One kind finishing uses wall finiss mixing device
Technical field
The present invention relates to a kind of mixing device, more particularly to a kind of finishing to use wall finiss mixing device.
Background technology
Finishing is also known as decorate or decoration.Refer to what is carried out in certain area and scope, including Hydroelectric Project Construction, wall,
What plate, ceiling, landscape etc. were realized, a whole set of arrangement and method for construction and design formed according to certain design concept and beautiful rule
Scheme.
In wall surfacing, it can all use to paint and mopping is carried out to metope, all can be and in order to make paint preferably use
It is time-consuming and laborious, mixing speed is slow, whipping process when being stirred mixing to paint using preceding, and being manually stirred to painting
Middle paint easily spills and causes to waste, while can also make ground dirty, thus there is an urgent need for research and development it is a kind of it is time saving and energy saving, mixing speed is fast, stir
Paint will not be spilt during mixing, and without causing to waste, will not make the finishing wall finiss mixing device on ground dirty.
The content of the invention
(1)Technical problems to be solved
Time-consuming and laborious, mixing speed is slow when the present invention is manually stirred paint to overcome, paint easily splashes in whipping process
Going out causes to waste, while the shortcomings that can also make ground dirty, the technical problem to be solved in the present invention is to provide it is a kind of it is time saving and energy saving, stir
It is fast to mix speed, paint will not be spilt in whipping process, without causing to waste, will not make the finishing wall finiss batch mixing on ground dirty
Device.
(2)Technical solution
In order to solve the above technical problem, the present invention provides such a finishing wall finiss mixing device, include bottom plate,
Agitator tank, drainage conduit, the first valve, lower hopper, cross bar, pipeline, conical pipe, discharging device and agitating device, bottom plate top right
Side is provided with agitator tank, and agitator tank lower right side is connected with drainage conduit, and drainage conduit in agitator tank with connect, and drainage conduit is equipped with the
One valve, is equipped with agitating device in agitator tank, and agitator tank left upper portion is provided with lower hopper, lower hopper with agitator tank is interior connects,
Cross bar is installed in lower hopper, is connected with pipeline on cross bar, pipeline top is connected with conical pipe, conical pipe with being connected in pipeline,
Conical pipe top is located at outside lower hopper, and bottom plate top left side is equipped with discharging device.
Preferably, discharging device includes motion bar, driving device, hold-down devices and clamping device, bottom plate top left side
Equipped with driving device, motion bar is connected with driving device, motion bar is located on front side of driving device, and motion bar is equipped with lower press fitting
Put, hold-down devices are equipped with clamping device.
Preferably, driving device includes the first cylinder, rack, support base, first bearing seat, first rotating shaft and gear,
Bottom plate top left side front and rear sides symmetrical expression is provided with support base, and support base crown center is provided with first bearing seat, front and rear
First rotating shaft is connected between the first bearing seat of both sides, gear, first rotating shaft front end and motion bar are installed in the middle part of first rotating shaft
Connection, bottom plate top left side are provided with the first cylinder, and in being vertically arranged, the first cylinder is located on the left of support base the first cylinder, the
Rack is installed, rack is located on the left of gear, rack and pinion engagement on the telescopic rod of one cylinder.
Preferably, hold-down devices include the first fixed block, the second cylinder, the first slide, the first sliding block and fixed plate, living
Lever lower part is provided with the first slide, and the first slide is equipped with the first sliding block, and the first sliding block is slidably matched with the first slide, and first
Fixed plate is installed, fixed plate is connected with clamping device, and motion bar lower part is provided with the first fixed block, the first fixed block on sliding block
Above the first slide, the second cylinder is installed on the first fixed block, the telescopic rod of the second cylinder is connected with the first sliding block.
Preferably, clamping device includes the second shaft, arc snap-gauge, kelly, the second fixed block and nut, in fixed plate
Second shaft is installed, two arc snap-gauges are installed in the second shaft, one of arc snap-gauge tail end is provided with kelly, card
Screw thread is carved with bar, another arc snap-gauge tail end is provided with the second fixed block, and through hole, kelly position are provided with the middle part of the second fixed block
In in through hole, being provided with nut on kelly, nut coordinates with kelly.
Preferably, agitating device has been further included, agitating device includes second bearing seat, motor, bull stick and agitating vane,
Agitator tank crown center is Embedded to be provided with second bearing seat, bull stick is provided with second bearing seat, between bull stick lower part is uniform
Every agitating vane is installed, the outer crown center of agitator tank is provided with motor, and in being vertically arranged, the output shaft of motor passes through motor
Shaft coupling is connected with bull stick top.
Preferably, flusher has been further included, flusher includes water tank, water pump, outlet pipe, check valve and the second valve
Door, bottom plate top left side are provided with water tank, and water tank is between support base and agitator tank, and bottom right is provided with water in water tank
Pump, the water outlet of water pump are connected with outlet pipe, and outlet pipe tail end is through tank top left side and lower hopper left upper portion and pipeline
Top connects, and outlet pipe in pipeline with connecting, and outlet pipe is equipped with check valve, and pipeline is equipped with the second valve.
Preferably, the second slide and the second sliding block have been further included, the second slide, the second slide position are installed at the top of bottom plate
On the left of the first cylinder, for the second slide in being vertically arranged, the second slide is equipped with the second sliding block coordinated with it, the second sliding block with
Second slide is slidably matched, and the second sliding block right flank is connected with rack left surface.
Preferably, rubber slab has been further included, two arc snap-gauge medial surfaces are fitted with rubber slab.
Operation principle:Operating personnel pour into water in agitator tank first, you can are placed on the paint kettle equipped with paint and put
Expect on device, you can start discharging device, paint kettle is moved to above conical pipe by discharging device, and then drives paint kettle downward
Mobile, paint kettle is moved down to be contacted with conical pipe, in conical pipe insertion paint kettle, closes discharging device, and is painted and passed through cone
In shape pipe flow ipe, the paint in pipeline flows out through lower hopper and flows into agitator tank, and paint is contacted with water.When in agitator tank
When having suitable paint, you can start discharging device and drive paint kettle to recover to original position, restart agitating device, agitating device
Mixing component, which rotates, is stirred paint and water, after paint is stirred evenly with water, you can close agitating device, operating personnel
The paint being stirred can be taken out and used.
Because discharging device includes motion bar, driving device, hold-down devices and clamping device, bottom plate top left side is equipped with
Driving device, motion bar is connected with driving device, and motion bar is located on front side of driving device, and motion bar is equipped with hold-down devices,
Hold-down devices are equipped with clamping device, when water level is when in agitator tank, operating personnel can paint kettle pressed from both sides by clamping device
Fasten, restart driving device, driving device drives motion bar to rotate forward, and motion bar is rotated forward drives paint kettle by hold-down devices
Rotate forward, and then when paint kettle is just being gone to directly over conical pipe, you can driving device is closed, restarts hold-down devices, lower press fitting
Put and drive paint kettle to move down, paint kettle is moved down to be contacted with conical pipe, and then is made in conical pipe insertion paint kettle, is closed
Hold-down devices, and then paint and pass through in conical pipe flow ipe, and flow into agitator tank.Similarly, when the paint in paint kettle is complete
When portion is flowed out, you can start hold-down devices and drive paint kettle to move up, close hold-down devices, you can start driving device and drive
Paint kettle recovers to original position, then is unclamped paint kettle by clamping device, and operating personnel can remove paint kettle.
Because driving device includes the first cylinder, rack, support base, first bearing seat, first rotating shaft and gear, bottom plate
Top left side front and rear sides symmetrical expression is provided with support base, and support base crown center is provided with first bearing seat, front and rear sides
First rotating shaft is connected between first bearing seat, gear is installed in the middle part of first rotating shaft, first rotating shaft front end is connected with motion bar,
Bottom plate top left side is provided with the first cylinder, and the first cylinder is in being vertically arranged, and the first cylinder is located on the left of support base, the first cylinder
Telescopic rod on rack is installed, rack is located on the left of gear, rack and pinion engagement, after paint kettle is clamped, operator
Member can start the telescopic rod elongation of the first cylinder, and the telescopic rod elongated carry-over bar of the first cylinder moves up, and rack is upward
Mobile band moving gear rotates forward, and gear, which rotates forward, drives first rotating shaft to rotate forward, and first rotating shaft, which rotates forward, drives motion bar to rotate forward, and then drives
Paint kettle rotates forward, when paint kettle is moved to directly over conical pipe, you can close the first cylinder.Similarly, when the oil in paint kettle
After paint all flows out, you can the telescopic rod for starting the first cylinder shortens, and then gear reversion drives motion bar to invert, and paint kettle
Inversion recovery closes the first cylinder to original position.
Because hold-down devices include the first fixed block, the second cylinder, the first slide, the first sliding block and fixed plate, activity
Bar lower part is provided with the first slide, and the first slide is equipped with the first sliding block, and the first sliding block is slidably matched with the first slide, and first slides
Fixed plate is installed, fixed plate is connected with clamping device, and motion bar lower part is provided with the first fixed block, the first fixed block position on block
Above the first slide, the second cylinder is installed on the first fixed block, the telescopic rod of the second cylinder is connected with the first sliding block, works as oil
When paint can is moved to directly over conical pipe, the telescopic rod that operating personnel can start the second cylinder shortens, and the second cylinder stretches
Bar, which shortens, drives the first sliding block to move down, and the first sliding block, which moves down, drives fixed plate to move down, and then is filled by clamping
Put and drive paint kettle to move down, paint kettle, which moves down, to be made in conical pipe insertion paint kettle, closes the second cylinder, and then paint
Flowed out by conical pipe.After the paint in paint kettle all flows out, you can start the telescopic rod elongation of the second cylinder, and then band
Dynamic paint kettle moves up recovery to original position, closes the second cylinder.
Because clamping device includes the second shaft, arc snap-gauge, kelly, the second fixed block and nut, pacify in fixed plate
Equipped with the second shaft, two arc snap-gauges are installed in the second shaft, one of arc snap-gauge tail end is provided with kelly, kelly
On be carved with screw thread, another arc snap-gauge tail end is provided with the second fixed block, is provided with through hole in the middle part of the second fixed block, kelly is located at
In through hole, nut is installed on kelly, nut coordinates with kelly, and operating personnel twist nut first, and nut rotation takes off with kelly
From, you can pull the separation of two arc snap-gauges, kelly departs from out of through hole, then by paint kettle be placed on two arc snap-gauges it
Between, operating personnel can close two arc snap-gauges, and make in kelly insertion through hole, then nut is sleeved on kelly and is twisted,
Nut rotation is contacted with the second fixed block, and then nut fixes two arc snap-gauges with the cooperation of the second fixed block, and will paint
Bucket is fixed, you can starts the first cylinder and paint kettle is moved to directly over conical pipe.Similarly, when the paint in paint kettle all flows
After going out, and when recovering to original position, you can twist nut again, and then two arc snap-gauges unclamp paint kettle, operating personnel are
Paint kettle can be removed.
Because having further included agitating device, agitating device includes second bearing seat, motor, bull stick and agitating vane, stirs
Mix it is Embedded among box top second bearing seat is installed, bull stick, bull stick lower part uniform intervals are installed in second bearing seat
Agitating vane is installed, the outer crown center of agitator tank is provided with motor, and for motor in being vertically arranged, the output shaft of motor passes through connection
Axis device is connected with bull stick top, and when paint, which is flowed into stirring, to be contacted with water, operating personnel can start motor rotation, and motor turns
Dynamic to drive bar rotation, bar rotation drives agitating vane to rotate, and agitating vane is rotated is stirred mixing to paint and water.When
After paint and water stir evenly, you can close motor, paint is taken out and is used, without being manually stirred mixing, time saving province
Power.
Because having further included flusher, flusher includes water tank, water pump, outlet pipe, check valve and the second valve,
Bottom plate top left side is provided with water tank, and water tank is between support base and agitator tank, and bottom right is provided with water pump, water in water tank
The water outlet of pump is connected with outlet pipe, and outlet pipe tail end connects on the left of tank top with lower hopper left upper portion with conduit upper
Connect, connected in outlet pipe and pipeline, outlet pipe is equipped with check valve, and pipeline is equipped with the second valve, and operating personnel first are by water
Pour into water tank, open the second valve, after all outflows are painted in paint kettle, you can close the second valve, start water pump, water
Water in water tank is pumped into outlet pipe by pump, and the water in outlet pipe is discharged into pipeline, and then being discharged by conical pipe in pipeline,
Water discharge is rinsed remaining paint in paint kettle.After being rinsed clean in paint kettle, you can switch off the pump, open the
Two valves, the water after flushing is flowed into agitator tank by pipeline to be stirred.In this way, it can prevent that residual paint causes wave in paint kettle
Take.
Because having further included the second slide and the second sliding block, the second slide is installed at the top of bottom plate, the second slide is located at
On the left of first cylinder, for the second slide in being vertically arranged, the second slide is equipped with the second sliding block coordinated with it, the second sliding block and the
Two slides are slidably matched, and the second sliding block right flank is connected with rack left surface, and when rack moves, rack drives second to slide at the same time
Block moves on the second slide, and then the second sliding block makes the more steady of rack movement with the second slide.
Because having further included rubber slab, two arc snap-gauge medial surfaces are fitted with rubber slab, when two arc snap-gauges will
When paint kettle is fixedly clamped, rubber slab is contacted with paint kettle, and then increases the frictional force with paint kettle, and makes two arc snap-gauges
More firm fixes paint kettle.
(3)Beneficial effect
The present invention can be rinsed the paint in paint kettle by flusher, and prevent paint is remained in paint kettle from leading
Cause to waste, reached that time saving and energy saving, mixing speed is fast, and paint will not be spilt in whipping process, without causing to waste, will not be done
The effect on dirty ground.
Brief description of the drawings
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is the first overlooking the structure diagram of clamping device of the present invention.
Fig. 3 is second of main structure diagram of the present invention.
Fig. 4 is the third main structure diagram of the present invention.
Fig. 5 is the 4th kind of main structure diagram of the present invention.
Fig. 6 is second of overlooking the structure diagram of clamping device of the present invention.
Mark in attached drawing for:1- bottom plates, 2- agitator tanks, 3- drainage conduits, the first valves of 4-, 5- lower hoppers, 6- cross bars, 7-
Pipeline, 8- conical pipes, 9- discharging devices, 91- motion bars, 92- driving devices, the first cylinders of 921-, 922- racks, 923- supports
Seat, 924- first bearing seats, 925- first rotating shafts, 926- gears, 93- hold-down devices, the first fixed blocks of 931-, the second gas of 932-
Cylinder, the first slides of 933-, the first sliding blocks of 934-, 935- fixed plates, 94- clamping devices, the second shafts of 941-, 942- arc cards
Plate, 943- kellies, the second fixed blocks of 944-, 945- through holes, 946- nuts, 10- agitating devices, 101- second bearing seats, 102-
Motor, 103- bull sticks, 104- agitating vanes, 11- flushers, 111- water tanks, 112- water pumps, 113- outlet pipes, 114- are unidirectional
Valve, the second valves of 115-, the second slides of 12-, the second sliding blocks of 13-, 14- rubber slabs.
Embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
One kind finishing uses wall finiss mixing device, as shown in figures 1 to 6, include bottom plate 1, agitator tank 2, drainage conduit 3, the first valve
4th, lower hopper 5, cross bar 6, pipeline 7, conical pipe 8, discharging device 9 and agitating device 10,1 top right side of bottom plate are provided with agitator tank
2,2 lower right side of agitator tank is connected with drainage conduit 3, and for drainage conduit 3 with being connected in agitator tank 2, drainage conduit 3 is equipped with the first valve 4,
Is equipped with agitating device 10 in agitator tank 2,2 left upper portion of agitator tank is provided with lower hopper 5, lower hopper 5 with agitator tank 2 is interior connects,
Cross bar 6 is installed in lower hopper 5, pipeline 7 is connected with cross bar 6,7 top of pipeline is connected with conical pipe 8, conical pipe 8 and pipeline 7
Interior connection, 8 top of conical pipe are located at outside lower hopper 5, and 1 top left side of bottom plate is equipped with discharging device 9.
Embodiment 2
One kind finishing uses wall finiss mixing device, as shown in figures 1 to 6, include bottom plate 1, agitator tank 2, drainage conduit 3, the first valve
4th, lower hopper 5, cross bar 6, pipeline 7, conical pipe 8, discharging device 9 and agitating device 10,1 top right side of bottom plate are provided with agitator tank
2,2 lower right side of agitator tank is connected with drainage conduit 3, and for drainage conduit 3 with being connected in agitator tank 2, drainage conduit 3 is equipped with the first valve 4,
Is equipped with agitating device 10 in agitator tank 2,2 left upper portion of agitator tank is provided with lower hopper 5, lower hopper 5 with agitator tank 2 is interior connects,
Cross bar 6 is installed in lower hopper 5, pipeline 7 is connected with cross bar 6,7 top of pipeline is connected with conical pipe 8, conical pipe 8 and pipeline 7
Interior connection, 8 top of conical pipe are located at outside lower hopper 5, and 1 top left side of bottom plate is equipped with discharging device 9.
Discharging device 9 includes motion bar 91, driving device 92, hold-down devices 93 and clamping device 94,1 top left of bottom plate
Side is equipped with driving device 92, and motion bar 91 is connected with driving device 92, and motion bar 91 is located at the front side of driving device 92, motion bar
91 are equipped with hold-down devices 93, and hold-down devices 93 are equipped with clamping device 94.
Embodiment 3
One kind finishing uses wall finiss mixing device, as shown in figures 1 to 6, include bottom plate 1, agitator tank 2, drainage conduit 3, the first valve
4th, lower hopper 5, cross bar 6, pipeline 7, conical pipe 8, discharging device 9 and agitating device 10,1 top right side of bottom plate are provided with agitator tank
2,2 lower right side of agitator tank is connected with drainage conduit 3, and for drainage conduit 3 with being connected in agitator tank 2, drainage conduit 3 is equipped with the first valve 4,
Is equipped with agitating device 10 in agitator tank 2,2 left upper portion of agitator tank is provided with lower hopper 5, lower hopper 5 with agitator tank 2 is interior connects,
Cross bar 6 is installed in lower hopper 5, pipeline 7 is connected with cross bar 6,7 top of pipeline is connected with conical pipe 8, conical pipe 8 and pipeline 7
Interior connection, 8 top of conical pipe are located at outside lower hopper 5, and 1 top left side of bottom plate is equipped with discharging device 9.
Discharging device 9 includes motion bar 91, driving device 92, hold-down devices 93 and clamping device 94,1 top left of bottom plate
Side is equipped with driving device 92, and motion bar 91 is connected with driving device 92, and motion bar 91 is located at the front side of driving device 92, motion bar
91 are equipped with hold-down devices 93, and hold-down devices 93 are equipped with clamping device 94.
Driving device 92 includes the first cylinder 921, rack 922, support base 923, first bearing seat 924, first rotating shaft
925 and gear 926,1 top left side front and rear sides of bottom plate it is symmetrical support base 923,923 crown center of support base peace are installed
Equipped with first bearing seat 924, first rotating shaft 925, the middle part of first rotating shaft 925 are connected between front and rear sides first bearing seat 924
Gear 926 is installed, 925 front end of first rotating shaft is connected with motion bar 91, and 1 top left side of bottom plate is provided with the first cylinder 921, the
For one cylinder 921 in being vertically arranged, the first cylinder 921 is located at the left side of support base 923, is provided with the telescopic rod of the first cylinder 921
Rack 922, rack 922 are located at the left side of gear 926, and rack 922 is engaged with gear 926.
Embodiment 4
One kind finishing uses wall finiss mixing device, as shown in figures 1 to 6, include bottom plate 1, agitator tank 2, drainage conduit 3, the first valve
4th, lower hopper 5, cross bar 6, pipeline 7, conical pipe 8, discharging device 9 and agitating device 10,1 top right side of bottom plate are provided with agitator tank
2,2 lower right side of agitator tank is connected with drainage conduit 3, and for drainage conduit 3 with being connected in agitator tank 2, drainage conduit 3 is equipped with the first valve 4,
Is equipped with agitating device 10 in agitator tank 2,2 left upper portion of agitator tank is provided with lower hopper 5, lower hopper 5 with agitator tank 2 is interior connects,
Cross bar 6 is installed in lower hopper 5, pipeline 7 is connected with cross bar 6,7 top of pipeline is connected with conical pipe 8, conical pipe 8 and pipeline 7
Interior connection, 8 top of conical pipe are located at outside lower hopper 5, and 1 top left side of bottom plate is equipped with discharging device 9.
Discharging device 9 includes motion bar 91, driving device 92, hold-down devices 93 and clamping device 94,1 top left of bottom plate
Side is equipped with driving device 92, and motion bar 91 is connected with driving device 92, and motion bar 91 is located at the front side of driving device 92, motion bar
91 are equipped with hold-down devices 93, and hold-down devices 93 are equipped with clamping device 94.
Driving device 92 includes the first cylinder 921, rack 922, support base 923, first bearing seat 924, first rotating shaft
925 and gear 926,1 top left side front and rear sides of bottom plate it is symmetrical support base 923,923 crown center of support base peace are installed
Equipped with first bearing seat 924, first rotating shaft 925, the middle part of first rotating shaft 925 are connected between front and rear sides first bearing seat 924
Gear 926 is installed, 925 front end of first rotating shaft is connected with motion bar 91, and 1 top left side of bottom plate is provided with the first cylinder 921, the
For one cylinder 921 in being vertically arranged, the first cylinder 921 is located at the left side of support base 923, is provided with the telescopic rod of the first cylinder 921
Rack 922, rack 922 are located at the left side of gear 926, and rack 922 is engaged with gear 926.
Hold-down devices 93 include the first fixed block 931, the second cylinder 932, the first slide 933, the first sliding block 934 and consolidate
Fixed board 935,91 lower part of motion bar are provided with the first slide 933, and the first slide 933 is equipped with the first sliding block 934, the first sliding block
934 are slidably matched with the first slide 933, and fixed plate 935 is provided with the first sliding block 934, and fixed plate 935 connects with clamping device 94
Connect, 91 lower part of motion bar is provided with the first fixed block 931, and the first fixed block 931 is located at the top of the first slide 933, and first fixes
Second cylinder 932 is installed, the telescopic rod of the second cylinder 932 is connected with the first sliding block 934 on block 931.
Clamping device 94 includes the second shaft 941, arc snap-gauge 942, kelly 943, the second fixed block 944 and nut
946, the second shaft 941 is installed in fixed plate 935, two arc snap-gauges 942 are installed in second shaft 941, one of them
942 tail end of arc snap-gauge is provided with kelly 943, and screw thread is carved with kelly 943, another 942 tail end of arc snap-gauge is provided with
Two fixed blocks 944, the middle part of the second fixed block 944 are provided with through hole 945, and kelly 943 is located in through hole 945, is provided with kelly 943
Nut 946, nut 946 coordinate with kelly 943.
Agitating device 10 is further included, agitating device 10 includes second bearing seat 101, motor 102, bull stick 103 and stirs
Blade 104 is mixed, 2 crown center of agitator tank is Embedded to be provided with second bearing seat 101, is provided with and turns in second bearing seat 101
Bar 103,103 lower part of bull stick is evenly spaced to be provided with agitating vane 104, and 2 outer crown center of agitator tank is provided with motor 102,
In being vertically arranged, the output shaft of motor 102 is connected motor 102 by shaft coupling with 103 top of bull stick.
Flusher 11 is further included, flusher 11 includes water tank 111, water pump 112, outlet pipe 113, check valve
114 and second valve 115,1 top left side of bottom plate is provided with water tank 111, water tank 111 be located at support base 923 and agitator tank 2 it
Between, bottom right is provided with water pump 112 in water tank 111, and the water outlet of water pump 112 is connected with outlet pipe 113,113 tail of outlet pipe
End is connected through 111 top left side of water tank and 5 left upper portion of lower hopper with 7 top of pipeline, outlet pipe 113 with pipeline 7 is interior connects,
Outlet pipe 113 is equipped with check valve 114, and pipeline 7 is equipped with the second valve 115.
The second slide 12 and the second sliding block 13 are further included, the top of bottom plate 1 is provided with the second slide 12, the second slide 12
Positioned at the left side of the first cylinder 921, for the second slide 12 in being vertically arranged, the second slide 12 is equipped with the second sliding block coordinated with it
13, the second sliding block 13 is slidably matched with the second slide 12, and 13 right flank of the second sliding block is connected with 922 left surface of rack.
Rubber slab 14 is further included, two 942 medial surfaces of arc snap-gauge are fitted with rubber slab 14.
Operation principle:Operating personnel pour into water in agitator tank 2 first, you can are placed on the paint kettle equipped with paint
Expect on device 9, you can start discharging device 9, paint kettle is moved to the top of conical pipe 8 by discharging device 9, and then drives paint kettle
Move down, paint kettle is moved down to be contacted with conical pipe 8, and conical pipe 8 is inserted into paint kettle, closes discharging device 9, and is painted
By the way that in 8 flow ipe 7 of conical pipe, the paint in pipeline 7 flows out through lower hopper 5 and flows into agitator tank 2, paint connects with water
Touch.When having suitable paint in agitator tank 2, you can start discharging device 9 and drive paint kettle to recover to original position, restart stirring
Device 10, the mixing component of agitating device 10, which rotates, is stirred paint and water, after paint is stirred evenly with water, you can close
Agitating device 10 is closed, the paint being stirred can be taken out and used by operating personnel.
Because discharging device 9 includes motion bar 91, driving device 92, hold-down devices 93 and clamping device 94, bottom plate 1 pushes up
Driving device 92 is equipped with the left of portion, motion bar 91 is connected with driving device 92, motion bar 91 is located at the front side of driving device 92, living
Lever 91 is equipped with hold-down devices 93, and hold-down devices 93 are equipped with clamping device 94, when water level is when in agitator tank 2, operator
Member can paint kettle be fixedly clamped by clamping device 94, restart driving device 92, driving device 92 drives motion bar 91
Rotating forward, motion bar 91 is rotated forward drives paint kettle to rotate forward by hold-down devices 93, and then when paint kettle is just being gone to directly over conical pipe 8
When, you can close driving device 92, restart hold-down devices 93, hold-down devices 93 drive paint kettle to move down, paint kettle to
Lower movement is contacted with conical pipe 8, and then conical pipe 8 is inserted into paint kettle, closes hold-down devices 93, and then paint and pass through taper
In 8 flow ipe 7 of pipe, and flow into agitator tank 2.Similarly, when the paint in paint kettle all flows out, you can start lower press fitting
Put 93 drive paint kettles to move up, close hold-down devices 93, you can start driving device 92 and drive paint kettle to recover to original position,
Paint kettle is unclamped by clamping device 94 again, operating personnel can remove paint kettle.
Because driving device 92 includes the first cylinder 921, rack 922, support base 923, first bearing seat 924, first
Shaft 925 and gear 926,1 top left side front and rear sides of bottom plate it is symmetrical support base 923 is installed, in the top of support base 923
Between first bearing seat 924 is installed, first rotating shaft 925, first rotating shaft 925 are connected between front and rear sides first bearing seat 924
Middle part is provided with gear 926, and 925 front end of first rotating shaft is connected with motion bar 91, and 1 top left side of bottom plate is provided with the first cylinder
921, in being vertically arranged, the first cylinder 921 is located on the left of support base 923 the first cylinder 921, on the telescopic rod of the first cylinder 921
Rack 922 is installed, rack 922 is located at the left side of gear 926, and rack 922 is engaged with gear 926, after paint kettle is clamped, behaviour
The telescopic rod elongation of the first cylinder 921 can be started by making personnel, and the telescopic rod elongated carry-over bar 922 of the first cylinder 921 is upward
Mobile, rack 922 moves up band moving gear 926 and rotates forward, and gear 926, which rotates forward, drives first rotating shaft 925 to rotate forward, first rotating shaft
925, which rotate forward drive motion bar 91, rotates forward, and then drives paint kettle to rotate forward, when paint kettle is moved to 8 surface of conical pipe, you can
Close the first cylinder 921.Similarly, after the paint in paint kettle all flows out, you can start the telescopic rod contracting of the first cylinder 921
It is short, and then the reversion of gear 926 drives motion bar 91 to invert, and paint kettle inversion recovery to original position, the first cylinder 921 of closing is
Can.
Because hold-down devices 93 include the first fixed block 931, the second cylinder 932, the first slide 933, the first sliding block 934
With fixed plate 935,91 lower part of motion bar is provided with the first slide 933, and the first slide 933 is equipped with the first sliding block 934, and first slides
Block 934 is slidably matched with the first slide 933, and fixed plate 935, fixed plate 935 and clamping device 94 are provided with the first sliding block 934
Connection, 91 lower part of motion bar are provided with the first fixed block 931, and the first fixed block 931 is located at the top of the first slide 933, and first is solid
Determine the second cylinder 932 is installed on block 931, the telescopic rod of the second cylinder 932 is connected with the first sliding block 934, when paint kettle moves
During to 8 surface of conical pipe, the telescopic rod that operating personnel can start the second cylinder 932 shortens, the telescopic rod of the second cylinder 932
Shorten and drive the first sliding block 934 to move down, the first sliding block 934, which moves down, drives fixed plate 935 to move down, and then passes through
Clamping device 94 drives paint kettle to move down, and paint kettle, which moves down, makes conical pipe 8 be inserted into paint kettle, closes the second cylinder
932, and then paint and flowed out by conical pipe 8.After the paint in paint kettle all flows out, you can start the second cylinder 932
Telescopic rod extends, and then drives paint kettle to move up recovery to original position, closes the second cylinder 932.
Because clamping device 94 includes the second shaft 941, arc snap-gauge 942, kelly 943, the second fixed block 944 and spiral shell
Mother 946, is provided with the second shaft 941 in fixed plate 935, two arc snap-gauges 942 is provided with the second shaft 941, wherein one
A 942 tail end of arc snap-gauge is provided with kelly 943, and screw thread is carved with kelly 943, another 942 tail end of arc snap-gauge is provided with
Second fixed block 944, the middle part of the second fixed block 944 are provided with through hole 945, and kelly 943 is located in through hole 945, is installed on kelly 943
There is nut 946, nut 946 coordinates with kelly 943, and operating personnel twist nut 946 first, and nut 946 rotates de- with kelly 943
From, you can pull two arc snap-gauges 942 to separate, kelly 943 departs from out of through hole 945, then paint kettle is placed on two arcs
Between shape snap-gauge 942, operating personnel can close two arc snap-gauges 942, and kelly 943 is inserted into through hole 945, then will
Nut 946 is sleeved on kelly 943 and twists, and nut 946 is rotated and contacted with the second fixed block 944, and then nut 946 and second is fixed
Block 944, which coordinates, fixes two arc snap-gauges 942, and paint kettle is fixed, you can starts the first cylinder 921 and moves paint kettle
To conical pipe 8.Similarly, when in paint kettle paint all flow out after, and recover to original position when, you can twist spiral shell again
Mother 946, and then two arc snap-gauges 942 unclamp paint kettle, operating personnel can remove paint kettle.
Because having further included agitating device 10, agitating device 10 includes second bearing seat 101, motor 102, bull stick 103
With agitating vane 104,2 crown center of agitator tank is Embedded to be provided with second bearing seat 101, is installed in second bearing seat 101
There is bull stick 103,103 lower part of bull stick is evenly spaced to be provided with agitating vane 104, and 2 outer crown center of agitator tank is provided with motor
102, in being vertically arranged, the output shaft of motor 102 is connected motor 102 by shaft coupling with 103 top of bull stick, when paint inflow is stirred
When being contacted in mixing with water, operating personnel can start motor 102 and rotate, and motor 102, which rotates, drives bull stick 103 to rotate, bull stick 103
Rotate and drive agitating vane 104 to rotate, agitating vane 104 is rotated is stirred mixing to paint and water.When paint and water stirring
After uniformly, you can motor 102 is closed, paint is taken out and is used, it is time saving and energy saving without being manually stirred mixing.
Because having further included flusher 11, flusher 11 includes water tank 111, water pump 112, outlet pipe 113, unidirectional
114 and second valve 115 of valve, 1 top left side of bottom plate are provided with water tank 111, water tank 111 be located at support base 923 and agitator tank 2 it
Between, bottom right is provided with water pump 112 in water tank 111, and the water outlet of water pump 112 is connected with outlet pipe 113,113 tail of outlet pipe
End is connected through 111 top left side of water tank and 5 left upper portion of lower hopper with 7 top of pipeline, outlet pipe 113 with pipeline 7 is interior connects,
Outlet pipe 113 is equipped with check valve 114, and pipeline 7 is equipped with the second valve 115, and water is poured into water tank 111 by operating personnel first
It is interior, the second valve 115 is opened, after all outflows are painted in paint kettle, you can the second valve 115 is closed, starts water pump 112,
Water in water tank 111 is pumped into outlet pipe 113 by water pump 112, and the water in outlet pipe 113 is discharged into pipeline 7, and then in pipeline 7
Discharged by conical pipe 8, water discharge in paint kettle it is remaining paint is rinsed.After being rinsed clean in paint kettle,
It can switch off the pump 112, open the second valve 115, the water after flushing passes through pipeline 7 and flows into stirring in agitator tank 2.In this way, can
Prevent that residual paint causes to waste in paint kettle.
Because having further included the second slide 12 and the second sliding block 13, the top of bottom plate 1 is provided with the second slide 12, and second slides
Rail 12 is located at the left side of the first cylinder 921, and in being vertically arranged, the second slide 12 is equipped with second coordinated with it and slides the second slide 12
Block 13, the second sliding block 13 are slidably matched with the second slide 12, and 13 right flank of the second sliding block is connected with 922 left surface of rack, works as tooth
When bar 922 moves, rack 922 drives the second sliding block 13 to be moved on the second slide 12 at the same time, and then the second sliding block 13 and second
It is more steady that slide 12 moves rack 922.
Because having further included rubber slab 14, two 942 medial surfaces of arc snap-gauge are fitted with rubber slab 14, when two arcs
When paint kettle is fixedly clamped by snap-gauge 942, rubber slab 14 is contacted with paint kettle, and then increases the frictional force with paint kettle, and is made
Two arc snap-gauges 942 are more firm to fix paint kettle.
Embodiment described above only expresses the preferred embodiment of the present invention, its description is more specific and detailed, but simultaneously
Therefore the limitation to the scope of the claims of the present invention cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art
For, without departing from the inventive concept of the premise, some deformations can also be made, improves and substitutes, these belong to this hair