CN109472426A - Material cost management method, system, storage medium and the terminal device of live project - Google Patents
Material cost management method, system, storage medium and the terminal device of live project Download PDFInfo
- Publication number
- CN109472426A CN109472426A CN201710799815.4A CN201710799815A CN109472426A CN 109472426 A CN109472426 A CN 109472426A CN 201710799815 A CN201710799815 A CN 201710799815A CN 109472426 A CN109472426 A CN 109472426A
- Authority
- CN
- China
- Prior art keywords
- information
- project
- live
- cost management
- consumption
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 title claims abstract description 259
- 238000007726 management method Methods 0.000 title claims abstract description 43
- 238000004590 computer program Methods 0.000 claims description 9
- 230000015654 memory Effects 0.000 claims description 9
- 238000004422 calculation algorithm Methods 0.000 claims description 8
- 238000000034 method Methods 0.000 claims description 4
- 230000005055 memory storage Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 17
- 238000005516 engineering process Methods 0.000 description 5
- RTZKZFJDLAIYFH-UHFFFAOYSA-N Diethyl ether Chemical compound CCOCC RTZKZFJDLAIYFH-UHFFFAOYSA-N 0.000 description 4
- 238000009430 construction management Methods 0.000 description 4
- 230000009467 reduction Effects 0.000 description 4
- 238000007619 statistical method Methods 0.000 description 4
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 239000011449 brick Substances 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 230000007123 defense Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000011521 glass Substances 0.000 description 2
- 238000010801 machine learning Methods 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- -1 reinforcing bar Substances 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000012549 training Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 239000013077 target material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention provides material cost management method, system, storage medium and the terminal device of a kind of live project, comprising the following steps: planning materials information needed for the project information based on predetermined material consumption models and live project obtains live project;Obtain the real material information of live project consumption;The planning materials information and the real material information are compared, comparison result is obtained.Material cost management method, system, storage medium and the terminal device of live project of the invention obtain the planning materials information of live project according to predetermined material consumption models, and the cost management to material is realized in the comparison based on planning materials information and real material information, so that it is cheer and bright for the material cost management of live project, it is practical.
Description
Technical field
The present invention relates to the technical fields of software management, more particularly to a kind of material cost management side of live project
Method, system, storage medium and terminal device.
Background technique
Building Information Model (Building Information Modeling, BIM) is after CAD (CAD
The another important Computer Applied Technology of engineering construction industry is appeared in after technology, and it is once unprecedented to cause building trade
Thorough revolution.The technology utilizes digital modeling software, improves Project design, the efficiency of construction and management, and to using the skill
The building enterprise of art brings great newly-increased value.
Design is improved using BIM platform at present, avoids doing over again, carries out analogue simulation, Optimizing Construction Scheme etc. with BIM
The relative maturity that technology has been applied.But for how to be still needed to further to carry out the material cost management of live project using BIM
Exploitation.
Summary of the invention
In view of the foregoing deficiencies of prior art, the purpose of the present invention is to provide a kind of material costs of live project
Management method, system, storage medium and terminal device are believed according to the planning materials that predetermined material consumption models obtain live project
Breath, and the cost management to material is realized in the comparison based on planning materials information and real material information, so that for live item
Target material cost management is cheer and bright, practical.
In order to achieve the above objects and other related objects, the present invention provides a kind of material cost management side of live project
Method, comprising the following steps: based on needed for the live project of the project information acquisition of predetermined material consumption models and live project
Draw material information;Obtain the real material information of live project consumption;Compare the planning materials information and the real material
Information obtains comparison result.
In one embodiment of the invention, the planning materials information is showed and is led by way of table and/or gunter drawing
Out.
In one embodiment of the invention, the predetermined material consumption models are using preset algorithm to a certain number of complete
It is obtained at the material consumption information and project information of live project are for statistical analysis.
In one embodiment of the invention, go out to be put in storage real material information described in acquisition of information according to the material received.
It further include when the planning materials information and the real material information are inconsistent in one embodiment of the invention
When, issue prompting message.
Accordingly, the present invention also provides a kind of material cost management system of live project, including first obtains module, the
Two obtain module and comparison module;
Described first, which obtains module, is used to obtain scene based on the project information of predetermined material consumption models and live project
Planning materials information needed for project;
The second acquisition module is used to obtain the real material information of live project consumption;
The comparison module obtains comparison result for comparing the planning materials information and the real material information.
