CN109139079A - Subway tunnel ventilating system - Google Patents
Subway tunnel ventilating system Download PDFInfo
- Publication number
- CN109139079A CN109139079A CN201811083861.5A CN201811083861A CN109139079A CN 109139079 A CN109139079 A CN 109139079A CN 201811083861 A CN201811083861 A CN 201811083861A CN 109139079 A CN109139079 A CN 109139079A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- air duct
- mechanical
- top row
- rail top
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000779 smoke Substances 0.000 claims abstract description 30
- 238000009423 ventilation Methods 0.000 claims abstract description 18
- 238000000605 extraction Methods 0.000 claims description 7
- 230000001105 regulatory effect Effects 0.000 claims description 5
- 238000006243 chemical reaction Methods 0.000 claims description 4
- 238000007599 discharging Methods 0.000 abstract description 3
- 239000003517 fume Substances 0.000 description 4
- 206010022000 influenza Diseases 0.000 description 4
- 230000003584 silencer Effects 0.000 description 4
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000007664 blowing Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 235000019504 cigarettes Nutrition 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F1/00—Ventilation of mines or tunnels; Distribution of ventilating currents
- E21F1/003—Ventilation of traffic tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Ventilation (AREA)
Abstract
The present invention relates to tunnel smoke discharging structure technical fields, disclose a kind of subway tunnel ventilating system, including station tunnel ventilation device;The station tunnel ventilation device include be respectively arranged on station both ends the first removing shaft and the second removing shaft, be respectively arranged on station tunnel both sides the first rail top row hot-flow flue and the second rail top row hot-flow flue, connection the first removing shaft and the first exhausting duct of the first rail top row hot-flow flue, be connected to the second exhausting duct of the second removing shaft and the second rail top row hot-flow flue and be mounted on the exhaust air box of station platform;The exhaust air box is connected to the first rail top row hot-flow flue or the second rail top row hot-flow flue.For the subway tunnel ventilating system under the premise of guaranteeing ventilation embankment, structure is simple, easy to implement, controls to adjust simple.
Description
Technical field
The present invention relates to tunnel smoke discharging structure technical fields, more particularly to a kind of subway tunnel ventilating system.
Background technique
" continuous length is greater than 60m to " metro design code " (GB50157-2013) the 28.4.4 articles regulation, but is not more than
The running tunnel of 300m and totally-enclosed lane preferably use natural draught system;When unconditionally using natural draught system, mechanical row should be set
Cigarette " causes this end to be frequently present of this currently, the equipment section length that equipment centralized end often occurs in domestic subway station is too long
Continuous length is greater than 60m but no more than 300m and the unconditional running tunnel for using natural draught system, for such running tunnel, mesh
The mechanical smoke extraction scheme that preceding country's subway is widely used has following two:
Scheme one: rail right above the running tunnel adds smoke outlet on road against the wind, makes the smoke outlet added distance should
The horizontal distance of running tunnel is no more than 30m, and smoke outlet form is the normally opened smoke outlet of manual adjustable.When normal operation, institute
Mouth is kept it turning on the smoke outlet and rail added against the wind, is opened station exhaust fan, is added smoke outlet using on rail against the wind road
It distributes when mouth excludes train dwelling against the wind with rail to the heat in tunnel;When in this running tunnel fire occurs for train, open
Station exhaust fan, using add smoke outlet and the rail on rail against the wind road, mouth is discharged fume against the wind.The program implements more convenient, skill
Art difficulty is lower, but the smoke outlet because being added is the normally opened smoke outlet of manual adjustable, and is located at the proximal end in rail road against the wind, is caused
The rail top tuyere air volume for being located at rail road distal end against the wind under normal operation operating condition is substantially reduced, and then leads to the row of station heat-extraction system
The thermal efficiency reduces.
Scheme two: rail right above the running tunnel adds smoke outlet on road against the wind, makes the smoke outlet added distance should
The horizontal distance of running tunnel is no more than 30m, and smoke outlet form is the normally closed smoke outlet of electric adjustable.When normal operation, increase
If smoke outlet remain turned-off, mouth is kept it turning on rail against the wind, open station exhaust fan, against the wind using the rail on rail against the wind road
Mouth excludes to distribute when train dwelling to the heat in tunnel;When in this running tunnel fire occurs for train, station heat extraction is opened
Blower opens simultaneously the normally closed type smoke outlet added, and using add smoke outlet and the rail on rail against the wind road, mouth is discharged fume against the wind.
The program is because the smoke outlet added is closed in normal conditions, is not in that scheme one leads to station heat extraction system like that therefore
The case where thermal discharge efficiency of system reduces;However, leading to its inspection because the electronic smoke outlet added is located exactly at the surface of route
It repairs highly inconvenient.
Summary of the invention
(1) technical problems to be solved
The object of the present invention is to provide a kind of subway tunnel ventilating systems, it is intended at least the solution prior art or the relevant technologies
Present in one of technical problem.
(2) technical solution
In order to solve the above technical problem, the present invention provides a kind of subway tunnel ventilating systems, including station tunnel to divulge information
Device;The station tunnel ventilation device includes being respectively arranged on first removing shaft at station both ends and the second removing shaft, setting respectively
In the first rail top row hot-flow flue on station tunnel both sides and the second rail top row hot-flow flue, the first removing shaft of connection and the first rail top row
First exhausting duct of hot-flow flue, the second exhausting duct of the second removing shaft of connection and the second rail top row hot-flow flue and installation are AT STATION
The exhaust air box of platform;The exhaust air box is connected to the first rail top row hot-flow flue or the second rail top row hot-flow flue.
Wherein, the exhaust air box is connected by air hose and the first rail top row hot-flow flue or the second rail top row hot-flow flue
It is logical;
It is provided with through-hole on the side wall of the exhaust air box, manual smoke exhaust fire damper and electronic more is installed in the through-hole
Leaf regulating valve.
It wherein, further include running tunnel ventilation device;The running tunnel ventilation device includes being respectively arranged on station both ends
The first mechanical ventilating shaft and the second mechanical ventilating shaft, the mechanical ventilating shaft of connection first and the first mechanical air duct of running tunnel, be connected to the
Second mechanical air duct of two mechanical ventilating shafts and running tunnel.
Wherein, the described first mechanical air duct includes two first mechanical air ducts being arranged in parallel, the described first mechanical air duct
It is equipped with the first tunnel blower and electric assembling air-valve;Described second mechanical air duct includes two the second mechanical blowings being arranged in parallel
Road, the described second mechanical air duct are equipped with the second tunnel blower and electric assembling air-valve.
Wherein, two noise eliminations for being located at first tunnel blower two sides are additionally provided on the described first mechanical air duct
Device, second machinery are additionally provided with two silencers for being located at second tunnel blower two sides on air duct.
Wherein, the running tunnel ventilation device further includes the first piston wind for being connected to the first mechanical ventilating shaft and running tunnel
The second piston air duct in road and connection second mechanical ventilating shaft and running tunnel, the first piston air duct and first machinery
Air duct is arranged in parallel, and the second piston air duct is arranged in parallel with the described second mechanical air duct, on the first piston air duct with
And electric assembling air-valve is provided on the second piston air duct.
Wherein, the described first mechanical air duct includes be connected to respectively with left lateral running tunnel and right lateral running tunnel two the
One mechanical air duct by-path, each described first mechanical air duct by-path are equipped with electric assembling air-valve, the described second mechanical air duct packet
Two second mechanical air duct by-paths being connected to respectively with left lateral running tunnel and right lateral running tunnel are included, each described second is mechanical
Air duct by-path is equipped with electric assembling air-valve.
Wherein, the first exhaust fan and electric assembling air-valve are provided on first exhausting duct;Second exhausting duct
On be provided with the second exhaust fan and electric assembling air-valve.
Wherein, first exhaust fan and second exhaust fan are frequency conversion fan.
Wherein, the first rail top row hot-flow flue and the second rail top row hot-flow flue be equipped with electric multiblade regulating valve and
Manual smoke exhaust fire damper.
(3) beneficial effect
Compared with prior art, the invention has the following advantages that
A kind of subway tunnel ventilating system provided by the invention, the first removing shaft pass through the first exhausting duct and the first rail top row
Hot-flow flue connection, the second removing shaft are connected to by the second exhausting duct with the second rail top row hot-flow flue, and the row of station platform is mounted on
Air compartment is connected to the first rail top row hot-flow flue or the second rail top row hot-flow flue, which is guaranteeing ventilating system
Under the premise of reliability, structure is simple, easy to implement, controls to adjust simple.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of subway tunnel ventilating system of the embodiment of the present invention;
In figure: 1- station platform;2- right lateral station tunnel;3- left lateral station tunnel;4- the first rail top row hot-flow flue;5-
Two rail top row hot-flow flues;6- electric multiblade regulating valve;7- electric assembling air-valve;The manual smoke exhaust fire damper of 8-;The first mechanical blowing of 9-
Well;The mechanical ventilating shaft of 10- second;The first removing shaft of 11-;The second removing shaft of 12-;13- silencer;The first tunnel blower of 14-;15-
First exhaust fan;The second exhaust fan of 16-;The second tunnel blower of 17-;18- air hose;19- exhaust air box;20- the first rail top row
The air inlet of hot-flow flue;The first exhausting duct of 21-;The second exhausting duct of 22-;The mechanical air duct 23- first;The mechanical air duct 24- second;
The air inlet of 25- the second rail top row hot-flow flue;26- first piston air duct;27- second piston air duct.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Following instance
For illustrating the present invention, but it is not intended to limit the scope of the invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ",
" thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " up time
The orientation or positional relationship of the instructions such as needle ", " counterclockwise ", " axial direction ", " radial direction ", " circumferential direction " be orientation based on the figure or
Positional relationship is merely for convenience of description of the present invention and simplification of the description, rather than the device or element of indication or suggestion meaning must
There must be specific orientation, be constructed and operated in a specific orientation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance
Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or
Implicitly include at least one this feature.In the description of the present invention, the meaning of " plurality " is at least two, such as two, three
It is a etc., unless otherwise specifically defined.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " etc.
Term shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be mechanical connect
It connects, is also possible to be electrically connected or can communicate each other;It can be directly connected, can also indirectly connected through an intermediary, it can be with
It is the interaction relationship of the connection or two elements inside two elements, unless otherwise restricted clearly.For this field
For those of ordinary skill, the specific meanings of the above terms in the present invention can be understood according to specific conditions.
In embodiments of the present invention, metro station tunnel includes the left lateral station tunnel 3 positioned at 1 two sides of station platform and the right side
Row station tunnel 2, running tunnel include left lateral running tunnel and right lateral running tunnel.
Fig. 1 is a kind of structural schematic diagram of subway tunnel ventilating system of the embodiment of the present invention, as shown in Figure 1, including station
Tunnel ventilation device, station tunnel ventilation device include the first removing shaft 11 and the second removing shaft for being respectively arranged on station both ends
12, it is respectively arranged on the first rail top row hot-flow flue 4 on 3 both sides of left lateral station tunnel and the second rail top row hot-flow flue 5, is respectively arranged on the right side
Another first rail top row hot-flow flue 4 on 2 both sides of row station tunnel and another second rail top row hot-flow flue 5 are connected to the first removing shaft
11 with the first exhausting duct 21 of two the first rail top row hot-flow flues 4, be connected to the second removing shaft 12 and two the second rail top row hot winds
Second exhausting duct 22 in road 5 is mounted on the exhaust air box 19 of station platform 1, exhaust air box 19 and the first rail top row hot-flow flue 4 or the second
The connection of rail top row hot-flow flue.
It should be noted that add an exhaust air box 19 in the station layer battery limits of equipment centralized end, exhaust air box 19 with
The first rail top row hot-flow flue 4 or the connection of the second rail top row hot-flow flue 5 in left lateral station tunnel 3;Or exhaust air box 19 and right lateral
The first rail top row hot-flow flue 4 or the connection of the second rail top row hot-flow flue 5 in station tunnel 2;Or exhaust air box 19 simultaneously and left lateral
The first rail top row hot-flow flue 4 in station tunnel 3 is connected to the first rail top row hot-flow flue 4 in right lateral station tunnel 2;Alternatively,
Exhaust air box 19 simultaneously with the second rail top row hot-flow flue 5 in left lateral station tunnel 3 and the second rail top row in right lateral station tunnel 2
Hot-flow flue 5 is connected to.
