[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN107633137A - A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method - Google Patents

A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method Download PDF

Info

Publication number
CN107633137A
CN107633137A CN201710858634.4A CN201710858634A CN107633137A CN 107633137 A CN107633137 A CN 107633137A CN 201710858634 A CN201710858634 A CN 201710858634A CN 107633137 A CN107633137 A CN 107633137A
Authority
CN
China
Prior art keywords
bim
dimensional
purpose project
professional system
threedimensional model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710858634.4A
Other languages
Chinese (zh)
Inventor
沈弓召
席刚
唐小锋
杨胜
黄微
周建锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd filed Critical Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Priority to CN201710858634.4A priority Critical patent/CN107633137A/en
Publication of CN107633137A publication Critical patent/CN107633137A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of electromechanical installation of subway based on BIM and fitting-out work construction method, it includes:The two dimensional surface design drawing of each professional system of purpose project, and the field survey data of purpose project are inputted, establish the threedimensional model of each professional system respectively;Establish the purpose project three-dimensional BIM with unified coordinate system;Collision detection, the result report of generation collision detection are carried out to purpose project three-dimensional BIM according to default tolerance;The threedimensional model of one or more professional system to purpose project three-dimensional BIM to modify corresponding to adjustment;The preview and correction of procedure connection and working face conversion are carried out based on amended purpose project three-dimensional BIM, and determines the working procedure of each professional system, the space coordinates of working face conversion and corresponding conversion time.This method can quickly establish BIM, simplify mounting means and reduce installation workload, and exempt from construction conflict and do over again, so as to improve installation effectiveness while installation cost is saved.

Description

A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method
Technical field
The present invention relates to the electromechanical installation of subway and fitting-out work technical field of construction, more particularly to a kind of ground based on BIM The electromechanical installation of iron and fitting-out work construction method.
Background technology
Subway station electromechanics installation project is related to ventilation, plumbing, fire-fighting, power and illumination, communication, signal, power supply etc. The characteristics of more than ten professional, and pipeline is arranged is that space is small, diversified in specifications, arrangement is intensive, need to be within the limited time and in space Install concentratedly, co-ordination amount is big, and conventional installation methods are restricted by following factor:
(1) because different specialties is designed by different personnel, even different specialties is carried out by different designing institutees Design, communication is not thorough between each other, and when carrying out pipeline layout, examination is not careful enough, causes the pipeline circuit between each specialty More leak be present, be plane drawing in addition, can not reasonable reaction virtual condition, easily cause pipeline to touch in space environment Hit.(2) Metro Space is narrow and small, installation operation limited space.Subway station electromechanics installation project be related to ventilation, plumbing, fire-fighting, Power and illumination, communication, signal, power supply, FAS more than ten of specialty, each specialty such as BAS, AFC, extinction using gas exist Pipeline specification differs, moves towards irregular, the disadvantages such as construction operation intersects, wants to install each special pipelines in limited space Arrange rational and orderly, uniform, difficulty be present.After the airduct of ventilating system installs, follow-up specialty such as electric, discharge The installation of pipeline suspension and support of water, communication system specialty loses operating space, and whom is caused and first constructed whose capable phenomenon, after Phase co-ordination is difficult.(3) device rooms pipeline is intensive, and pipeline arrangement in space has difficulties.In all kinds of subway device rooms, Such as Air Conditioning Facilities, refrigerator room room area is small, pipeline is more, layout design is all often that Preliminary design only has rough plane Figure, spatial arrangement will unit in charge of construction according to room space structure voluntarily Deepen Design pipeline move towards, easily cause pipeline it is crowded, In a jumble, intersect, outward appearance is unsightly also not easy to operation maintenance.
Architecture information model (BulidingInfromationModeling, BIM) technology is that one kind is set applied to engineering Meter builds the digitization instrument of management, and the relevant information of various projects is integrated by parameter model.BIM technology at home and abroad city The application of field of track traffic is still in the starting stage, main at present to locate in industry still without being applied on a large scale In the research and development stage.
However, BIM technology the application of field of track traffic still have modeling speed is slow, key position can not be directed to and Small space carries out arrangement adjustment, the conflict progress duration that causes to construct because of procedure connection and working face conversion conflict delay etc. it is many Problem.
The content of the invention
An object of the present invention at least that, for how to overcome the above-mentioned problems of the prior art, there is provided a kind of The electromechanical installation of subway based on BIM and fitting-out work construction method, can quickly establish BIM, simplify mounting means and reduce and pacify Workload is filled, and exempts from construction conflict and does over again, so as to improve installation effectiveness while installation cost is saved.
Method to achieve these goals, the technical solution adopted by the present invention include following aspects.
A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method, it includes:Input each specialty of purpose project The two dimensional surface design drawing of system, and the field survey data of purpose project, the three-dimensional mould of each professional system is established respectively Type;Based on the threedimensional model of each professional system, the purpose project three-dimensional BIM with unified coordinate system is established;According to default appearance Difference carries out collision detection, the result report of generation collision detection to purpose project three-dimensional BIM;According to collision detection result report and Modification strategy, adjust corresponding to one or more professional system threedimensional model to be modified to purpose project three-dimensional BIM; The preview and correction of procedure connection and working face conversion are carried out based on amended purpose project three-dimensional BIM, and is determined each special The working procedure of industry system, the space coordinates of working face conversion and corresponding conversion time.
Preferably, the threedimensional model of each professional system includes:Building structure threedimensional model, ventilating system three-dimensional mould Type, crane span structure system threedimensional model, discharge water fire fighting system threedimensional model and air-conditioner water system threedimensional model.
Preferably, the modification strategy includes:Crane span structure is adjusted to the superiors, airduct crane span structure is adjusted to intermediate layer, will Water pipe is adjusted to the bottom.
Preferably, the collision detection is included between the threedimensional model of each professional system according to purpose project three-dimensional BIM Unified coordinate system carry out the overlapping detection of three-dimensional space position, obtain the conflict area between each professional system and its three-dimensional coordinate Data.
Preferably, the collision detection detects including hole reservation collision, and it includes obtaining institute in purpose project three-dimensional BIM Have the sectional view of reserving hole, according to each professional system reserving hole sized data and hole offset, collinearly merge tolerance, And round the conflict area between each professional system reserving hole of value acquisition and its three-dimensional coordinate data.
Preferably, the conflict area includes in purpose project three-dimensional BIM existing between the entity in each professional system Occur simultaneously, or the distance between entity is less than default tolerance value.
Preferably, methods described further comprises:Engineering material system is carried out based on amended purpose project three-dimensional BIM Meter, generate material planning;Set in material planning and set according to the working procedure of each professional system, working face conversion conversion time Put the production of material in each professional system and enter field time.
Preferably, the preview for carrying out procedure connection and working face conversion and correction include:By purpose project three-dimensional BIM In whole entities according to affiliated professional system, different colours are set, and according to first up and then down, first big after small, construction in layer original The sequencing of each professional system construction then arranged carries out work progress preview;The construction occurred in being previewed according to work progress Order conflicts, adjust corresponding to the working procedure of one or more professional system, the space coordinates and correspondingly of working face conversion Conversion time or material production and/or enter field time.
Preferably, it is described purpose project three-dimensional BIM is modified including:1200 × 4500mm battery limits corridor is hung Head space interior 1500mm × 800mm or 1250mm × 630mm ventilation shaft, caliber is 200mm and insulation layer thickness is 50mm Freeze cycle waterpipe, the power and lighting crane span structure that size is 800mm × 200mm, fire that size is 400mm × 200mm from Dynamic warning system FAS crane span structures and the BAS BAS crane span structures that size is 200mm × 200mm are high in reserved 250mm On the premise of the operating space of degree, integrate the arrangement optimization of suspension and support.
Preferably, methods described establishes the threedimensional model and purpose project three of each professional system using MagiCAD softwares BIM is tieed up, and carries out collision detection.
In summary, by adopting the above-described technical solution, the present invention at least has the advantages that:
By quickly establish include building, wind, water, electricity, hanger system multi-specialized integrated BIM, can shorten and build The mould time, speed up the work;By setting different tolerances to carry out crash analysis to the building of whole station, electromechanical model, and Shi Faxian simultaneously solves all pipeline collision problems, can not only realize that all professional pipeline reasonable Arrangements improve installation and operation Quality, additionally it is possible to effectively avoid construction from conflicting and do over again, save installation cost and improve installation effectiveness;Moreover, carried out based on BIM Material Takeoff simultaneously formulates material planning, can further simplify mounting means, reduces installation workload, so as to shorten the duration, drop Low engineering cost;The preview that procedure connection and working face are changed is carried out by BIM, on the basis of each specialty correction, formulates work Journey sequence of construction scheme, it can effectively promote duration progress.
Brief description of the drawings
Fig. 1 is the electromechanical installation of the subway according to an embodiment of the invention based on BIM and the stream of fitting-out work construction method Cheng Tu.
Fig. 2 is the discharge water fire fighting system threedimensional model schematic diagram established according to one embodiment of the invention.
Fig. 3 is the air-conditioner water system threedimensional model schematic diagram established according to one embodiment of the invention.
Fig. 4 is the purpose project three-dimensional BIM schematic diagrames established according to one embodiment of the invention.
Fig. 5 is the purpose project three-dimensional BIM partial schematic diagrams before collision detection is carried out according to one embodiment of the invention.
Fig. 6 is that the purpose project three-dimensional BIM partial schematic diagrams after collision detection are carried out according to one embodiment of the invention.
Embodiment
Below in conjunction with the accompanying drawings and embodiment, the present invention will be described in further detail, so that the purpose of the present invention, technology Scheme and advantage are more clearly understood.It should be appreciated that specific embodiment described herein is only to explain the present invention, and do not have to It is of the invention in limiting.
By quickly establishing BIM, the modeling time can be shortened, speeded up the work;By setting different tolerances pair The building of whole station, electromechanical model carry out crash analysis, find in time and solve all pipeline collision problems, can not only realize institute The pipeline reasonable Arrangement for having specialty improves installation and operation quality, additionally it is possible to effectively avoids construction from conflicting and do over again, saves installation Cost simultaneously improves installation effectiveness;Moreover, carrying out Material Takeoff based on BIM and formulating material planning, it can further simplify installation Mode, reduce installation workload, so as to shorten the duration, reduce engineering cost;Procedure connection is carried out by BIM and working face is changed Preview, it is each specialty correction on the basis of, formulate engineering construction sequence scheme, can effectively promote duration progress.In the market The BIM modeling softwares of main flow are the Revit groupwares of autodesk, inc., wherein electromechanical installation modeling software is RevitMEP.In addition there are Pu Luogeman Co., Ltds of Finland MagiCADfor AutoCAD softwares in electromechanical installation, under Method provided in an embodiment of the present invention is described in detail by taking MagiCAD softwares as an example for text.
As shown in figure 1, the electromechanical installation of the subway based on BIM according to an embodiment of the invention and fitting-out work construction method Comprise the following steps:
Step 101:Input two dimensional surface design drawing and field survey data
Specifically, using the electromechanical installation of certain subway station and fitting-out work as purpose project, each professional system of subway station Two dimensional surface design drawing can be the CAD electronic drawing formatted files that each Specialty Design institute provides, and field survey data are main The physical dimension data obtained are checked including carrying out live field survey to the subway station building structure.
Step 102:The threedimensional model of each professional system is established respectively
First, it is soft with MagiCAD with reference to civil engineering structure plane drawing and by live field survey review physical dimension Part to purpose project building structure entity carry out three-dimensional modeling, and according to structure rank establish successively building structure threedimensional model, Ventilating system threedimensional model, crane span structure system threedimensional model, discharge water fire fighting system threedimensional model (as shown in Figure 2) and air-conditioning Water system threedimensional model (as shown in Figure 3).
Step 103:Establish the purpose project three-dimensional BIM with unified coordinate system
Specifically, the three-dimensional BIM model for each system built up entirely to be stood by MagiCAD software synthesises composition, Such as shown in Fig. 4.
Step 104:Carry out collision detection, the result report of generation collision detection
After completing BIM modelings, by setting different tolerances to enter the building of whole station, electromechanical model in MagiCAD Row crash analysis.For example, it is 100mm to set airduct tolerance and water pipe tolerance respectively, sewage pipe tolerance is 50mm, and electric object is public Difference is 50mm, and collision detection collision inspection is carried out by the fagerh_ceil_allfiveo_geometry functions of MagiCAD softwares Report is looked into, is drawn at the point of impingement 1195, and its three-dimensional coordinate data.Wherein, collided determined by the report of collision detection result Region can include multiple points of impingement, such as shown in Fig. 5, the air channel 1 and air channel 2 that are belonging respectively to different system have overlay region Domain.
In a preferred embodiment, collision detection can further include the detection of hole reservation collision, and it includes obtaining mesh The sectional view of all reserving holes in engineering three-dimensional BIM is marked, it is inclined according to each professional system reserving hole sized data and hole Shifting amount, collinearly merge tolerance and round the conflict area between each professional system reserving hole of value acquisition and its three-dimensional coordinate Data.
Step 105:Purpose project three-dimensional BIM is modified
For example, being adjusted by crane span structure to the superiors, airduct crane span structure is adjusted to intermediate layer, water pipe is adjusted to the bottom Modification strategy under, obtain modification result as shown in Figure 6, wherein keep air channel 1 model it is constant, change air channel 2 formation from And avoid conflicting.
Step 106:Determine working procedure, the space coordinates of working face conversion and corresponding conversion time
Specifically, the preview and correction for carrying out procedure connection and working face conversion can include:By purpose project three-dimensional BIM In whole entities according to affiliated professional system, different colours are set, and according to first up and then down, first big after small, construction in layer original The sequencing of each professional system construction then arranged carries out work progress preview;The construction occurred in being previewed according to work progress Order conflicts, adjust corresponding to the working procedure of one or more professional system, the space coordinates and correspondingly of working face conversion Conversion time or material production and/or enter field time.
In a further embodiment, methods described further comprises:Carried out based on amended purpose project three-dimensional BIM Engineering material counts, and generates material planning;And set according to the working procedure of each professional system, working face conversion conversion time The production of material in each professional system is set in material planning and enters field time.For example, using BIM Material Takeoff functions to model Be calculated the very detailed material plannings such as the professional subsystem of point floor point, and can be with according to amended Optimized model Obtain the pipeline unit of specific size, can directly produce the pipeline unit of refinement during construction by factory to scene, scene can root It is mounted directly according to model without processing at the scene.Material Takeoff workload is greatlyd save, and material planning is finely accurate, knot Close construction speed arrangement can elaborate scheme material time of arrival, avoid live material stacking or material from not showing up and cause the duration to drag Prolong.The method for changing the survey calculation pipeline specification size in construction in traditional construction, by the material unifiedly calculated before constructing Statistical form is processed and formed at one time the foolproof installation in scene in factory, installs simple and fast.Workload is greatlyd save, simplifies peace Dress mode, shorten the duration, is engineering economy cost.
In a preferred embodiment, the above method can be further to key equipment room, small space, comprehensive suspension and support Arrangement optimizes.For example, to 1500mm × 800mm or 1250mm in the 1200 × 4500mm battery limits corridor ceiling void × 630mm ventilation shaft, caliber is 200mm and insulation layer thickness is 50mm freeze cycle waterpipe, size be 800mm × 200mm power and lighting crane span structure, the automatic fire alarm system FAS crane span structures that size is 400mm × 200mm and size are 200mm × 200mm BAS BAS crane span structures, on the premise of the operating space of reserved 250mm height, carry out comprehensive Close the arrangement optimization of suspension and support.Not only accomplish that pipeline connection and reasonable arrangement is attractive in appearance, improved installation quality, moreover it is possible to efficiently solve and set Standby comprehensive pipeline is complicated, installs the technical barriers such as space anxiety concentratedly, and cost-effective, resultant effect is good.
BIM is quickly established by MagiCAD softwares in the various embodiments described above, it is stagnant to solve design schedule in metro project Afterwards, the problem of influenceing modeling and subsequent applications;By using BIM, " multi-specialized pipeline collision detection " is completed, " in small space The work such as pipeline and comprehensive suspension and support arrangement optimization design ", " hole is reserved ", realizes the comprehensive pipeline arrangement optimization based on BIM Design;Realize that material planning automatically generates using BIM, and then the production of material in each professional system is set and enters field time;Profit Divide the procedure connection of construction point and the preview and correction of working face conversion with BIM achievement units, and determine applying for each professional system Work process, the space coordinates of working face conversion and corresponding conversion time, so as to reduce installation workload, shorten the duration, and drop Low engineering cost.BIM modelings are completed by MagiCAD softwares, using BIM in pipeline layout balanced design, examined by colliding Survey, by the point of impingement as early as possible feed back to designer, timely cooperation and communication is carried out with owner, consultant, in the Deepen Design stage The pipeline collision at the scene of reducing as far as possible and phenomenon of doing over again.This can not only exclude the collision that can be run into project construction link in time Conflict, substantially reduces resulting modification application list, more substantially increases the production efficiency of job site, reduce due to applying Cost caused by work is coordinated increases and construction delay.
It is described above, the only detailed description of the specific embodiment of the invention, rather than limitation of the present invention.Correlation technique The technical staff in field is not in the case where departing from the principle and scope of the present invention, various replacements, modification and the improvement made It should be included in the scope of the protection.

Claims (10)

1. a kind of electromechanical installation of the subway based on BIM and fitting-out work construction method, it is characterised in that methods described includes:
The two dimensional surface design drawing of each professional system of purpose project, and the field survey data of purpose project are inputted, respectively Establish the threedimensional model of each professional system;
Based on the threedimensional model of each professional system, the purpose project three-dimensional BIM with unified coordinate system is established;
Collision detection, the result report of generation collision detection are carried out to purpose project three-dimensional BIM according to default tolerance;
According to collision detection result report and change strategy, adjust corresponding to one or more professional system threedimensional model with Purpose project three-dimensional BIM is modified;
The preview and correction of procedure connection and working face conversion are carried out based on amended purpose project three-dimensional BIM, and is determined each The working procedure of individual professional system, the space coordinates of working face conversion and corresponding conversion time.
2. according to the method for claim 1, it is characterised in that the threedimensional model of each professional system includes:Building knot Structure threedimensional model, ventilating system threedimensional model, crane span structure system threedimensional model, discharge water fire fighting system threedimensional model and air-conditioning Water system threedimensional model.
3. according to the method for claim 1, it is characterised in that the modification strategy includes:Crane span structure is adjusted to the superiors, Airduct crane span structure is adjusted to intermediate layer, water pipe is adjusted to the bottom.
4. according to the method for claim 1, it is characterised in that the collision detection is included in the three-dimensional mould of each professional system The overlapping detection of three-dimensional space position is carried out according to purpose project three-dimensional BIM unified coordinate system between type, obtains each professional system Between conflict area and its three-dimensional coordinate data.
5. according to the method for claim 1, it is characterised in that the collision detection detects including hole reservation collision, its Sectional view including obtaining all reserving holes in purpose project three-dimensional BIM, according to each professional system reserving hole sized data And hole offset, collinearly merge tolerance and round conflict area between each professional system reserving hole of value acquisition and Its three-dimensional coordinate data.
6. the method according to claim 4 or 5, it is characterised in that the conflict area includes the reality in each professional system Exist between body in purpose project three-dimensional BIM and occur simultaneously, or the distance between entity is less than default tolerance value.
7. according to the method for claim 1, it is characterised in that methods described further comprises:Based on amended target Engineering three-dimensional BIM carries out engineering material statistics, generates material planning;
Set in material planning and each professional system is set according to the working procedure of each professional system, working face conversion conversion time The production of middle material and enter field time.
8. according to the method for claim 7, it is characterised in that it is described carry out procedure connection and working face conversion preview and Correction includes:Whole entities in purpose project three-dimensional BIM are set into different colours according to affiliated professional system, and according on first Under afterwards, the sequencing of each professional system of first big after small, construction in layer principle arrangement construction carry out work progress preview;Root The sequence of construction conflict occurred in being previewed according to work progress, the working procedure of one or more corresponding professional system of adjustment, Working face conversion space coordinates and corresponding conversion time or material production and/or enter field time.
9. according to the method for claim 1, it is characterised in that it is described purpose project three-dimensional BIM is modified including:It is right 1500mm × 800mm or 1250mm × 630mm ventilation shaft, caliber in the 1200 × 4500mm battery limits corridor ceiling void Power and lighting crane span structure that the freeze cycle waterpipe for being 50mm for 200mm and insulation layer thickness, size are 800mm × 200mm, chi It is very little be 400mm × 200mm automatic fire alarm system FAS crane span structures and building automation that size is 200mm × 200mm System BAS crane span structures, on the premise of the operating space of reserved 250mm height, integrate the arrangement optimization of suspension and support.
10. according to the method for claim 1, it is characterised in that methods described establishes each specialty using MagiCAD softwares and is The threedimensional model and purpose project three-dimensional BIM of system, and carry out collision detection.
CN201710858634.4A 2017-09-21 2017-09-21 A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method Pending CN107633137A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710858634.4A CN107633137A (en) 2017-09-21 2017-09-21 A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710858634.4A CN107633137A (en) 2017-09-21 2017-09-21 A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method

Publications (1)

Publication Number Publication Date
CN107633137A true CN107633137A (en) 2018-01-26

Family

ID=61102287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710858634.4A Pending CN107633137A (en) 2017-09-21 2017-09-21 A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method

Country Status (1)

Country Link
CN (1) CN107633137A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108320108A (en) * 2018-02-09 2018-07-24 中建五局第三建设有限公司 Method for reflecting large-span engineering project progress
CN108763821A (en) * 2018-06-15 2018-11-06 中国机械工业机械工程有限公司 A kind of urban rail transit elevated station mechanical and electric equipment installation method
CN109214118A (en) * 2018-10-15 2019-01-15 河北省建筑材料工业设计研究院 A kind of cement production enterprise Industrial Design Method based on BIM
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109918760A (en) * 2019-03-01 2019-06-21 中铁八局集团第二工程有限公司 Reinforcing bar modeling method based on Revit interoperability
CN110795784A (en) * 2019-10-08 2020-02-14 上海建工五建集团有限公司 Electromechanical modeling method and system
CN110795825A (en) * 2019-10-08 2020-02-14 上海建工五建集团有限公司 Method and system for distinguishing specialties in collaborative modeling
CN111651822A (en) * 2020-05-29 2020-09-11 深圳市华阳国际工程设计股份有限公司 Hole information generation method and device of BIM (building information modeling) model and storage device
CN112184174A (en) * 2020-10-12 2021-01-05 中国科学院计算技术研究所厦门数据智能研究院 Method for automatically generating construction scheme of shelter type building
CN113076584A (en) * 2021-04-12 2021-07-06 山西省工业设备安装集团有限公司 BIM-based electromechanical construction method for corridor of subway station equipment area
CN113127949A (en) * 2019-12-31 2021-07-16 久瓴(上海)智能科技有限公司 Building model processing method and device, computer equipment and readable storage medium
CN114254415A (en) * 2020-09-23 2022-03-29 中铁八局集团昆明铁路建设有限公司 Building construction method based on BIM preset model
TWI767764B (en) * 2021-06-23 2022-06-11 中興工程顧問股份有限公司 The modeling method of csd and sem
CN115860499A (en) * 2023-02-28 2023-03-28 安徽智享云科技有限公司 Multi-professional work-type coordination construction management system based on BIM technology
CN116882014A (en) * 2023-07-11 2023-10-13 广东方程建筑科技有限公司 Automatic building design method based on BIM technology

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103500371A (en) * 2013-08-08 2014-01-08 机械工业第六设计研究院有限公司 Change control method based on BIM
CN104966154A (en) * 2015-06-09 2015-10-07 广州市水电设备安装有限公司 BIM technology-based temporary water and temporary electricity management method and system
CN105808835A (en) * 2016-03-04 2016-07-27 上海宝冶集团有限公司 Method for assembling pipelines of electromechanical system based on BIM (Building Information Modeling)
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107066750A (en) * 2017-04-26 2017-08-18 中天建设集团有限公司天津分公司 A kind of method for solving the arrangement of electrical and mechanical comprehensive pipeline

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103500371A (en) * 2013-08-08 2014-01-08 机械工业第六设计研究院有限公司 Change control method based on BIM
CN104966154A (en) * 2015-06-09 2015-10-07 广州市水电设备安装有限公司 BIM technology-based temporary water and temporary electricity management method and system
CN105808835A (en) * 2016-03-04 2016-07-27 上海宝冶集团有限公司 Method for assembling pipelines of electromechanical system based on BIM (Building Information Modeling)
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107066750A (en) * 2017-04-26 2017-08-18 中天建设集团有限公司天津分公司 A kind of method for solving the arrangement of electrical and mechanical comprehensive pipeline

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高继传 等: "三维管线综合设计在南京地铁中的应用探讨", 《铁道标准设计》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108320108A (en) * 2018-02-09 2018-07-24 中建五局第三建设有限公司 Method for reflecting large-span engineering project progress
CN108763821A (en) * 2018-06-15 2018-11-06 中国机械工业机械工程有限公司 A kind of urban rail transit elevated station mechanical and electric equipment installation method
CN109214118A (en) * 2018-10-15 2019-01-15 河北省建筑材料工业设计研究院 A kind of cement production enterprise Industrial Design Method based on BIM
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109918760B (en) * 2019-03-01 2023-02-21 中铁八局集团第二工程有限公司 Revit interoperability-based steel bar modeling method
CN109918760A (en) * 2019-03-01 2019-06-21 中铁八局集团第二工程有限公司 Reinforcing bar modeling method based on Revit interoperability
CN110795784A (en) * 2019-10-08 2020-02-14 上海建工五建集团有限公司 Electromechanical modeling method and system
CN110795825A (en) * 2019-10-08 2020-02-14 上海建工五建集团有限公司 Method and system for distinguishing specialties in collaborative modeling
CN110795825B (en) * 2019-10-08 2024-02-13 上海建工五建集团有限公司 Method and system for distinguishing professions in collaborative modeling
CN113127949A (en) * 2019-12-31 2021-07-16 久瓴(上海)智能科技有限公司 Building model processing method and device, computer equipment and readable storage medium
CN111651822A (en) * 2020-05-29 2020-09-11 深圳市华阳国际工程设计股份有限公司 Hole information generation method and device of BIM (building information modeling) model and storage device
CN114254415A (en) * 2020-09-23 2022-03-29 中铁八局集团昆明铁路建设有限公司 Building construction method based on BIM preset model
CN112184174A (en) * 2020-10-12 2021-01-05 中国科学院计算技术研究所厦门数据智能研究院 Method for automatically generating construction scheme of shelter type building
CN112184174B (en) * 2020-10-12 2022-05-27 中国科学院计算技术研究所厦门数据智能研究院 Method for automatically generating construction scheme of shelter type building
CN113076584A (en) * 2021-04-12 2021-07-06 山西省工业设备安装集团有限公司 BIM-based electromechanical construction method for corridor of subway station equipment area
TWI767764B (en) * 2021-06-23 2022-06-11 中興工程顧問股份有限公司 The modeling method of csd and sem
CN115860499A (en) * 2023-02-28 2023-03-28 安徽智享云科技有限公司 Multi-professional work-type coordination construction management system based on BIM technology
CN116882014A (en) * 2023-07-11 2023-10-13 广东方程建筑科技有限公司 Automatic building design method based on BIM technology

Similar Documents

Publication Publication Date Title
CN107633137A (en) A kind of electromechanical installation of the subway based on BIM and fitting-out work construction method
Pan et al. Building energy simulation and its application for building performance optimization: A review of methods, tools, and case studies
CN102867076B (en) BIM (Building Information Modeling)-based metro comprehensive pipeline clearance detection method
CN101556704B (en) Method for establishing temporary supporting frame system assembled by steel structures
CN106202723A (en) A kind of BIM subway work method
CN106683198A (en) 3D automatic modeling and scheduling rendering method for integrated pipe network
CN107895031B (en) Self-adaptive dynamic scheduling method of building information model in three-dimensional digital city scene
Li et al. Numerical simulation, PIV measurements and analysis of air movement influenced by nozzle jets and heat sources in underground generator hall
CN105468796A (en) Method for establishing temporary support moulding bed system for steel structure assembly
CN107256310A (en) A kind of high-order three-dimensional design method for receiving water cooling tower water collector
CN112765701A (en) Design and construction integrated construction method for new farmer village
KR100683120B1 (en) A right to enjoy sunshine disturbance analysis system and method thereof
Ding et al. Coupled natural ventilation modeling for contextual parametric design decision support
Liu et al. RETRACTED ARTICLE: Ecological technology of green building in the initial stage of design based on BIM technology
CN113312692A (en) BIM-based public building electromechanical installation engineering construction method
CN112328666A (en) Intelligent building supervision operation and maintenance system based on cloud platform technology
Ying et al. Building virtual scene construction and environmental impact analysis based on image processing
Zhu et al. Design study on green sports building based on BIM
Li et al. A comprehensive morphological classification scheme for local ventilation performance zones in spatially heterogeneous urban areas
CN114117601A (en) Method and system for problem discovery in building complex design
Hong et al. Application of BIM technology in building mechanical and electrical engineering modeling and pipeline inspection
Xu et al. Research on decoration design of green building based on BIM technology
Wu et al. Research on Application of BIM+ GIS Technology in Building Life Cycle
Wang Analysis on the Application of BIM Technology in the Design of Building Rebuilding
Liu Application of BIM technology in a prefabricated complex project

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180126