[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN108343407A - Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology - Google Patents

Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology Download PDF

Info

Publication number
CN108343407A
CN108343407A CN201810131067.7A CN201810131067A CN108343407A CN 108343407 A CN108343407 A CN 108343407A CN 201810131067 A CN201810131067 A CN 201810131067A CN 108343407 A CN108343407 A CN 108343407A
Authority
CN
China
Prior art keywords
oil
well
injection
gas
mixed gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810131067.7A
Other languages
Chinese (zh)
Inventor
邹积鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810131067.7A priority Critical patent/CN108343407A/en
Publication of CN108343407A publication Critical patent/CN108343407A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/166Injecting a gaseous medium; Injecting a gaseous medium and a liquid medium
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/164Injecting CO2 or carbonated water

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Physical Or Chemical Processes And Apparatus (AREA)

Abstract

The invention discloses a kind of oil, the spontaneous carbon dioxide low temperature of well mixes gas plugging releasing oil displacement technology, it is related to oil field development field, the technology includes oil, the spontaneous carbon dioxide low temperature of well mixes gas plugging releasing oil displacement construction technology, pass through oil first, well injects carbon dioxide de-plugging agent to stratum, then in injection mixed gas and surfactant liquid, mixed gas is that air is isolated by mixed gas separation device, mixed gas separation device controls oxygen content simultaneously, surfactant liquid extemporaneous preparation, injection mode is replaced using the mode that is continuously injected into or multistage plug, inject surfactant liquid and mixed gas, use gas liquid ratio for 1:1; circulate operation; terminate to construction; this technology is that mixing gas drive is combined with block releasing technique; realize oily, well de-plugging, decompression, augmented injection and the displacement of reservoir oil purpose; it is the novel oil production technology for integrating de-plugging, cracking, viscosity reduction and viscous crude lighting, the surfactant displacement of reservoir oil, mixed gas drive, the oil recovery of crude oil dilution method, adapts to the needs of oil field production and environmental protection.

Description

Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology
Technical field
The present invention relates to oil field development fields, and in particular to be that a kind of oil, the spontaneous carbon dioxide low temperature of well mix gas solution Stifled technology of reservoir sweep.
Background technology
Currently, the oil reservoir development in many oil fields in China has been enter into the middle and later periods, there are water ratio in oil well height, water injection well note not into The problem of water, oil, well expose in developing, becomes increasingly conspicuous, and input-output ratio is big, there is the problems such as taping the latent power difficulty, conventional to recover the oil Water injection technology has been unable to meet production needs, chemical displacement of reservoir oil technology is used in order to improve recovery ratio, such as polymer displacement of reservoir oil, buck Drive, combination flooding, surface-active displacement of reservoir oil etc., but as oil reservoir complex situations increase, chemical displacement of reservoir oil difficulty is increased, due to chemical flooding Finish selection is difficult, such as the requirement of chemical oil displacement agent high efficiency, economy, the feature of environmental protection, requirement, the Produced Liquid processing of injected system The problems such as, while there is alkali drive fouling, fingering in the construction process, surfactant flooding fingering, combination flooding is of high cost, injection pipe The problems such as fouling of column and tool, note ternary composite driving be easy to cause formation blockage, and backflow waste liquid is difficult, and environmental protection pressure is big etc. Problem, these factors limit chemical displacement of reservoir oil technology application.Simultaneously because oil field is exploited for a long time, strata pressure is made to decline, had a large amount of Producing well formation depletion is serious, and energy is insufficient, causes many crude oil in underground to be difficult to produce, so that crude output is successively decreased soon, therefore be Remaining Oil improves oil recovery factor, and the displacement of reservoir oil is carried out using air insufflation techiques, air insufflation techiques for example carbon dioxide injection, natural gas, Nitrogen etc. has proved to be a kind of efficient raising recovery efficiency technique, but there are air sources for carbon dioxide injection, natural gas, nitrogen technology Insufficient and of high cost problem, application is restricted, therefore air injection technology is more and more paid attention to, using air injection Technology exploit light oil reservoir be a creative raising recovery ratio new technology, it the advantages of be that air source is wide, at This is cheap, and to China mostly heterogeneous thin layer, for aclinic acline, it is simple to note due to gas string and viscous fingering The oil displacement efficiency of air is restricted, and also leads to oxygen and channel to oil well to cause some security risks, is noted in particular with oil field The extension of water development time, oil layer pollution affect oil well productivity, closely related with oil mining during oil field development Technological factor and many other factors, cause near wellbore zone to pollute, as oil field third time is exploited, Exploitation degree is constantly deep Enter, the reservoir of exploitation is in Non-primary Trunk Die Cavity, based on oil sheet and off-balancesheet layer, in the process of development, due to various factors, to cause Near wellbore permeability declines and water injection well water sucting thickness is caused to reduce, water absorbing capacity is deteriorated, and injection allocation requirement is not achieved, makes oil well Production capacity is not in full use, and seriously affects the effect of oil field development, and therefore, in order to solve oil removing, well near wellbore zone blocks, and carries Oil reservoir potential is given full play to its permeability, supplement stratum energy, the patented technology " titanium dioxide that my invention country has authorized Carbonate the raffinate not row's of returning technique after de-plugging agent and acidification ", it can release the blocking pollution problem of near wellbore zone very well, in conjunction with Upper patented technology, the spontaneous carbon dioxide low temperature of oil, well that I has developed new suitable oil field mix gas plugging releasing oil displacement technology, just It is to mix gas drive oil phase using acidification and hypoxemia to combine, has oil, well near wellbore zone to block using Acidizing Technology releasing, utilize foam Hypoxemia, which mixes gas, can reduce the gentle relative permeability of water, increase oil displacement efficiency and be related to volume, can increase substantially adopting for oil reservoir Yield and oil displacement efficiency.
Invention content
The purpose of the present invention is provide a kind of oily, mixed gas plugging releasing oil displacement of the spontaneous carbon dioxide low temperature of well regarding to the issue above Technology, this technology are that mainly mixing gas drive is combined with block releasing technique, and oil well or water injection well are before injecting gaseous mixture, first A certain amount of carbon dioxide acidification blocking remover is injected, which mainly can dissolve inorganic scale and wax and asphalitine, and generate Great amount of carbon dioxide gas, while formation temperature being made to increase, to make the gaseous mixture separated in the slave air being subsequently implanted into It is fully chemically and physically reacted with crude oil generation, de-plugging agent and gaseous mixture collective effect release the pollution on stratum and reach oil well increasing The purpose of oil and water injection well decompression, augmented injection.Then gaseous mixture is injected into stratum by oil well or water injection well, mixing air source is main A large amount of N in air is isolated by mixed gas separation device2、O2And CO2Mixed gas isolates sky using mixed gas separation device O in gas2, oxygen content is controlled in 5%-8%, therefore can control O2It injects less than 8% in stratum, a large amount of N in mixed gas2It mends Fill the energy on stratum, O2The viscosity reduction of heat and the viscosity reduction of surfactant and the viscosity reduction of reaction product are generated with the oxidation reaction of crude oil all With displacement of reservoir oil effect, the gentle relative permeability of water can be reduced using foam, blocks high permeability zone, improve gaseous mixture heterogeneous Flow condition in oil reservoir controls gas fingering, reduces gas-liquid yield ratio, postpones the break through of gas, increases oil displacement efficiency And swept volume, to increase substantially the recovery ratio of oil reservoir.The technology solves chemical existing for chemical displacement of reservoir oil technology Oil displacement agent selection is difficult, such as chemical oil displacement agent high efficiency, economy, feature of environmental protection requirement, requirement, the Produced Liquid processing of injected system The problems such as, while there is alkali drive fouling, fingering in the construction process, the problems such as surfactant flooding fingering, combination flooding is of high cost, Solve the problems, such as that air insufflation techiques exist simultaneously, the air source as existing for carbon dioxide injection, natural gas, nitrogen is insufficient and of high cost Problem, also solving simple air injection, there are has channelings and viscous fingering, cause oxygen to channel to oil well and cause some security risks.Together When solve the oil field production problem of formation depletion and water injection well difficult water injection, therefore oil, the spontaneous carbon dioxide low temperature of well are mixed Gas block releasing technique be de-plugging, cracking viscosity reduction and viscous crude lighting, surfactant flooding, mixed gas drive, the oil recovery of crude oil dilution method in Novel, efficient, the inexpensive oil recovery technique of one, it adapts to the needs of oil field production, adapts to the needs of environmental protection.
The present invention is achieved through the following technical solutions:Gas plugging releasing oil displacement is mixed including oil, the spontaneous carbon dioxide low temperature of well What construction technology was realized, a certain amount of carbon dioxide acidification blocking remover is injected to stratum by oil well or water injection well first, then It is the N that air is isolated by mixed gas separation device in injection mixed gas and surfactant liquids, mixed gas2、O2With CO2Mixed gas, at the same by mixed gas separation device control mixed gas oxygen content, surfactant liquids extemporaneous preparation, Injection mode is replaced using the mode that is continuously injected into or multistage plug, surfactant liquids and mixed gas are injected, using gas liquid ratio It is 1:1, circulate operation, until construction terminates.
The oxygen content of the mixed gas is 5% ~ 8%, the oxygen content < 8% in stratum.
The gas liquid ratio is 1:1 is mixed gas volume and surfactant liquids volume ratio under formation pressure.
Oil, the spontaneous carbon dioxide low temperature of well mix the operational procedure of gas plugging releasing oil displacement construction technology:
1, well site prepares, the facility of wellhead assembly and wellsite is oil-proof, gas leakage, and notice production crew installs well head before constructing Equipment, water injection well are fixed with wire cable anchor;
(1)To the above casing of gas injection packer carry out clear water pressure testing, after meeting the requirements can gas injection, casing pressure test 20mPa, voltage stabilizing 30min, it is qualification that pressure drop, which is less than 0.5mPa,;
(2)Cementing quality is reexamined, needs to meet gas injection intensity requirement;
(3)During tubing string tripping in, oil pipe thread junction, which need to apply, wipes stop-leak compound, and pipe wire buckle winds sealant tape;
(4)Packer bears pressure difference up and down and is intended to reach requirement, meets the higher demand of gas injection pressure;
(5)After tubing string is setting, clear water to well head or less 100m or so is filled in oil jacket annular space;
(6)Before construction, all valves of production tree and tubing and casing are checked, find to loosen fastening in time, the timely replacement of damage, peace Charge of oil, set pressure gauge, pipeline pressure resistance 30mPa;
2, injection device is installed:
(1)Other than air compressor, proportioning pump or pump truck are mounted on away from well head 20m, injection pipeline uses the pipe of pressure resistance 30mPa Line, and install;
(2)Power supply unit type selecting and installation, the special power supply unit that injection, output flow use(Transformer, power distribution cabinet, cable Deng), meet power requirements, the special power supply units such as construction period air compressor, pump, system heat preservation, household electricity and be mounted on Near oil well or the affiliated measuring station of injection well(3-5)At rice;
(3)The emptying design of construction period production fluid gas, oil well produced fluid are put into interim gathering and transferring process, output gas into overhead opening Slack tank, casing gas are vented into blow-down pipe;
(4)Construction well group surveys production profile, construction well changes decentralized wellhead, and casing installs blow-down pipe, it is desirable that drain is away from well head At 25m, pressure gauge and sampler are installed;
Field personnel should be far from pressure line when 3, constructing, and irrelevant personnel should be far from well site;
4, solution is prepared:Match liquid with water injection well water or tap water, high temperature foam agent and room temperature foaming agent is being added with liquid pool, is matching Control surface activating agent liquid is spare;Well construction 10-15m31-2 are matched liquid with liquid pool;
5, start injection device I first(Pump truck)A certain amount of carbon dioxide acidification blocking remover is injected to stratum;
6 and then in injection mixed gas and surfactant liquids, use gas liquid ratio for 1:1, first use injection device I(Pump truck) A certain amount of surfactant liquids are injected, separation equipment is then started(Mixed gas separation device)With injection device II(Air compressor machine) Inject a certain amount of mixed gas, mixed gas separation device controls the oxygen content of mixed gas in 5%-8%, using being continuously injected into mode Or multistage plug replaces injection mode, surfactant liquids and mixed gas, circulate operation is injected, until construction terminates;
7, the direct metaideophone of water injection well after the completion of constructing, by oil reservoir requirement injection allocation water filling;Oil well closing well 4-6 hours, then turns pumping Production.
The beneficial effects of the invention are as follows:The present invention is a kind of oily, mixed gas plugging releasing oil displacement skill of the spontaneous carbon dioxide low temperature of well Art, this technology are that mixing gas drive technology is combined with acidification block releasing technique, first before oil well or water injection well injection gaseous mixture A certain amount of carbon dioxide acidification blocking remover is first injected, which mainly can dissolve inorganic scale and wax and asphalitine, de-plugging Agent and gaseous mixture collective effect release the pollution on stratum and achieve the purpose that oil well and increase oil, water injection well decompression and augmented injection;Then lead to It crosses oil well, water injection well and injects low-oxygen gas mixture body and surfactant solution into stratum, achieve the purpose that plugging releasing oil displacement, simultaneously It solves stratum liquid deficit and water injection well note is not intake, make low production efficiency and the production problem of well closing well.
The displacement of reservoir oil energy that the present invention uses is low-oxygen gas mixture body, and note low-oxygen gas mixture body is conducive to keep strata pressure, There is certain elastic potential energy after injecting stratum, supplement the energy on stratum, the flexible drive of gas plays good gaslift, the row of helping It is acted on the displacement of reservoir oil.
The low-oxygen gas mixture that the present invention injects oil reservoir knows from experience the oilhole road preferentially occupied in porous media, and entering water can not The stratum of entrance, the original crude oil in bound state, which is displaced duct, becomes flowable crude oil, while occupying top oil reservoir, increases Add oil displacement pressure, to improve oil displacement efficiency, reduces residual oil saturation.
The present invention injects low-oxygen gas mixture body and the crude oil oxicracking lighting of oil reservoir, and oxidation generates carbon dioxide and heat Amount enhances crude oil flow performance, reduces viscosity of crude.Crude oil oxidation generates surface reactive material, forms surfactant flooding, Improve Development Response of Oilfield.
The displacement effect of the present invention:Low-oxygen gas mixture body, oil, water three-phase form emulsion, reduce the viscosity of crude oil, to Oil displacement efficiency is improved, occurs Gravity Separation between the fluid and reservoir fluid of injection, non-phase-mixing driving is formed, oil reservoir can be improved and exist Longitudinal development degree, so as to improve development effectiveness.