Preferably, exhaust air box 19 top setting air hose 18 with by exhaust air box 19 simultaneously with left lateral station tunnel 3 in
First rail top row hot-flow flue 4 is connected to the first rail top row hot-flow flue 4 in right lateral station tunnel 2, while in the side of exhaust air box 19
Through-hole is set on wall, manual smoke exhaust fire damper 8 and electric multiblade regulating valve 6 are installed in through-hole.Preferably, in exhaust air box 19
Through-hole is respectively set on opposite side wall, manual smoke exhaust fire damper 8 and electric multiblade tune are installed respectively in each through-hole
Save valve 6;
And the distance between through-hole and the air inlet of a nearest first rail top row hot-flow flue are less than or equal to 60m;Through-hole
It is also smaller than at a distance from the air inlet in the first mechanical air duct 23 equal to 60m.
When the subway tunnel ventilating system operates normally, the electric control valve on exhaust air box side wall is kept to close, the first rail
The air inlet of the air inlet of top row hot-flow flue and the second rail top row hot-flow flue is kept it turning on, open the first exhaust fan of station and
Second exhaust fan excludes train using the air inlet of the first rail top row hot-flow flue and the air inlet of the second rail top row hot-flow flue and stops
It is distributed when standing to the heat in tunnel;When in this running tunnel fire occurs for train, the first exhaust fan of station and the are opened
Two exhaust fans open simultaneously the electric control valve on exhaust air box side wall, utilize the hole on exhaust air box side wall, the first rail top row
The air inlet of the air inlet of hot-flow flue and the second rail top row hot-flow flue is discharged fume.
It is remained turned-off under the electric control valve nominal situation added on exhaust air box side wall, is only merely under operating condition of discharging fume
It opens, therefore, the thermal discharge efficiency that not will lead to station heat-extraction system reduces;And added electric control valve and manually smoke evacuation
Fire resisting damper is mounted in the exhaust air box of station layer battery limits, and maintenance is extremely convenient.
In addition, according to an embodiment of the invention, being provided with first exhaust fan 15 and one on the first exhausting duct 21
Electric assembling air-valve 7;Second exhaust fan 16 and an electric assembling air-valve 7 are provided on second exhausting duct 22.
It should be noted that being equipped with silencer 13 between electric assembling air-valve 7 and the first removing shaft 11;Electric assembling wind
Silencer 13 is installed between valve 7 and the second removing shaft 12;First exhaust fan 15 and electric assembling air-valve 7 are connected in series, the
Two exhaust fans 16 and electric assembling air-valve 7 are connected in series;Another is provided on the air inlet pipeline of first exhaust fan 15 to disappear
Sound device 13;Another silencer 13 is provided on the air inlet pipeline of second exhaust fan 16.
In addition, can either be automatically controlled by control system for according to an embodiment of the invention, and can control manually
System, it is convenient and reliable, fire can be coped in time.First rail top row hot-flow flue 4 and the second rail top row hot-flow flue 5 are equipped with electronic
Multi-clack control valve 6;
And first be equipped with manual smoke exhaust fire damper 8 on rail top row hot-flow flue 4 and the second rail top row hot-flow flue 5.
Wherein, the air inlet 20 of multiple first rail top row hot-flow flues is provided on the first rail top row hot-flow flue 4;Second rail top
The air inlet 25 of multiple second rail top row hot-flow flues is provided on heat extraction air duct 5.
Further, according to an embodiment of the invention, in order to enhance the draught capacity of the subway tunnel ventilating system, the ground
Iron Tunnel Ventilation System further includes running tunnel ventilation device, and running tunnel ventilation device includes be respectively arranged on station both ends
The of one mechanical ventilating shaft 9 and the second mechanical ventilating shaft 10, the mechanical ventilating shaft 9 of connection first and left lateral running tunnel and right lateral running tunnel
Second mechanical air duct 24 of one mechanical air duct 23, the mechanical ventilating shaft 10 of connection second and left lateral running tunnel and right lateral running tunnel.
Preferably, the first mechanical air duct 23 includes two first mechanical air ducts being arranged in parallel, and is set on the first mechanical air duct
There are first tunnel blower 14 and an electric assembling air-valve 7;Second mechanical air duct includes two the second machines being arranged in parallel
Tool air duct, the second mechanical air duct are equipped with second tunnel blower 17 and an electric assembling air-valve 7.
In order to reduce the noise of the subway tunnel ventilating operation, it is preferable that be additionally provided on the first mechanical air duct 23 point
Not Wei Yu 14 two sides of the first tunnel blower two silencers 13, be additionally provided on the second mechanical air duct 24 and be located at the second tunnel
Two silencers 13 of 17 two sides of blower.
Preferably, the first mechanical air duct 23 includes be connected to respectively with left lateral running tunnel and right lateral running tunnel two the
One mechanical air duct by-path often states the first mechanical air duct by-path and is equipped with an electric assembling air-valve 7, and the second mechanical air duct includes point
Two second mechanical air duct by-paths not being connected to left lateral running tunnel and right lateral running tunnel, every one second mechanical air duct by-path
It is equipped with an electric assembling air-valve 7.
Preferably, running tunnel ventilation device further includes the first piston wind for being connected to the first mechanical ventilating shaft 9 and running tunnel
The second piston air duct 27 in road 26 and connection second mechanical ventilating shaft and running tunnel, first piston air duct 26 be arranged in parallel
Two first mechanical air ducts are arranged in parallel, and second piston air duct 27 is arranged in parallel with two second mechanical air ducts being arranged in parallel,
An electric assembling air-valve 7 is provided on first piston air duct 26 and on second piston air duct 27.
Preferably, the first exhaust fan 15 and the second exhaust fan 16 are frequency conversion fan, the first tunnel blower 14 and
Two tunnel blowers 17 are the blower with positive and negative rotating function without frequency conversion function.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (10)
1. a kind of subway tunnel ventilating system, which is characterized in that including station tunnel ventilation device;The station tunnel ventilation dress
The the first rail top set the first removing shaft and the second removing shaft including being respectively arranged on station both ends, be respectively arranged on station tunnel both sides
Heat extraction air duct and the second rail top row hot-flow flue, are connected to the first removing shaft of connection and the first exhausting duct of the first rail top row hot-flow flue
Second exhausting duct of the second removing shaft and the second rail top row hot-flow flue and the exhaust air box for being mounted on station platform;The exhaust air box
It is connected to the first rail top row hot-flow flue or the second rail top row hot-flow flue.
2. subway tunnel ventilating system as described in claim 1, which is characterized in that the exhaust air box passes through air hose and described the
One rail top row hot-flow flue or the second rail top row hot-flow flue connection;
It is provided with through-hole on the side wall of the exhaust air box, manual smoke exhaust fire damper and electric multiblade tune are installed in the through-hole
Save valve.
3. subway tunnel ventilating system as described in claim 1, which is characterized in that further include running tunnel ventilation device;Institute
Stating running tunnel ventilation device includes the first mechanical ventilating shaft and the second mechanical ventilating shaft, the first machine of connection for being respectively arranged on station both ends
The mechanical air duct of the first of tool ventilating shaft and running tunnel, the second machinery air duct for be connected to the second mechanical ventilating shaft and running tunnel.
4. subway tunnel ventilating system as claimed in claim 3, which is characterized in that the described first mechanical air duct is set including parallel connection
The mechanical air duct of two first set, the described first mechanical air duct are equipped with the first tunnel blower and electric assembling air-valve;Described
Two mechanical air ducts include two second mechanical air ducts being arranged in parallel, the described second mechanical air duct be equipped with the second tunnel blower and
Electric assembling air-valve.
5. subway tunnel ventilating system as claimed in claim 4, which is characterized in that be additionally provided on the first mechanical air duct point
Not Wei Yu first tunnel blower two sides two silencers, be additionally provided on the second mechanical air duct and be located at described the
Two silencers of two tunnel blower two sides.
6. subway tunnel ventilating system as claimed in claim 3, which is characterized in that the running tunnel ventilation device further includes
The mechanical ventilating shaft of connection first and the first piston air duct of running tunnel and be connected to the second of the second machinery ventilating shaft and running tunnel
Piston air duct, the first piston air duct are arranged in parallel with the described first mechanical air duct, the second piston air duct and described the
Two mechanical air ducts are arranged in parallel, and are provided with electric assembling wind on the first piston air duct and on the second piston air duct
Valve.
7. subway tunnel ventilating system as claimed in claim 3, which is characterized in that the first mechanical air duct include respectively with
The two first mechanical air duct by-paths that left lateral running tunnel is connected to right lateral running tunnel, each described first mechanical air duct by-path
It is equipped with electric assembling air-valve, the described second mechanical air duct includes being connected to respectively with left lateral running tunnel and right lateral running tunnel
Two second mechanical air duct by-paths, each described second mechanical air duct by-path are equipped with electric assembling air-valve.
8. subway tunnel ventilating system as described in claim 1, which is characterized in that be provided with first on first exhausting duct
Exhaust fan and electric assembling air-valve;The second exhaust fan and electric assembling air-valve are provided on second exhausting duct.
9. subway tunnel ventilating system as claimed in claim 8, which is characterized in that first exhaust fan and described second
Exhaust fan is frequency conversion fan.
10. subway tunnel ventilating system as described in claim 1, which is characterized in that the first rail top row hot-flow flue and institute
It states the second rail top row hot-flow flue and is equipped with electric multiblade regulating valve and manual smoke exhaust fire damper.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811083861.5A CN109139079A (en) | 2018-09-17 | 2018-09-17 | Subway tunnel ventilating system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811083861.5A CN109139079A (en) | 2018-09-17 | 2018-09-17 | Subway tunnel ventilating system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109139079A true CN109139079A (en) | 2019-01-04 |
Family
ID=64814523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811083861.5A Pending CN109139079A (en) | 2018-09-17 | 2018-09-17 | Subway tunnel ventilating system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109139079A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110118099A (en) * | 2019-06-03 | 2019-08-13 | 中国安全生产科学研究院 | A kind of Fire Ventilation smoke exhaust method of sub-interchange platform |
CN110454210A (en) * | 2019-08-22 | 2019-11-15 | 河南工业大学 | Subway is grown up admission section threaded list road smoke control system out |
CN111980742A (en) * | 2020-08-14 | 2020-11-24 | 中国安全生产科学研究院 | Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station |
CN112983527A (en) * | 2021-03-30 | 2021-06-18 | 中国安全生产科学研究院 | Integrated station tunnel ventilation system and smoke exhaust method thereof |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000073699A (en) * | 1998-08-27 | 2000-03-07 | Metropolitan Expressway Public Corp | Ventilation and smoke-discharging system for road tunnel |
CN1521464A (en) * | 2003-01-29 | 2004-08-18 | 北京城建设计研究总院有限责任公司 | Multifunctional equipment integration system for underground ventilation and air conditioning |
CN2725769Y (en) * | 2004-08-16 | 2005-09-14 | 北京城建设计研究总院有限责任公司 | Urban rail traffic fan parallel type ventilation integrated system |
CN102519110A (en) * | 2011-12-09 | 2012-06-27 | 上海市隧道工程轨道交通设计研究院 | Subway platform ventilation and smoke removal distribution structure in station with opened-closed system |
CN102720519A (en) * | 2012-06-21 | 2012-10-10 | 广州地铁设计研究院有限公司 | Novel tunnel ventilation system for subway station |
CN105525935A (en) * | 2016-01-27 | 2016-04-27 | 中铁第四勘察设计院集团有限公司 | Combined and closed subway station ventilation and air conditioning system and application thereof |
CN206889006U (en) * | 2017-06-28 | 2018-01-16 | 中铁第四勘察设计院集团有限公司 | A kind of subway tunnel ventilating system |
CN206889008U (en) * | 2017-06-28 | 2018-01-16 | 中铁第四勘察设计院集团有限公司 | A kind of nozzle supply air system for non-totally-enclosed platform door system subway station |
CN108049905A (en) * | 2017-11-03 | 2018-05-18 | 中国安全生产科学研究院 | A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway |
CN209067263U (en) * | 2018-09-17 | 2019-07-05 | 中铁四院集团西南勘察设计有限公司 | Subway tunnel ventilating system |
-
2018
- 2018-09-17 CN CN201811083861.5A patent/CN109139079A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000073699A (en) * | 1998-08-27 | 2000-03-07 | Metropolitan Expressway Public Corp | Ventilation and smoke-discharging system for road tunnel |
CN1521464A (en) * | 2003-01-29 | 2004-08-18 | 北京城建设计研究总院有限责任公司 | Multifunctional equipment integration system for underground ventilation and air conditioning |
CN2725769Y (en) * | 2004-08-16 | 2005-09-14 | 北京城建设计研究总院有限责任公司 | Urban rail traffic fan parallel type ventilation integrated system |
CN102519110A (en) * | 2011-12-09 | 2012-06-27 | 上海市隧道工程轨道交通设计研究院 | Subway platform ventilation and smoke removal distribution structure in station with opened-closed system |
CN102720519A (en) * | 2012-06-21 | 2012-10-10 | 广州地铁设计研究院有限公司 | Novel tunnel ventilation system for subway station |
CN105525935A (en) * | 2016-01-27 | 2016-04-27 | 中铁第四勘察设计院集团有限公司 | Combined and closed subway station ventilation and air conditioning system and application thereof |
CN206889006U (en) * | 2017-06-28 | 2018-01-16 | 中铁第四勘察设计院集团有限公司 | A kind of subway tunnel ventilating system |
CN206889008U (en) * | 2017-06-28 | 2018-01-16 | 中铁第四勘察设计院集团有限公司 | A kind of nozzle supply air system for non-totally-enclosed platform door system subway station |
CN108049905A (en) * | 2017-11-03 | 2018-05-18 | 中国安全生产科学研究院 | A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway |
CN209067263U (en) * | 2018-09-17 | 2019-07-05 | 中铁四院集团西南勘察设计有限公司 | Subway tunnel ventilating system |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110118099A (en) * | 2019-06-03 | 2019-08-13 | 中国安全生产科学研究院 | A kind of Fire Ventilation smoke exhaust method of sub-interchange platform |
CN110118099B (en) * | 2019-06-03 | 2020-04-07 | 中国安全生产科学研究院 | Fire ventilation and smoke exhaust method for subway transfer station platform |
CN110454210A (en) * | 2019-08-22 | 2019-11-15 | 河南工业大学 | Subway is grown up admission section threaded list road smoke control system out |
CN111980742A (en) * | 2020-08-14 | 2020-11-24 | 中国安全生产科学研究院 | Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station |
CN111980742B (en) * | 2020-08-14 | 2021-07-13 | 中国安全生产科学研究院 | Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station |
CN112983527A (en) * | 2021-03-30 | 2021-06-18 | 中国安全生产科学研究院 | Integrated station tunnel ventilation system and smoke exhaust method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209067263U (en) | Subway tunnel ventilating system | |
CN109139079A (en) | Subway tunnel ventilating system | |
CN106246581B (en) | Pressurizing fan structure and air conditioner with same | |
CN206889006U (en) | A kind of subway tunnel ventilating system | |
CN109139081A (en) | A kind of high methane Extra Long Tunnel Construction method of ventilation | |
CN108266217A (en) | Metro station tunnel heat-extraction system | |
CN102519110A (en) | Subway platform ventilation and smoke removal distribution structure in station with opened-closed system | |
CN201367032Y (en) | Air temperature and pressure regulation device for machine room of electric locomotive | |
CN206054351U (en) | Pressurizing fan structure and air conditioner with same | |
CN207132519U (en) | Nuclear power plant nuclear island ventilation parameters unit | |
CN106016322B (en) | flue gas desulfurization device | |
CN204740928U (en) | Main intelligent ventilation system who becomes room total heat exchange | |
CN209426527U (en) | Layout and caravan air conditioner in concealed type caravan outdoor machine of air-conditioner and caravan | |
CN208803864U (en) | Metro station tunnel heat-extraction system | |
CN102513323A (en) | Fume exhaust layout structure for subway platform and screen door system | |
CN207554095U (en) | A kind of subterranean tunnel ventilating system | |
CN207314749U (en) | A kind of skyscraper Smoke prevention fume extractor | |
CN201302252Y (en) | Fresh air conveying device | |
JP5271656B2 (en) | Air conditioning control method and air conditioning control system | |
CN210738888U (en) | Power station boiler fan system with asymmetric power distribution | |
CN212409179U (en) | Refrigerator concatenation formula wind channel structure and have its refrigerator | |
CN107816755A (en) | A kind of active beam-cooling and cold beam air-conditioning system | |
CN202641710U (en) | Subway air conditioning unit with heat-exchanging forcible exhaust emission system | |
CN219775901U (en) | Ventilation and air conditioning device for common pipeline of subway station public area | |
CN207372010U (en) | Draught cupboard and draught cupboard ventilating system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |