
(6) system of the invention can effectively eliminate arch formation, protect by the way that vibrator is arranged in dewatered sludge warehouse outer wall Barrier operation is continuously gone on smoothly, in addition, also passing through the tilt angle inside control feed bin, the mobile cross of setting in feed bin Blade further ensures that discharging is smooth, ensures continuously going on smoothly for operation.
Detailed description of the invention
Fig. 1 is the structural schematic diagram for the system that collaboration of the invention solidifies dewatered sludge and primary sludge.
Each label indicates in figure:
1, dewatered sludge warehouse;2, the first screw conveyor;3, sludge crusher;4, the first belt conveyor;5, deodorization is sprayed Device;6, primary warehouse of sludge;7, the second screw conveyor;8, middle sand hopper;9, the second belt conveyor;10, solidify auxiliary material Storage tank;11, third screw conveyor;12, level-one mixed stirring device;13, second level mixed stirring device.
Specific embodiment
Below in conjunction with Figure of description and specific preferred embodiment, the invention will be further described, but not therefore and It limits the scope of the invention.
A method of collaboration solidification dewatered sludge and primary sludge include the following steps:
S1, primary sludge and middle sand, solidification auxiliary material progress level-one are stirred, obtain primary solidification sludge;
S2, primary solidification sludge is stirred with through broken dewatered sludge second level, carries out collaboration solidification, it is dirty obtains solidification Mud.
In above-mentioned method, count in mass ratio, dewatered sludge: primary sludge quality ratio is 1: 0.5~1.5.
In above-mentioned method, in the step S1, the solidification auxiliary material is cement and curing agent;It counts in mass ratio, it is primary Sludge: middle sand: cement: curing agent 1: 0.1~0.3: 0.1~0.3: 0.02~0.1.
In above-mentioned method, the cement is extraordinary quick hardening cement, and the curing agent is quick lime, in miberal powder, early strength agent One or more combination.
In above-mentioned method, in the step S2, the partial size < 10cm through broken dewatered sludge, optimized particle size is ≤5cm;The dewatered sludge is the anaerobically digested sludge through frame dehydration.
In above-mentioned method, in the step S1, the time that the level-one is stirred is 2~3min;The step S2 In, the time that the second level is stirred is 2~5min.
A kind of collaboration solidifies the system of dewatered sludge Yu primary sludge, including second level mixed stirring device 13, for storing, Broken dewatered sludge and convey dewatered sludge to second level mixed stirring device 13 dewatered sludge storage-broken-conveying mechanism, with And for blending the primary sludge of mix, middle sand and the level-one mixed stirring device 12 for solidifying auxiliary material, dress is mixed in the level-one 12 discharge port is set to connect with the feed inlet of the second level mixed stirring device 13.
The level-one mixed stirring device 12 is level-one blender, and the second level mixed stirring device 13 is second level stirring Machine.
Above-mentioned system, the dewatered sludge storage-broken-conveying mechanism includes dewatered sludge warehouse 1, sludge crusher 3, for dewatered sludge to be delivered to the first screw conveyor 2 of sludge crusher 3 and be used for will be after sludge crusher 3 be broken Dewatered sludge be delivered to the first belt conveyor 4 of second level mixed stirring device 13, the dewatered sludge warehouse 1 passes through discharging Mouth is connected to the feed inlet of the first screw conveyor 2, and the discharge port of first screw conveyor 2 is located at the sludge crusher Above 3 feed inlet, first belt conveyor 4 is set to below the discharge port of the sludge crusher 3, first skin It is extended in the second level mixed stirring device 13 with conveyer 4 far from one end of the sludge crusher 3.Frame dehydration sludge It unloads into dewatered sludge warehouse 1, is pressed by the first screw conveyor (discharging spiral pipe) 2 of the orlop lower part of dewatered sludge warehouse 1 Frame dehydration sludge is delivered to sludge crusher 3 and is crushed by special speed, and dewatered sludge is broken into the fritter of certain partial size It drops down onto the first belt conveyor 4 and is delivered in second level mixed stirring device 13 by the first belt conveyor 4.
Above-mentioned system further includes primary warehouse of sludge 6, middle sand hopper 8, solidifies auxiliary material storage tank 10, is primary for conveying Second screw conveyor 7 of sludge, for the second belt conveyor 9 of sand in conveying and for conveying the third spiral shell for solidifying auxiliary material Conveyer 11 is revolved, second belt conveyor 9 is set to the lower section of middle 8 discharge port of sand hopper, second Belt Conveying Machine 9 extends in the level-one mixed stirring device 12 far from one end of middle sand hopper 8, and second screw conveyor 7 passes through Feed inlet is connected to the discharge port of the primary warehouse of sludge 6, the feed inlet of the third screw conveyor 11 and the solidification The discharge port of auxiliary material storage tank 10 is connected to, the discharge port of second screw conveyor 7 and third screw conveyor 11 with it is described The feed inlet of level-one mixed stirring device 12 connects.Primary sludge in primary warehouse of sludge 6 passes through the second spiral transferring of lower part Send machine (primary sludge discharging spiral) 7 to be delivered to level-one mixed stirring device 12, the middle sand in middle sand hopper 8 pass through lower part the Two belt conveyors 9 are delivered to level-one mixed stirring device 12, and the material solidified in auxiliary material storage tank 10 passes through third helical feed Machine (solidification auxiliary material discharging spiral) 11 enters level-one mixed stirring device 12.Primary dirt is realized in level-one mixed stirring device 12 After mud and middle sand and solidification auxiliary material primary solidification, into second level mixed stirring device 13, while dewatered sludge fritter passes through first Belt conveyor 4 enters second level mixed stirring device 13, using the easy mix having after primary sludge primary solidification, glues Property and frame dehydration sludge crushing are at the aggregate properties having after certain partial size, and dewatered sludge is small during secondary curing Block plays skeleton function and the primary sludge package that is cured, while reducing the dosage of sand in aggregate, and it is cured to be finally reached collaboration Effect.
Above-mentioned system further includes the spray deodorization device 5 for spraying deodorization medicament to the dewatered sludge warehouse 1, It sprays deodorization device 5 and is set to 1 top of dewatered sludge warehouse, foul smell is avoided to leak.The spray deodorization device 5 is stored up including medicament Case, spray pump and spray nozzle.
Above-mentioned system, the solidification auxiliary material storage tank 10 at least there are two, a storage cement, another storage solidification Agent.
Above-mentioned system, the door of the dewatered sludge warehouse 1 are equipped with automatic inductor, the automatic inductor and spray 5 automatic linkage of deodorization device triggers automatic inductor under door open state, triggers automatic inductor to spray deodorization device 5 conveying signals, start deodorization spray pump, and closed type triggering stops.
Above-mentioned system, 1 outer wall of the dewatered sludge warehouse middle part and lower part respectively arrange that one is used to eliminate arch formation Vibrator, and two vibrators are arranged in opposite directions.It whether smooth can be discharged according to the discharging spiral pipe of the first screw conveyor 2, Start vibrator and eliminates arch formation.
Above-mentioned system, first belt conveyor 4 and the second belt conveyor 9 are all provided in the two sides along conveying direction Fender is set to prevent sludge from falling, is equipped with cleaning shoe in the conveying end of each belt conveyor.
Feed inlet to the orlop tilt angle of above-mentioned system, the dewatered sludge warehouse 1 is 50 °~70 °, in favor of going out Expect smooth.
Above-mentioned system is equipped with maintenance valve together in the middle part of the dewatered sludge warehouse 1, convenient for periodic inspection dimension in storehouse Shield.
Above-mentioned system, the 1 storehouse inner wall of dewatered sludge warehouse are equipped with the anti-sticking polyethylene board of macromolecule.
Above-mentioned system, the interior mobile cross blade equipped with hydraulic-driven of the dewatered sludge warehouse 1 is, it can be achieved that sludge Broken arch and precrushing.
Above-mentioned system, the 2, second screw conveyor of first screw conveyor (dewatered sludge discharging spiral) are (primary Sludge discharges spiral) 7 and third screw conveyor (solidification auxiliary material discharge spiral) 11 be all made of shaftless screw, frequency control is adjusted Save unit time load.
Above-mentioned system, second belt conveyor (middle sand belt conveyer) 9 use frequency control, when adjusting unit Between load.
Above-mentioned system, the sludge crusher 3 are oppositely rolling roller crusher;The oppositely rolling roller crusher motor is equipped with protection Switch autostop and is alarmed when current is excessive, and motor can invert when maintenance.
Embodiment 1
The system that a kind of collaboration of the invention solidifies dewatered sludge Yu primary sludge, as described in Figure 1, including dress is mixed in second level Set 13, for storing, broken dewatered sludge and the dewatered sludge storage-that conveys dewatered sludge to second level mixed stirring device 13 it is broken Broken-conveying mechanism and for blending the primary sludge of mix, middle sand and the level-one mixed stirring device 12 for solidifying auxiliary material, it is described The discharge port of level-one mixed stirring device 12 is connect with the feed inlet of the second level mixed stirring device 13.
The level-one mixed stirring device 12 is level-one blender, and the second level mixed stirring device 13 is second level stirring Machine.
Above-mentioned system, the dewatered sludge storage-broken-conveying mechanism includes dewatered sludge warehouse 1, sludge crusher 3, for dewatered sludge to be delivered to the first screw conveyor 2 of sludge crusher 3 and be used for will be after sludge crusher 3 be broken Dewatered sludge be delivered to the first belt conveyor 4 of second level mixed stirring device 13, the dewatered sludge warehouse 1 passes through discharging Mouth is connected to the feed inlet of the first screw conveyor 2, and the discharge port of first screw conveyor 2 is located at the sludge crusher Above 3 feed inlet, first belt conveyor 4 is set to below the discharge port of the sludge crusher 3, first skin It is extended in the second level mixed stirring device 13 with conveyer 4 far from one end of the sludge crusher 3.Frame dehydration sludge It unloads into dewatered sludge warehouse 1, is pressed by the first screw conveyor (discharging spiral pipe) 2 of the orlop lower part of dewatered sludge warehouse 1 Frame dehydration sludge is delivered to sludge crusher 3 and is crushed by special speed, and dewatered sludge is broken into the fritter of certain partial size It drops down onto the first belt conveyor 4 and is delivered in second level mixed stirring device 13 by the first belt conveyor 4.
Above-mentioned system further includes primary warehouse of sludge 6, middle sand hopper 8, solidifies auxiliary material storage tank 10, is primary for conveying Second screw conveyor 7 of sludge, for the second belt conveyor 9 of sand in conveying and for conveying the third spiral shell for solidifying auxiliary material Conveyer 11 is revolved, second belt conveyor 9 is set to the lower section of middle 8 discharge port of sand hopper, second Belt Conveying Machine 9 extends in the level-one mixed stirring device 12 far from one end of middle sand hopper 8, and second screw conveyor 7 passes through Feed inlet is connected to the discharge port of the primary warehouse of sludge 6, the feed inlet of the third screw conveyor 11 and the solidification The discharge port of auxiliary material storage tank 10 is connected to, the discharge port of second screw conveyor 7 and third screw conveyor 11 with it is described The feed inlet of level-one mixed stirring device 12 connects.Primary sludge in primary warehouse of sludge 6 passes through the second spiral transferring of lower part Send machine (primary sludge discharging spiral) 7 to be delivered to level-one mixed stirring device 12, the middle sand in middle sand hopper 8 pass through lower part the Two belt conveyors 9 are delivered to level-one mixed stirring device 12, and the material solidified in auxiliary material storage tank 10 passes through third helical feed Machine (solidification auxiliary material discharging spiral) 11 enters level-one mixed stirring device 12.Primary dirt is realized in level-one mixed stirring device 12 After mud and middle sand and solidification auxiliary material primary solidification, into second level mixed stirring device 13, while dewatered sludge fritter passes through first Belt conveyor 4 enters second level mixed stirring device 13, using the easy mix having after primary sludge primary solidification, glues Property and frame dehydration sludge crushing are at the aggregate properties having after certain partial size, and dewatered sludge is small during secondary curing Block plays skeleton function and the primary sludge package that is cured, while reducing the dosage of sand in aggregate, and it is cured to be finally reached collaboration Effect.