In one embodiment of the invention, the first acquisition module is also used to the planning materials information passing through table
And/or the form of gunter drawing shows and exports.
In one embodiment of the invention, the predetermined material consumption models are using preset algorithm to a certain number of complete
It is obtained at the material consumption information and project information of live project are for statistical analysis.
In one embodiment of the invention, described second obtains module goes out to be put in storage described in acquisition of information according to the material received
Real material information.
It further include reminding module in one embodiment of the invention, in the planning materials information and the practical material
When expecting that information is inconsistent, prompting message is issued.
Meanwhile the present invention also provides a kind of storage medium, it is stored thereon with computer program, which is executed by processor
The material cost management method of Shi Shixian live project described in any of the above embodiments.
Finally, the present invention also provides a kind of terminal device, including communicator, processor and memory;
The communicator is used to obtain the project information and real material information of live project;
The memory is for storing computer program;
The project information and real material information for the live project that the processor is used to be obtained according to the communicator, hold
The computer program of the row memory storage, to execute the material cost management method of scene project described in any of the above-described.
As described above, material cost management method, system, storage medium and the terminal device of live project of the invention,
It has the advantages that
(1) the planning materials information of live project can be obtained according to predetermined material consumption models, and be based on planning materials
The cost management to material is realized in the comparison of information and real material information;
(2) cheer and bright for the material cost management of live project, it is advantageously implemented the material cost to live project
Real-time control;
(3) easy to operate, it is practical.
Detailed description of the invention
Fig. 1 is shown as flow chart of the material cost management method of live project of the invention in an embodiment;
Fig. 2 is shown as structural schematic diagram of the material cost management system of live project of the invention in an embodiment;
Fig. 3 is shown as the structural schematic diagram of terminal device of the invention in an embodiment.
Component label instructions
The material cost management system of 1 live project
11 first obtain module
12 second obtain module
13 comparison modules
3 terminal devices
31 communicators
32 processors
33 memories
Specific embodiment
Illustrate embodiments of the present invention below by way of specific specific example, those skilled in the art can be by this specification
Other advantages and efficacy of the present invention can be easily understood for disclosed content.The present invention can also pass through in addition different specific realities
The mode of applying is embodied or practiced, the various details in this specification can also based on different viewpoints and application, without departing from
Various modifications or alterations are carried out under spirit of the invention.It should be noted that in the absence of conflict, following embodiment and implementation
Feature in example can be combined with each other.
It should be noted that illustrating the basic structure that only the invention is illustrated in a schematic way provided in following embodiment
Think, only shown in schema then with related component in the present invention rather than component count, shape and size when according to actual implementation
Draw, when actual implementation kenel, quantity and the ratio of each component can arbitrarily change for one kind, and its assembly layout kenel
It is likely more complexity.
Material cost management method, system, storage medium and the terminal device of live project of the invention can be according to pre-
If material consumption model obtains the planning materials information of live project, and the ratio based on planning materials information and real material information
To realizing cost management to material, so as to realize live project material cost real-time control.It should be noted that
Scene project involved in the present invention includes but is not limited to building site project.
As shown in Figure 1, the material cost management method of live project of the invention includes following step in an embodiment
It is rapid:
Step S1, plan needed for the project information based on predetermined material consumption models and live project obtains live project
Material information.
In the present invention, planning materials information needed for live project being obtained by predetermined material consumption models.Also
It is to say, for specific live project, its project information, which is input to the predetermined material consumable module, automatically to be obtained
Take required planning materials information.
Preferably, the project information of live project includes floor quantity, floor attribute, the house type letter for being under the jurisdiction of same floor
Breath etc..The floor attribute includes underground garage, people's air defense garage, lobby floor, inhabitation layer, office layer etc..For different
Floor attribute, predetermined material consumption models correspond to different material consumption parameters.Meanwhile predetermined material consumption models are also according to building
Layer number and it is under the jurisdiction of the house type information of same floor the plan consumption of required various types of materials is arranged.
Preferably, the planning materials information includes the material type and corresponding consumption of materials of plan consumption.
In one embodiment of the invention, the predetermined material consumption models are using preset algorithm to a certain number of complete
It is obtained at the material consumption information and project information of live project are for statistical analysis.Specifically, a certain number of to be completed
The material consumption information and project information of live project carry out machine learning as training sample, based on preset algorithm, and then obtain
To corresponding predetermined material consumption models.The predetermined material consumption models can obtain institute based on each project information of live project
The plan consumption of the various types of materials needed.For example, learning every floor for the building site project in a 2 floor rooms
After the house type parameter in room, the meter of the materials such as cement, reinforcing bar, glass, brick can be obtained according to the predetermined material consumable module
Cancellation consumption.Therefore, predetermined material consumption models of the present invention have very strong data foundation, so as to avoid by people
The subjective uncertainty of the empirically determined consumption of materials of work.