The technology of the present invention is to be effectively bonded together the advantages of gas drive and chemical flooding, is not only improved due to gas and water Viscous fingering caused by viscosity differences controls gas fingering, reduces gas-liquid yield ratio, postpones the break through of gas, increases Oil displacement efficiency and swept volume, while the gentle relative permeability of water can be reduced using foam, high permeability zone is blocked, mixing is improved Flow condition of the gas in non-homogeneous pay, to increase substantially the recovery ratio of oil reservoir.
The technology of the present invention is efficient, inexpensive, ecological, environmental protective oil recovery technique, and the raw material used have efficient Property, economy, safe ecological, environmental protective, with the performance easily injected, the low-oxygen gas mixture source of injection relies primarily on mixed gas separation Device isolates a large amount of N in air2、O2And CO2Mixed gas, it is extensive and at low cost using air source, and gas drive and chemical flooding are simultaneously It carries out, reduces production cost, the air source and surfactant ecological, environmental protective used will not pollute stratum, note simultaneously It is convenient to enter, and meets the needs of oil field.
The technology of the present invention is safety and environmental protection technology, in construction note low-oxygen gas mixture drives oil recovery process, ensures air compressor machine It works under conditions of safely and effectively, controls rational gas injection speed, ensure that oxidation reaction can occur completely for oxygen in stratum, Accomplish effectively to monitor in stratum and production, ensure the oxygen content in producing well in safe range, since hypoxemia mixes Gas drive and chemical flooding are combined, and solving simple air injection, there are has channelings and viscous fingering, while solving since oxygen channels to Oil well causes the problem of some security risks.
The technology of the present invention is to mix gas drive oil phase using acidification de-plugging and hypoxemia to combine, and dissolves plugging technique solution using Compound-acid Oil removing, well near wellbore zone block, increase the permeability and formation temperature on stratum, make gaseous mixture carry chemical agent preferably into In the machine matter for entering oil reservoir, physical and chemical reaction occurs with crude oil, increases oil displacement efficiency and swept volume, oil can be increased substantially The recovery ratio of Tibetan.
The technology of the present invention is acidification de-plugging, cracking viscosity reduction and viscous crude lighting, surfactant flooding, mixed gas drive, original Oily dilution method is recovered the oil in novel, the efficient inexpensive oil recovery technique of one, it adapts to the needs of oil field production, adapts to environment and protects The needs of shield.
Description of the drawings
Fig. 1 is that the spontaneous carbon dioxide low temperature of well of the present invention mixes gas plugging releasing oil displacement construction technology figure
In figure:1 water injection well, 2 air compressor machines, 3 mixed gas separation devices, 4 distributing room for water injection water tubing strings, 5 de-plugging agent material-compound tanks, 6 surfaces are lived Property agent return with liquid pool, 7 production valves, 8 dose out powders penstocks, 9 and wash valve, 10 pump trucks.
Fig. 2 is that the spontaneous carbon dioxide low temperature of oil well of the present invention mixes gas plugging releasing oil displacement construction technology figure
In figure:1 oil well, 2 air compressor machines, 3 mixed gas separation devices, 4 water-tank lorries, 5 de-plugging agent material-compound tanks, 6 surfactants match liquid Pond, 7 pump trucks, 8 sleeve valves.
Below in conjunction with example, the invention will be further described:
Embodiment 1
The present invention is that a kind of oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology, first by water injection well to stratum A certain amount of carbon dioxide acidification blocking remover is injected, is then in injection mixed gas and surfactant liquids, mixed gas The N that air is isolated by mixed gas separation device2、O2And CO2Mixed gas, while gaseous mixture is controlled by mixed gas separation device The oxygen content of body, surfactant liquids extemporaneous preparation replace injection mode using the mode that is continuously injected into or multistage plug, inject table Face activating agent liquid and mixed gas, use gas liquid ratio for 1:1 circulate operation, until construction terminates.
Oil, the spontaneous carbon dioxide low temperature of well mix the operational procedure of gas plugging releasing oil displacement construction technology:
1, well site prepares, the facility of wellhead assembly and wellsite is oil-proof, gas leakage, and notice production crew installs well head before constructing Equipment, water injection well are fixed with wire cable anchor;
(1)To the above casing of gas injection packer carry out clear water pressure testing, after meeting the requirements can gas injection, casing pressure test 20mPa, voltage stabilizing 30min, it is qualification that pressure drop, which is less than 0.5mPa,;
(2)Cementing quality is reexamined, needs to meet gas injection intensity requirement;
(3)During tubing string tripping in, oil pipe thread junction, which need to apply, wipes stop-leak compound, and pipe wire buckle winds sealant tape;
(4)Packer bears pressure difference up and down and is intended to reach requirement, meets the higher demand of gas injection pressure;
(5)After tubing string is setting, clear water to well head or less 100m or so is filled in oil jacket annular space;
(6)Before construction, all valves of production tree and tubing and casing are checked, find to loosen fastening in time, the timely replacement of damage, peace Charge of oil, set pressure gauge, pipeline pressure resistance 30mPa;
2, injection device is installed:
(1)Other than air compressor, proportioning pump or pump truck are mounted on away from well head 20m, injection pipeline uses the pipe of pressure resistance 30mPa Line, and install;
(2)Power supply unit type selecting and installation, the special power supply unit that injection, output flow use(Transformer, power distribution cabinet, cable Deng), meet power requirements, the special power supply units such as construction period air compressor, pump, system heat preservation, household electricity and be mounted on Near oil well or the affiliated measuring station of injection well(3-5)At rice;
(3)The emptying design of construction period production fluid gas, oil well produced fluid are put into interim gathering and transferring process, output gas into overhead opening Slack tank, casing gas are vented into blow-down pipe;
(4)Construction well group surveys production profile, construction well changes decentralized wellhead, and casing installs blow-down pipe, it is desirable that drain is away from well head At 25m, pressure gauge and sampler are installed;
Field personnel should be far from pressure line when 3, constructing, and irrelevant personnel should be far from well site;
4, solution is prepared:Match liquid with water injection well water, fetched water by distributing room for water injection water tubing string 4, high temperature foam is being added with liquid pool It is spare to prepare surfactant liquids for agent and room temperature foaming agent;
5, start injection device I first(Pump truck 10)A certain amount of carbon dioxide acidification blocking remover is injected to stratum;
6 and then in injection mixed gas and surfactant liquids, use gas liquid ratio for 1:1, first use injection device I(Pump truck 10)A certain amount of surfactant liquids are injected, separation equipment is then started(Mixed gas separation device 3)With injection device II(It is empty Press 2)A certain amount of mixed gas is injected, mixed gas separation device controls the oxygen content of mixed gas in 5%-8%, using continuous note Enter mode, surfactant liquids and mixed gas, circulate operation is injected, until construction terminates;
7, the direct metaideophone of water injection well after the completion of constructing, by oil reservoir requirement injection allocation water filling.
The using effect of embodiment 1:In August, 2010 mixes gas in Liaohe oilfield oil, the spontaneous carbon dioxide low temperature of well Block releasing technique constructs to water injection well, due to water injection well injection carbon dioxide acidification blocking remover, low-oxygen gas mixture and surface Living solution releases formation blockage, realizes augmented injection, the dynamic change for well group of constructing, water injection pressure is up to before constructing 13.5mPa, day water distribution quantity 80m3, and the amount of being actually implanted into 20m3, well water filling layer blocking is serious, substantially notes and does not intake, Wo Men Should be into using the mode that is continuously injected into, injection carbon dioxide acidification blocking remover, low-oxygen gas mixture and surfactant solution are initial to note It is 19mPa to enter pressure, and using high injection pressure, after injecting a period of time, pressure drops to 14mPa, completes to note by detail design Enter amount, water injection rate reaches 80m after construction3, water injection pressure stabilization is in 7mPa, the pollution of releasing near wellbore zone and blocking, by applying Work improves the intake profile of the water filling layer, and corresponding oil well majority surface casing pressure increases, and well air content increases, take 1 mouthful of oil well into It has gone and has taken gas sample, be oxygen content analysis, the equal < 1.0% of on-the-spot test air guide oxygen content, well below the control of air guide oxygen content Index < 8%, before the well group gas injection, a line well group daily oil production drops to 16.2t/d by 21.7t/d, after gas injection daily oil production by 16.2t/d is raised to 20.6t/d, and daily oil production is stablized in 16.2t/d or so at present, controls well group yield downward trend, moves Liquid level averagely rises 250m, and highest rises 500m, and daily fluid production rate is maintained at 228m3More than, see apparent effect, two wires well Daily oil production drops to 10.4t/d by 16.1t/d before group construction, and daily average oil production drops to 5.7 t/d in 5 months, Daily oil production is raised to 13.2t/d by 10.4t/d after gas injection, and daily oil production is stablized in 12t/d or so at present, controls well group production Downward trend is measured, apparent effect has been seen.
Embodiment 2
The present invention is that a kind of oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology, first by water injection well to stratum A certain amount of carbon dioxide acidification blocking remover is injected, is then in injection mixed gas and surfactant liquids, mixed gas The N that air is isolated by mixed gas separation device2、O2And CO2Mixed gas, while gaseous mixture is controlled by mixed gas separation device The oxygen content of body, surfactant liquids extemporaneous preparation, oil recovery are continuously injected into mode or multistage plug alternating injection mode, inject table Face activating agent liquid and mixed gas, use gas liquid ratio for 1:1 circulate operation, until construction terminates.
Oil, the spontaneous carbon dioxide low temperature of well mix the operational procedure of gas plugging releasing oil displacement construction technology:
1, well site prepares, the facility of wellhead assembly and wellsite is oil-proof, gas leakage, and notice production crew installs well head before constructing Equipment, water injection well are fixed with wire cable anchor;
(1)To the above casing of gas injection packer carry out clear water pressure testing, after meeting the requirements can gas injection, casing pressure test 20mPa, voltage stabilizing 30min, it is qualification that pressure drop, which is less than 0.5mPa,;
(2)Cementing quality is reexamined, needs to meet gas injection intensity requirement;
(3)During tubing string tripping in, oil pipe thread junction, which need to apply, wipes stop-leak compound, and pipe wire buckle winds sealant tape;
(4)Packer bears pressure difference up and down and is intended to reach requirement, meets the higher demand of gas injection pressure;
(5)After tubing string is setting, clear water to well head or less 100m or so is filled in oil jacket annular space;
(6)Before construction, all valves of production tree and tubing and casing are checked, find to loosen fastening in time, the timely replacement of damage, peace Charge of oil, set pressure gauge, pipeline pressure resistance 30mPa;
2, injection device is installed:
(1)Other than air compressor, proportioning pump or pump truck are mounted on away from well head 20m, injection pipeline uses the pipe of pressure resistance 30mPa Line, and install;
(2)Power supply unit type selecting and installation, the special power supply unit that injection, output flow use(Transformer, power distribution cabinet, cable Deng), meet power requirements, the special power supply units such as construction period air compressor, pump, system heat preservation, household electricity and be mounted on Near oil well or the affiliated measuring station of injection well(3-5)At rice;
(3)The emptying design of construction period production fluid gas, oil well produced fluid are put into interim gathering and transferring process, output gas into overhead opening Slack tank, casing gas are vented into blow-down pipe;
(4)Construction well group surveys production profile, construction well changes decentralized wellhead, and casing installs blow-down pipe, it is desirable that drain is away from well head At 25m, pressure gauge and sampler are installed;
Field personnel should be far from pressure line when 3, constructing, and irrelevant personnel should be far from well site;
4, solution is prepared:Match liquid with water injection well water, fetched water by distributing room for water injection water tubing string 4, high temperature foam is being added with liquid pool It is spare to prepare surfactant liquids for agent and room temperature foaming agent;
5, start injection device I first(Pump truck 10)A certain amount of carbon dioxide acidification blocking remover is injected to stratum;
6 and then in injection mixed gas and surfactant liquids, use gas liquid ratio for 1:1, first use injection device I(Pump truck 10)A certain amount of surfactant liquids are injected, separation equipment is then started(Mixed gas separation device 3)With injection device II(It is empty Press 2)A certain amount of mixed gas is injected, mixed gas separation device controls the oxygen content of mixed gas in 5%-8%, using multistage plug Alternately injection mode injects surfactant liquids and mixed gas, circulate operation, until construction terminates;
7, the direct metaideophone of water injection well after the completion of constructing, by oil reservoir requirement injection allocation water filling.
The using effect of embodiment 2:In June, 2013 mixes gas in Liaohe oilfield oil, the spontaneous carbon dioxide low temperature of well Block releasing technique constructs to water injection well, the dynamic change for well group of constructing, and before well group construction, most wells yield declines, Aqueous rising, individual wells are connected to, and water breakthrough occurs, and well group yield drops to 15t/d, application on June 25th, 2013 by 42t/d Oil, the spontaneous carbon dioxide low temperature of well mix gas block releasing technique and are constructed, and are initially injected well injection removal of bridge formation agent, then note Enter low-oxygen gas mixture and surfactant solution, which injects 4 slugs using multistage plug alternating injection mode, initial note of constructing It is 3mPa to enter pressure, and injection rate is completed by detail design, and injection average pressure is stablized in 10mPa, and mixed gas is made uniformly to promote, The generation for preventing too early has channeling, after construction, water injection pressure is stablized in 7mPa or so, and water injection rate is maintained at wanting for injection allocation It asks,
Improve the intake profile of the water filling layer by construction, corresponding well water declines, and improves recovery ratio, and corresponding oil well is most Surface casing pressure increases, and well air content increases, and takes 1 mouthful of oil well to carry out taking gas sample, has done oxygen content analysis, on-the-spot test air guide oxygen The equal < 1.0% of content, well below the Con trolling index < 8% of air guide oxygen content, the corresponding oil well of the well group is with obvious effects, the well group Daily fluid production rate rises to 107.7t/d by 41t/d before gas injection, and daily oil production is raised to 6.6t/d by 4.4t/d, continues 5 months, mesh Day before yesterday stable yield is producing, and adds up to increase oil 300t, hydrodynamic face rises to 1940m by 1036m highests, it is seen that is practicing During oil, the spontaneous carbon dioxide low temperature of well mix gas block releasing technique, oil displacement efficiency and coefficient are improved, with the extension of time, Application effect can be more obvious.
Embodiment 3
The present invention is a kind of oily, mixed gas plugging releasing oil displacement technology of the spontaneous carbon dioxide low temperature of well, is noted first to stratum by oil well Enter a certain amount of carbon dioxide acidification blocking remover, then in injection mixed gas and surfactant liquids, mixed gas is empty The N that gas is isolated by mixed gas separation device2、O2And CO2Mixed gas, while mixed gas is controlled by mixed gas separation device Oxygen content, surfactant liquids extemporaneous preparation, using multistage plug alternating injection mode injection surfactant liquids and mixed Gas is closed, uses gas liquid ratio for 1:1 circulate operation, until construction terminates.
Oil, the spontaneous carbon dioxide low temperature of well mix the operational procedure of gas plugging releasing oil displacement construction technology:
1, well site prepares, the facility of wellhead assembly and wellsite is oil-proof, gas leakage, and notice production crew installs well head before constructing Equipment;
(1)To the above casing of gas injection packer carry out clear water pressure testing, after meeting the requirements can gas injection, casing pressure test 20mPa, voltage stabilizing 30min, it is qualification that pressure drop, which is less than 0.5mPa,;
(2)Cementing quality is reexamined, needs to meet gas injection intensity requirement;
(3)During tubing string tripping in, oil pipe thread junction, which need to apply, wipes stop-leak compound, and pipe wire buckle winds sealant tape;
(4)Packer bears pressure difference up and down and is intended to reach requirement, meets the higher demand of gas injection pressure;
(5)After tubing string is setting, clear water to well head or less 100m or so is filled in oil jacket annular space;
(6)Before construction, all valves of production tree and tubing and casing are checked, find to loosen fastening in time, the timely replacement of damage, peace Charge of oil, set pressure gauge, pipeline pressure resistance 30mPa;
2, injection device is installed:
(1)Other than air compressor, proportioning pump or pump truck are mounted on away from well head 20m, injection pipeline uses the pipe of pressure resistance 30mPa Line, and install;
(2)Power supply unit type selecting and installation, the special power supply unit that injection, output flow use(Transformer, power distribution cabinet, cable Deng), meet power requirements, the special power supply units such as construction period air compressor, pump, system heat preservation, household electricity and be mounted on Near oil well or the affiliated measuring station of injection well(3-5)At rice;
(3)The emptying design of construction period production fluid gas, oil well produced fluid are put into interim gathering and transferring process, output gas into overhead opening Slack tank, casing gas are vented into blow-down pipe;
(4)Construction well group surveys production profile, construction well changes decentralized wellhead, and casing installs blow-down pipe, it is desirable that drain is away from well head At 25m, pressure gauge and sampler are installed;
Field personnel should be far from pressure line when 3, constructing, and irrelevant personnel should be far from well site;
4, solution is prepared:It draws tap water to match liquid with water-tank lorry, high temperature foam agent and room temperature foaming agent is being added with liquid pool, with tabulation Face activating agent liquid is spare;
5, start injection device I first(Pump truck 7)A certain amount of carbon dioxide acidification blocking remover is injected from casing to stratum;
6 and then in injection mixed gas and surfactant liquids, use gas liquid ratio for 1:1, first use injection device I(Pump truck 7) A certain amount of surfactant liquids are injected, separation equipment is then started(Mixed gas separation device 3)With injection device II(Air compressor machine 2)A certain amount of mixed gas is injected, mixed gas separation device is controlled the oxygen content of mixed gas in 5%-8%, replaced using multistage plug Injection mode injects surfactant liquids and mixed gas, circulate operation, until construction terminates from casing;
7, then oil well closing well 4-6 hours after the completion of constructing turns pumping production.
The using effect of embodiment 3:2010 low in Liaohe Oil Field dawn oil recovery factory application oil, the spontaneous carbon dioxide of well The mixed gas block releasing technique of temperature has carried out test construction of handling up to daybreak 1-42-039 oil wells, implements time September 29 to October 2, is somebody's turn to do Well sandstone thickness 32.9m, the number of plies 16 completes carbon dioxide acidification blocking remover injection rate according to detail design dosage, gaseous mixture is noted Enter amount, surfactant injection rate, the well daily fluid production rate rises to 4t/d by 0t/d before gas injection after construction, and daily oil production is by 0t/d It is raised to 1.4t/d, aqueous 65% after gas injection, 317 days production times, current daily production rate stabilization is producing, and adds up to increase oil 444t, increase Liquid 1268t, oil increasing effect is apparent, the line well closed on after daybreak 1-42-039 wells note gaseous mixture(Daybreak 141038, daybreak 14139, daybreak 142038)With two wires well(Daybreak 14239C, daybreak 141039)Increase oil 18t, 13t, 17.4t, 99t, 21.6t respectively, adds up to 169t. Same period liquid level test data before and after measure was compared with the upper same period in period, and the sinking rate of pump significantly improves, and was illustrated by noting gaseous mixture Afterwards, the expansion energy of air supplements stratum energy, the fluid supply capacity of oil well is improved, by Liaohe Oil Field daybreak 1-42-039 wells Offset well casing gas monitors, and on 1 day ~ November 19 October in 2010, oxygen content is 0.00% ~ 0.24% in casing gas, is substantially existed 0.10% or so variation, well below 8%, reaches construction safety requirement, opening well and making production:Oxygen content in monitoring tube gas, oxygen content < 8% can normal opening well and making production.

Claims (4)

1. it includes oil, the spontaneous carbon dioxide low temperature of well that a kind of oil, the spontaneous carbon dioxide low temperature of well, which mix gas plugging releasing oil displacement technology, Mixed gas plugging releasing oil displacement construction technology, is characterized in that:The oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement and construct work Skill injects a certain amount of carbon dioxide acidification blocking remover by oil well or water injection well to stratum first, then in injection gaseous mixture Body and surfactant liquids, mixed gas are the N that air is isolated by mixed gas separation device2、O2And CO2Mixed gas, together When by mixed gas separation device control mixed gas oxygen content, surfactant liquids extemporaneous preparation, using the side of being continuously injected into Formula or multistage plug replace injection mode, inject surfactant liquids and mixed gas, use gas liquid ratio for 1:1, circulate operation, Terminate to construction.
2. oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology according to claim 1, it is characterised in that:Institute The oxygen content of mixed gas is stated 5% ~ 8%, the oxygen content < 8% in stratum.
3. oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology according to claim 1, it is characterised in that:Institute It is 1 to state gas liquid ratio:1 is mixed gas volume and surfactant liquids volume ratio under formation pressure.
4. oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology according to claim 1, it is characterised in that:Institute Stating the operational procedure of the mixed gas plugging releasing oil displacement construction technology of oil, the spontaneous carbon dioxide low temperature of well is:(1)Well site prepares, well head fills It sets and does not answer oil leak, gas leakage with the facility of wellsite, notice production crew installs wellhead equipment, water injection well steel wire before constructing Line anchor is fixed;A, to the above casing of gas injection packer carry out clear water pressure testing, after meeting the requirements can gas injection, casing pressure test 20mPa, Voltage stabilizing 30min, it is qualification that pressure drop, which is less than 0.5mPa,;B, cementing quality is reexamined, needs to meet gas injection intensity requirement;C, tubing string During tripping in, oil pipe thread junction, which need to apply, wipes stop-leak compound, and pipe wire buckle winds sealant tape;D, packer is born Upper and lower pressure difference is intended to reach requirement, meets the higher demand of gas injection pressure;E, after tubing string is setting, clear water is filled extremely in oil jacket annular space 100m or so below import;F, before construction, all valves of production tree and tubing and casing are checked, find to loosen fastening in time, damage Timely replacement, installation oil, set pressure gauge, pipeline pressure resistance 30mPa;(2)Injection device is installed:A, air compressor, proportioning pump Or other than pump truck is mounted on away from well head 20m, injection pipeline uses the pipeline of pressure resistance 30mPa, and installs;B, power supply unit type selecting and Installation, the special power supply unit that injection, output flow use(Transformer, power distribution cabinet, cable etc.), meet construction period air pressure The power requirements such as contracting machine, pump, system heat preservation, household electricity, special power supply unit are mounted on oil well or the affiliated measuring station of injection well Near(3-5)At rice;C, construction period production fluid gas emptying design, oil well produced fluid into interim gathering and transferring process, output gas into Overhead opening blow-down tank, casing gas are vented into blow-down pipe;D, construction well group surveys production profile, construction well changes decentralized wellhead, covers Pipe installs blow-down pipe, it is desirable that at 25 meters away from well head of drain, installs pressure gauge and sampler;(3)Work on the spot when construction Personnel should be far from pressure line, and irrelevant personnel should be far from well site;(4)Prepare solution:Match liquid with water injection well water or tap water, High temperature foam agent and room temperature foaming agent is added with liquid pool, it is spare to prepare surfactant liquids;Well construction 10-15m3 1-2 It is a to match liquid with liquid pool;(5)Start injection device I first(Pump truck)A certain amount of carbon dioxide acidification blocking remover is injected to stratum; (6)Then in injection mixed gas and surfactant liquids, use gas liquid ratio for 1:1, first use injection device I(Pump truck)Injection A certain amount of surfactant liquids, then start separation equipment(Mixed gas separation device)With injection device II(Air compressor machine)Injection A certain amount of mixed gas, mixed gas separation device control the oxygen content of mixed gas in 5%-8%, using the mode that is continuously injected into or more Slug replaces injection mode, surfactant liquids and mixed gas, circulate operation is injected, until construction terminates;(7)Construction is completed The direct metaideophone of water injection well afterwards, by oil reservoir requirement injection allocation water filling;Then oil well closing well 4-6 hours turns pumping production.
CN201810131067.7A 2018-02-09 2018-02-09 Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology Pending CN108343407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810131067.7A CN108343407A (en) 2018-02-09 2018-02-09 Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810131067.7A CN108343407A (en) 2018-02-09 2018-02-09 Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology

Publications (1)

Publication Number Publication Date
CN108343407A true CN108343407A (en) 2018-07-31

Family

ID=62959196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810131067.7A Pending CN108343407A (en) 2018-02-09 2018-02-09 Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology

Country Status (1)

Country Link
CN (1) CN108343407A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109538178A (en) * 2019-01-15 2019-03-29 西南石油大学 Spontaneous CO in a kind of layer2Inflating medium system preferred embodiment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1451844A (en) * 2003-05-09 2003-10-29 辽河石油勘探局 Heat, electricity, CO2 and N2 united supply making method for oil field production
CN2616684Y (en) * 2003-05-09 2004-05-19 辽河石油勘探局 Heat, electricity, Co2, N2 united supply apparatus for oil field production
CN102367730A (en) * 2011-09-23 2012-03-07 大庆高新区黑帝庙稠油试采技术开发有限公司 Heavy oil multiphase thermal huff and puff oil recovery method
CN103937475A (en) * 2014-04-22 2014-07-23 大庆中油泰克石油技术服务有限公司 Carbon dioxide acidification blocking remover and process of not reversely discharging raffinate after acidification
US20160376882A1 (en) * 2015-04-09 2016-12-29 Paul E. Mendell Gas diverter for well and reservoir stimulation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1451844A (en) * 2003-05-09 2003-10-29 辽河石油勘探局 Heat, electricity, CO2 and N2 united supply making method for oil field production
CN2616684Y (en) * 2003-05-09 2004-05-19 辽河石油勘探局 Heat, electricity, Co2, N2 united supply apparatus for oil field production
CN102367730A (en) * 2011-09-23 2012-03-07 大庆高新区黑帝庙稠油试采技术开发有限公司 Heavy oil multiphase thermal huff and puff oil recovery method
CN103937475A (en) * 2014-04-22 2014-07-23 大庆中油泰克石油技术服务有限公司 Carbon dioxide acidification blocking remover and process of not reversely discharging raffinate after acidification
US20160376882A1 (en) * 2015-04-09 2016-12-29 Paul E. Mendell Gas diverter for well and reservoir stimulation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
YJ8968957: "化学驱提高采收率", 《道客巴巴》 *
吉亚娟等: "注空气采油工艺的风险分析及安全控制技术", 《石油化工安全环保技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109538178A (en) * 2019-01-15 2019-03-29 西南石油大学 Spontaneous CO in a kind of layer2Inflating medium system preferred embodiment

Similar Documents

Publication Publication Date Title
Clark A hydraulic process for increasing the productivity of wells
CN102002351B (en) Selective chemical water shutoff agent for gravel-packed well
CN102587873B (en) Carbon dioxide huff-puff water-control oil-increasing method for horizontal well
CN102618228B (en) Plugging agent for clastic rock oil reservoir horizontal well, preparation method and water plugging method
CN108868706B (en) Method for exploiting natural gas hydrate by directional drilling supercritical carbon dioxide fracturing and displacement
CN102423655B (en) Large-flow fracturing fluid preparation system and method
CN107420081B (en) Fracturing method for realizing effective partial pressure of compact heterogeneous reservoir
CN107060704B (en) Supercritical CO2It is atomized deep penetration acid fracturing method
CN209483309U (en) Gas lift device
CN106837268B (en) Control water gas-injection oil-production integration method for increasing
CN101915079B (en) Integrated de-plugging yield increasing process
CN108049858A (en) The fine and close compound sand fracturing method of the preposition accumulation of energy of oil well carbon dioxide
US20210108491A1 (en) Integrated construction method of fracturing and tertiary oil recovery for low-permeability reservoir
CN204941492U (en) Regulation device is injected in water injection well umbilical duct holostrome position
CN201874543U (en) Underground boosting water injection process pipe string
CN208220728U (en) Thick oil well pipe column
CN114183115B (en) Efficient natural gas hydrate exploitation system and method
CN108343407A (en) Oil, the spontaneous carbon dioxide low temperature of well mix gas plugging releasing oil displacement technology
CN105201473A (en) Multiple-oil-layer deep profile control injection device and oil layer deep profile control realizing method thereof
CN103470233B (en) Heavy oil reservoir natural gas huff-puff oil production process system and oil production method
CN205714119U (en) A kind of gas hydrate quarrying apparatus
CN107882544B (en) A kind of mixing heat release method for removing blockage for carbonate cementation molding sand rock heavy oil wells
CN107246257A (en) Heterogeneous reservoir is acidified remodeling method
CN204266988U (en) A kind of pilot-controlled switch sliding sleeve
CN109057770A (en) The system for carrying out gas-lift production using this well recycling gas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180731

WD01 Invention patent application deemed withdrawn after publication