Above-mentioned system further includes the spray deodorization device 5 for spraying deodorization medicament to the dewatered sludge warehouse 1, Foul smell is avoided to leak.The spray deodorization device 5 includes medicament storage tank, spray pump and spray nozzle.
Above-mentioned system, the door of the dewatered sludge warehouse 1 are equipped with automatic inductor, the automatic inductor and spray 5 automatic linkage of deodorization device triggers automatic inductor under door open state, triggers automatic inductor to spray deodorization device 5 conveying signals, start deodorization spray pump, and closed type triggering stops.
Above-mentioned system, 1 outer wall of the dewatered sludge warehouse middle part and lower part respectively arrange that one is used to eliminate arch formation Vibrator, and two vibrators are arranged in opposite directions.It whether smooth can be discharged according to the discharging spiral pipe of the first screw conveyor 2, Start vibrator and eliminates arch formation.
Above-mentioned system, first belt conveyor 4 and the second belt conveyor 9 are all provided in the two sides along conveying direction Fender is set to prevent sludge from falling, is equipped with cleaning shoe in the conveying end of each belt conveyor.
Feed inlet to the orlop tilt angle of above-mentioned system, the dewatered sludge warehouse 1 is 50 °~70 °, in favor of going out Expect smooth.
Above-mentioned system, the middle part of the dewatered sludge warehouse 1 are equipped with maintenance valve together, convenient for periodic inspection dimension in storehouse Shield.
Above-mentioned system, the storehouse inner wall of the dewatered sludge warehouse 1 are equipped with the anti-sticking polyethylene board of macromolecule.
Above-mentioned system, the interior mobile cross blade equipped with hydraulic-driven of the dewatered sludge warehouse 1 is, it can be achieved that sludge Broken arch and precrushing.
Above-mentioned system, the 2, second screw conveyor of first screw conveyor (dewatered sludge discharging spiral) are (primary Sludge discharges spiral) 7 and third screw conveyor (solidification auxiliary material discharge spiral) 11 be all made of shaftless screw, frequency control is adjusted Save unit time load.
Above-mentioned system, second belt conveyor (middle sand belt conveyer) 9 use frequency control, when adjusting unit Between load.
Above-mentioned system, the sludge crusher 3 are oppositely rolling roller crusher;The oppositely rolling roller crusher motor is equipped with protection Switch autostop and is alarmed when current is excessive, and motor can invert when maintenance.
At work, frame dehydration sludge is unloaded into dewatered sludge warehouse 1 system of the present embodiment, in dewatered sludge warehouse When 1 door opens charging, triggering automatic inductor starting spray deodorization device 5 carries out deodorization medicament spray, reduces foul smell and dissipates and overflows. Sludge crusher 3, which is delivered to, according to setting rate by the first screw conveyor (dewatered sludge discharging spiral) 2 is broken into dehydration Sludge fritter, while starting vibrator carries out Vibrated baiting, dewatered sludge fritter when the first screw conveyor 2 falls without material Sludge falls to the first belt conveyor 4 and is delivered in second level mixed stirring device 13.
Primary sludge in primary warehouse of sludge 6 is by the second screw conveyor (primary sludge discharging spiral) 7 by setting Rate enters in level-one mixed stirring device 12, and middle sand hopper 8 passes through the second skin with the material solidified in auxiliary material storage tank 10 respectively Band conveyer 9 and third screw conveyor (solidification auxiliary material discharging spiral) 11 enter in level-one mixed stirring device 12, and middle sand rises Skeleton function, solidification auxiliary material play solidification.After realizing primary sludge primary solidification in level-one mixed stirring device 12, enter In second level mixed stirring device 13.In second level mixed stirring device 13, the primary sludge of primary solidification is mixed with dewatered sludge fritter Blending is closed, wherein dewatered sludge fritter plays skeleton function and the primary sludge package that is cured, reach the cured effect of collaboration, Gu Sludge is in that large-scale bulk enters landfill yard after change.
Embodiment 2
In a comprehensive fixed-end forces garden, frame dehydration sludge average moisture content 58.1%, primary sludge average moisture content 80%.In conventional primary sludge curing project, sand, cement and curing agent are solidified in, and each weight of material proportion is original Primary sludge: middle sand: cement: curing agent=1: 0.2: 0.2: 0.05.
A kind of method that collaboration of the invention solidifies dewatered sludge Yu primary sludge, includes the following steps:
(1) by primary sludge and middle sand, solidification auxiliary material (cement, curing agent) primary sludge according to the weight ratio: middle sand: cement: Curing agent=1: in level-one blender carry out level-one stirring at 0.1: 0.2: 0.05, and level-one mixing time is 2min, tentatively solid to carry out Change, obtains the primary sludge of primary solidification;Dewatered sludge is crushed, dewatered sludge fritter, partial size 5cm are obtained.
(2) secondary blender is delivered to dewatered sludge fritter by primary solidification is primary, and carry out in secondary blender Dewatered sludge fritter and the primary sludge of primary solidification carry out second level stirring, and second level mixing time is 2min, are solidified, are solidified Cheng Zhong, dewatered sludge fritter play certain skeleton function and the primary sludge package that is cured, reach the cured effect of collaboration, obtain Solidification sludge.
In whole process, by adjusting dewatered sludge discharging spiral frequency, the conveying of dewatered sludge and primary sludge is controlled Rate (discharge velocity) is than being 1: 0.5~1: 1.5, and control is 1: 0.6 in the present embodiment, i.e. control dewatered sludge and primary sludge Quality be 1: 0.6.
Resulting solidification sludge parameter are as follows: moisture content 49.2%, unconfined compressive strength 56.3KN/m2, four-bladed vane is anti- Cutting intensity is 32.06KN/m2, infiltration coefficient 6.12*10-6Cm/s carries out sanitary landfills disposition and meets index of correlation requirement.
Embodiment 3
In a comprehensive fixed-end forces garden, frame dehydration sludge average moisture content 59.0%, primary sludge average moisture content 80%.In conventional primary sludge curing project, sand, cement and curing agent are solidified in, and each weight of material proportion is original Primary sludge: middle sand: cement: curing agent=1: 0.2: 0.2: 0.05.
A kind of method that collaboration of the invention solidifies dewatered sludge Yu primary sludge, includes the following steps:
(1) by primary sludge and middle sand, solidification auxiliary material (cement, curing agent) primary sludge according to the weight ratio: middle sand: cement: Curing agent=1: in level-one blender carry out level-one stirring at 0.1: 0.2: 0.05, and level-one mixing time is 2.5min, preliminary to carry out Solidification, obtains the primary sludge of primary solidification;Dewatered sludge is crushed, dewatered sludge fritter, partial size 4cm are obtained;
(2) secondary blender is delivered to dewatered sludge fritter by primary solidification is primary, and be dehydrated in secondary blender Sludge fritter and the primary sludge of primary solidification carry out second level stirring, and second level mixing time is 2.5min, are solidified, solidification process In, dewatered sludge fritter plays certain skeleton function and the primary sludge package that is cured, reach the cured effect of collaboration, consolidate Change sludge.
In whole process, by adjusting dewatered sludge discharging spiral frequency, control dewatered sludge and primary sludge discharging speed Rate ratio is 1: 1.1, i.e., the quality of control dewatered sludge and primary sludge is 1: 0.6.
Resulting solidification sludge parameter are as follows: moisture content 49.7%, unconfined compressive strength 70.5KN/m2, four-bladed vane is anti- Cutting intensity is 36.08KN/m2, infiltration coefficient 4.06*10-6Cm/s carries out sanitary landfills disposition and meets index of correlation requirement.
Embodiment 4
In a comprehensive fixed-end forces garden, frame dehydration sludge average moisture content 60%, primary sludge average moisture content 80%. In conventional primary sludge curing project, sand, cement and curing agent are solidified in, and each weight of material proportion is primary dirt Mud: middle sand: cement: curing agent=1: 0.2: 0.2: 0.05.
A kind of method that collaboration of the invention solidifies dewatered sludge Yu primary sludge, includes the following steps:
It is 1: 1.4 by adjusting dewatered sludge discharging spiral frequency to control dewatered sludge and primary sludge discharge velocity ratio, that is, controls The quality of dewatered sludge processed and primary sludge is 1: 1.4, dewatered sludge by entering secondary blender after broken, primary sludge with Middle sand and solidification auxiliary material (cement, curing agent) are mixed with according to primary sludge: middle sand: cement: curing agent=1: 0.1: 0.2: 0.05, Enter secondary blender after level-one blender primary solidification, dewatered sludge fritter and primary solidification are carried out in secondary blender Primary sludge mix blending, dewatered sludge fritter play certain skeleton function and the primary sludge package that is cured, it is solid to reach collaboration The effect of change.
Level-one mixing time is 3min, and second level mixing time is 3min, and dewatered sludge fritter partial size is 4.0cm.
The moisture content of obtained solidification sludge is 48.6%, unconfined compressive strength 83.2KN/m2, vane is strong Degree is 40.01KN/m2, infiltration coefficient 3.02*10-5Cm/s carries out sanitary landfills disposition and meets index of correlation requirement.
According to relevant national standard, need to meet into landfill yard Sludge Property claimed below: unconfined compressive strength >=50KN/ m2, vane strength >=25KN/m2, infiltration coefficient 10-6Cm/s~10-5Cm/s, moisture content≤60%.The present invention utilizes Comprehensive fixed-end forces garden (project of frame dehydration containing anaerobic digestion and primary sludge curing project) two kinds of sludge shale features, and It is organically combined and carries out collaboration curing process, there is reasonability, technical feasibility, do not increasing production auxiliary materials cost item additionally Under part, reach frame dehydration sludge with primary sludge and cooperate with solidification effect, meets landfill yard and march into the arena requirement.
Although the present invention is disclosed as above with preferred embodiment, however, it is not intended to limit the invention.It is any to be familiar with ability The technical staff in domain, without deviating from the scope of the technical scheme of the present invention, all using the technology contents pair of the disclosure above Technical solution of the present invention makes many possible changes and modifications or equivalent example modified to equivalent change.Therefore, all Without departing from the content of technical solution of the present invention, according to the present invention technical spirit any simple modification made to the above embodiment, Equivalent variations and modification, all shall fall within the protection scope of the technical scheme of the invention.

Claims (10)

1. a kind of method that collaboration solidifies dewatered sludge Yu primary sludge, which comprises the steps of:
S1, primary sludge and middle sand, solidification auxiliary material progress level-one are stirred, and carry out primary solidification, obtain primary solidification Sludge;
S2, primary solidification sludge is stirred with through broken dewatered sludge progress second level, and carries out collaboration solidification, consolidate Change sludge.
2. the method that collaboration as described in claim 1 solidifies dewatered sludge Yu primary sludge, which is characterized in that in mass ratio Meter, dewatered sludge: primary sludge is 1: 0.5~1.5.
3. the method that collaboration as described in claim 1 solidifies dewatered sludge Yu primary sludge, which is characterized in that the step S1 In, the solidification auxiliary material is cement and curing agent;It counts in mass ratio, primary sludge: middle sand: cement: curing agent 1: 0.1~ 0.3: 0.1~0.3: 0.02~0.1.
4. the method that the collaboration as described in claims 1 to 3 any one solidifies dewatered sludge Yu primary sludge, feature exist In in the step S2, the partial size < 10cm through broken dewatered sludge, the dewatered sludge is detesting through frame dehydration Oxygen digested sludge.
5. the method that the collaboration as described in claims 1 to 3 any one solidifies dewatered sludge Yu primary sludge, feature exist In in the step S1, the time that the level-one is stirred is 2~3min;In the step S2, the second level is stirred Time be 2~5min.
6. the system that a kind of collaboration solidifies dewatered sludge Yu primary sludge, which is characterized in that including second level mixed stirring device (13), for storing, broken dewatered sludge and the dehydration that conveys broken dewatered sludge to second level mixed stirring device (13) it is dirty It mud storage-broken-conveying mechanism and is mixed and fills for blending the primary sludge of mix, middle sand and solidify the level-one of auxiliary material It sets (12), the feed inlet of the discharge port of the level-one mixed stirring device (12) and the second level mixed stirring device (13) connects It connects.
7. the system that collaboration as claimed in claim 6 solidifies dewatered sludge Yu primary sludge, which is characterized in that the dehydration is dirty Mud storage-broken-conveying mechanism includes dewatered sludge warehouse (1), sludge crusher (3), the first screw conveyor (2) and first Belt conveyor (4), the dewatered sludge warehouse (1) are connected to the first screw conveyor (2), first screw conveyor (2) discharge port is located above the feed inlet of the sludge crusher (3), and first belt conveyor (4) is set to described Below the discharge port of sludge crusher (3), first belt conveyor (4) is prolonged far from the one end of the sludge crusher (3) It extends in the second level mixed stirring device (13).
8. the system that collaboration as claimed in claims 6 or 7 solidifies dewatered sludge Yu primary sludge, which is characterized in that further include Primary warehouse of sludge (6), middle sand hopper (8), solidification auxiliary material storage tank (10), the second screw conveyor (7), the second belt conveyor (9) and third screw conveyor (11), second belt conveyor (9) are set to the lower section of middle sand hopper (8) discharge port, Second belt conveyor (9) extends in the level-one mixed stirring device (12) far from the one end of middle sand hopper (8), institute The feed inlet for stating the second screw conveyor (7) is connected to the discharge port of the primary warehouse of sludge (6), the third helical feed The feed inlet of machine (11) is connected to the discharge port for solidifying auxiliary material storage tank (10), second screw conveyor (7) and third The discharge port of screw conveyor (11) all extends in the level-one mixed stirring device (12).
9. the system that collaboration as claimed in claims 6 or 7 solidifies dewatered sludge Yu primary sludge, which is characterized in that further include For the spray deodorization device (5) to the dewatered sludge warehouse (1) spray deodorization medicament;
The charging door of the dewatered sludge warehouse (1) is equipped with automatic inductor, the automatic inductor and spray deodorization device (5) automatic linkage.
10. the system that collaboration as claimed in claims 6 or 7 solidifies dewatered sludge Yu primary sludge, which is characterized in that described de- The vibrator for being used to eliminate arch formation, and two vibrators are respectively arranged in the middle part and lower part of sewage sludge warehouse (1) outer wall Opposite arrangement;
First belt conveyor (4) and the second belt conveyor (9) are respectively provided with fender in the two sides along conveying direction, The conveying end of two belt conveyors is equipped with cleaning shoe.
CN201811533744.4A 2018-12-14 2018-12-14 A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge Pending CN109607989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811533744.4A CN109607989A (en) 2018-12-14 2018-12-14 A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811533744.4A CN109607989A (en) 2018-12-14 2018-12-14 A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge

Publications (1)

Publication Number Publication Date
CN109607989A true CN109607989A (en) 2019-04-12

Family

ID=66009220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811533744.4A Pending CN109607989A (en) 2018-12-14 2018-12-14 A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge

Country Status (1)

Country Link
CN (1) CN109607989A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000024694A (en) * 1998-07-09 2000-01-25 Ohmoto Gumi Co Ltd Method for dehydrating and solidifying high-water- content slurry
JP2007196086A (en) * 2006-01-24 2007-08-09 Japan Organo Co Ltd Concentration volume reduction process and arrangement of sludge
CN101538146A (en) * 2009-04-27 2009-09-23 武汉理工大学 Harmless utilization method of electroplating sludge and oily sludge resources
CN102515706A (en) * 2011-12-27 2012-06-27 浙江方远建材科技有限公司 High-performance ceramsite and preparation method thereof
CN104326634A (en) * 2014-11-24 2015-02-04 广州珞珈环境技术有限公司 Composite sludge treatment process
CN106966567A (en) * 2017-05-31 2017-07-21 威海市水务环保科技有限责任公司 Sludge drying method of disposal
CN107381990A (en) * 2017-08-30 2017-11-24 湖南军信环保股份有限公司 A kind of method of sludge curing
CN108083586A (en) * 2016-11-23 2018-05-29 广州新致晟环保科技机械设备有限公司 The combination unit of dewatered sludge and its manufacturing method and drying method
CN209412046U (en) * 2018-12-14 2019-09-20 湖南军信环保股份有限公司 The system that a kind of collaboration solidifies dewatered sludge Yu primary sludge

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000024694A (en) * 1998-07-09 2000-01-25 Ohmoto Gumi Co Ltd Method for dehydrating and solidifying high-water- content slurry
JP2007196086A (en) * 2006-01-24 2007-08-09 Japan Organo Co Ltd Concentration volume reduction process and arrangement of sludge
CN101538146A (en) * 2009-04-27 2009-09-23 武汉理工大学 Harmless utilization method of electroplating sludge and oily sludge resources
CN102515706A (en) * 2011-12-27 2012-06-27 浙江方远建材科技有限公司 High-performance ceramsite and preparation method thereof
CN104326634A (en) * 2014-11-24 2015-02-04 广州珞珈环境技术有限公司 Composite sludge treatment process
CN108083586A (en) * 2016-11-23 2018-05-29 广州新致晟环保科技机械设备有限公司 The combination unit of dewatered sludge and its manufacturing method and drying method
CN106966567A (en) * 2017-05-31 2017-07-21 威海市水务环保科技有限责任公司 Sludge drying method of disposal
CN107381990A (en) * 2017-08-30 2017-11-24 湖南军信环保股份有限公司 A kind of method of sludge curing
CN209412046U (en) * 2018-12-14 2019-09-20 湖南军信环保股份有限公司 The system that a kind of collaboration solidifies dewatered sludge Yu primary sludge

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周海燕等: ""镁盐固化污泥及污泥焚烧灰渣作为原生污泥新型固化剂应用工艺研究"", vol. 19, no. 3, pages 48 - 49 *
杨洁等: ""富营养化水体原位控磷技术研究及应用"", vol. 29, no. 2, pages 10 - 17 *
铁道部原机务局组织: "《净软水设备》", 中国铁道出版社, pages: 261 *

Similar Documents

Publication Publication Date Title
CN104445853B (en) A kind of method and apparatus realizing deeply dehydrating sludge with straw and wood flour
CN206736066U (en) A kind of combined type deep dehydration system for sludge
CN209412046U (en) The system that a kind of collaboration solidifies dewatered sludge Yu primary sludge
CN105668986B (en) A kind of drying sludge dehydration system and method
CN102389726B (en) Mixed processing device of solid waste and curing agent
CN103664136A (en) Sintered brick material prepared by utilizing wet petroleum sludge as well as preparation method and application of sintered brick material
CN106694157A (en) Novel construction waste disposal device
CN109607989A (en) A kind of collaboration solidifies the method and system of dewatered sludge Yu primary sludge
CN202744461U (en) Harmless brickmaking system of household garbage
JP2013121568A (en) Method of recycling construction sludge
JPH09294998A (en) Method and apparatus for reutilizing sludge as resources
CN209240265U (en) Bridge pier is poured with multistage with concrete production system
KR100725842B1 (en) Sludge treatment method and the apparatus in recycling of construction waste
KR101192499B1 (en) Method of mixing clay powder with waste and sewage sludge used for manufacturing process for clay brick
CN206796166U (en) A kind of buried concrete and brick production line
CN115873606A (en) Soil conditioner prepared from waste materials and preparation method and preparation device thereof
KR102253153B1 (en) mortar composition using oyster shell and manufacturing of it, compaction grouting method using oyster shell
CN206927772U (en) A kind of cured modified equipment for being prepared into recycling fuel of river bottom mud
EP0104773B1 (en) Apparatus and method for treating liquid and semi-solid organic waste materials
KR101473963B1 (en) Mixing device of sludge of cover material
CN205528358U (en) Sludge dewatering drying process system
CN2626697Y (en) Device for blending viscous material with other material
JP3680017B2 (en) Sludge regeneration treatment method
CN206154512U (en) Concrete mixing plant dosing unit
CN216550097U (en) Sludge granulation device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412