[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN107299588A - Prefabricated concrete-filled steel tube and spiced by steel reinforced concrete bridge pier - Google Patents

Prefabricated concrete-filled steel tube and spiced by steel reinforced concrete bridge pier Download PDF

Info

Publication number
CN107299588A
CN107299588A CN201710524593.5A CN201710524593A CN107299588A CN 107299588 A CN107299588 A CN 107299588A CN 201710524593 A CN201710524593 A CN 201710524593A CN 107299588 A CN107299588 A CN 107299588A
Authority
CN
China
Prior art keywords
reinforced concrete
concrete
prefabricated
section
prefabricated reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710524593.5A
Other languages
Chinese (zh)
Other versions
CN107299588B (en
Inventor
王连广
侯雯峪
韩华峰
王浩
张俊
裴家兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeastern University China
Original Assignee
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeastern University China filed Critical Northeastern University China
Priority to CN201710524593.5A priority Critical patent/CN107299588B/en
Publication of CN107299588A publication Critical patent/CN107299588A/en
Application granted granted Critical
Publication of CN107299588B publication Critical patent/CN107299588B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种预制钢管混凝土与钢筋混凝土拼装桥墩,其包括桥墩基础、预制钢管混凝土节段、一个或多个预制钢筋混凝土的中间节段和预制钢筋混凝土顶节段,其中,所述桥墩基础与所述预制钢管混凝土节段借助于设于所述桥墩基础设上的底锚栓固定连接,所述预制钢管混凝土节段与所述预制钢筋混凝土中间节段、及多个所述预制钢筋混凝土中间节段之间、预制钢筋混凝土中间节段与预制钢筋混凝土顶节段之间借助于连接单元固定连接。本发明各部分组件结构简单,不仅可以便于工厂预制,还便于现场拼接,以提高施工作业速度,也能有效降低现场作业强度。该拼装桥墩除具有承载力高,较好的抗压、抗弯、抗剪能力,以及良好的耐久性外,还具有抗震性能好等优点。

The invention relates to a prefabricated steel pipe concrete and reinforced concrete assembled bridge pier, which includes a bridge pier foundation, a prefabricated steel pipe concrete section, one or more prefabricated reinforced concrete middle sections and a prefabricated reinforced concrete top section, wherein the bridge pier foundation The prefabricated steel pipe concrete section is fixedly connected with the prefabricated steel pipe concrete section by means of the bottom anchor bolt arranged on the foundation of the bridge pier. The middle sections, the prefabricated reinforced concrete middle section and the prefabricated reinforced concrete top section are fixedly connected by means of connecting units. The structure of each part of the invention is simple, which not only facilitates factory prefabrication, but also facilitates on-site splicing, so as to improve the construction operation speed and effectively reduce the on-site operation intensity. The assembled bridge pier not only has high bearing capacity, good compressive resistance, bending resistance, shear resistance, and good durability, but also has the advantages of good seismic performance.

Description

预制钢管混凝土与钢筋混凝土拼装桥墩Prefabricated steel pipe concrete and reinforced concrete bridge piers

技术领域technical field

本发明属于桥梁工程领域,具体涉及一种预制钢管混凝土与钢筋混凝土拼装桥墩。The invention belongs to the field of bridge engineering, and in particular relates to a bridge pier assembled with prefabricated steel pipe concrete and reinforced concrete.

背景技术Background technique

目前,我国建造的大部分桥梁都是由现浇钢筋混凝土桥台、现浇混凝土桥墩、现浇混凝土桥面板及预制混凝土梁组成。现浇混凝土施工需要耗费大量的时间,并需要许多现场施工程序,这些程序会对交通流、工作区的安全和环境造成负面影响,特别是,在施工环境复杂、施工空间、气候条件及环境保护条件等因素的制约下,严重影响桥梁建筑施工的进程。At present, most of the bridges built in my country are composed of cast-in-place reinforced concrete abutments, cast-in-place concrete piers, cast-in-place concrete bridge decks and precast concrete beams. Cast-in-place concrete construction is time-consuming and requires many on-site construction procedures that negatively affect traffic flow, safety in the work area and the environment, especially in complex construction environments, construction spaces, climatic conditions and environmental protection Conditions and other factors seriously affect the progress of bridge construction.

针对预制混凝土墩柱与基础连接技术、预制混凝土节段之间连接技术、预制混凝土节段与盖梁的连接,以及连接后的受力性能,特别是连接后整体墩柱的抗震性能的研究相对比较少,使其应用范围还是受到了限制。Research on the connection technology between precast concrete piers and foundations, the connection technology between precast concrete sections, the connection between precast concrete sections and cover beams, and the mechanical performance after connection, especially the seismic performance of integral pier columns after connection Relatively few, so that its scope of application is still limited.

发明内容Contents of the invention

(一)要解决的技术问题(1) Technical problems to be solved

为了解决现有技术的上述问题,本发明提供一种预制钢管混凝土与钢筋混凝土拼装桥墩,具有实用性强、耐久性好、抗震性能优越等优点,采用提前预制桥墩的各部分,现场拼装,加快工期,并能有效保护施工环境。In order to solve the above-mentioned problems in the prior art, the present invention provides a prefabricated steel pipe concrete and reinforced concrete bridge pier, which has the advantages of strong practicability, good durability, and superior seismic performance. construction period, and can effectively protect the construction environment.

(二)技术方案(2) Technical solution

为了达到上述目的,本发明采用的主要技术方案包括:In order to achieve the above object, the main technical solutions adopted in the present invention include:

一种预制钢管混凝土与钢筋混凝土拼装桥墩,其包括桥墩基础、预制钢管混凝土节段、一个或多个预制钢筋混凝土中间节段和预制钢筋混凝土顶节段,其中,所述桥墩基础与所述预制钢管混凝土节段借助于设于所述桥墩基础设上的底锚栓固定连接,所述预制钢管混凝土节段与所述预制钢筋混凝土中间节段、及多个所述预制钢筋混凝土中间节段之间、预制钢筋混凝土中间节段与预制钢筋混凝土顶节段之间借助于连接单元固定连接。A prefabricated steel pipe concrete and reinforced concrete assembled bridge pier, which includes a bridge pier foundation, a prefabricated steel pipe concrete section, one or more prefabricated reinforced concrete middle sections and a prefabricated reinforced concrete top section, wherein the bridge pier foundation and the prefabricated The concrete-filled steel pipe section is fixedly connected by means of bottom anchor bolts arranged on the pier foundation, and the prefabricated steel pipe concrete section is connected with the prefabricated reinforced concrete middle section and between a plurality of prefabricated reinforced concrete middle sections. The room, the prefabricated reinforced concrete middle segment and the prefabricated reinforced concrete top segment are fixedly connected by means of connecting units.

作为如上所述拼装桥墩的一种优选方案,所述连接单元包括多个中空的连接器和从连接器内向所在预制钢筋混凝土中间节段的下端延伸的纵向钢筋,其中,多个所述连接器沿所述预制钢管混凝土节段或每个所述预制钢筋混凝土中间节段的上端侧面一周间隔设置,所述连接器内嵌于各自的混凝土节段中;所述中空的连接器包括开放的上下端,其靠近上下端的侧表面上设有横向伸出所述节段外侧的注射嘴,所述注射嘴为可拆卸设置,并与所述连接器内部连通;As a preferred solution for assembling bridge piers as described above, the connecting unit includes a plurality of hollow connectors and longitudinal steel bars extending from the inside of the connectors to the lower end of the prefabricated reinforced concrete intermediate section where the plurality of connectors It is arranged at intervals along the upper side of the prefabricated steel pipe concrete segment or each prefabricated reinforced concrete intermediate segment, and the connectors are embedded in the respective concrete segments; the hollow connectors include open upper and lower The side surface near the upper and lower ends is provided with an injection nozzle extending laterally outside the segment, the injection nozzle is detachable and communicated with the inside of the connector;

所述纵向钢筋从每个所述预制钢筋混凝土中间节段的下端对应所述连接器的位置外露,该外露的纵向钢筋对应插入相邻的所述连接器中,该纵向钢筋的上端伸入各自对应上端的所述连接器中至少一部分;The longitudinal steel bar is exposed from the position corresponding to the connector at the lower end of each prefabricated reinforced concrete middle section, and the exposed longitudinal steel bar is correspondingly inserted into the adjacent connector, and the upper end of the longitudinal steel bar extends into each at least a portion of said connector corresponding to the upper end;

所述预制钢筋混凝土顶节段的上端设有预埋顶锚螺栓,所述预制钢筋混凝土顶节段的下端对应所述预制钢筋混凝土中间节段中连接器的位置设有外露的纵向钢筋,所述外露的纵向钢筋插入对应的连接器中,该纵向钢筋的上端与所述预制钢筋混凝土顶节段上端平行。The upper end of the prefabricated reinforced concrete top section is provided with pre-embedded top anchor bolts, and the lower end of the prefabricated reinforced concrete top section is provided with exposed longitudinal reinforcement corresponding to the position of the connector in the prefabricated reinforced concrete middle section. The exposed longitudinal steel bar is inserted into the corresponding connector, and the upper end of the longitudinal steel bar is parallel to the upper end of the prefabricated reinforced concrete top section.

作为如上所述拼装桥墩的一种优选方案,所述拼装桥墩拼接后,向所述中空的连接器下端的注射嘴注射灌浆料,当所述灌浆料注满所述中空的连接器后,卸下所有的所述注射嘴,并密封连接所述注射嘴的注射口。As a preferred solution for assembling the bridge piers as described above, after the assembled bridge piers are spliced, inject grouting material into the injection nozzle at the lower end of the hollow connector, and when the grouting material fills the hollow connector, unload Lower all the injection nozzles, and seal the injection port connecting the injection nozzles.

作为如上所述拼装桥墩的一种优选方案,所述连接单元包括连接螺栓、连接钢板和连接锚筋,其中,所述连接螺栓预埋于所述预制钢管混凝土节段、所述预制钢筋混凝土中间节段及所述预制钢筋混凝土顶节段的上表面,所述连接钢板固定设于所述预制钢筋混凝土中间节段及所述预制钢筋混凝土顶节段的下端,所述连接锚筋的下端固定连接于所述连接钢板的上表面中间,所述连接锚筋的上端向下弯曲;在所述连接钢板上对应所述连接螺栓设有通孔,在所述预制钢筋混凝土中间节段及所述预制钢筋混凝土顶节段的下端对应所述通孔的上方设有用于浇筑混凝土的空腔。As a preferred solution for assembling bridge piers as described above, the connecting unit includes connecting bolts, connecting steel plates and connecting anchor bars, wherein the connecting bolts are pre-embedded in the prefabricated steel pipe concrete segment and the middle of the prefabricated reinforced concrete section and the upper surface of the prefabricated reinforced concrete top section, the connecting steel plate is fixed on the lower end of the prefabricated reinforced concrete middle section and the prefabricated reinforced concrete top section, and the lower end of the connecting anchor bar is fixed Connected to the middle of the upper surface of the connecting steel plate, the upper end of the connecting anchor bar is bent downward; the connecting steel plate is provided with a through hole corresponding to the connecting bolt, and the middle section of the prefabricated reinforced concrete and the A cavity for pouring concrete is provided at the lower end of the prefabricated reinforced concrete top segment corresponding to the above through hole.

作为如上所述拼装桥墩的一种优选方案,所述拼装桥墩还包括有盖梁,所述盖梁设于所述预制钢筋混凝土顶节段的上方,二者借助预埋于所述预制钢筋混凝土顶节段上方的顶锚螺栓与对应所述盖梁上的预留孔连接,在所述预留孔的上方设有用于浇筑混凝土的空腔。As a preferred solution for the assembled bridge pier as described above, the assembled bridge pier also includes a cover beam, the cover beam is arranged above the prefabricated reinforced concrete top section, and the two are pre-embedded in the prefabricated reinforced concrete The top anchor bolt above the top section is connected to the corresponding reserved hole on the cover beam, and a cavity for pouring concrete is provided above the reserved hole.

作为如上所述拼装桥墩的一种优选方案,所述预制钢管混凝土节段包括中间浇筑有混凝土的钢管、基础垫钢板和多个剪力连接件,所述剪力连接件均固定于所述钢管内壁,所述基础垫钢板设于所述钢管底部,所述基础垫钢板的面积大于所述钢管的横截面面积,并在所述钢管主体投影面积之外的基础垫钢板上对应所述底锚栓设置连接孔。As a preferred solution for assembling bridge piers as described above, the prefabricated steel pipe concrete segment includes a steel pipe with concrete poured in the middle, a base plate and a plurality of shear connectors, and the shear connectors are all fixed to the steel pipe Inner wall, the base backing steel plate is arranged at the bottom of the steel pipe, the area of the base backing steel plate is larger than the cross-sectional area of the steel pipe, and the base backing steel plate outside the projected area of the main body of the steel pipe corresponds to the bottom anchor Bolt set connection hole.

作为如上所述拼装桥墩的一种优选方案,所述剪力连接件均为栓钉,所述栓钉的钉尖焊接于所述钢管上,所述栓钉交错布置。As a preferred solution for assembling bridge piers as described above, the shear connectors are all studs, the nail tips of the studs are welded to the steel pipes, and the studs are arranged in a staggered manner.

作为如上所述拼装桥墩的一种优选方案,所述剪力连接件均为带孔钢板,所述带孔钢板为设有多个等间距通孔的条带形钢板,所述带孔钢板平行固定于所述钢管内壁上。进一步地,可以在通孔内布置钢筋,以便起到更好的连接作用。As a preferred solution for assembling bridge piers as described above, the shear connectors are all steel plates with holes, and the steel plates with holes are strip-shaped steel plates with a plurality of equidistant through holes, and the steel plates with holes are parallel to each other. fixed on the inner wall of the steel pipe. Further, steel bars can be arranged in the through holes for better connection.

作为如上所述拼装桥墩的一种优选方案,所述预制钢筋混凝土中间节段和预制钢筋混凝土顶节段为内设有多个纵向钢筋、多个箍筋的混凝土,其中,多个所述纵向钢筋靠近所述混凝土边沿一周间隔布置,多个所述箍筋均环绕固定于所有所述纵向钢筋的外侧,沿所述纵向钢筋在纵向间隔布置。As a preferred solution for assembling bridge piers as described above, the prefabricated reinforced concrete middle segment and the prefabricated reinforced concrete top segment are concrete with a plurality of longitudinal steel bars and a plurality of stirrups inside, wherein a plurality of the longitudinal The reinforcing bars are arranged at intervals around the edge of the concrete, and a plurality of stirrups are fixed around the outer sides of all the longitudinal reinforcing bars, and are arranged at longitudinal intervals along the longitudinal reinforcing bars.

作为如上所述拼装桥墩的一种优选方案,所述预制钢管混凝土节段和所述预制钢筋混凝土中间节段及顶阶段的横截面为圆形、方形、椭圆或其它形状。As a preferred solution for assembling bridge piers as described above, the cross-sections of the prefabricated steel pipe concrete section, the prefabricated reinforced concrete middle section and the top stage are circular, square, elliptical or other shapes.

(三)有益效果(3) Beneficial effects

本发明的有益效果是:The beneficial effects of the present invention are:

本发明提供的预制钢管混凝土与钢筋混凝土拼装桥墩,在桥梁墩柱基础上方采用预制钢管混凝土节段,而墩身其它部分采用预制钢筋混凝土的中间节段及顶节段,在连接处通过浇筑或灌注加强固定两相邻预制的钢管混凝土节段或钢筋混凝土中间节段间的连接强度,将预制钢管混凝土节段与预制钢筋混凝土中间节段及顶节段合理连接成整体。通过后期连接时现场浇筑或灌注的手段,这样不仅能保证相邻两预制钢筋混凝土柱节段的连接强度,从而可以保证桥墩的整体质量,而且各部分组件结构简单,不仅可以便于工厂预制,还便于现场拼接,以提高施工作业速度,也能有效降低现场作业强度。该拼装桥墩除具有承载力高,较好的抗压、抗弯、抗剪能力,以及良好的耐久性外,还具有抗震性能好等优点。通过提前预制,现场拼接,具有施工速度快、不影响正常交通、施工工期短,施工噪音低、物料堆放场地少,利于保护现场施工环境等优势。The prefabricated steel pipe concrete and reinforced concrete assembled bridge pier provided by the present invention adopts the prefabricated steel pipe concrete segment above the foundation of the bridge pier column, while the other parts of the pier body adopt the middle segment and the top segment of prefabricated reinforced concrete, and the joint is poured or Infusion strengthens and fixes the connection strength between two adjacent prefabricated steel pipe concrete sections or reinforced concrete middle sections, and reasonably connects the prefabricated steel pipe concrete sections with the prefabricated reinforced concrete middle section and the top section into a whole. By means of on-site pouring or pouring during the later connection, not only can the connection strength of two adjacent prefabricated reinforced concrete column segments be guaranteed, so as to ensure the overall quality of the pier, but also the components of each part have a simple structure, which is not only convenient for factory prefabrication, but also It is convenient for on-site splicing to increase the speed of construction operations and effectively reduce the intensity of on-site operations. The assembled bridge pier not only has high bearing capacity, good compressive resistance, bending resistance, shear resistance, and good durability, but also has the advantages of good seismic performance. Through prefabrication in advance and on-site splicing, it has the advantages of fast construction speed, no impact on normal traffic, short construction period, low construction noise, and less material storage space, which is conducive to protecting the construction environment on site.

进一步在预制钢管混凝土节段中设有剪力连接件,将钢管和混凝土形成整体,共同受力、变形协调,抗震性能提高。Further, a shear connector is provided in the prefabricated concrete-filled steel tube section to form a whole with the steel tube and the concrete, to jointly bear force and coordinate deformation, and to improve the seismic performance.

附图说明Description of drawings

图1为本发明一优选拼装桥墩总体结构的纵向剖面图;Fig. 1 is a longitudinal sectional view of a preferred assembled pier overall structure of the present invention;

图2为本发明图1中预制钢管混凝土节段的结构示意图;Fig. 2 is the structural representation of the prefabricated steel pipe concrete section in Fig. 1 of the present invention;

图3为图2中在Ⅰ处的横截面示意图;Fig. 3 is a cross-sectional schematic view at I in Fig. 2;

图4为图2中在Ⅱ处的横截面示意图;Fig. 4 is a cross-sectional schematic view at II in Fig. 2;

图5为图1中的预制钢筋混凝土中间节段的结构示意图;Fig. 5 is a schematic structural view of the prefabricated reinforced concrete middle segment in Fig. 1;

图6为图5中在Ⅲ处的横截面示意图;Fig. 6 is a schematic cross-sectional view at III in Fig. 5;

图7为图5中在Ⅳ处的横截面示意图;Fig. 7 is a schematic cross-sectional view at IV in Fig. 5;

图8为一优选剪力连接件的结构示意图;Fig. 8 is a schematic structural view of a preferred shear connector;

图9为另一优选拼装桥墩总体结构的纵向剖面图;Fig. 9 is a longitudinal sectional view of another preferred assembled pier overall structure;

图10为图9中预制钢筋混凝土中间节段的结构示意图;Fig. 10 is a schematic structural view of the prefabricated reinforced concrete middle segment in Fig. 9;

图11为图10中在Ⅴ处的横截面示意图;Fig. 11 is a schematic cross-sectional view at V in Fig. 10;

图12为图10中在Ⅵ处的横截面示意图;Fig. 12 is a schematic cross-sectional view at VI in Fig. 10;

图13为图9中预制钢筋混凝土顶节段上端的横截面示意图;Fig. 13 is a schematic cross-sectional view of the upper end of the prefabricated reinforced concrete top segment in Fig. 9;

图14为连接螺栓的结构示意图;Fig. 14 is the structural representation of connecting bolt;

图15为带孔钢板的结构示意图。Fig. 15 is a structural schematic diagram of a steel plate with holes.

【附图标记说明】[Description of Reference Signs]

1:桥墩基础;1: pier foundation;

2:预制钢管混凝土节段;2: Prefabricated steel tube concrete segment;

3:预制钢筋混凝土中间节段;3: Prefabricated reinforced concrete middle segment;

4:预制钢筋混凝土顶节段;4: Prefabricated reinforced concrete top segment;

5:底锚栓;5: Bottom anchor bolt;

6:钢管;6: steel pipe;

7:基础垫钢板;7: Base pad steel plate;

8:连接孔;8: connection hole;

9:连接器;9: Connector;

10:纵向钢筋;10: Longitudinal reinforcement;

11:注射嘴;11: injection nozzle;

12:箍筋;12: Stirrup;

13:盖梁;13: cover beam;

14:顶锚螺栓;14: top anchor bolt;

15:盖梁后浇筑混凝土;15: Pouring concrete after covering the beam;

16:剪力连接件;16: shear connector;

17:连接螺栓;17: connecting bolts;

18:连接钢板;18: connecting steel plate;

19:连接锚筋;19: connect the anchor bars;

20:连接处后浇筑混凝土;20: Concrete is poured after the connection;

21:通孔;21: through hole;

22;连接处后浇筑混凝土空腔;22; Concrete cavity is poured after the joint;

23:带帽螺栓;23: cap bolt;

24:栓帽垫板;24: bolt cap backing plate;

25:螺母垫板;25: nut backing plate;

26:紧固螺母;26: fastening nut;

27:条带形钢板。27: Strip-shaped steel plate.

具体实施方式detailed description

为了更好的解释本发明,以便于理解,下面结合附图,通过具体实施方式,对本发明作详细描述。In order to better explain the present invention and facilitate understanding, the present invention will be described in detail below through specific embodiments in conjunction with the accompanying drawings.

实施例1Example 1

一种预制钢管混凝土与钢筋混凝土拼装桥墩,如图1所示,其包括由下至上依次为桥墩基础1、预制钢管混凝土节段2、一个或多个预制钢筋混凝土中间节段3和预制钢筋混凝土顶节段4,其中,桥墩基础1与预制钢管混凝土节段2借助于设于所述桥墩基础1设上的底锚栓5固定连接,预制钢管混凝土节段2与预制钢筋混凝土中间节段3、及多个预制钢筋混凝土中间节段3之间、预制钢筋混凝土中间节段3与预制钢筋混凝土顶节段4之间借助于连接单元固定连接。A kind of prefabricated steel pipe concrete and reinforced concrete assembled bridge pier, as shown in Figure 1, it includes successively from bottom to top pier foundation 1, prefabricated steel pipe concrete section 2, one or more prefabricated reinforced concrete intermediate sections 3 and prefabricated reinforced concrete The top section 4, wherein, the bridge pier foundation 1 and the prefabricated steel pipe concrete section 2 are fixedly connected by means of the bottom anchor bolt 5 arranged on the bridge pier foundation 1, and the prefabricated steel pipe concrete section 2 and the prefabricated reinforced concrete middle section 3 , and a plurality of prefabricated reinforced concrete middle sections 3, and between the prefabricated reinforced concrete middle section 3 and the prefabricated reinforced concrete top section 4 are fixedly connected by means of connecting units.

具体地,如图2-图4所示,其中图3和图4为图2中在Ⅰ和Ⅱ处在横截面结构示意图,预制钢管混凝土节段2包括中间浇筑有混凝土的钢管6,钢管6底部固定有基础垫钢板7,基础垫钢板7的面积大于钢管6的面积,并在钢管6主体投影面积之外的基础垫钢板7上对应底锚栓5设置有连接孔8,预制钢管混凝土节段2的横截面设为圆形,预制钢筋混凝土中间节段3和预制钢筋混凝土顶节段4的横截面对应设置为圆形。Specifically, as shown in Fig. 2-Fig. 4, Fig. 3 and Fig. 4 are schematic diagrams of the cross-sectional structure at I and II in Fig. The base plate 7 is fixed at the bottom, the area of the base plate 7 is larger than the area of the steel pipe 6, and the base plate 7 outside the projected area of the steel pipe 6 is provided with a connecting hole 8 corresponding to the bottom anchor bolt 5, and the prefabricated steel pipe concrete section The cross-section of the section 2 is set to be circular, and the cross-sections of the prefabricated reinforced concrete middle section 3 and the prefabricated reinforced concrete top section 4 are correspondingly set to be circular.

连接单元包括多个连接器9和多个外露的纵向钢筋10,具体地,沿预制钢管混凝土节段2上端侧面一周间隔设置的多个连接器9,连接器9内嵌于预制钢管混凝土节段2中,靠近沿预制钢管混凝土节段2的外侧边沿间隔设置,连接器9中为空腔,空腔对应的上下两端伸出预制钢管混凝土节段2的侧边设有可拆卸注射嘴11,注射嘴11连通连接器9的空腔,可拆卸注射嘴可通过螺纹连接设置。The connection unit includes a plurality of connectors 9 and a plurality of exposed longitudinal steel bars 10, specifically, a plurality of connectors 9 arranged at intervals along the upper side of the prefabricated steel pipe concrete section 2, and the connectors 9 are embedded in the prefabricated steel pipe concrete section In 2, it is arranged at intervals close to the outer edge of the prefabricated steel pipe concrete section 2, and the connector 9 is a cavity, and the upper and lower ends of the cavity corresponding to the side of the prefabricated steel pipe concrete section 2 are provided with detachable injection nozzles 11 , the injection nozzle 11 communicates with the cavity of the connector 9, and the detachable injection nozzle can be set through threaded connection.

如图5-图7所示,相对应的在预制钢筋混凝土中间节段3对应连接器9的位置设有纵向钢筋10;纵向钢筋10末端伸出预制钢筋混凝土中间节段3的下端形成外露的纵向钢筋,该外露的纵向钢筋正好可伸入相邻节段的连接器9的空腔中,预制钢筋混凝土中间节段3的上端对应预制钢管混凝土节段2上端连接器的对应位置设有连接器9,本节段中的纵向钢筋10的上端一部分插入该连接器9设置,则预制钢筋混凝土中间节段3为靠近混凝土边沿一周间隔布置多个纵向钢筋10,纵向钢筋10的下端一部分超出预制钢筋混凝土中间节段3的下表面一部分,作为连接下一段节段的连接单元的一部分,此外,为了紧固结构在纵向钢筋10的外围一周固定有多个箍筋12,箍筋12均环绕固定于所有纵向钢筋10的外侧,沿纵向钢筋10在纵向间隔布置。As shown in Fig. 5-Fig. 7, a longitudinal steel bar 10 is correspondingly provided at the position corresponding to the connector 9 of the prefabricated reinforced concrete middle section 3; Longitudinal reinforcement, the exposed longitudinal reinforcement can just extend into the cavity of the connector 9 of the adjacent segment, and the upper end of the prefabricated reinforced concrete middle segment 3 corresponds to the corresponding position of the upper end connector of the prefabricated steel pipe concrete segment 2. A part of the upper end of the longitudinal steel bar 10 in this section is inserted into the connector 9 to set, then the prefabricated reinforced concrete middle section 3 is arranged with a plurality of longitudinal steel bars 10 at intervals around the edge of the concrete, and a part of the lower end of the longitudinal steel bar 10 exceeds the prefabricated A part of the lower surface of the reinforced concrete middle segment 3 is used as a part of the connection unit connecting the next segment. In addition, in order to fasten the structure, a plurality of stirrups 12 are fixed around the periphery of the longitudinal reinforcement 10, and the stirrups 12 are all fixed around On the outside of all the longitudinal reinforcement bars 10, the longitudinal reinforcement bars 10 are arranged at intervals in the longitudinal direction.

预制钢筋混凝土顶节段4不同于预制钢筋混凝土中间节段3的是,其上端未设有连接器9,而是预埋有顶锚螺栓,顶锚螺栓靠近预制钢筋混凝土顶节段4的中央设置,且纵向钢筋10的上端与预制钢筋混凝土顶节段4的上端平行。The prefabricated reinforced concrete top section 4 is different from the prefabricated reinforced concrete middle section 3 in that there is no connector 9 at its upper end, but a top anchor bolt is pre-embedded, and the top anchor bolt is close to the center of the prefabricated reinforced concrete top section 4 set, and the upper end of the longitudinal reinforcement 10 is parallel to the upper end of the prefabricated reinforced concrete top section 4.

进行拼接桥墩时,将两相邻的预制钢筋混凝土中间节段3吊装安放至预制钢管混凝土节段2的上方,外露的纵向钢筋10正好插入预制钢管混凝土节段2的连接器9中,从下端的注射嘴11注射专用高强、无收缩的灌浆料,如可采用JG/T 408-2013钢筋连接用套筒灌浆料,灌浆料灌满连接器9的空腔后可从上端的注射嘴11流出停止灌浆,之后卸除注射嘴11封闭注射口。When splicing bridge piers, two adjacent prefabricated reinforced concrete intermediate sections 3 are hoisted and placed above the prefabricated steel pipe concrete section 2, and the exposed longitudinal steel bar 10 is just inserted into the connector 9 of the prefabricated steel pipe concrete section 2. The injection nozzle 11 is specially used for high-strength, non-shrinkage grouting material, such as JG/T 408-2013 sleeve grouting material for steel bar connection, which can flow out from the upper injection nozzle 11 after filling the cavity of the connector 9 Stop grouting, and then remove the injection nozzle 11 to close the injection port.

在预制钢筋混凝土顶节段4的上端还设有盖梁13,在盖梁13上对应预制钢筋混凝土顶节段4上端的顶锚螺栓的位置预留有通孔,通孔的上部预留有盖梁后浇筑混凝土空腔,用于盖梁13通过螺栓连接后,在盖梁后浇筑混凝土空腔内浇筑混凝土形成盖梁后浇筑混凝土15,盖梁后浇筑混凝土15加固盖梁13与预制钢筋混凝土中间节段3的连接,并且对顶锚螺栓外露部分起到密闭作用。The upper end of the prefabricated reinforced concrete top section 4 is also provided with a cover beam 13, and a through hole is reserved on the cover beam 13 corresponding to the top anchor bolt at the upper end of the prefabricated reinforced concrete top section 4, and a through hole is reserved in the upper part of the through hole. After the cover beam, the concrete cavity is poured, and after the cover beam 13 is connected by bolts, the concrete is poured in the cavity after the cover beam to form the cover beam and then the concrete is poured 15, and the cover beam is poured with concrete 15 to strengthen the cover beam 13 and the prefabricated steel bars The connection of the concrete middle segment 3, and plays a sealing role on the exposed part of the top anchor bolt.

此外,在预制钢管混凝土节段中,钢管6的内壁上设有多个剪力连接件16,剪力连接件16可极大加强钢管6与混凝土的连接强度,提高钢管混凝土节段的整体受力能力。剪力连接件16可设为栓钉,如图8所示,栓钉的钉尖焊接于钢管6上,多个栓钉是交错布置的。In addition, in the prefabricated CFST section, multiple shear connectors 16 are provided on the inner wall of the steel pipe 6. The shear connectors 16 can greatly strengthen the connection strength between the steel pipe 6 and the concrete, and improve the overall bearing capacity of the CFST segment. ability. The shear connector 16 can be set as a stud, as shown in FIG. 8 , the nail tip of the stud is welded on the steel pipe 6 , and a plurality of studs are arranged in a staggered manner.

本实施例中的预制钢管混凝土与钢筋混凝土拼装桥墩各组件的制作方法,如图1所示,包括如下步骤:The manufacturing method of each component of the prefabricated steel pipe concrete and reinforced concrete assembled pier in this embodiment, as shown in Figure 1, includes the following steps:

(1)制作钢管混凝土节段:按设计要求制作钢管6,在钢管6内焊接剪力连接件16,并将钢管6焊接在基础垫钢板7上,固定连接器9,在钢管6内浇筑混凝土,形成钢管混凝土节段;(1) Fabrication of steel pipe concrete section: manufacture steel pipe 6 according to the design requirements, weld shear connector 16 in steel pipe 6, weld steel pipe 6 on base plate 7, fix connector 9, and pour concrete in steel pipe 6 , forming a concrete filled steel tube segment;

(2)制作钢筋混凝土中间节段:制作模板和钢筋骨架(纵向钢筋10和箍筋12),固定连接器9,在模板内浇筑混凝土,形成钢筋混凝土中间节段;(2) Make reinforced concrete middle section: make formwork and reinforcement skeleton (longitudinal steel bar 10 and stirrup 12), fix connector 9, pour concrete in formwork, form reinforced concrete middle section;

(3)制作钢筋混凝土顶节段:制作模板、钢筋骨架(纵向钢筋10和箍筋12),固定顶锚螺栓,在模板内浇筑混凝土,形成钢筋混凝土顶节段;(3) Making the reinforced concrete top section: making formwork, reinforcing steel skeleton (longitudinal reinforcement 10 and stirrup 12), fixing jack bolts, pouring concrete in the formwork to form the reinforced concrete top section;

(4)在制作桥墩基础1上,预埋底锚螺栓;(4) On the pier foundation 1, the bottom anchor bolts are pre-embedded;

(5)制作盖梁13,设置连接处后浇筑混凝土空腔及通孔。(5) Make the cover beam 13, and pour concrete cavities and through holes after setting the joints.

上述各组件的安装:Installation of the above components:

(1)将钢管混凝土节段2通过预埋底锚螺栓5固定在桥墩基础1上;(1) Fix the steel pipe concrete segment 2 on the pier foundation 1 through the embedded bottom anchor bolt 5;

(2)将钢筋混凝土中间节段3中的伸出钢筋插入钢管混凝土节段2的连接器9中;(2) Insert the protruding steel bar in the reinforced concrete middle section 3 into the connector 9 of the steel pipe concrete section 2;

(3)将置于上方的钢筋混凝土中间节段3中的伸出钢筋插入相邻的置于下方连接器9中;(3) Insert the protruding steel bars placed in the reinforced concrete middle segment 3 above into the adjacent connector 9 placed below;

(4)将置于上方的钢筋混凝土顶节段4中的伸出钢筋插入相邻的置于下方的钢筋混凝土中间节段3的连接器9中;(4) Insert the protruding steel bars in the reinforced concrete top section 4 placed above into the connector 9 of the adjacent reinforced concrete middle section 3 placed below;

(5)将盖梁13放在钢筋混凝土顶节段4上,钢筋混凝土顶节段4的预埋顶锚螺栓14穿过盖梁13的通孔,用螺母固定;(5) The cover beam 13 is placed on the reinforced concrete top section 4, and the pre-embedded top anchor bolt 14 of the reinforced concrete top section 4 passes through the through hole of the cover beam 13, and is fixed with a nut;

(6)通过注射嘴11,向连接器9内从下向上注射灌浆料;(6) Through the injection nozzle 11, inject the grouting material into the connector 9 from bottom to top;

(7)卸除注射嘴11,用混凝土封闭注射口;(7) Remove the injection nozzle 11, and close the injection port with concrete;

(8)向盖梁13中盖梁后浇筑混凝土空腔内浇筑混凝土形成盖梁后浇筑混凝土15。(8) Concrete is poured in the cavity of the cover beam 13 to form the post-concrete 15 of the cover beam.

实施例2Example 2

本实施例是在实施例1的基础上,如图不同于实施例1的是,预制钢管混凝土节段2、预制钢筋混凝土中间节段3及预制钢筋混凝土顶节段4的横截面均为方形,即预制钢管混凝土节段2中的钢管也为方形设置,当然根据需要可以设置为其它形状。This embodiment is based on embodiment 1, as shown in the figure, it is different from embodiment 1 in that the cross-sections of prefabricated steel pipe concrete segment 2, prefabricated reinforced concrete middle segment 3 and prefabricated reinforced concrete top segment 4 are all square , that is, the steel pipes in the prefabricated steel pipe concrete segment 2 are also set in a square shape, and of course they can be set in other shapes as required.

本实施例中的连接单元不同于实施例1中,如图9所示,其连接单元包括连接螺栓17、连接钢板18和连接锚筋19。连接螺栓17是埋置于下方节段中的顶端,沿节段边沿一周间隔设置,连接钢板18是设置于上方节段中的下端,在连接钢板18上对应连接螺栓17设有用于连接的通孔,通孔的上方预留有连接处后浇筑混凝土空腔,用于浇筑形成连接处后浇筑混凝土20,以密封连接螺栓的外露部分并加固连接;在连接钢板18中间设有连接锚筋19,连接锚筋19的上端设为向下弯曲的弯钩,向下弯曲的弯钩状用于增强混凝土与连接钢板18之间的锚固,提高连接位置的抗力。The connecting unit in this embodiment is different from that in Embodiment 1. As shown in FIG. 9 , the connecting unit includes connecting bolts 17 , connecting steel plates 18 and connecting anchor bars 19 . Connecting bolt 17 is the top that is embedded in the lower segment, and is arranged at intervals along the edge of the segment. Connecting steel plate 18 is arranged at the lower end of the upper segment. hole, the top of the through hole is reserved with a joint before pouring a concrete cavity, which is used to pour concrete 20 after forming the joint, so as to seal the exposed part of the connecting bolt and strengthen the connection; in the middle of the connecting steel plate 18, a connecting anchor bar 19 is provided The upper end of the connecting anchor bar 19 is set as a downwardly bent hook, and the downwardly bent hook shape is used to strengthen the anchorage between the concrete and the connecting steel plate 18 and improve the resistance of the connecting position.

如图10-图12所示,预制钢筋混凝土中间节段3为下端设有连接钢板18,连接钢板18上对应连接螺栓17设有用于连接的通孔21,通孔的上方设有连接处后浇筑混凝土空腔22,连接钢板18的上表面中间设有连接锚筋19,连接锚筋19的下端固定连接于连接钢板18,连接锚筋19的上端向下弯曲;预制钢筋混凝土中间节段3的边沿一周还间隔设有纵向钢筋10,环绕所有的纵向钢筋10的外围固定有箍筋12,沿所述纵向钢筋10在纵向间隔布置有多个箍筋12,预制钢筋混凝土中间节段3的上端预埋有连接螺栓17,用于与上部节段通过螺母将两相邻节段固定。As shown in Figures 10-12, the prefabricated reinforced concrete middle segment 3 is provided with a connecting steel plate 18 at the lower end, and the corresponding connecting bolt 17 on the connecting steel plate 18 is provided with a through hole 21 for connection, and the upper part of the through hole is provided with a joint. Concrete cavity 22 is poured, connecting anchor bar 19 is provided in the middle of the upper surface of connecting steel plate 18, the lower end of connecting anchor bar 19 is fixedly connected to connecting steel plate 18, and the upper end of connecting anchor bar 19 is bent downward; prefabricated reinforced concrete middle section 3 There are also longitudinal reinforcing bars 10 at intervals around the edge of the edge, and stirrups 12 are fixed around the periphery of all longitudinal reinforcing bars 10, and a plurality of stirrups 12 are arranged at longitudinal intervals along the longitudinal reinforcing bars 10, and the prefabricated reinforced concrete middle segment 3 The upper end is pre-embedded with connecting bolts 17, which are used to fix the two adjacent segments with the upper segment through nuts.

在预制钢管混凝土节段上端沿外边沿一周间隔预埋有连接螺栓17。Connecting bolts 17 are pre-embedded at intervals along the outer edge of the upper end of the prefabricated steel pipe concrete section.

如图13所示,预制钢筋混凝土顶节段不同于预制钢筋混凝土中间节段的是,其上端预埋的顶锚螺栓14位置不同于连接螺栓17设置,顶锚螺栓14位于预制钢筋混凝土顶节段上表面的中央设置。As shown in Figure 13, the prefabricated reinforced concrete top section is different from the prefabricated reinforced concrete middle section in that the position of the top anchor bolt 14 embedded in the upper end is different from that of the connecting bolt 17, and the top anchor bolt 14 is located at the prefabricated reinforced concrete top section. Central setting on the upper surface of the segment.

如图14所示,连接螺栓和顶锚螺栓均可设为包括带帽螺栓23、栓帽垫板24、螺母垫板25和紧固螺母26,其中带帽螺栓23、栓帽垫板24用于预埋于混凝土中,安装上方的节段后,将螺母垫板25和紧固螺母26套于带帽螺栓23中紧固。As shown in Figure 14, the connecting bolt and the top anchor bolt can be set to include a cap bolt 23, a bolt cap backing plate 24, a nut backing plate 25 and a fastening nut 26, wherein the cap bolt 23, the bolt cap backing plate 24 are used After being pre-embedded in concrete and installing the upper segment, the nut backing plate 25 and the fastening nut 26 are sleeved in the cap bolt 23 for fastening.

本实施例中的预制钢管混凝土与钢筋混凝土拼装桥墩各组件的制作方法,如图9所示,不同于实施例1中的步骤:The manufacturing method of each component of the prefabricated steel pipe concrete and reinforced concrete assembled pier in this embodiment, as shown in Figure 9, is different from the steps in Embodiment 1:

(1)制作钢管混凝土节段2:固定连接器9变为固定连接锚栓17,其它操作不变;(1) Making the steel pipe concrete segment 2: the fixed connector 9 becomes the fixed connection anchor bolt 17, and other operations remain unchanged;

(2)制作钢筋混凝土中间节段:连接钢板18开设通孔、焊接连接锚筋19,制作模板和钢筋骨架(纵向钢筋10和箍筋),固定连接钢板18、连接螺栓17,设置连接处后浇筑混凝土空腔,在模板内浇筑混凝土,形成预制钢筋混凝土中间节段3;(2) Make the reinforced concrete middle section: connect the steel plate 18 to open through holes, weld and connect the anchor bar 19, make the formwork and steel bar skeleton (longitudinal steel bar 10 and stirrup), fix the connecting steel plate 18, connecting bolt 17, after setting the joint Pouring the concrete cavity, pouring concrete in the formwork to form the prefabricated reinforced concrete middle segment 3;

(3)制作钢筋混凝土顶节段:连接钢板18开设通孔、焊接连接锚筋19,制作模板、钢筋骨架(纵向钢筋10和箍筋),固定顶锚螺栓14,设置连接处后浇筑混凝土空腔,在模板内浇筑混凝土,形成预制钢筋混凝土顶节段4。(3) Make the reinforced concrete top section: connect the steel plates 18 to open through holes, weld and connect the anchor bars 19, make formwork, steel bar skeletons (longitudinal steel bars 10 and stirrups), fix the top anchor bolts 14, and pour concrete voids after setting the joints. Cavity, concrete is poured in the template to form the prefabricated reinforced concrete top section 4.

组件安装步骤如下:Component installation steps are as follows:

(1)将预制钢管混凝土节段2通过预埋底锚螺栓5固定在桥墩基础1上;(1) Fix the prefabricated steel pipe concrete segment 2 on the pier foundation 1 through the embedded bottom anchor bolt 5;

(2)将预制钢筋混凝土中间节段3放到预制钢管混凝土节段2上,预制钢管混凝土节段2上的连接螺栓17穿入预制钢筋混凝土中间节段3中连接钢板18的预留的通孔,并用紧固螺母固定;(2) Put the prefabricated reinforced concrete middle section 3 on the prefabricated steel pipe concrete section 2, and the connecting bolts 17 on the prefabricated steel pipe concrete section 2 penetrate into the reserved passage of the connecting steel plate 18 in the prefabricated reinforced concrete middle section 3 holes, and fixed with fastening nuts;

(3)将预制钢筋混凝土中间节段3放到另一预制钢筋混凝土中间节段3上,预制钢筋混凝土中间节段3上的连接螺栓17穿入相邻的钢筋混凝土中间节段中连接钢板18的预留的通孔,并用螺母垫板和紧固螺母固定;(3) Put the prefabricated reinforced concrete intermediate section 3 on another prefabricated reinforced concrete intermediate section 3, and the connecting bolts 17 on the prefabricated reinforced concrete intermediate section 3 penetrate the connecting steel plate 18 in the adjacent reinforced concrete intermediate section The reserved through hole, and fixed with the nut backing plate and fastening nut;

(4)将预制钢筋混凝土顶节段4放到预制钢筋混凝土中间节段3的上方,通过螺母将二者固定,(4) Put the prefabricated reinforced concrete top section 4 above the prefabricated reinforced concrete middle section 3, and fix the two by nuts,

(5)将盖梁13置于预制钢筋混凝土顶节段4上,预制钢筋混凝土顶节段4上的预埋顶锚螺栓穿过盖梁13的预留的通孔,用螺母垫板和紧固螺母固定;(5) Place the cover beam 13 on the prefabricated reinforced concrete top segment 4, the pre-embedded top anchor bolts on the prefabricated reinforced concrete top segment 4 pass through the reserved through hole of the cover beam 13, and use the nut backing plate and tight Fixed nut;

(6)向连接处后浇筑混凝土空腔浇筑混凝土形成连接处后浇筑混凝土20;(6) post-pouring concrete 20 to the junction after pouring concrete into the cavity to form the junction;

(7)向盖梁后浇筑混凝土空腔内浇筑混凝土形成盖梁后浇筑混凝土15,预制钢管混凝土与钢筋混凝土拼装桥墩拼接完成。(7) Concrete is poured into the post-concrete cavity of the cover beam to form the post-concrete 15 of the cover beam, and the splicing of prefabricated steel pipe concrete and reinforced concrete piers is completed.

实施例3Example 3

本实施例在实施例1的基础上,将剪力连接件16设为带孔钢板,如图15所示,带孔钢板为条带形钢板27上设有间隔等距的通孔21,通孔的设置有利于增强剪力连接件16与混凝土之间的连接,提高共同工作、变形协调的能力,带孔钢板平行焊接于钢管的内壁,且在钢管内壁上间隔布置。进一步,可以在通孔内布置钢筋,以便起到更好的连接作用,在沿钢管内一周的同一水平位置的带孔钢板的通孔中均贯穿有钢筋,形成钢筋绕钢管内壁或外壁一圈,钢筋可焊接在通孔中,进一步来加强钢管与混凝土的连接。In this embodiment, on the basis of Embodiment 1, the shear connector 16 is made as a steel plate with holes. The setting of the holes is beneficial to strengthen the connection between the shear connector 16 and the concrete, and improve the ability to work together and coordinate deformation. The steel plates with holes are welded parallel to the inner wall of the steel pipe and arranged at intervals on the inner wall of the steel pipe. Further, steel bars can be arranged in the through holes for better connection, and steel bars are penetrated in the through holes of the perforated steel plates at the same horizontal position along the inner circumference of the steel pipe to form a circle of steel bars around the inner wall or outer wall of the steel pipe. , steel bars can be welded in the through holes to further strengthen the connection between the steel pipe and the concrete.

以上所述,仅是本发明的较佳实施例而已,并非是对本发明做其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例。但是凡是未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本发明技术方案的保护范围。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention in other forms. Any skilled person who is familiar with this profession may use the technical content disclosed above to change or remodel it into an equivalent change. Example. However, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still belong to the protection scope of the technical solution of the present invention.

Claims (10)

1. a kind of Prefabricated concrete-filled steel tube and spiced by steel reinforced concrete bridge pier, it is characterised in that it includes pier footing, pre-manufactured steel Pipe concrete section, one or more prefabricated reinforced concrete interstitial segments and prefabricated reinforced concrete epimerite section, wherein, it is described Pier footing is fixedly connected with the Prefabricated concrete-filled steel tube section by means of the bottom crab-bolt set located at the pier footing, institute State in the middle of Prefabricated concrete-filled steel tube section and the prefabricated reinforced concrete interstitial segment and multiple prefabricated reinforced concretes Fixed and connected by means of connection unit between section, between prefabricated reinforced concrete interstitial segment and prefabricated reinforced concrete epimerite section Connect.
2. assembly bridge pier as claimed in claim 1, it is characterised in that the connection unit include multiple hollow connectors and The longitudinal reinforcement extended out of connector to the lower end of place prefabricated reinforced concrete interstitial segment, wherein, multiple connections Device upper side one-week interval of the prefabricated reinforced concrete interstitial segment along the Prefabricated concrete-filled steel tube section or each Set, the connector is embedded in respective concrete segment;The hollow connector includes open upper and lower side, and it is leaned on The side surface of nearly upper and lower side is provided with the injection nozzle crossed out on the outside of the section, and the injection nozzle is detachable setting, and With being connected inside the connector;
The longitudinal reinforcement is outside the position of the lower end correspondence connector of each prefabricated reinforced concrete interstitial segment In dew, the adjacent connector of the exposed longitudinal reinforcement correspondence insertion, the upper end of the longitudinal reinforcement is stretched into each correspondence At least a portion in the connector at end;
Anchor bolt is pushed up in the upper end of the prefabricated reinforced concrete epimerite section provided with pre-buried, the prefabricated reinforced concrete epimerite section The position of connector is provided with exposed longitudinal reinforcement in the lower end correspondence prefabricated reinforced concrete interstitial segment, described exposed Longitudinal reinforcement is inserted in corresponding connector, and the upper end of the longitudinal reinforcement is put down with prefabricated reinforced concrete top segments upper side OK.
3. assembly bridge pier as claimed in claim 2, it is characterised in that after the assembled bridge pier splicing, to the hollow company The injection nozzle injection grouting material of device lower end is connect, after the grouting material fills the hollow connector, is unloaded all described Injection nozzle, and it is tightly connected the injection port of the injection nozzle.
4. assembly bridge pier as claimed in claim 1, it is characterised in that the connection unit includes connecting bolt, junction steel plate With connection dowel, wherein, the connecting bolt is embedded in the Prefabricated concrete-filled steel tube section, the prefabricated reinforced concrete in advance Between section and the upper surface of prefabricated reinforced concrete epimerite section, the junction steel plate is fixed at the precast reinforced coagulation The lower end of native interstitial segment and prefabricated reinforced concrete epimerite section, the lower end of the connection dowel is fixedly connected on the company Connect in the middle of the upper surface of steel plate, the upper end of the connection dowel is bent downwardly;The correspondence connection spiral shell on the junction steel plate Bolt is provided with through hole, in the prefabricated reinforced concrete interstitial segment and the lower end correspondence institute of prefabricated reinforced concrete epimerite section The top of through hole is stated provided with the cavity for casting concrete.
5. assembly bridge pier as claimed in claim 1, it is characterised in that the assembled bridge pier also includes bent cap, the bent cap Located at the top of prefabricated reinforced concrete epimerite section, the two by being embedded in prefabricated reinforced concrete epimerite section top in advance Top anchor bolt connected with the preformed hole on the corresponding bent cap, in the top of the preformed hole provided with being used for casting concrete Cavity.
6. assembly bridge pier as claimed in claim 1, it is characterised in that the Prefabricated concrete-filled steel tube section is poured including centre There are the steel pipe, basic pading plate and multiple shear connectors of concrete, the shear connector is both secured to the steel pipe inner wall, The basic pading plate is located at the steel pipe bottom, and the area of the basic pading plate is more than the cross-sectional area of the steel pipe, And the correspondence bottom crab-bolt sets connecting hole on the basic pading plate outside the steel pipe main body projected area.
7. assembly bridge pier as claimed in claim 6, it is characterised in that the shear connector is peg, the peg Nail tip is welded on the steel pipe, the peg interlaced arrangement.
8. assembly bridge pier as claimed in claim 6, it is characterised in that the shear connector is steel plate with holes, the band Hole steel plate is the strip-form steel plate provided with multiple equally spaced vias, and the steel plate with holes is parallel to be fixed on the steel pipe inner wall.
9. assembly bridge pier as claimed in claim 1, it is characterised in that the prefabricated reinforced concrete interstitial segment and pre-manufactured steel Reinforced concrete epimerite section is provided with multiple longitudinal reinforcements, the concrete of multiple stirrups to be interior, wherein, multiple longitudinal reinforcements are close The concrete edge arranges that multiple stirrups are around the outside for being fixed on all longitudinal reinforcements, edge along one-week interval The longitudinal reinforcement is in longitudinally spaced arrangement.
10. assembly bridge pier as claimed in any one of claims 1-9 wherein, it is characterised in that the Prefabricated concrete-filled steel tube section Cross section with the prefabricated reinforced concrete interstitial segment and epimerite section is circular, square, oval or other shapes.
CN201710524593.5A 2017-06-30 2017-06-30 Precast concrete filled steel tubular and reinforced concrete piers Active CN107299588B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710524593.5A CN107299588B (en) 2017-06-30 2017-06-30 Precast concrete filled steel tubular and reinforced concrete piers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710524593.5A CN107299588B (en) 2017-06-30 2017-06-30 Precast concrete filled steel tubular and reinforced concrete piers

Publications (2)

Publication Number Publication Date
CN107299588A true CN107299588A (en) 2017-10-27
CN107299588B CN107299588B (en) 2019-02-12

Family

ID=60135684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710524593.5A Active CN107299588B (en) 2017-06-30 2017-06-30 Precast concrete filled steel tubular and reinforced concrete piers

Country Status (1)

Country Link
CN (1) CN107299588B (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118611A (en) * 2018-01-23 2018-06-05 安徽省交通控股集团有限公司 A kind of prefabricated pier, plate tubular Crossing brace connection structure
CN108149585A (en) * 2018-01-31 2018-06-12 福建工程学院 A kind of splicing construction and joining method of the pier stud segment of precast assembly bridge pier
CN109577176A (en) * 2019-01-30 2019-04-05 深圳市市政设计研究院有限公司福建分公司 A kind of combined connecting concrete pier of steel tube and its construction method
CN109811648A (en) * 2019-03-04 2019-05-28 北京工业大学 A railway solid high pier with prestressed segmental connection of prefabricated assembled segments
CN109914234A (en) * 2019-03-22 2019-06-21 西安建筑科技大学 A bolted prefabricated segmental shear-assembled concrete pier
CN110094015A (en) * 2018-01-29 2019-08-06 中铁城际规划建设有限公司 A kind of complex beam-column structure of construction
CN110409626A (en) * 2019-07-24 2019-11-05 中国十七冶集团有限公司 A kind of pre-buried hanging ring and installation process method
CN110685216A (en) * 2019-09-23 2020-01-14 福建工程学院 A RUHPC-NC composite bridge pier and its construction method
CN110847019A (en) * 2019-11-20 2020-02-28 北京工业大学 Connection method and structure of reinforced concrete hollow tube piers based on steel plate connection
CN110924291A (en) * 2019-11-19 2020-03-27 东北大学 Prefabricated stiff concrete-filled steel tube and reinforced concrete piers and construction technology
CN110952440A (en) * 2019-11-19 2020-04-03 东北大学 Prefabricated section steel concrete and reinforced concrete spliced pier and construction process
CN110965459A (en) * 2019-12-04 2020-04-07 中交路桥建设有限公司 A kind of bridge pier protection device and construction method thereof resistant to salt-alkali corrosion erosion
CN111691309A (en) * 2020-07-07 2020-09-22 郑琼华 Method for connecting bridge pier and cross beam of bridge
CN111877140A (en) * 2020-01-10 2020-11-03 中国国家铁路集团有限公司 Connecting structure for segment prefabricated assembled pier combination and construction method
CN112593480A (en) * 2020-12-18 2021-04-02 中冶南方工程技术有限公司 Plant-growing concrete assembled bridge pier
CN113356012A (en) * 2021-06-25 2021-09-07 青海省交通建设管理有限公司 Assembly type bridge structure in tunnel and construction method thereof
CN113481870A (en) * 2021-08-11 2021-10-08 柳州欧维姆机械股份有限公司 Prestressed anchoring structure system for assembling multi-segment bridge pier and assembling construction method of multi-segment bridge pier
CN114592436A (en) * 2022-03-18 2022-06-07 四川省公路规划勘察设计研究院有限公司 Pier capping beam lower support system and construction method thereof
CN114942213A (en) * 2022-07-25 2022-08-26 东北大学 Asphalt concrete permeability coefficient testing arrangement
CN115125825A (en) * 2022-06-24 2022-09-30 山东高速济青中线公路有限公司 Dry-type precast concrete bridge deck steel-concrete connection structure and manufacturing method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000314174A (en) * 1999-04-30 2000-11-14 Ken Tomomitsu Concrete support producing method
KR20120133867A (en) * 2011-06-01 2012-12-11 (주)광원아이앤디 Segmental concrete-filled-steel tube column construction method
CN105735112A (en) * 2016-04-14 2016-07-06 北京工业大学 Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier
CN105908621A (en) * 2016-06-29 2016-08-31 北京工业大学 Damage-controllable self-resetting section prefabricated assembled steel pipe concrete bridge pier and manufacturing method thereof
CN106677056A (en) * 2017-02-16 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Prefabricated double-column vase bridge pier and assembling construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000314174A (en) * 1999-04-30 2000-11-14 Ken Tomomitsu Concrete support producing method
KR20120133867A (en) * 2011-06-01 2012-12-11 (주)광원아이앤디 Segmental concrete-filled-steel tube column construction method
CN105735112A (en) * 2016-04-14 2016-07-06 北京工业大学 Bolt connection-based rapid assembling precast rectangular concrete filled steel tube bridge pier
CN105908621A (en) * 2016-06-29 2016-08-31 北京工业大学 Damage-controllable self-resetting section prefabricated assembled steel pipe concrete bridge pier and manufacturing method thereof
CN106677056A (en) * 2017-02-16 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Prefabricated double-column vase bridge pier and assembling construction method thereof

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118611A (en) * 2018-01-23 2018-06-05 安徽省交通控股集团有限公司 A kind of prefabricated pier, plate tubular Crossing brace connection structure
CN108118611B (en) * 2018-01-23 2023-10-17 安徽省交通控股集团有限公司 Prefabricated mound, board cylindric shear force prop connection structure
CN110094015A (en) * 2018-01-29 2019-08-06 中铁城际规划建设有限公司 A kind of complex beam-column structure of construction
CN108149585A (en) * 2018-01-31 2018-06-12 福建工程学院 A kind of splicing construction and joining method of the pier stud segment of precast assembly bridge pier
CN109577176A (en) * 2019-01-30 2019-04-05 深圳市市政设计研究院有限公司福建分公司 A kind of combined connecting concrete pier of steel tube and its construction method
CN109577176B (en) * 2019-01-30 2024-04-23 深圳市市政设计研究院有限公司福建分公司 Composite connection type concrete filled steel tube pier and construction method thereof
CN109811648B (en) * 2019-03-04 2021-04-02 北京工业大学 Railway solid high pier for connecting prefabricated assembled segments in prestress segmented manner
CN109811648A (en) * 2019-03-04 2019-05-28 北京工业大学 A railway solid high pier with prestressed segmental connection of prefabricated assembled segments
CN109914234A (en) * 2019-03-22 2019-06-21 西安建筑科技大学 A bolted prefabricated segmental shear-assembled concrete pier
CN109914234B (en) * 2019-03-22 2024-02-23 西安建筑科技大学 Precast segment shear-resistant spliced concrete pier connected through bolts
CN110409626A (en) * 2019-07-24 2019-11-05 中国十七冶集团有限公司 A kind of pre-buried hanging ring and installation process method
CN110685216A (en) * 2019-09-23 2020-01-14 福建工程学院 A RUHPC-NC composite bridge pier and its construction method
CN110952440A (en) * 2019-11-19 2020-04-03 东北大学 Prefabricated section steel concrete and reinforced concrete spliced pier and construction process
CN110924291A (en) * 2019-11-19 2020-03-27 东北大学 Prefabricated stiff concrete-filled steel tube and reinforced concrete piers and construction technology
CN110952440B (en) * 2019-11-19 2021-06-15 东北大学 Prefabricated section steel concrete and reinforced concrete spliced pier and construction process
CN110847019A (en) * 2019-11-20 2020-02-28 北京工业大学 Connection method and structure of reinforced concrete hollow tube piers based on steel plate connection
CN110965459A (en) * 2019-12-04 2020-04-07 中交路桥建设有限公司 A kind of bridge pier protection device and construction method thereof resistant to salt-alkali corrosion erosion
CN111877140A (en) * 2020-01-10 2020-11-03 中国国家铁路集团有限公司 Connecting structure for segment prefabricated assembled pier combination and construction method
CN111691309B (en) * 2020-07-07 2021-11-05 中交(临沂)建筑科技有限公司 Method for connecting bridge pier and cross beam of bridge
CN111691309A (en) * 2020-07-07 2020-09-22 郑琼华 Method for connecting bridge pier and cross beam of bridge
CN112593480A (en) * 2020-12-18 2021-04-02 中冶南方工程技术有限公司 Plant-growing concrete assembled bridge pier
CN112593480B (en) * 2020-12-18 2025-04-04 中冶南方工程技术有限公司 A kind of planted concrete assembled bridge pier
CN113356012A (en) * 2021-06-25 2021-09-07 青海省交通建设管理有限公司 Assembly type bridge structure in tunnel and construction method thereof
CN113481870A (en) * 2021-08-11 2021-10-08 柳州欧维姆机械股份有限公司 Prestressed anchoring structure system for assembling multi-segment bridge pier and assembling construction method of multi-segment bridge pier
CN114592436A (en) * 2022-03-18 2022-06-07 四川省公路规划勘察设计研究院有限公司 Pier capping beam lower support system and construction method thereof
CN115125825A (en) * 2022-06-24 2022-09-30 山东高速济青中线公路有限公司 Dry-type precast concrete bridge deck steel-concrete connection structure and manufacturing method thereof
CN114942213B (en) * 2022-07-25 2022-10-25 东北大学 A test device for the permeability coefficient of asphalt concrete
CN114942213A (en) * 2022-07-25 2022-08-26 东北大学 Asphalt concrete permeability coefficient testing arrangement

Also Published As

Publication number Publication date
CN107299588B (en) 2019-02-12

Similar Documents

Publication Publication Date Title
CN107299588A (en) Prefabricated concrete-filled steel tube and spiced by steel reinforced concrete bridge pier
CN107268807B (en) A prefabricated concrete-filled steel tubular column
CN107354862B (en) Prefabricated interlayer steel tube concrete and hollow steel bar concrete assembly bridge pier
CN106869316B (en) Combined frame system and construction method of beam-column flange made of concrete-filled steel tubes
CN105113389B (en) Prefabricated steel-concrete composite structure pier column member
CN108301317A (en) A kind of assembled bridge pier structure and its construction method
CN112900246A (en) Novel segment prefabricated assembled pier and assembling method thereof
CN110952440B (en) Prefabricated section steel concrete and reinforced concrete spliced pier and construction process
CN108571070B (en) Prefabricated steel tube concrete ring beam connecting structure and construction method
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN106930436B (en) A reinforced concrete shear wall with built-in prestressed steel diagonal braces
CN207228402U (en) The reinforced concrete shear wall of built-in prestress steel diagonal brace
CN108797791A (en) A kind of assembly method of upper and lower self-heat conserving external wall and floor
CN106958319A (en) Precast concrete post component and connected node
CN108678164A (en) Connect beam type Building block structure
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN114592688B (en) Construction method of oblique reinforced concrete shear wall based on equivalent rod model
CN108412120A (en) A kind of shaped steel and the building structure including the shaped steel
CN108729541B (en) Connect beam type Building block construction method
CN209293228U (en) Assembled wall foot connected node
CN209163210U (en) A kind of fashioned iron and the building structure including the fashioned iron
CN108729544B (en) Dry-and wet-type composite joint pin-connected panel construction
CN109577176A (en) A kind of combined connecting concrete pier of steel tube and its construction method
CN221030828U (en) Shear wall of steel tube concrete hidden column formwork
CN208105474U (en) A kind of assembly node of upper and lower interior wall and floor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant