CN109403296A - A kind of pressure fluid jacking type pile pulling technology - Google Patents

A kind of pressure fluid jacking type pile pulling technology Download PDF

Info

Publication number
CN109403296A
CN109403296A CN201811253454.4A CN201811253454A CN109403296A CN 109403296 A CN109403296 A CN 109403296A CN 201811253454 A CN201811253454 A CN 201811253454A CN 109403296 A CN109403296 A CN 109403296A
Authority
CN
China
Prior art keywords
steel
pipe pile
sealing plate
hydraulic pump
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811253454.4A
Other languages
Chinese (zh)
Inventor
葛磊
赵林
石跃权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Deep Ocean Technology Co Ltd
Original Assignee
Qingdao Deep Ocean Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Deep Ocean Technology Co Ltd filed Critical Qingdao Deep Ocean Technology Co Ltd
Priority to CN201811253454.4A priority Critical patent/CN109403296A/en
Publication of CN109403296A publication Critical patent/CN109403296A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

A kind of pressure fluid jacking type pile pulling technology: whole steel-pipe pile is extracted using the method for high pressure water (or compressed air etc.).The technical program embodiment mainly includes mud exhauster, high-pressure hydraulic pump, valve, sealing plate, steel-pipe pile;The mud exhauster excludes the silt inside steel-pipe pile before pile pulling starts;The sealing plate is equipped with valve and for connecting the flange of high-pressure hydraulic pump;Silt inside the steel-pipe pile cleans out sealing welding at the top of rear sealing plate and steel-pipe pile, and does consolidation process to sealing plate, guarantees that sealing plate can bear sufficiently large upward top lift;The valve is used to be vented when high-pressure hydraulic pump fills the water in steel-pipe pile, and valve is closed after exhaust;The high-pressure hydraulic pump fills the water in steel-pipe pile, and high pressure water acts on one upward top lift of formation on sealing plate, and sealing plate drives steel-pipe pile to move upwards.

Description

A kind of pressure fluid jacking type pile pulling technology
Technical field
The invention mainly relates to discarded platform spud leg demolition technique field waterborne, be also related to (across river) bridge over strait, harbour, It is big straight in the retired building of the dismounting of the provisional large diameter steel pipe pile in the fields such as man-made island, treatment of soft foundation and above-mentioned field The dismounting of diameter steel-pipe pile;It is specially a kind of to extract steel-pipe pile by the way of jacking with pressure fluids such as high pressure water, compressed airs Technology.
Background technique
With the development of marine economy, the quantity of marine facility platform is more and more, and the early 21st century, the whole world has more than 7270 marine oil and gas production facilities, the projected life of general marine oil and gas facility at 20 years or so, as marine facility is on active service The extension of time has quite a few facility to all suffer from the problem of reaching the service life period.According to legal requirement, these are arrived Up to economic life period, or appropriate retired discarded dismounting processing must not be carried out in the marine facility used.Marine facility Discarded removal cost is very expensive, and the retired waste disposal of marine oil and gas facility be increasingly becoming offshore petroleum industry one is important Subject under discussion causes everybody extensive concern.
According to country pertinent regulations, need to will be retired after fixed platform steel-pipe pile below the mud face of present position seabed not Position excision less than 4.0m, usually used diamond-wire saw cut, abrasive high-pressure water jet are cut, in hydraulic rotary Cutter is rotatably cut or other vibrations pull out and wait technical methods expense relatively high, under normal circumstances, one pile institute of every cutting The direct cost of generation is up to ten thousand yuan of 30-50.
Summary of the invention
The purpose of the present invention is to provide a kind of pressure fluid jacking type pile pulling technology scheme, the technical program not only can be with Salvage material, and cost can be greatly reduced, while work progress can also be made more safe and environment-friendly.
To achieve the above object, The technical solution adopted by the invention is as follows: coming by taking high pressure water as an example in the technical scheme It is specific to introduce;The technical program embodiment mainly includes mud exhauster, high-pressure hydraulic pump, valve, sealing plate, steel-pipe pile;The mud exhauster The silt inside steel-pipe pile is excluded before pile pulling starts;The sealing plate is equipped with valve and for connecting the method for high-pressure hydraulic pump It is blue;Silt inside the steel-pipe pile cleans out sealing welding at the top of rear sealing plate and steel-pipe pile, and does consolidation process to sealing plate, Guarantee that sealing plate can bear sufficiently large upward top lift;The valve is used to be vented when high-pressure hydraulic pump fills the water in steel-pipe pile, Valve is closed after exhaust;The high-pressure hydraulic pump fills the water in steel-pipe pile, and high pressure water, which acts on sealing plate, forms one upwards Top lift, sealing plate drive steel-pipe pile move upwards.
Detailed description of the invention
Fig. 1 is first step schematic diagram of the invention;
Fig. 2 is second step of the invention, third step, the 4th step, the 5th step schematic diagram;
In figure: 1- mud exhauster, 2- steel-pipe pile, 3- water pump, 4- valve, 5- flange, 6- sealing plate, 7- pressure duct, 8- high pressure Water pump.
Specific embodiment
Below in conjunction with attached drawing 1, attached drawing 2, technical solution in the embodiment of the present invention progress is clear, is fully described by, Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the technology of the present invention The embodiment of embodiment, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
One, the step method of single steel-pipe pile is extracted:
The first step is filled the water by water pump 3 into steel-pipe pile 2 referring to Fig. 1, mud exhauster 1 is placed in inside steel-pipe pile 2, The mixture removing of silt and water in steel-pipe pile 2 is finished using mud exhauster 1 simultaneously.
Second step, referring to Fig. 2, the sealing plate 6 and 2 top sealing welding of steel-pipe pile that are equipped with valve 4 and flange 5, and it is right Sealing plate 6 does consolidation process, guarantees that sealing plate 6 is able to bear sufficiently large upward top lift.
Third step, referring to Fig. 2, high-pressure hydraulic pump 8 is made by 5 airtight connection of flange on pressure duct 7 and sealing plate 6 High-pressure hydraulic pump 8 is connected to steel-pipe pile 2.
4th step starts high-pressure hydraulic pump 8 to 2 internal water flooding of steel-pipe pile, to have at valve 4 referring to Fig. 2, opening valve 4 High-pressure hydraulic pump 8 is closed when water flows out, and closes valve 4.
5th step continues referring to Fig. 2, opening high-pressure hydraulic pump 8 to 2 internal water flooding of steel-pipe pile, sealing plate 6 will by one to On top lift;With the increase of 2 internal pressure of steel-pipe pile, when the top lift that sealing plate 6 is subject to is greater than mud around 2 outer wall of steel-pipe pile When soil is to its downward frictional resistance, steel-pipe pile 2 is under the drive of sealing plate 6, relative to ambient earth, steel-pipe pile 2 will generate to On position it is mobile, by controlling the rate of water injection of high-pressure hydraulic pump 8, steel-pipe pile 2 is kept constantly to move upwards;When steel-pipe pile 2 When moving upward to certain altitude, steel-pipe pile 2 can directly be extracted with crane ship.
During above-mentioned four step, the high pressure water that 2 bottom of steel-pipe pile extrudes can form seepage flow along 2 outer wall of steel-pipe pile, The combination of soil and steel-pipe pile 2 can be destroyed, so that 2 surrounding frictional resistance of steel-pipe pile be made to reduce;If 2 outside of steel-pipe pile is rubbed It is excessive to wipe resistance, 2 outboard friction resistance of steel-pipe pile can be reduced by some corresponding ancillary technique means.
Two, the step method that more steel-pipe piles of lateral ties structure are arranged at top is extracted simultaneously:
Mud exhauster is placed in inside steel-pipe pile by the first step, is filled the water by water pump into steel-pipe pile, while using mud exhauster Silt removing in steel-pipe pile is finished, removes as much as possible using mud exhauster or other ancillary equipments if needed (or rush Pine) lateral ties member upper silt.
Second step sealing welding at the top of the sealing plate and each steel-pipe pile for being equipped with valve and flange, and does each sealing plate Consolidation process guarantees that sealing plate can bear sufficiently large upward top lift.
Third step is equipped with a high-pressure hydraulic pump to every steel-pipe pile, by every high-pressure hydraulic pump by pressure duct with it is each Flange airtight connection on sealing plate, is connected to high-pressure hydraulic pump with steel-pipe pile.
4th step opens the valve on each sealing plate, while starting high-pressure hydraulic pump to steel-pipe pile internal water flooding, to each valve High-pressure hydraulic pump is closed when there are flowing out at door, closes valve.
5th step starts high-pressure hydraulic pump simultaneously again and continues to each steel-pipe pile internal water flooding, each sealing plate by one to On top lift;With the increase of each steel-pipe pile internal water pressure, when the top lift that sealing plate is subject to is greater than around steel-pipe pile outer wall When soil is to its downward frictional resistance, steel-pipe pile is under the drive of sealing plate, and relative to ambient earth, steel-pipe pile will generate upward Position it is mobile, control the speed that each steel-pipe pile moves upwards by controlling the rate of water injection of each high-pressure hydraulic pump, keep Each steel-pipe pile is synchronous to be risen, and when arriving certain altitude, is closed each high-pressure hydraulic pump, can directly be pulled out each steel-pipe pile with crane ship Out.
The high pressure pile pulling technology waterborne that the present invention uses is not limited solely to high pressure water pile pulling, and compressed air etc. can also be used A variety of media carry out various forms of high pressure pile pullings.
While there has been shown and described that technical solution of the present invention embodiment, for those of ordinary skill in the art and Speech, it is possible to understand that these embodiments can be carried out with a variety of variations without departing from the principles and spirit of the present invention, repaired Change, replacement and variant, protection scope of the present invention is defined by the appended claims and the equivalents thereof.

Claims (3)

1. a kind of pressure fluid jacking type pile pulling technology be by the pressure fluids such as high pressure water, compressed air using jacking in the way of Whole steel-pipe pile is extracted;Technical solution of the present invention embodiment mainly include mud exhauster, high-pressure hydraulic pump (or air compressor machine), valve, Sealing plate, steel-pipe pile;The mud exhauster is used for the silt being discharged in steel-pipe pile, by the silt inside steel-pipe pile before pile pulling starts After exclusion, mud exhauster is taken out;The sealing plate is equipped with valve and for connecting high-pressure hydraulic pump for closing steel-pipe pile, sealing plate Flange, high-pressure hydraulic pump inside flange on sealing plate and steel-pipe pile by being connected to.
2. the silt inside steel-pipe pile cleans out sealing welding at the top of rear sealing plate and steel-pipe pile, and to envelope according to claim 1 Plate does consolidation process, guarantees that sealing plate can bear sufficiently large upward top lift.
3. valve is used to be vented when high-pressure hydraulic pump fills the water in steel-pipe pile according to claim 1, valve is closed after exhaust Door, is again started up high-pressure hydraulic pump and fills the water in steel-pipe pile, and high pressure water acts on one upward top lift of formation, sealing plate on sealing plate Steel-pipe pile is driven to move upwards.
CN201811253454.4A 2018-10-25 2018-10-25 A kind of pressure fluid jacking type pile pulling technology Pending CN109403296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811253454.4A CN109403296A (en) 2018-10-25 2018-10-25 A kind of pressure fluid jacking type pile pulling technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811253454.4A CN109403296A (en) 2018-10-25 2018-10-25 A kind of pressure fluid jacking type pile pulling technology

Publications (1)

Publication Number Publication Date
CN109403296A true CN109403296A (en) 2019-03-01

Family

ID=65469829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811253454.4A Pending CN109403296A (en) 2018-10-25 2018-10-25 A kind of pressure fluid jacking type pile pulling technology

Country Status (1)

Country Link
CN (1) CN109403296A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323876A (en) * 2020-11-03 2021-02-05 北京顺义建筑企业集团公司 Method for detecting pile end resistance of pile formed by holding-pressure type hammering and pressure grouting by small-area method
CN114045831A (en) * 2021-12-21 2022-02-15 中交第二航务工程局有限公司 Novel device for underwater drawing steel pipe pile under space limited condition and construction method
WO2022038219A1 (en) * 2020-08-21 2022-02-24 Treehouse Denmark Aps A method and a tool assembly for the removal of a monopile foundation

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0782744A (en) * 1993-09-13 1995-03-28 Toshihiko Fujii Pile-drawing method and casing pipe used therefor
JPH09268555A (en) * 1996-03-27 1997-10-14 Daiho Constr Co Ltd Pile drawing method and device thereof
CN202530460U (en) * 2012-02-08 2012-11-14 中国石油化工股份有限公司 Auxiliary pile extracting mechanism
CN103243717A (en) * 2012-02-08 2013-08-14 中国石油化工股份有限公司 Auxiliary pile pulling mechanism and using method thereof
CN103741691A (en) * 2014-02-11 2014-04-23 中国石油大学(华东) Device and method for dismantling offshore pile pipe through reversed pulling under pressure
CN103882900A (en) * 2014-03-20 2014-06-25 中交第二航务工程局有限公司 Underwater mud suction device and construction method for conducting underwater cutting pile pulling through underwater mud suction device
CN104594350A (en) * 2015-02-09 2015-05-06 张继红 Pore pressure counterforce steel pipe pile pulling method and pipe pulling device thereof
CN108487248A (en) * 2018-05-30 2018-09-04 中石化石油工程技术服务有限公司 Deep-well drawing out soil equipment and its construction method in a kind of snag

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0782744A (en) * 1993-09-13 1995-03-28 Toshihiko Fujii Pile-drawing method and casing pipe used therefor
JPH09268555A (en) * 1996-03-27 1997-10-14 Daiho Constr Co Ltd Pile drawing method and device thereof
CN202530460U (en) * 2012-02-08 2012-11-14 中国石油化工股份有限公司 Auxiliary pile extracting mechanism
CN103243717A (en) * 2012-02-08 2013-08-14 中国石油化工股份有限公司 Auxiliary pile pulling mechanism and using method thereof
CN103741691A (en) * 2014-02-11 2014-04-23 中国石油大学(华东) Device and method for dismantling offshore pile pipe through reversed pulling under pressure
CN103882900A (en) * 2014-03-20 2014-06-25 中交第二航务工程局有限公司 Underwater mud suction device and construction method for conducting underwater cutting pile pulling through underwater mud suction device
CN104594350A (en) * 2015-02-09 2015-05-06 张继红 Pore pressure counterforce steel pipe pile pulling method and pipe pulling device thereof
CN108487248A (en) * 2018-05-30 2018-09-04 中石化石油工程技术服务有限公司 Deep-well drawing out soil equipment and its construction method in a kind of snag

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022038219A1 (en) * 2020-08-21 2022-02-24 Treehouse Denmark Aps A method and a tool assembly for the removal of a monopile foundation
CN112323876A (en) * 2020-11-03 2021-02-05 北京顺义建筑企业集团公司 Method for detecting pile end resistance of pile formed by holding-pressure type hammering and pressure grouting by small-area method
CN114045831A (en) * 2021-12-21 2022-02-15 中交第二航务工程局有限公司 Novel device for underwater drawing steel pipe pile under space limited condition and construction method
CN114045831B (en) * 2021-12-21 2023-10-27 中交第二航务工程局有限公司 Novel device for water drawing steel pipe pile under space limited condition and construction method

Similar Documents

Publication Publication Date Title
US20200291754A1 (en) Hydrate solid-state fluidization mining method and system under underbalanced reverse circulation condition
CN109403296A (en) A kind of pressure fluid jacking type pile pulling technology
CN103334444B (en) A kind of method for blocking of foundation pit dewatering well pressure release type
CN103806422B (en) A kind of submarine leaked collection system
CN109778789A (en) A kind of Face Slab of Concrete-faced Rockfill is come to nothing the underwater repair system in area
CN109707443B (en) Recoverable tunnel drainage system and method
CN103507109B (en) Underwater dry type cutting cabin and application method thereof
CN206128099U (en) Novel precipitation well shut -in well device
CN106759360A (en) A kind of slag removal grouting apparatus and the slag removal grouting method using the device
CN104975612A (en) Novel water open caisson construction technology
CN208309566U (en) A kind of water-stopping steel sheet pile
JPH09287156A (en) Construction method of compressed air storage plant by use of submerged abandoned mine
CN104358231B (en) A kind of Underwater Slope mold-bagged concrete reinforced construction method
CN113737834A (en) Recyclable negative pressure injection type open caisson structure and construction method
CN201554005U (en) Large-flow and high-speed jet sealing drilling and pouring orifice safety control device under high pressure water
CN107642100A (en) Apparatus and method for FS final spice engagement cavity draining
CN209040133U (en) Well-covering device for dewatering well suitable for rich groundwater region
CN106381878A (en) Environment-friendly dismantling construction method for two-layer steel sheet pile and soil core composite cofferdam
CN203527525U (en) Underwater dry type cutting cabin
CN210770491U (en) Single-ball exhaust valve
CN107504315A (en) A kind of construction method that Jiang Guandao is got over using baric systerm reparation seepage
Warnock Experiences of the Bureau of Reclamation
CN111894069A (en) Underwater environment-friendly cutter suction type dredging device for urban ecological river and construction method thereof
CN208685608U (en) Deep-well drawing out soil equipment in a kind of snag
CN203284787U (en) Composite pipe well precipitation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301

RJ01 Rejection of invention patent application after publication