In one embodiment of the invention, the planning materials information can be showed by way of table and/or gunter drawing
And export, in order to which the plan consumption of various types of materials is clearly understood quickly.
Step S2, the real material information of live project consumption is obtained.
The real material information of live project consumption can be obtained by following either type in the present invention:
A) the real material information that construction personnel is manually entered is obtained.
Specifically, construction personnel is manually entered the real material information of live project with predetermined period, i.e. a variety of materials
Actual consumption amount.For example, construction personnel is at interval of the real material information for being manually entered primary live project a week, thus just
In the actual consumption amount of statistical material.Wherein, the length of predetermined period cannot be too long, in case construction personnel is too long due to the time
Leading to the real material information of input has deviation;The length of predetermined period also can not ether it is short, to increase the work of construction personnel
It measures, is unfavorable for the coordination arrangement of construction speed.Specific predetermined period need to arrange according to the property of live project, construction, people
The factors such as member's configuration are rationally arranged.
2) material that reception warehouse terminal or construction management end are sent goes out storage information, goes out to be put in storage letter based on the material
Breath obtains the real material information of live project consumption.
Specifically, it by being communicatively coupled with warehouse terminal or construction management terminal, obtains material and goes out storage information.It is silent
Recognize library material amount and subtracts the actual consumption amount that storage quantity of material is material.Which can not only obtain the reality of material in real time
Border consumption, and manually input bring error is avoided, accuracy is high.
Step S3, the planning materials information and the real material information are compared, comparison result is obtained.
Specifically, it based on acquired planning materials information and real material information, is compared, obtains comparison result.
The comparison result includes that material consumption maintains an equal level, material consumption excess and material consumption are reduced.Wherein, material consumption maintains an equal level and refers to
Actual material consumption amount is equal to planning materials consumption;Material consumption excessively refers to that actual material consumption amount disappears greater than planning materials
Consumption;Material consumption reduction refers to that actual material consumption amount is less than planning materials consumption.
It further include when the planning materials information and the real material information are inconsistent in one embodiment of the invention
When, issue prompting message.Preferably, the prompting message includes voice messaging, text information, particular color highlighted information
One of or multiple combinations.Wherein, particular color highlighted information, which refers to, is highlighted planning materials using particular color
Information and real material information are to show that material consumption is excessive and material consumption reduces.For example, use is red when material consumption excess
Color is highlighted real material information;When material consumption reduction, it is highlighted planning materials information with green, thus clear bright
Ground illustrates material consumption as a result, the user experience is improved.
As shown in Fig. 2, the material cost management system 1 of live project of the invention is obtained including first in an embodiment
Modulus block 11, second obtains module 12 and comparison module 13.
First, which obtains module 11, is used to obtain live item based on the project information of predetermined material consumption models and live project
Planning materials information needed for mesh.
In the present invention, planning materials information needed for live project being obtained by predetermined material consumption models.Also
It is to say, for specific live project, its project information, which is input to the predetermined material consumable module, automatically to be obtained
Take required planning materials information.
Preferably, the project information of live project includes floor quantity, floor attribute, the house type letter for being under the jurisdiction of same floor
Breath etc..The floor attribute includes underground garage, people's air defense garage, lobby floor, inhabitation layer, office layer etc..For different
Floor attribute, predetermined material consumption models correspond to different material consumption parameters.Meanwhile predetermined material consumption models are also according to building
Layer number and it is under the jurisdiction of the house type information of same floor the plan consumption of required various types of materials is arranged.
Preferably, the planning materials information includes the material type and corresponding consumption of materials of plan consumption.
In one embodiment of the invention, the predetermined material consumption models are using preset algorithm to a certain number of complete
It is obtained at the material consumption information and project information of live project are for statistical analysis.Specifically, a certain number of to be completed
The material consumption information and project information of live project carry out machine learning as training sample, based on preset algorithm, and then obtain
To corresponding predetermined material consumption models.The predetermined material consumption models can obtain institute based on each project information of live project
The plan consumption of the various types of materials needed.For example, learning every floor for the building site project in a 2 floor rooms
After the house type parameter in room, the meter of the materials such as cement, reinforcing bar, glass, brick can be obtained according to the predetermined material consumable module
Cancellation consumption.Therefore, predetermined material consumption models of the present invention have very strong data foundation, so as to avoid by people
The subjective uncertainty of the empirically determined consumption of materials of work.
In one embodiment of the invention, first acquisition module 11 be also used to by the planning materials information by table and/
Or the form of gunter drawing shows and exports, in order to which the plan consumption of various types of materials is clearly understood quickly.
Second acquisition module 12 is used to obtain the real material information of live project consumption.
The real material information of live project consumption can be obtained by following either type in the present invention:
A) the real material information that construction personnel is manually entered is obtained.
Specifically, construction personnel is manually entered the real material information of live project with predetermined period, i.e. a variety of materials
Actual consumption amount.For example, construction personnel is at interval of the real material information for being manually entered primary live project a week, thus just
In the actual consumption amount of statistical material.Wherein, the length of predetermined period cannot be too long, in case construction personnel is too long due to the time
Leading to the real material information of input has deviation;The length of predetermined period also can not ether it is short, to increase the work of construction personnel
It measures, is unfavorable for the coordination arrangement of construction speed.Specific predetermined period need to arrange according to the property of live project, construction, people
The factors such as member's configuration are rationally arranged.
2) material that reception warehouse terminal or construction management end are sent goes out storage information, goes out to be put in storage letter based on the material
Breath obtains the real material information of live project consumption.
Specifically, it by being communicatively coupled with warehouse terminal or construction management terminal, obtains material and goes out storage information.It is silent
Recognize library material amount and subtracts the actual consumption amount that storage quantity of material is material.Which can not only obtain the reality of material in real time
Border consumption, and manually input bring error is avoided, accuracy is high.
Comparison module 13 is connected with the first acquisition module 11 and the second acquisition module 12, for comparing the planning materials letter
Breath and the real material information obtain comparison result.
Specifically, it based on acquired planning materials information and real material information, is compared, obtains comparison result.
The comparison result includes that material consumption maintains an equal level, material consumption excess and material consumption are reduced.Wherein, material consumption maintains an equal level and refers to
Actual material consumption amount is equal to planning materials consumption;Material consumption excessively refers to that actual material consumption amount disappears greater than planning materials
Consumption;Material consumption reduction refers to that actual material consumption amount is less than planning materials consumption.
It further include reminding module in one embodiment of the invention, in the planning materials information and the practical material
When expecting that information is inconsistent, prompting message is issued.Preferably, the prompting message includes voice messaging, text information, particular color
One of highlighted information or multiple combinations.Wherein, particular color highlighted information refers to highlighted using particular color
Display planning materials information and real material information are to show that material consumption is excessive and material consumption reduces.For example, when material disappears
When consumption is excessive, real material information is highlighted with red;When material consumption reduction, planning materials letter is highlighted with green
Breath, to illustrate material consumption cheer and brightly as a result, the user experience is improved.
It is stored with computer program on storage medium of the invention, which realizes any of the above-described when being executed by processor
The material cost management method of the live project.Preferably, the storage medium includes: ROM, RAM, magnetic or disk
Etc. the various media that can store program code.
As shown in figure 3, terminal device 3 of the invention includes communicator 31, processor 32 and memory in an embodiment
33。
The communicator 31 is used to obtain the project information and real material information of live project.
The memory 33 is for storing computer program.
The processor 32 is connected with the communicator 31 and the memory 33, for being obtained according to the communicator 31
Live project project information and real material information, the computer program that the memory 31 stores is executed, on executing
State the material cost management method of any one live project.
Preferably, processor 32 can be general processor, including central processing unit (CentralProcessingUnit,
Abbreviation CPU), network processing unit (NetworkProcessor, abbreviation NP) etc.;It can also be digital signal processor
(DigitalSignalProcessing, abbreviation DSP), specific integrated circuit
(ApplicationSpecificIntegratedCircuit, abbreviation ASIC), field programmable gate array (Field-
ProgrammableGateArray, abbreviation FPGA) either other programmable logic device, discrete gate or transistor logic device
Part, discrete hardware components.
In conclusion the material cost management method of live project of the invention, system, storage medium and terminal device energy
The enough planning materials information that live project is obtained according to predetermined material consumption models, and it is based on planning materials information and real material
The cost management to material is realized in the comparison of information;It is cheer and bright for the material cost management of live project, it is advantageously implemented
Real-time control to the material cost of live project;It is easy to operate, it is practical.So the present invention effectively overcomes existing skill
Various shortcoming in art and have high industrial utilization value.
The above-described embodiments merely illustrate the principles and effects of the present invention, and is not intended to limit the present invention.It is any ripe
The personage for knowing this technology all without departing from the spirit and scope of the present invention, carries out modifications and changes to above-described embodiment.Cause
This, institute is complete without departing from the spirit and technical ideas disclosed in the present invention by those of ordinary skill in the art such as
At all equivalent modifications or change, should be covered by the claims of the present invention.
Claims (12)
1. a kind of material cost management method of scene project, it is characterised in that: the following steps are included:
Planning materials information needed for project information based on predetermined material consumption models and live project obtains live project;
Obtain the real material information of live project consumption;
The planning materials information and the real material information are compared, comparison result is obtained.
2. the material cost management method of scene project according to claim 1, it is characterised in that: the planning materials letter
Breath is showed and is exported by way of table and/or gunter drawing.
3. the material cost management method of scene project according to claim 1, it is characterised in that: the predetermined material disappears
Consumption model is to be united using preset algorithm to a certain number of material consumption information that live project is completed and project information
Meter analysis obtains.
4. the material cost management method of scene project according to claim 1, it is characterised in that: according to the material received
Expect to be put in storage real material information described in acquisition of information out.
5. the material cost management method of scene project according to claim 1, it is characterised in that: further include when the meter
When drawing material information and the inconsistent real material information, prompting message is issued.
6. a kind of material cost management system of scene project, it is characterised in that: obtain module, the second acquisition module including first
And comparison module;
Described first, which obtains module, is used to obtain live project based on the project information of predetermined material consumption models and live project
Required planning materials information;
The second acquisition module is used to obtain the real material information of live project consumption;
The comparison module obtains comparison result for comparing the planning materials information and the real material information.
7. the material cost management system of scene project according to claim 6, it is characterised in that: described first obtains mould
Block is also used to that the planning materials information is showed and exported by way of table and/or gunter drawing.
8. the material cost management system of scene project according to claim 6, it is characterised in that: the predetermined material disappears
Consumption model is to be united using preset algorithm to a certain number of material consumption information that live project is completed and project information
Meter analysis obtains.
9. the material cost management system of scene project according to claim 6, it is characterised in that: described second obtains mould
Root tuber goes out to be put in storage real material information described in acquisition of information according to the material received.
10. the material cost management system of scene project according to claim 6, it is characterised in that: further include reminding mould
Block, for issuing prompting message in the planning materials information and the inconsistent real material information.
11. a kind of storage medium, is stored thereon with computer program, which is characterized in that the realization when program is executed by processor
The material cost management method of live project described in any one of claims 1 to 5.
12. a kind of terminal device, it is characterised in that: including communicator, processor and memory;
The communicator is used to obtain the project information and real material information of live project;
The memory is for storing computer program;
The project information and real material information for the live project that the processor is used to be obtained according to the communicator execute institute
The computer program of memory storage is stated, with the material cost management of scene project described in any one of perform claim requirement 1 to 5
Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710799815.4A CN109472426A (en) | 2017-09-07 | 2017-09-07 | Material cost management method, system, storage medium and the terminal device of live project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710799815.4A CN109472426A (en) | 2017-09-07 | 2017-09-07 | Material cost management method, system, storage medium and the terminal device of live project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109472426A true CN109472426A (en) | 2019-03-15 |
Family
ID=65657971
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710799815.4A Pending CN109472426A (en) | 2017-09-07 | 2017-09-07 | Material cost management method, system, storage medium and the terminal device of live project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109472426A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110428222A (en) * | 2019-07-23 | 2019-11-08 | 深圳市莫川建筑空间设计有限公司 | Finishing project management-control method and system |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130090972A1 (en) * | 2011-01-17 | 2013-04-11 | Sung Woo Shin | System for assessing an environmental load of building during life cycle |
CN103337005A (en) * | 2013-05-31 | 2013-10-02 | 中建钢构有限公司 | Management method for engineering progress and cost management system |
CN104680321A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM technology-based visual material control system and method |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105868502A (en) * | 2016-04-22 | 2016-08-17 | 广州硕品物联网科技有限公司 | BIM (building information modeling) based material management system and control method thereof |
CN106056268A (en) * | 2016-05-17 | 2016-10-26 | 北京诺士诚国际工程项目管理有限公司 | Engineering project management cloud platform system based on material tracking |
CN106779325A (en) * | 2016-11-29 | 2017-05-31 | 河北建筑工程学院 | A kind of engineering management monitoring system and method |
CN106897813A (en) * | 2017-01-13 | 2017-06-27 | 同济大学 | A kind of large shield tunnel intelligent management system based on BIM and AI |
CN106934540A (en) * | 2017-03-07 | 2017-07-07 | 西安理工大学 | A kind of architecture engineering material cost budgeting method based on Revit |
CN107133769A (en) * | 2017-05-31 | 2017-09-05 | 浙江精工钢结构集团有限公司 | A kind of intelligent inventory pre-warning management system based on BIM models |
-
2017
- 2017-09-07 CN CN201710799815.4A patent/CN109472426A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130090972A1 (en) * | 2011-01-17 | 2013-04-11 | Sung Woo Shin | System for assessing an environmental load of building during life cycle |
CN103337005A (en) * | 2013-05-31 | 2013-10-02 | 中建钢构有限公司 | Management method for engineering progress and cost management system |
CN104680321A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM technology-based visual material control system and method |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105868502A (en) * | 2016-04-22 | 2016-08-17 | 广州硕品物联网科技有限公司 | BIM (building information modeling) based material management system and control method thereof |
CN106056268A (en) * | 2016-05-17 | 2016-10-26 | 北京诺士诚国际工程项目管理有限公司 | Engineering project management cloud platform system based on material tracking |
CN106779325A (en) * | 2016-11-29 | 2017-05-31 | 河北建筑工程学院 | A kind of engineering management monitoring system and method |
CN106897813A (en) * | 2017-01-13 | 2017-06-27 | 同济大学 | A kind of large shield tunnel intelligent management system based on BIM and AI |
CN106934540A (en) * | 2017-03-07 | 2017-07-07 | 西安理工大学 | A kind of architecture engineering material cost budgeting method based on Revit |
CN107133769A (en) * | 2017-05-31 | 2017-09-05 | 浙江精工钢结构集团有限公司 | A kind of intelligent inventory pre-warning management system based on BIM models |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110428222A (en) * | 2019-07-23 | 2019-11-08 | 深圳市莫川建筑空间设计有限公司 | Finishing project management-control method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105023201B (en) | Assembled architecture Deepen Design and construction method based on BIM and big data | |
Chen et al. | Modeling and performance evaluation of supply chains using batch deterministic and stochastic Petri nets | |
CN105426572B (en) | The exchange method and system of multi-dimensional data and P6 databases based on BIM | |
CN106803150A (en) | Municipal Engineering Construction progress msg management method and system based on BIM | |
CN108573112B (en) | Space flight test emission two-dimensional layout analysis method based on digital simulation | |
CN109558412A (en) | The data growing method and device of assembled architecture construct platform | |
CN107247757A (en) | Construction project document classification storage and retrieval method and system based on BIM | |
Sakikhales et al. | Using agile project management and BIM for improved building performance | |
CN102789520A (en) | Visual modeling method for airplane assembling process | |
CN106326557A (en) | Arrangement method and arrangement device for building decoration | |
CN117173367B (en) | Method and equipment for establishing dynamic landscape plant component library based on Rhino | |
CN109472426A (en) | Material cost management method, system, storage medium and the terminal device of live project | |
CN110019435A (en) | Data processing method and system based on assembled architecture platform | |
CN103902757A (en) | System and method for rapid creation and interaction of three-dimensional model | |
Isikdag et al. | A synopsis of the handbook of research on building information modeling | |
CN108052726A (en) | A kind of building materials business and construction Information uploading system based on BIM models | |
CN105224300B (en) | A kind of visual modeling method based on system member view construction system view | |
Ezema et al. | Industrial design and simulation of a JIT material handling system | |
TWM535357U (en) | Construction history monitoring management system guided by engineering planning | |
CN105205854B (en) | Data center 3D modeling method and device | |
Zhao et al. | Toward automatic calculation of construction quantity based on building information modeling | |
KR20210114621A (en) | Design system of building | |
Liu et al. | Study on BIM technology application prospect in engineering management industry | |
WO2020056671A1 (en) | Data growth method and device for fabricated building construction platform | |
CN109472425A (en) | Labor Cost Management method, system, storage medium and the terminal device of live project |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190315 |