CN108316153B - A kind of construction method of multistory reinforced concrete slab - Google Patents

A kind of construction method of multistory reinforced concrete slab Download PDF

Info

Publication number
CN108316153B
CN108316153B CN201810122616.4A CN201810122616A CN108316153B CN 108316153 B CN108316153 B CN 108316153B CN 201810122616 A CN201810122616 A CN 201810122616A CN 108316153 B CN108316153 B CN 108316153B
Authority
CN
China
Prior art keywords
layer
vibrator
steel bar
vibrating
adjacent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810122616.4A
Other languages
Chinese (zh)
Other versions
CN108316153A (en
Inventor
蔡天成
邱继峰
魏恒相
刘帅
刘鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Engineering Co Ltd of China Railway 19 Bureau Group Co Ltd
Original Assignee
Seventh Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seventh Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical Seventh Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201810122616.4A priority Critical patent/CN108316153B/en
Publication of CN108316153A publication Critical patent/CN108316153A/en
Application granted granted Critical
Publication of CN108316153B publication Critical patent/CN108316153B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention provides a kind of construction method of multistory reinforced concrete slab, the construction method, which includes that reinforcing bar is folded, pricks step, clear mould moistens step, concreting step and curing step, the construction method binds distance by changing the folded reinforcing bar binding structure pricked in step of reinforcing bar and reinforcing bar pad, change the spacing of vibrating of the vibrator in concreting step, what the single of concrete slab poured thickness and concrete layer pours interval time, change the parameters such as the curing time of concrete slab in curing step, so that the multistory reinforced concrete slab constructed out has the compression strength for improving the multistory reinforced concrete slab constructed out, honeycomb is sewed and mend and eliminated to the intensity for reducing multistory reinforced concrete slab, the advantages of leaking muscle.

Description

A kind of construction method of multistory reinforced concrete slab
Technical field
The present invention relates to bridge panel technical field of construction, specifically, being to be related to a kind of multilayer for bridge panel The construction method of armored concrete panel.
Background technique
With the fast development of the infrastructures such as highroad, railway, so that science of bridge building technology also obtains significantly It is promoted, this also causes, quality requirement higher and higher to the technical requirements of bridge construction to be increasingly stringenter.And it is built in modern bridge If in, bridge panel, bridge pier etc. are of crucial importance, wherein for bridge panel, the size of compression strength There is important influence to the total quality of bridge, and in modern bridge panel, concrete is the important composition of bridge panel Part, and current most bridges are directly poured using concrete, are had it from great, discontinuity, are led Bridge panel is caused to be easy uneven by weight, when over time, bridge panel is easy for slight crack occur and collapse, to jeopardize the public Safety.For this purpose, bridge panel has developed the method that some multilayers pour, still, mesh on the basis of traditional single layer pours Before the multilayer casting method that is widely used be also to carry out concreting according to traditional panel pouring construction method, and it is this The bridge panel of method output is still difficult to meet actual demand, and when bridge panel occurs damaged, carries out secondary Repairing will increase economic loss, and the difficulty repaired is big, technical requirements are high.Furthermore it, also can be one even if having carried out secondary repairing Determine the actual performance that bridge is influenced in degree, there are security risks.
Summary of the invention
To solve the above-mentioned problems, the main object of the present invention is to provide a kind of multistory reinforced concrete for improving and constructing out The compression strength of panel eliminates honeycomb, leakage muscle, and reduces the multistory reinforced concrete of multistory reinforced concrete slab intensity distribution The construction method of panel.
In order to realize that the main object of the present invention, the present invention provide a kind of construction method of multistory reinforced concrete slab, Wherein, including reinforcing bar is folded and pricks step, is bound respectively to multistory reinforced layer using traditional planar process, in adjacent two layers reinforcing bar Multiple reinforcing bar pads, multiple reinforcing bar pad rectangular array settings, and the distance between two neighboring reinforcing bar pad is arranged in interval between layer It is 5 times to 8 times of the distance between adjacent two layers steel bar layer;Clear mould moistens step, carries out mould to the multistory reinforced layer bound Plate is built, and is watered into the template put up, and keeps template wet;Concreting step, the placement layer by layer coagulation into template Soil to carry out concreting to each layer of steel bar layer, the concrete layer poured every time with a thickness of between adjacent two layers steel bar layer Distance half to 2/3rds, and the thickness of concrete layer is at least 5 centimetres, after every layer concrete layer pours, makes It is vibrated with vibrator to concrete layer, carries out next layer concrete layer after the completion of vibrating and pour, vibrate, until completing multilayer The one-piece casting of armored concrete panel;Curing step, it is right within 12 hours after multistory reinforced concrete slab pours Multistory reinforced concrete slab is covered, and carries out water seasoning, curing period be 5 round the clock to 8 round the clock.
Further embodiment is concreting step further include: pouring between the time between adjacent two layers concrete layer It is divided into 15 minutes to 30 minutes.
Further scheme is, 1 times to 1.5 of the operating radius of the vibrating spear that spacing is vibrator of vibrating of vibrator Times.
Further scheme is concreting step further include: is being vibrated using vibrator to concrete layer When, if vibrator is close to steel bar layer, the spacing of vibrating of vibrator is reduced into 0.8 times to 1 times of the operating radius of vibrating spear.
Further scheme is concreting step further include: is carrying out when vibrating of next layer concrete layer, vibration Upper 4 centimetres to 6 centimetres of layer concrete layer of tamper insertion.
Further scheme is that clear mould moistens step further include: after the completion of template is built, first to the sundries in template Be purged with the greasy dirt in steel bar layer, and check template template seam between plastic layer or mortar whether pad, then into Row waters into the template put up.
One Preferable scheme is that, the distance between two neighboring reinforcing bar pad is the distance between adjacent two layers steel bar layer 5 times, the half with a thickness of the distance between adjacent two layers steel bar layer of the concrete layer poured every time, curing period is 5 Round the clock, the time interval that pours between adjacent two layers concrete layer is 15 minutes, the vibration that spacing is vibrator of vibrating of vibrator 1 times of the operating radius of tamper, and if vibrator close to steel bar layer when, vibrator vibrate spacing be vibrating spear operating radius 0.8 times.
Another Preferable scheme is that, the distance between two neighboring reinforcing bar pad is the distance between adjacent two layers steel bar layer 6.5 times, the concrete layer poured every time with a thickness of 7th/12nd of the distance between adjacent two layers steel bar layer, curing period Round the clock for 6.5, the time interval that pours between adjacent two layers concrete layer is 22.5 minutes, and the spacing of vibrating of vibrator is vibration 1.25 times for smashing the operating radius of the vibrating spear of device, and if vibrator close to steel bar layer when, vibrator vibrate spacing be vibrate 0.9 times of the operating radius of stick.
Another Preferable scheme is that, the distance between two neighboring reinforcing bar pad is the distance between adjacent two layers steel bar layer 8 times, the concrete layer poured every time with a thickness of 2/3rds of the distance between adjacent two layers steel bar layer, curing period 8 A the time interval that pours between adjacent two layers concrete layer is 30 minutes round the clock, and the spacing of vibrating of vibrator is vibrator 1.5 times of the operating radius of vibrating spear, and if vibrator close to steel bar layer when, vibrator vibrate spacing be vibrating spear effect 1 times of radius.
Further embodiment is that concreting step further includes pouring observation of steps, and pouring observation of steps includes: per complete At one layer of steel bar layer concreting when, check whether reinforcing bar, the built-in fitting of template and the steel bar layer poured move Dynamic, deformation or blocking if so, stopping concreting immediately, and are modified before the concrete layer initial set poured.
Therefore the construction method of the multistory reinforced concrete slab of offer of the invention have improve construct out it is more The compression strength of layer armored concrete panel eliminates honeycomb, leakage muscle, and reduces the excellent of multistory reinforced concrete slab intensity distribution Point mainly passes through the vibration of the binding distance, vibrator of the reinforcing bar binding structure, reinforcing bar pad for changing multistory reinforced concrete slab Smash spacing, the single of concrete layer pours thickness, concrete layer pours interval time and multistory reinforced concrete slab Curing time enables the multistory reinforced concrete slab poured out to have excellent physical property, and can effectively improve The compression strength of multistory reinforced concrete slab, so that the multistory reinforced concrete slab poured out can satisfy bridge panel Actual demand, and eliminate honeycomb, leak the defects of muscle.
Detailed description of the invention
Fig. 1 is the flow diagram of the construction method first embodiment of the multistory reinforced concrete slab of the present invention.
Fig. 2 is the experimental data table of each embodiment of construction method of the multistory reinforced concrete slab of the present invention.
The invention will be further described with reference to the accompanying drawings and embodiments.
Specific embodiment
The construction method of multistory reinforced concrete slab provided by the invention is constructed for the panel to bridge floor, into And the compression strength for improving the multistory reinforced concrete slab constructed out is played, honeycomb, leakage muscle are eliminated, and effectively reduce composite steel The distribution intensity of reinforced concrete panel, so that multistory reinforced concrete slab can satisfy the actual demand of bridge.
The construction method first embodiment of multistory reinforced concrete slab:
As shown in Figure 1, the construction method of multistory reinforced concrete slab, which includes that reinforcing bar is folded, pricks the wet step of step S1, clear mould S2, concreting step S3 and curing step S4.
Wherein, the folded step S1 that pricks of reinforcing bar includes: the reinforcing bar that dimension is chosen according to Practical Project requirement, using traditional Planar process respectively binds multistory reinforced layer, and multiple reinforcing bar pads are arranged in interval between adjacent two layers steel bar layer, multiple Reinforcing bar pads rectangular array setting, and the distance between two neighboring reinforcing bar pad is the 5 of the distance between adjacent two layers steel bar layer Again to 8 times.
Specifically, first bottom layer of the reinforcing steel layer is bound using planar process, then, on the bottom layer of the reinforcing steel layer upper berth bound If multiple reinforcing bar pads, and multiple reinforcing bars pad rectangular array is arranged, then, used on the multiple reinforcing bar pads laid Planar process carries out the binding of second layer steel bar layer.Then, above-mentioned reinforcing bar pad lay-up operation and steel bar layer binding operation completion pair are repeated The binding of remaining steel bar layer, until completing all reinforcing bars binding of multistory reinforced concrete slab.
In addition, the number of plies of steel bar layer is three layers or three layers or more, and the distance between bottom layer of the reinforcing steel layer and template bottom surface are / 5th of the distance between adjacent two layers steel bar layer are to a quarter, and the maximum between bottom layer of the reinforcing steel layer and template bottom surface Distance is less than 5 centimetres;The distance between top layer steel bar layer and template top surface are five points of the distance between adjacent two layers steel bar layer One of to a quarter, and the maximum distance between top layer steel bar layer and template top surface is less than 5 centimetres.The present embodiment bottom layer of the reinforcing steel The distance between layer and template bottom surface are 1/5th of the distance between adjacent two layers steel bar layer, top layer steel bar layer and template top The distance between face is 1/5th of the distance between adjacent two layers steel bar layer.Also, the two neighboring reinforcing bar of the present embodiment The distance between pad is 5 times of the distance between adjacent two layers steel bar layer.
It includes: to carry out template to the multistory reinforced layer bound to build that clear mould, which moistens step S2, after the completion of template is built, Greasy dirt in the sundries such as soil, rubbish in template and steel bar layer is carried out it is clear, in order to avoid influence multistory reinforced concrete surface The pouring quality of plate.Then, whether the plastic layer or mortar detected between the template seam of template pads, and avoids in casting process Concrete leaks.Then, it waters into the template put up, template is made to keep wet.
Concreting step S3 includes: that concrete is stirred according to the formula of design requirement, be then segmented concrete, In the injection template of layering.Specifically, to template by concreting in lifts to carry out concreting to each layer of steel bar layer, When pouring, guarantee the half with a thickness of the distance between adjacent steel bar layer of concrete layer poured every time to three/ One, and the thickness of concrete layer is at least 5 centimetres.In addition, after every layer concrete layer pours, using vibrator to the concrete layer It vibrates, carries out next layer concrete layer after the completion of vibrating and pour, vibrate, until completing the whole of multistory reinforced concrete slab Body pours.
Specifically, two points with a thickness of the distance between adjacent steel bar layer of the concrete layer poured every time of the present embodiment One of.In addition, between adjacent two layers concrete layer pour time interval be 15 minutes to 30 minutes, adjacent the two of the present embodiment The time interval that pours between layer concrete layer is 15 minutes.
In addition, the spacing of vibrating that vibrator when vibrating to concrete layer, controls vibrator is vibrating for vibrator 1 times to 1.5 times of the operating radius of side, the vibrator of the present embodiment vibrate spacing be vibrator the side that vibrates operating radius 1 times.And when being vibrated using vibrator to concrete layer, if vibrator close to steel bar layer or when touching steel bar layer, The spacing of vibrating of vibrator is reduced into 0.8 times to 1 times of the operating radius of vibrating spear, the vibrator of the present embodiment is close to reinforcing bar The spacing of vibrating of vibrator, is reduced into 0.8 times of the operating radius of vibrating spear by layer or when touching steel bar layer.Furthermore into When vibrating of the next layer concrete layer of row, i.e., vibrator when vibrating to the concrete layer more than second layer, answer by vibrating spear It is inserted into upper 4 centimetres to 6 centimetres of layer concrete layer, it is preferable that vibrating spear should be inserted into 5 centimetres of a layer concrete layer.
Concreting step S3 further includes pouring observation of steps, and pouring observation of steps includes: to complete each layer of reinforcing bar When the concreting of layer, check whether reinforcing bar, the built-in fitting of template and the steel bar layer poured mobile, deformation or stifled occur Plug.If so, stopping concreting immediately, and to template and the steel bar layer poured before the concrete layer initial set poured Reinforcing bar, built-in fitting is modified.
Curing step S4 includes: after multistory reinforced concrete slab pours, to composite steel within 12 hours Reinforced concrete panel is covered, and pour maintenance, curing period be 5 round the clock to 8 round the clock, the curing period of the present embodiment Round the clock for 5.
The construction method second embodiment of multistory reinforced concrete slab:
Using the inventive concept of the construction method first embodiment of multistory reinforced concrete slab, multistory reinforced concrete surface The construction method second embodiment and first embodiment of plate the difference is that:
In the folded bundle step of reinforcing bar, the distance between two neighboring reinforcing bar point is the distance between adjacent two layers steel bar layer 6.5 times, and the distance between top layer steel bar layer and template top surface are 9th/40th of the distance between adjacent two layers steel bar layer, The distance between bottom layer of the reinforcing steel layer and template bottom surface are 9th/40th of the distance between adjacent two layers steel bar layer.
Poured in step in concreting, the concrete layer poured every time with a thickness of between adjacent two layers steel bar layer 7th/12nd of distance, the time interval that pours between adjacent two layers concrete layer is 22.5 minutes.In addition, the vibration of vibrator 1.25 times for smashing the operating radius for the vibrating spear that spacing is vibrator, and when being vibrated using vibrator to concrete layer, If vibrator is reduced into the operating radius of vibrating spear close to steel bar layer or when touching steel bar layer, by the spacing of vibrating of vibrator 0.9 times.
In curing step, to the curing period of the multistory reinforced concrete slab poured be 6.5 round the clock.
The construction method 3rd embodiment of multistory reinforced concrete slab:
Using the inventive concept of the construction method first embodiment of multistory reinforced concrete slab, multistory reinforced concrete surface The construction method 3rd embodiment and first embodiment of plate the difference is that:
In the folded bundle step of reinforcing bar, the distance between two neighboring reinforcing bar point is the distance between adjacent two layers steel bar layer 8 times, and the distance between top layer steel bar layer and template top surface are a quarter of the distance between adjacent two layers steel bar layer, bottom The distance between steel bar layer and template bottom surface are a quarter of the distance between adjacent two layers steel bar layer.
Poured in step in concreting, the concrete layer poured every time with a thickness of between adjacent two layers steel bar layer 2/3rds of distance, the time interval that pours between adjacent two layers concrete layer is 330 minutes.In addition, vibrator vibrates Spacing is 1.5 times of the operating radius of the vibrating spear of vibrator, and when being vibrated using vibrator to concrete layer, if vibration Device is smash close to steel bar layer or when touching steel bar layer, the spacing of vibrating of vibrator is reduced into 1 times of the operating radius of vibrating spear.
In curing step, to the curing period of the multistory reinforced concrete slab poured be 8 round the clock.
As shown in Fig. 2, Fig. 2 is that the multistory reinforced concrete slab that various embodiments of the present invention are constructed out is applied with the prior art The parameter comparison table for the multistory reinforced concrete slab that work goes out.According to " Standard for inspection and assessment of strength of concrete " (GBJ107-87) The multistory reinforced concrete slab constructed out to construction method of the invention of the defined method of inspection and technological means it is related Performance is detected, and can be seen that by taking the first embodiment of the present invention to 3rd embodiment as an example and in conjunction with Fig. 2 of the invention The multistory reinforced concrete slab that construction method is constructed out is compared with for the prior art, and multistory reinforced coagulation can be effectively eliminated The honeycomb of native panel leaks the problem of muscle, and then can effectively improve the performance of multistory reinforced concrete slab, and can obviously drop The deviation of low built-in fitting and the deviation of absolute altitude improve the quality and assembly precision of multistory reinforced concrete slab.In addition, of the invention The compression strength of the multistory reinforced concrete slab constructed out significantly improve compared with the prior art, intensity distribution is compared to existing There is technology to be effectively reduced, so that multistory reinforced concrete slab there can be better stability.
As it can be seen that reinforcing bar binding structure, the reinforcing bar pad of construction method of the invention by the multistory reinforced concrete slab of change Binding distance, the spacing of vibrating of vibrator, concrete layer pour thickness, concrete layer pours interval time and multilayer The parameters such as the curing time of armored concrete panel, and then the problem of leaking muscle is eliminated from source, and because effective control steel The distribution relation of muscle layer and spacing is controlled by reinforcing bar pad, thus the case where leaking muscle caused by preventing reinforcing steel bars exposed hair It is raw.Furthermore for the multistory reinforced concrete slab that construction method of the invention is constructed out, due to can be according to adjacent reinforcing bar The position of the spacing of layer and reinforcing bar pad controls vibrate position and the number that vibrates (spacing determines by vibrating) of concrete layer, And then it reduces or eliminates possible existing for honeycomb.And for intensity, due to stable bar construction and and reinforcing bar The corresponding vibrating method of structure, and then the concrete structure of multistory reinforced concrete slab has been tamped, it improves multistory reinforced The intensity of concrete slab.Further, since using multistory reinforced layer structure, and make between keeping certain between adjacent steel bar layer Away from so that be capable of forming between steel bar layer be combined with each other but mutually independent space structure, enable to general beat Hole operation is only burdened with influence on a certain steel bar layer, and the performance without will affect other steel bar layers ensure that multistory reinforced concrete The stability of panel.
In conclusion the construction method of multistory reinforced concrete slab provided by the invention is by changing multistory reinforced coagulation The reinforcing bar binding structure of native panel, the binding distance of reinforcing bar pad, the spacing of vibrating of vibrator, concrete layer single pour thickness Degree, concrete layer pour the curing time of interval time and multistory reinforced concrete slab, so that the composite steel poured out Reinforced concrete panel can have excellent physical property, and can effectively improve the pressure resistance of multistory reinforced concrete slab Degree, so that the multistory reinforced concrete slab poured out can satisfy the actual demand of bridge panel, and eliminate honeycomb, leakage muscle etc. The multistory reinforced concrete that defect, the compression strength for the multistory reinforced concrete slab constructed out with raising and reduction are constructed out The intensity distribution of panel.
Finally it is emphasized that the above description is only a preferred embodiment of the present invention, it is not intended to restrict the invention, it is right For those skilled in the art, the present invention can have various change and change, all within the spirits and principles of the present invention, Any modification, equivalent substitution, improvement and etc. done, should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of construction method of multistory reinforced concrete slab characterized by comprising
Reinforcing bar is folded to prick step, is bound respectively to multistory reinforced layer using planar process, between the steel bar layer described in adjacent two layers Interval is arranged multiple reinforcing bar pads, multiple reinforcing bars pad rectangular arrays settings, and between the two neighboring reinforcing bar pad away from From 5 times to 8 times for the distance between steel bar layer described in adjacent two layers;
Clear mould moistens step, and the steel bar layer described in the multilayer bound carries out template and builds, and into the template put up Watering keeps the template wet;
Concreting step, concreting in lifts is poured with carrying out concrete each layer steel bar layer in Xiang Suoshu template It builds, the half with a thickness of the distance between steel bar layer described in adjacent two layers of the concrete layer poured every time to three/ Two, and the thickness of the concrete layer is at least 5 centimetres, after every layer of concrete layer pours, using vibrator to described mixed Solidifying soil layer vibrates, and carries out next layer concrete layer after the completion of vibrating and pours, vibrates, until completing the multistory reinforced coagulation The one-piece casting of native panel;
Curing step, after the multistory reinforced concrete slab pours, to the multistory reinforced coagulation within 12 hours Native panel is covered, and carries out water seasoning, curing period be 5 round the clock to 8 round the clock.
2. construction method according to claim 1, it is characterised in that:
The concreting step further include:
The time interval that pours between concrete layer described in adjacent two layers is 15 minutes to 30 minutes.
3. construction method according to claim 2, it is characterised in that:
1 times to 1.5 times of operating radius of the vibrating spear that spacing is the vibrator of vibrating of the vibrator.
4. construction method according to claim 3, it is characterised in that:
The concreting step further include:
It, will if the vibrator is close to the steel bar layer when being vibrated using the vibrator to the concrete layer The spacing of vibrating of the vibrator is reduced into 0.8 times to 1 times of the operating radius of the vibrating spear.
5. construction method according to claim 4, it is characterised in that:
The concreting step further include:
When vibrating of next layer concrete layer is being carried out, the vibrating spear is inserted into upper one layer of 4 centimetres to 6 lis of concrete layer Rice.
6. construction method according to claim 5, it is characterised in that:
The clear mould moistens step further include:
After the completion of the template is built, first the greasy dirt on the sundries and the steel bar layer in the template is purged, and It checks whether plastic layer or mortar between the template seam of the template pad, then waters into the template put up.
7. construction method according to claim 6, it is characterised in that:
The distance between two neighboring described reinforcing bar pad is 5 times of the distance between steel bar layer described in adjacent two layers;
The half with a thickness of the distance between steel bar layer described in adjacent two layers of the concrete layer poured every time;
The curing period be 5 round the clock;
The time interval that pours between concrete layer described in adjacent two layers is 15 minutes;
1 times of operating radius of the vibrating spear that spacing is the vibrator of vibrating of the vibrator, and if the vibrator lean on When the nearly steel bar layer, 0.8 times of the operating radius that spacing is the vibrating spear of vibrating of the vibrator.
8. construction method according to claim 6, it is characterised in that:
The distance between two neighboring described reinforcing bar pad is 6.5 times of the distance between steel bar layer described in adjacent two layers;
The concrete layer poured every time with a thickness of 7/12nds of the distance between steel bar layer described in adjacent two layers;
The curing period be 6.5 round the clock;
The time interval that pours between concrete layer described in adjacent two layers is 22.5 minutes;
1.25 times of operating radius of the vibrating spear that spacing is the vibrator of vibrating of the vibrator, and if the vibrator When close to the steel bar layer, 0.9 times of the operating radius that spacing is the vibrating spear of vibrating of the vibrator.
9. construction method according to claim 6, it is characterised in that:
The distance between two neighboring described reinforcing bar pad is 8 times of the distance between steel bar layer described in adjacent two layers;
The concrete layer poured every time with a thickness of 2/3rds of the distance between steel bar layer described in adjacent two layers;
The curing period be 8 round the clock;
The time interval that pours between concrete layer described in adjacent two layers is 30 minutes;
1.5 times of operating radius of the vibrating spear that spacing is the vibrator of vibrating of the vibrator, and if the vibrator When close to the steel bar layer, 1 times of the operating radius that spacing is the vibrating spear of vibrating of the vibrator.
10. construction method according to any one of claims 1 to 9, it is characterised in that:
The concreting step further includes pouring observation of steps, and the observation of steps that pour include:
When every concreting for completing one layer of steel bar layer, the reinforcing bar of inspection template and the steel bar layer poured, Whether built-in fitting there is mobile, deformation or blocking;
If so, stopping concreting immediately, and it is modified before the concrete layer initial set poured.
CN201810122616.4A 2018-02-07 2018-02-07 A kind of construction method of multistory reinforced concrete slab Active CN108316153B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810122616.4A CN108316153B (en) 2018-02-07 2018-02-07 A kind of construction method of multistory reinforced concrete slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810122616.4A CN108316153B (en) 2018-02-07 2018-02-07 A kind of construction method of multistory reinforced concrete slab

Publications (2)

Publication Number Publication Date
CN108316153A CN108316153A (en) 2018-07-24
CN108316153B true CN108316153B (en) 2019-09-24

Family

ID=62902983

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810122616.4A Active CN108316153B (en) 2018-02-07 2018-02-07 A kind of construction method of multistory reinforced concrete slab

Country Status (1)

Country Link
CN (1) CN108316153B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102021879A (en) * 2010-12-31 2011-04-20 上海市城市建设设计研究院 Rail transit steel structure bridge
KR20120108073A (en) * 2011-03-23 2012-10-05 (주)삼현피에프 Manufacturing method of box type steel-concrete composite girder and construction method of thereof
CN103266562A (en) * 2013-06-09 2013-08-28 福州大学 Flexible damping continuous bridge deck pavement structure system of intrados type arch bridge and construction process thereof
CN203213011U (en) * 2013-04-25 2013-09-25 湖南固特邦土木技术发展有限公司 Bridge paving structure reinforced by bridge deck reinforcing layer
CN105887655A (en) * 2016-05-18 2016-08-24 同济大学 Combined beam containing perforated plate connectors and construction method of combined beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102021879A (en) * 2010-12-31 2011-04-20 上海市城市建设设计研究院 Rail transit steel structure bridge
KR20120108073A (en) * 2011-03-23 2012-10-05 (주)삼현피에프 Manufacturing method of box type steel-concrete composite girder and construction method of thereof
CN203213011U (en) * 2013-04-25 2013-09-25 湖南固特邦土木技术发展有限公司 Bridge paving structure reinforced by bridge deck reinforcing layer
CN103266562A (en) * 2013-06-09 2013-08-28 福州大学 Flexible damping continuous bridge deck pavement structure system of intrados type arch bridge and construction process thereof
CN105887655A (en) * 2016-05-18 2016-08-24 同济大学 Combined beam containing perforated plate connectors and construction method of combined beam

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"K53+827库竹大桥桥面铺装施工方案";百度;《https://wenku.baidu.com/view/3a0971cbb4daa58da1114a0b.html》;20160703;文献施工方案和质量保证体系部分 *

Also Published As

Publication number Publication date
CN108316153A (en) 2018-07-24

Similar Documents

Publication Publication Date Title
CN106869402B (en) Assembly concrete component and its manufacturing method
CN103938864B (en) Infilled wall Constructional Col-umn Construction engineering method
CN104514305B (en) 3D printing truss cassette ceiling and its construction method
CN104372890A (en) Construction method of bare concrete prefabricated box beam with complicated structure
CN107882240A (en) The prefabricated superimposed sheet of one kind regeneration monolith and its manufacture craft
CN108660935A (en) A kind of construction method of reinforced concrete arch bridge
CN205776987U (en) A kind of assembled cavity floor
CN109356016A (en) A kind of light section-ultra-high performance concrete stiffness bracket floor and construction method
CN109306714A (en) Jump the control distress in concrete construction method that storehouse method is combined with expansion reinforcing band
CN106760050A (en) The attachment structure and through processing method of shear wall and after-pouring concrete frame beam
CN103195259A (en) Foam concrete prefabricated slab and method for reinforcing concrete structure by same
CN110093850A (en) A kind of seamless bridge corbel back slab construction and its construction method with X-shaped steel muscle
CN207363251U (en) A kind of track-type facilities for being used to control the pitched roof gradient and thickness
CN108316153B (en) A kind of construction method of multistory reinforced concrete slab
CN103696439A (en) Immersed tube pouring method
CN106245770B (en) Expanded letter variable cross-section annular stiffness beam construction method
CN108756037A (en) A kind of mounting structure of the whole anti-floating of GBF square chests cassette ceiling
CN109235266A (en) A kind of construction method of toughened internal stress
CN106639101A (en) Assembled type cavity composite floor slab construction method
CN103306439A (en) Pouring technology for implanting high anti-leakage and anti-crack protective layer into roof structure layer
CN108374522A (en) A kind of the protective layer skeleton and its board member arrangement and method for construction of building structure
JPS6245809A (en) Construction for dam
CN113202010A (en) Prestressed concrete cast-in-place box girder structure and construction method thereof
CN107366427B (en) A kind of city cast-in-situ hollow Sandwich Plates concrete construction method
CN207143627U (en) Fully-prefabricated assembled overall road structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200514

Address after: 510000 room 6-707, No.2, Huafei street, Fengze West Road, Nansha District, Guangzhou City, Guangdong Province (temporary business place)

Patentee after: Guangzhou Engineering Co., Ltd. of China Railway 19th Bureau Group

Address before: 519020 China railway building, 111, changwan Road, Gongbei, Zhuhai, Guangdong

Patentee before: NO.7 ENGINEERING CO., LTD. OF CHINA RAILWAY 19 BUREAU Group