CN109487750A - Pile formula semicircular wave breaker structure and construction method - Google Patents

Pile formula semicircular wave breaker structure and construction method Download PDF

Info

Publication number
CN109487750A
CN109487750A CN201811552195.5A CN201811552195A CN109487750A CN 109487750 A CN109487750 A CN 109487750A CN 201811552195 A CN201811552195 A CN 201811552195A CN 109487750 A CN109487750 A CN 109487750A
Authority
CN
China
Prior art keywords
pile
foundation pile
semi
foundation
circular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811552195.5A
Other languages
Chinese (zh)
Inventor
王晓晖
李晓舟
黄东海
孙鹏
杨琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waterway Engineering Design and Consulting Co Ltd
Original Assignee
Shanghai Waterway Engineering Design and Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waterway Engineering Design and Consulting Co Ltd filed Critical Shanghai Waterway Engineering Design and Consulting Co Ltd
Priority to CN201811552195.5A priority Critical patent/CN109487750A/en
Publication of CN109487750A publication Critical patent/CN109487750A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/062Constructions floating in operational condition, e.g. breakwaters or wave dissipating walls
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

Pile formula semicircular wave breaker structure and construction method, structure include: top semi-circular structure, foundation pile structure and grouting material, and top semi-circular structure is fixedly connected by grouting material with foundation pile structure.Wherein, foundation pile structure includes: foundation pile, blotter and river bottom protection block stone.The present invention is compared with traditional technology, and by the advantage using conjugate semi-circular structure and foundation pile structure, top semi-circular structure, which provides, resists the functions such as wave stroke, water blocking sand, and lower part pile foundation provides vertical and horizontal direction bearing capacity.Breakwater bedding only can be flattened simply, do not have to carry out stiffening basic ground, construction time and construction cost is greatly saved.Built semi-circular structure can also be used as the operation platform for closing on block pile foundation, improve construction efficiency, save ship machine expense.The geology that this invention works is relatively deep particularly suitable for the depth of water, top Soft Soil Layer is thicker, may be used as breakwater or waterway regulation building etc..

