CN109519157A - Heat yield-increasing technique in coal bed gas well underground - Google Patents

Heat yield-increasing technique in coal bed gas well underground Download PDF

Info

Publication number
CN109519157A
CN109519157A CN201811145245.8A CN201811145245A CN109519157A CN 109519157 A CN109519157 A CN 109519157A CN 201811145245 A CN201811145245 A CN 201811145245A CN 109519157 A CN109519157 A CN 109519157A
Authority
CN
China
Prior art keywords
bed gas
coal bed
coal
gas well
high temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811145245.8A
Other languages
Chinese (zh)
Inventor
李德慧
李兵
徐云
何宜霏
张永成
杜立强
张江华
张为
刘亮亮
秦玉霞
王越
白杨
郭丁丁
崔宇翔
解宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Jincheng Anthracite Mining Group Co Ltd
Original Assignee
Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Jincheng Anthracite Mining Group Co Ltd filed Critical Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority to CN201811145245.8A priority Critical patent/CN109519157A/en
Publication of CN109519157A publication Critical patent/CN109519157A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/24Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection
    • E21B43/2401Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection by means of electricity
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/006Production of coal-bed methane

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Solid Fuels And Fuel-Associated Substances (AREA)

Abstract

The present invention relates to coal bed gas well mining technology fields, for the volume increase for realizing coal bed gas well head, the invention proposes a kind of coal bed gas well undergrounds to heat yield-increasing technique, be by the annular space of existing coal bed gas well oil pipe and casing one bottom of tripping in be high temperature resistant glass fibre reinforced plastic screen casing, top be annular space steel pipe composition structure, the annular space steel pipe on top is connect with wellhead sealing, it is high temperature-resistant cable in annular space steel pipe, it is heating rod in high temperature resistant glass fibre reinforced plastic screen casing, high temperature-resistant cable and heating rod connecting part are to be tightly connected;Heating rod is directly realized the water at coal bed gas well bottom after being powered and is heated, and around the heat diffusion to shaft bottom coal seam that the water in coal seam gradually releases heating rod, accelerates the coal bed gas parsing in coal seam reservoirs.The present invention is by directly changing bottom hole temperature (BHT) field to the heating of coal seam reservoirs;Improve the recovery ratio of coal bed gas;Accelerate the extraction of coal bed gas in coal seam;Shaft bottom water temperature increases the Brownian movement for increasing coal dust, improves coal dust indirectly and accumulates holddown well workover problem.

Description

Heat yield-increasing technique in coal bed gas well underground
Technical field
The present invention relates to coal bed gas well mining technology field, specially a kind of coal bed gas well underground heating volume increase work Skill.
Background technique
China is one of coal bed gas resource country the most abundant.The exploitation of coal bed gas is not only to China's energy safeguard and coal Mine is of great significance safely, and to energy resource structure is improved, clean energy resource development is promoted also to be of great significance.But from coal seam From the point of view of gas industry development status, methane output and utilization long-run development are slow, do not go out to obtain essence by years development Raising.The fundamental factor developed slowly be the geological conditions of China's complexity cause the production technique difficulty of coal bed gas compared with Greatly, it is directed to the research theory achievement of forefathers, proposes a kind of method for increasing yield of coal bed gas with strong applicability.Specifically by straight It connects and is heated in coal bed gas well underground to change the temperature field of coal seam reservoirs and increase the yield-increasing technique of methane output.
Summary of the invention
The purpose of the invention patent is: proposing a kind of coal bed gas well underground on the basis of existing theory only supports Yield-increasing technique is heated, which can realize the volume increase of coal bed gas well head.
The present invention adopts the following technical scheme that;
A kind of coal bed gas well underground heating yield-increasing technique, is by the tripping in the annular space of existing coal bed gas well oil pipe and casing The structure that one bottom is high temperature resistant glass fibre reinforced plastic screen casing, top is annular space steel pipe composition, the annular space steel pipe and wellhead sealing on top Connection, is high temperature-resistant cable in annular space steel pipe, is heating rod, high temperature-resistant cable and heating rod in high temperature resistant glass fibre reinforced plastic screen casing Connecting part is to be tightly connected;Heating rod directly realizes heating to the water at coal bed gas well bottom after being powered, and the water in coal seam will gradually add Around the heat diffusion that hot pin releases to shaft bottom coal seam, accelerate the coal bed gas parsing in coal seam reservoirs.
The annular space steel pipe will be more than hydrodynamic face, and the interface of high temperature resistant glass fibre reinforced plastic screen casing and annular space steel pipe will be placed in hydrodynamic It is more than face.
The interface of the high temperature-resistant cable and heating rod will be placed in hydrodynamic face or more.
It can reach following effect through the invention: bottom hole temperature (BHT) field changed by the heating directly to coal seam reservoirs;Improve coal The recovery ratio of layer gas;Accelerate the extraction of coal bed gas in coal seam;Shaft bottom water temperature increases the Brownian movement for increasing coal dust, improves indirectly Coal dust accumulates holddown well workover problem.The assembling of complete equipment device is simple, and technological operation is simple, has practical operability.Especially It is the coal bed gas well that will affect suitable for down-hole mining.The assembling of complete equipment device is simple, and technological operation is simple, has and actually may be used Operability.
Detailed description of the invention
Heat yield-increasing technique schematic diagram in Fig. 1 coal bed gas well shaft bottom;
In figure: polished rod (1), outlet pipeline (2), outlet pipe (3), cementing concrete (4), high temperature-resistant cable (5), annular space steel pipe (6), high temperature resistant glass fibre reinforced plastic screen casing (7), heating rod (8), high temperature resistant glass fibre reinforced plastic screen casing underseal (9), coal seam (10), casing (11), Oil pipe (12).
Specific embodiment
This modification scheme is to increase a part of device on the basis of existing coal bed gas well, and specific implementation method is as follows:
According to the annular space steel pipe and high temperature resistant glass fibre reinforced plastic screen casing of coal seam depth and coal seam thickness production corresponding length, in existing coal One bottom of tripping in is high temperature resistant glass fibre reinforced plastic screen casing in the annular space of layer gas well oil pipe and casing, and top is the knot of annular space steel pipe composition The annular space steel pipe of structure, top is connect with wellhead sealing, is high temperature-resistant cable in annular space steel pipe, is heating in glass reinforced plastic screen casing Stick, high-temperature cable and heating rod connecting part are to be tightly connected.2, directly the water at coal bed gas well bottom is realized after heating rod is powered and is added Heat around the heat diffusion to shaft bottom coal seam that the water in coal seam gradually releases heating rod, accelerates the coal bed gas in coal seam reservoirs Parsing.
The present invention improves the recovery ratio of coal bed gas, accelerates coal by directly changing bottom hole temperature (BHT) field to the heating of coal seam reservoirs The extraction of coal bed gas in layer, is the coal bed gas well that will affect especially suitable for down-hole mining, and water temperature raising in shaft bottom increases coal dust Brownian movement, indirectly improve coal dust accumulate holddown well workover problem.The assembling of complete equipment device is simple, and technological operation is simple, tool There is practical operability.
Although being described above in conjunction with preferred embodiment of the attached drawing to this patent, this patent is not limited to The specific embodiment stated, the above mentioned embodiment is only schematical, be not it is restrictive, this field it is common Technical staff, when not departing from this patent objective and scope of the claimed protection, may be used also under the enlightenment of this patent By make it is many in the form of, these are belonged within the protection scope of this patent.

Claims (3)

1. yield-increasing technique is heated in a kind of coal bed gas well underground, which is characterized in that be by existing coal bed gas well oil pipe (12) It is high temperature resistant glass fibre reinforced plastic screen casing (7) with one bottom of tripping in the annular space of casing (11), the knot that top is annular space steel pipe (6) composition The annular space steel pipe (6) of structure, top is connect with wellhead sealing, is high temperature-resistant cable (5) in annular space steel pipe (6), in high temperature resistant glass It is heating rod (8) in glass steel screen casing (7), high temperature-resistant cable (5) and heating rod (8) connecting part are to be tightly connected;Heating rod (8) is logical Heating directly is realized to the water at coal bed gas well bottom after electricity, the heat diffusion that the water in coal seam gradually releases heating rod (8) is extremely Around the coal seam of shaft bottom, accelerate the coal bed gas parsing in coal seam reservoirs.
2. yield-increasing technique is heated in coal bed gas well underground according to claim 1, which is characterized in that the annular space steel pipe (6) Will be more than hydrodynamic face, the interface of high temperature resistant glass fibre reinforced plastic screen casing (7) and annular space steel pipe (6) will be placed in hydrodynamic face or more.
3. yield-increasing technique is heated in coal bed gas well underground according to claim 2, which is characterized in that the high temperature-resistant cable (5) hydrodynamic face or more is placed in the interface of heating rod (8).
CN201811145245.8A 2018-09-29 2018-09-29 Heat yield-increasing technique in coal bed gas well underground Pending CN109519157A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811145245.8A CN109519157A (en) 2018-09-29 2018-09-29 Heat yield-increasing technique in coal bed gas well underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811145245.8A CN109519157A (en) 2018-09-29 2018-09-29 Heat yield-increasing technique in coal bed gas well underground

Publications (1)

Publication Number Publication Date
CN109519157A true CN109519157A (en) 2019-03-26

Family

ID=65771502

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811145245.8A Pending CN109519157A (en) 2018-09-29 2018-09-29 Heat yield-increasing technique in coal bed gas well underground

Country Status (1)

Country Link
CN (1) CN109519157A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110578508A (en) * 2019-08-05 2019-12-17 邓惠荣 Horizontal well one-well multi-mining combined coal bed gas mining and coal gasification method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4456186A (en) * 1981-03-09 1984-06-26 Chisso Engineering Co. Ltd. Electrically heated reactor for high temperature and pressure chemical reactions
US20020033253A1 (en) * 2000-04-24 2002-03-21 Rouffignac Eric Pierre De In situ thermal processing of a hydrocarbon containing formation using insulated conductor heat sources
CN1508389A (en) * 2002-12-13 2004-06-30 石油大学(北京) Coalbed Gas Thermal Exploitation Method
CN104912522A (en) * 2015-05-11 2015-09-16 中国矿业大学 Combined drainage and mining device and technology for coal-bed gas well in high stress area
CN106884638A (en) * 2017-04-14 2017-06-23 太原理工大学 A kind of In Situ Heating method of coal bed gas heating exploitation
CN206860160U (en) * 2017-06-26 2018-01-09 山西页岩气有限公司 The gas yield-increasing apparatus of coal measures three
CN107701157A (en) * 2017-09-30 2018-02-16 太原理工大学 A kind of device and method of underground heat injection transformation coal seam physical characteristic

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4456186A (en) * 1981-03-09 1984-06-26 Chisso Engineering Co. Ltd. Electrically heated reactor for high temperature and pressure chemical reactions
US20020033253A1 (en) * 2000-04-24 2002-03-21 Rouffignac Eric Pierre De In situ thermal processing of a hydrocarbon containing formation using insulated conductor heat sources
CN1508389A (en) * 2002-12-13 2004-06-30 石油大学(北京) Coalbed Gas Thermal Exploitation Method
CN104912522A (en) * 2015-05-11 2015-09-16 中国矿业大学 Combined drainage and mining device and technology for coal-bed gas well in high stress area
CN106884638A (en) * 2017-04-14 2017-06-23 太原理工大学 A kind of In Situ Heating method of coal bed gas heating exploitation
CN206860160U (en) * 2017-06-26 2018-01-09 山西页岩气有限公司 The gas yield-increasing apparatus of coal measures three
CN107701157A (en) * 2017-09-30 2018-02-16 太原理工大学 A kind of device and method of underground heat injection transformation coal seam physical characteristic

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110578508A (en) * 2019-08-05 2019-12-17 邓惠荣 Horizontal well one-well multi-mining combined coal bed gas mining and coal gasification method

Similar Documents

Publication Publication Date Title
CN201212387Y (en) Gas injection, gas production and brine discharge integration process pipe column for underground gas storage
CN110029968B (en) Device for drilling hydrate micro well and quickly completing well and working method
CN105625993B (en) Hot dry rock multi-cycle heating system and its production method
CN110397428A (en) A coalbed methane displacement method for joint exploitation of coalbed methane by vertical wells and U-shaped butt-joint wells
CN103321622A (en) Sand draining and oil extracting method in manner of integrating injection and extraction for thermal producing well and device thereof
CN106930730A (en) A kind of pumping method of abandoned mine goaf coal bed gas
CN201218066Y (en) Down-hole decompression tool
CN204941480U (en) The horizontal well completion sleeve pipe of segmentation exploitation and the tubing string of formation thereof can be realized
CN109519157A (en) Heat yield-increasing technique in coal bed gas well underground
CN201620768U (en) Self-spraying and lifting combined pipe column
CN201100124Y (en) An under-well pipe pole for hot collection of thick oil
CN212428755U (en) Oil pipe water-mixing steam-injection hollow rod oil extraction integrated pipe column
CN202900204U (en) Underground throttle for continuous oil pipe
CN203321478U (en) Switch fracturing sliding sleeve
CN105178934A (en) Horizontal well throttling-free straddle type double-seal single-clamp fracturing process
CN101936152A (en) Seaborne thick oil thermal extracting and lifting technology and device
CN107630693B (en) Be applied to shale gas exploitation's electronic hydraulic fracturing device
CN202338290U (en) Integrated tubular column with double-seal gas lift well completion
CN201972681U (en) Heat injection and mechanical oil extraction integrated device
CN202348231U (en) Geothermal wellbore insulating system
CN204627573U (en) Tubular column equipment of two horizontal wells of SAGD
CN214944177U (en) CO (carbon monoxide)2Oil well driving non-killing oil production pipe column
CN205297515U (en) Coiled tubing drags hydraulic jet fracturing unit
CN110318712B (en) Underground hydraulic motor special for oil extraction
CN204609843U (en) Hydraulic drive type oil extraction system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190326

RJ01 Rejection of invention patent application after publication