Description

Pile formula semicircular wave breaker structure and construction method
Technical field
The present invention relates to water conservancies, marine traffic engineering field, and in particular to pile formula semicircular wave breaker structure and construction method.
Background technique
Breakwater structure is built under the poor geological condition of soil property, generally requires carry out basement process.The depth of water it is relatively deep, The thicker region of Soft Soil Layer, often project cost is very high for conventional method for processing foundation.
To solve the above-mentioned problems, we are made that a series of improvement.
Summary of the invention
The object of the present invention is to provide pile formula semicircular wave breaker structure and construction methods, to overcome the prior art Existing disadvantages mentioned above and deficiency.
Pile formula semicircular wave breaker structure includes: top semi-circular structure, foundation pile structure and grouting material, top semicircular body Structure is fixedly connected by grouting material with foundation pile structure;
Wherein, the foundation pile structure includes: foundation pile, blotter and river bottom protection block stone, the foundation pile by grouting material with it is upper Portion semi-circular structure two sides are fixedly connected, and the blotter is connect with foundation pile, are connected on the outside of the river bottom protection block stone and blotter It connects, for the structure of the foundation pile for elongated structure or by more piece stake connection structure, the quantity of the foundation pile is 4.
Further, the top semi-circular structure includes: top semicircular body and preformed hole, and the preformed hole is set to top half Circle two sides, the quantity of the preformed hole are 4, and the preformed hole is connect by grouting material with foundation pile, the top semicircular body Structure be hollow reinforced concrete structure.
Pile formula semicircular breakwater construction method, it is characterised in that: the following steps are included:
Step 1: pressing four foundation stake of floating piling construction technology, the measures such as pile sinking leading truck can be taken to guarantee foundation pile position Accuracy.
Step 2: being laid with blotter.
Step 3: being lightered by plate to construction site after the completion of the prefabrication of semi-circular concrete units of top.
Step 4: crane barge ship places semicircular body using special hanger.
Step 5: grout sealing device being installed after adjusting semicircle body position.
Step 6: injecting high-strength grout in the annulus between foundation pile and preformed hole.
Step 7: being sequentially completed the construction of remaining pile formula semi-circular structure, in structure two sides throwing river bottom protection block stone, complete stake Hold the construction of formula semicircular breakwater.
Beneficial effects of the present invention:
The present invention passes through the advantage using conjugate semi-circular structure and foundation pile structure, top half compared with traditional technology Circle structure, which provides, resists the functions such as wave stroke, water blocking sand, and lower part pile foundation provides vertical and horizontal direction bearing capacity.Anti- wave Levee foundation bed only can be flattened simply, do not have to carry out stiffening basic ground, construction time and construction cost is greatly saved.It is built Semi-circular structure can also be used as the operation platform for closing on block pile foundation, improve construction efficiency, save ship machine expense.This invention The geology that works is relatively deep particularly suitable for the depth of water, top Soft Soil Layer is thicker, may be used as breakwater or waterway regulation building Deng.
Detailed description of the invention:
Fig. 1 is the structural diagram of the present invention.
Appended drawing reference:
Top semi-circular structure 100, top semicircular body 110 and preformed hole 120.
Foundation pile structure 200, foundation pile 210, blotter 220, river bottom protection block stone 230 and grouting material 300.
Specific embodiment
Below in conjunction with specific embodiment, progress explanation is made to the present invention.It should be understood that following embodiment is merely to illustrate this hair It is bright not for limiting the scope of the invention.
Embodiment 1
Fig. 1 is the structural diagram of the present invention.
As shown in Figure 1, pile formula semicircular wave breaker structure includes: top semi-circular structure 100,200 and of foundation pile structure Grouting material 300, top semi-circular structure 100 are fixedly connected by grouting material 300 with foundation pile structure 200;
Wherein, foundation pile structure 200 includes: foundation pile 210, blotter 220 and river bottom protection block stone 230, and foundation pile 210 passes through grouting Material 300 is fixedly connected with 100 two sides of top semi-circular structure, and blotter 220 is connect with foundation pile 210, river bottom protection block stone 230 with it is broken It is connected on the outside of stone bed course 220, for the structure of foundation pile 210 for elongated structure or by more piece stake connection structure, the quantity of foundation pile 210 is 4 Root.
Top semi-circular structure 100 includes: top semicircular body 110 and preformed hole 120, and preformed hole 120 is set to top semicircle 110 two sides of body, the quantity of preformed hole 120 are 4, and preformed hole 120 is connect by grouting material 300 with foundation pile 210, top semicircular body 110 structure is hollow reinforced concrete structure.
Pile formula semicircular breakwater construction method the following steps are included:
Step 1: pressing four foundation stake of floating piling construction technology, the measures such as pile sinking leading truck can be taken to guarantee foundation pile position Accuracy.
Step 2: being laid with blotter.
Step 3: being lightered by plate to construction site after the completion of the prefabrication of semi-circular concrete units of top.
Step 4: crane barge ship places semicircular body using special hanger.
Step 5: grout sealing device being installed after adjusting semicircle body position.
Step 6: injecting high-strength grout in the annulus between foundation pile and preformed hole.
Step 7: being sequentially completed the construction of remaining pile formula semi-circular structure, in structure two sides throwing river bottom protection block stone, complete stake Hold the construction of formula semicircular breakwater.
The working principle of the invention is that 110 part preformed hole of top semicircular body, 120 diameter is slightly larger than 210 diameter of foundation pile, Top semi-circular structure 100 is aligned after the completion of constructing and places by foundation pile 210, and it is heavy that limit can be set as needed on 210 top of foundation pile Device, top semi-circular structure 100 are connect with lower part foundation pile 210 using high-strength grout 300.Top semicircular body 110 is hollow Reinforced concrete structure, wall thickness and scale according to works Force Calculation and function it needs to be determined that.Foundation pile 210 be elongated structure or It is connected and composed by more piece stake, can be PHC tubular pole, PC tubular pole, steel-pipe pile, filled circles stake, solid square pile, hollow square pile, TSC Or PRC;Foundation pile 210 can connect when more piece being used to connect for same type stake or different types of built pile.The present invention passes through Using the advantage of conjugate semi-circular structure and foundation pile structure, top semi-circular structure, which provides, resists wave stroke, water blocking sand Etc. functions, lower part pile foundation provide vertical and horizontal direction bearing capacity.Breakwater bedding only can be flattened simply, not have to carry out ground Construction time and construction cost is greatly saved in base consolidation process.Built semi-circular structure, which can also be used as, closes on block pile foundation Operation platform, improve construction efficiency, save ship machine expense.This invention works is particularly suitable for the depth of water compared with deep, top is soft The geology of thicker soil may be used as breakwater or waterway regulation building etc..
A specific embodiment of the invention is illustrated above, but the present invention is not limited thereto, without departing from Spirit of the invention, the present invention can also have various change.

Claims (3)

1. pile formula semicircular wave breaker structure characterized by comprising top semi-circular structure (100), foundation pile structure (200) and grouting material (300), the top semi-circular structure (100) are fixed by grouting material (300) and foundation pile structure (200) Connection;
Wherein, the foundation pile structure (200) includes: foundation pile (210), blotter (220) and river bottom protection block stone (230), the base Stake (210) is fixedly connected by grouting material (300) with top semi-circular structure (100) two sides, the blotter (220) and base It is connect on the outside of stake (210) connection, the river bottom protection block stone (230) and blotter (220), the structure of the foundation pile (210) is logical Long structure or by more piece stake connection structure, the quantity of the foundation pile (210) is 4.
2. pile formula semicircular wave breaker structure according to claim 1, it is characterised in that: the top semi-circular structure It (100) include: top semicircular body (110) and preformed hole (120), the preformed hole (120) is set to top semicircular body (110) two Side, the quantity of the preformed hole (120) are 4, and the preformed hole (120) is connect by grouting material (300) with foundation pile (210), The structure of the top semicircular body (110) is hollow reinforced concrete structure.
3. pile formula semicircular breakwater construction method, it is characterised in that: the following steps are included:
Step 1: pressing four foundation stake of floating piling construction technology, the measures such as pile sinking leading truck can be taken to guarantee the accurate of foundation pile position Degree;
Step 2: being laid with blotter;
Step 3: being lightered by plate to construction site after the completion of the prefabrication of semi-circular concrete units of top;
Step 4: crane barge ship places semicircular body using special hanger;
Step 5: grout sealing device being installed after adjusting semicircle body position;
Step 6: injecting high-strength grout in the annulus between foundation pile and preformed hole;
Step 7: being sequentially completed the construction of remaining pile formula semi-circular structure, in structure two sides throwing river bottom protection block stone, complete pile formula Semicircular breakwater construction.
CN201811552195.5A 2018-12-18 2018-12-18 Pile formula semicircular wave breaker structure and construction method Pending CN109487750A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811552195.5A CN109487750A (en) 2018-12-18 2018-12-18 Pile formula semicircular wave breaker structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811552195.5A CN109487750A (en) 2018-12-18 2018-12-18 Pile formula semicircular wave breaker structure and construction method

Publications (1)

Publication Number Publication Date
CN109487750A true CN109487750A (en) 2019-03-19

Family

ID=65710679

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811552195.5A Pending CN109487750A (en) 2018-12-18 2018-12-18 Pile formula semicircular wave breaker structure and construction method

Country Status (1)

Country Link
CN (1) CN109487750A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158538A (en) * 2019-05-28 2019-08-23 武汉中力岩土工程有限公司 Pile formula semicircular wave breaker structure and construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0723022U (en) * 1993-10-07 1995-04-25 新日本製鐵株式会社 Breakwater structure
CN2340807Y (en) * 1998-04-10 1999-09-29 交通部第一航务工程勘察设计院 Wave dissipation breakwater
KR20000018384A (en) * 1998-09-01 2000-04-06 황해웅 Air floating type breakwater using semicircle mat
CN1970888A (en) * 2005-11-23 2007-05-30 天津得鑫电机有限公司 Semicircular breakwater
CN104314042A (en) * 2014-10-22 2015-01-28 天津港航工程有限公司 Construction method of breakwater in pile-supported cylindrical caisson structure
CN106522157A (en) * 2016-11-24 2017-03-22 河海大学 Self-power-generation type breakwater device and power generation method thereof
CN108867547A (en) * 2018-08-19 2018-11-23 天津大学 The construction method of semi-circular caisson and pile foundation combined type breakwater
CN108999142A (en) * 2018-08-19 2018-12-14 天津大学 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
CN209603047U (en) * 2018-12-18 2019-11-08 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0723022U (en) * 1993-10-07 1995-04-25 新日本製鐵株式会社 Breakwater structure
CN2340807Y (en) * 1998-04-10 1999-09-29 交通部第一航务工程勘察设计院 Wave dissipation breakwater
KR20000018384A (en) * 1998-09-01 2000-04-06 황해웅 Air floating type breakwater using semicircle mat
CN1970888A (en) * 2005-11-23 2007-05-30 天津得鑫电机有限公司 Semicircular breakwater
CN104314042A (en) * 2014-10-22 2015-01-28 天津港航工程有限公司 Construction method of breakwater in pile-supported cylindrical caisson structure
CN106522157A (en) * 2016-11-24 2017-03-22 河海大学 Self-power-generation type breakwater device and power generation method thereof
CN108867547A (en) * 2018-08-19 2018-11-23 天津大学 The construction method of semi-circular caisson and pile foundation combined type breakwater
CN108999142A (en) * 2018-08-19 2018-12-14 天津大学 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
CN209603047U (en) * 2018-12-18 2019-11-08 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨甜丽: "自由水面透空式半圆体防波堤水动力性能研究", 硕士电子期刊工程科技Ⅱ辑, no. 9, pages 2 - 4 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158538A (en) * 2019-05-28 2019-08-23 武汉中力岩土工程有限公司 Pile formula semicircular wave breaker structure and construction method

Similar Documents

Publication Publication Date Title
CN1837512B (en) Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN103015367B (en) High-efficiency economical construction method for revetment
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN104314042B (en) Adopt the levee construction method of pile formula case barrel structure
CN203684242U (en) Mud flat area geotechnical bag mud composite cofferdam type underwater construction platform
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN103397634A (en) Anchoring construction method for fastener steel tube pile cofferdam
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN107059914A (en) A kind of ring-type for being used for shallow overburden or naked rock area in water is embedded to set basis
CN204456058U (en) A kind of constructing structure reducing building base subsidence speed
CN110241813A (en) A kind of buried prefabricated tubular pile of transmission line of electricity brill
CN206503157U (en) The embedding rock mixing pile foundation of offshore wind farm
CN109487750A (en) Pile formula semicircular wave breaker structure and construction method
CN204282295U (en) Pile formula case cylinder breakwater structure
CN209603047U (en) Pile formula semicircular wave breaker structure
CN204266164U (en) Concrete veneer and grill-shaped cement soil wall combined type bank protection structure
CN215441846U (en) Foundation anti-settling structure
CN102146669B (en) Movable/fixed man-made island cylindrical foundation
CN201738286U (en) Tetrapod pier type structure
CN212026234U (en) Combined cofferdam of jet grouting pile and submerged large-diameter cylinder
CN210151776U (en) Structure of balance weight type retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination