[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN107288657B - The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground - Google Patents

The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground Download PDF

Info

Publication number
CN107288657B
CN107288657B CN201710660504.XA CN201710660504A CN107288657B CN 107288657 B CN107288657 B CN 107288657B CN 201710660504 A CN201710660504 A CN 201710660504A CN 107288657 B CN107288657 B CN 107288657B
Authority
CN
China
Prior art keywords
grouting
water
pipe
drainage
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710660504.XA
Other languages
Chinese (zh)
Other versions
CN107288657A (en
Inventor
张伟杰
王喆
魏久传
石守桥
尹会永
李孝朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201710660504.XA priority Critical patent/CN107288657B/en
Publication of CN107288657A publication Critical patent/CN107288657A/en
Application granted granted Critical
Publication of CN107288657B publication Critical patent/CN107288657B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,包括联合运用地质分析与地球物理探查手段,查明治理区水文地质条件;渗透失稳破坏段及影响区内支护强化;泄水降压‑分层注浆治理方案设计;泄水降压钻孔施工与分层注浆工程实施及动态调整;泄水降压孔高压大流量动水封堵;加强围岩变形监测等步骤。采用本工法施工后,通过对弱胶结岩体加固和高压大流量涌水封堵分层次、分阶段实施,有效解决了工治理工程周期长、易引发二次地质灾害的难题,提高了注浆效率,创造了良好的社会效益和经济效益。

The invention discloses a comprehensive control method for grouting in the seepage failure zone of the weakly cemented rock mass at the top of an underground project, which includes the combined use of geological analysis and geophysical exploration methods to find out the hydrogeological conditions of the treatment area; the seepage instability failure section and the affected area Support strengthening; design of drainage and pressure reduction-layered grouting treatment plan; drainage and pressure reduction drilling construction and layered grouting project implementation and dynamic adjustment; drainage and pressure reduction hole high-pressure and large-flow dynamic water sealing; strengthening enclosure Rock deformation monitoring and other steps. After this construction method is adopted, the reinforcement of weakly cemented rock mass and the plugging of high-pressure and large-flow water influx are implemented in layers and stages, which effectively solves the problem of long construction period and easy to cause secondary geological disasters, and improves grouting efficiency. , creating good social and economic benefits.

Description

The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
Technical field
The present invention relates to a kind of tunnels and underground engineering geological hazard control technology, the undergrounds such as especially a kind of tunnel tunnel Weak cementing rock mass seepage failure area sluicing decompression-delamination pour slurry comprehensive processing method at the top of engineering.
Background technique
Fault belt, packed type are inevitably passed through in the construction of the underground engineerings such as tunnel, power station, mine working The unfavorable geologic bodies such as solution cavity, all badness geologic bodies are often connected to rich water water-bearing layer, become water space and containing conduit pipe, quilt Long-term water burst is tended to occur after exposure.Trace it to its cause is that excavation disturbance causes to generate plastic failure area and free face, ground in country rock Being lauched penetration causes the fine graineds ingredient such as clay to be carried out, and the scale of conduit pipe extends with exposure duration and increased, table It is now that at one or a few places concentrate water burst;At the same time, coffer mechanics performance runs down, and top plate sedimentation, side wall convergence quickly increase Greatly, serious person causes larger landslide, and induced water inrush is dashed forward mud.In addition, western each mining area coal such as China Inner Mongol, Xinjiang Resourceful, these regional coal-bearing strata diagenesis times are short, the main cementing difference of mining coal seam adjoining rock, and in roof strata Thickness is usually dispersed with up to hundred meters of water-bearing layer.To prevent top plate water damage, top plate water-bearing layer must be carried out before working face extraction Draining hook.It is limited by cementing Rock Nature weak, intensity is low, constantly softening, argillization country rock, and companion during roof water white-out With hydraulic fracture, conduit pipe in rock mass is caused to gradually form and become the important channel type seeped under roof water;Channel extension And networking can lead to large-scale roof strata and generate displacement, partial region forms the water storages such as absciss layer in intersection containing water barrier Construction.Under the multiple factors long terms such as lithology, groundwater seepage pressure, construction, rock mass seepage failure damage type geology calamity Evil is lasting to be occurred, and underground engineering construction and operation security are seriously threatened.
The disaster of underground engineering such case mainly passes through two methods of Enhanced support and grouting and reinforcing or two methods Implement simultaneously.Presently, there are following problems: 1. supporting intensity is increasing, and cost is higher and higher, but country rock self-strength does not have It is improved, calamity source and channel is caused not to punish, there are still landslides, roof fall risk;2. country rock self-strength can be improved in slip casting, reduce Its permeability, however, gap is big, infiltration is strong, intensity is low, cementing weak feature since catastrophe area rock mass has, it is difficult to bear high Grouting pressure, static pressure grouting may cause the secondary geological disasters such as landslide by force.Therefore, the prominent discharge disaster of such underground engineering is controlled Reason needs to carry out under the premise of ensureing that roof rock mass is stablized, i.e., supporting reinforcement+reasonable grouting process conjunctive use could obtain reason The regulation effect thought.
Summary of the invention
The purpose of the present invention is exist to overcome the above-mentioned prior art to administer in weak cementing rock mass seepage failure geological disaster Such as regulation effect pay no attention to and think of the problems such as easily causing secondary disaster, provide a kind of top of underground weak cementing rock mass infiltration Destruction area slip casting integrated control method.
To achieve the above object, the present invention adopts the following technical solutions:
A kind of weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, comprising the following steps:
A) conjunctive use geological analysis and geophysical exploration about exhausted means are found out and administer area's hydrogeologic condition, comprising:
1) draws research area's hydrogeological profile, analyzes underground engineering superstratum lithology combination feature, determines and causes calamity Water-bearing layer and master control conduit pipe type;
2) carries out the work of top plate geophysical exploration about exhausted, draws a circle to approve overlying strata hydrous fluids form and range, instructs hazard management work Make;
B) seepage failure destroys supporting in section and the zone of influence and strengthens, i.e., is mutually tied using interim rigid protection with flexible support The means of conjunction destroy seepage failure and form supporting strengthening segment within the scope of section and adjacent 10 ~ 20m;
C) sluicing decompression-delamination pour slurry resolution design is enclosed that is, in roof strata hydrous fluids construction sluicing decompression hole Delamination pour slurry reinforced hole is applied around sluicing decompression hole;Injected hole point sequence is constructed, and using protrusive segmenting slip casting mode to above covering Stratum gradually reinforces from shallow to deep;Finally sluicing decompression hole slip casting is blocked;
D) it is rich sufficiently to reinforce country rock mesohigh to the sluicing decompression drilling construction and delamination pour slurry engineering construction of step C) by Weak cementing rock mass between water construction and underground engineering, inlet well arrangement and grouting parameter in the light of actual conditions dynamically adjust;
E) sluicing decompression hole high-pressure high-flow blocking in flowing water, including sluicing decompression hole are infused using sluicing-slip casting and static pressure Two stages grouting method is starched to carry out;Water burst controlling in hole is drained by tapping pipe in drain hole, steel pipe is fixed by mould bag And sluicing-slip casting stage annular diffusion space is constituted with hole wall;After grout cures, closes tapping pipe and open static pressure grouting Stage;
F) surrouding rock deformation real-time monitoring ensures that engineering safety is implemented.
The step A) in 1) specifically include the rock of the weak cementing water barrier that research causes between calamity water-bearing layer and underground engineering Property and thickness space Distribution Characteristics, qualitative analysis administer area's rock mass underground aquaporin forming process and rock mass reduction deformation original Cause judges a possibility that absciss layer occurs.
It 2) specifically includes in the step A and research area is pushed up using transient electromagnetic, geological radar geophysical exploration about exhausted method Plate is detected, and top plate rich water zone position and form are analyzed;By with hydrogeologic section joint interpretation, draw a circle to approve and absciss layer area or lead Water constructs controlling water-containing space, that is, conduit pipe range, instructs inlet well and drain hole pattern and depth.
Interim rigid protection in the step B is selected as grillage, concrete column or I-steel according to construction condition Bracing members, 1000 ~ 2000mm of every Pin spacing;The C20 gunite concrete that the flexible support uses with a thickness of 250mm thickness, it is built-in Single layer steel mesh.
The step C) in, if top plate hydrous fluids are separated strata seeper area, sluice and drop directly against construction in the middle part of absciss layer area Press hole;If surrounding rock deterioration is mainly caused by tomography class permeable structure, the decompression hole that sluices is applied in master control containing on permeable structure Trip forces underground water to be mainly discharged along drain hole so that Groundwater movement channel is truncated.
The step D) in, sluicing decompression hole is applied for the roof strata hydrous fluids in underground engineering superstratum, is let out Water decompression hole is using geological drilling rig construction elevation angle hole, and steps are as follows:
First using Noncoring drill bit aperture to 6m, the long 5m outer diameter seamless steel pipe of tripping in makees level-one orifice tube;
It is cased with the 1# mould bag processed by geotextiles on the outside of the level-one orifice tube, and mould bag is located at and is welded on level-one orifice tube On two 1# limiters between;
The 1# mould bag upper/lower terminal head is fixed on level-one outside of sleeve using wire binding mode, and lower end connects 1# Grouting Pipe;
Pass through the slip casting into 1# mould bag of 1# Grouting Pipe behind level-one orifice tube tripping in hole;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows: the cement slurry ratio of mud, that is, water and 42.5R are general Logical cement quality ratio is 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cement single slurry and Waterglass volume ratio is 2:1, and slip casting termination pressure is selected as 2.5MPa;
1# mould bag is propped up after the grout cures of injection, at the same squeeze around be crushed soft rock mass, reach level-one orifice tube with Breaking surrounding rock is closely engaged and the purpose of fixed orifice pipe;
After level-one orifice tube is fixed, constructed using Noncoring drill bit to design hole depth, the second hole of tripping in seamless steel pipe production Mouth pipe;Fixing seal is rolled up by quick-hardening cement between the second level orifice tube and level-one orifice tube;
Second level aperture length of tube is 10 ~ 15m, and 5 ~ 10m of front end is fabricated to floral tube, is drilled with multiple groups water seepage hole, has both played drilling Retaining wall effect, prevents drilling from blocking, and underground water in water abundant ground can be made to be discharged.
The step D) in, around sluicing, delamination pour slurry reinforced hole is laid in decompression drilling, lays mode according to site operation Condition is arranged as annular or rectangle;The grouting and reinforcing hole is divided into 3 sequences, wherein I sequence pitch of holes is 4 ~ 6m, II sequence hole Spacing is 2 ~ 3m, and III sequence pitch of holes is 1m, successively implements slip casting to each sequence hole according to I ~ III sequence in work progress.
Injecting paste material selects cement-sodium silicate double liquid, and grouting parameter is as follows: the cement slurry ratio of mud, that is, water and 42.5R are general Logical cement quality ratio is 0.8:1 ~ 1:1;For concentration of sodium silicate between 35 ~ 42Be, modulus is 2.3 ~ 3.0,42.5R ordinary cement list Slurry and waterglass volume ratio are 1:1 ~ 3:1, and slip casting termination pressure is selected as 2 ~ 3MPa.
The step E) in, sluicing decompression hole, which blocks, uses sluicing-slip casting and static pressure grouting two stages grouting method, including Following steps:
It is processed into tapping pipe first with seamless steel pipe, tapping pipe both ends thread is connected to each other by screw thread;
The 2# mould bag processed by geotextiles is cased on the outside of the tapping pipe of the top, and 2# mould bag is between 2# limiter;
2# mould bag upper/lower terminal head is fixed on the outside of tapping pipe using wire binding mode, and lower end connects 2# Grouting Pipe;
Tapping pipe is sent to predetermined position through screwed connection drilling machine, by drilling machine, i.e. 2# mould bag is arranged to master control in drilling 1 ~ 2m below conduit pipe position;
After tapping pipe tripping in, using 2# Grouting Pipe to 2# mould bag slip casting;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows: the cement slurry ratio of mud, that is, water and 42.5R are general Logical cement quality ratio is 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cement single slurry and Waterglass volume ratio is 2:1, and slip casting termination pressure is selected as 2 ~ 3MPa;
2# mould bag is propped up after injection grout cures, while squeezing and being crushed soft rock mass around to fix tapping pipe, and forcing Water burst is flowed out through tapping pipe in hole;
Tapping pipe lower end is connect with second level orifice tube through 1# filling adaptor;
1# filling adaptor processes two circular holes and is each passed through tapping pipe and 2# by screwed connection second level orifice tube, bottom plate Grouting Pipe installs latter three to tapping pipe and is welded and fixed;
Annular space between tapping pipe and hole wall becomes the slurries diffusion admittance of first stage slip casting;
First stage slip casting is to be let out by the 3# Grouting Pipe connecting with 1# filling adaptor in tapping pipe in sluicing-slip casting stage Implement during water, reinforces drain hole superficial part country rock;
Injecting paste material uses cement single slurry, and grouting parameter is as follows: the cement slurry ratio of mud, that is, water and 42.5R light water shale Amount is than 0.8:1~1:1,3 ~ 4MPa of grouting pressure.
After sluicing-slip casting stage terminates 48 hours, slurries gelinite is able to bear grouting pressure;
Being blocked using tapping pipe slip casting containing conduit pipe is the static pressure grouting stage, passes through screwed connection through 2# filling adaptor Sluicing tube end, water burst can be closed by closing high-pressure ball valve;
Implement static pressure grouting through 4# Grouting Pipe, static pressure grouting mainly filling tapping pipe and its exposure contain conduit pipe, And by high pressure ground water preservation space metathesis be slurries, thus reach block channel, intercept water source, reinforce the multiple mesh of water barrier 's.
Injecting paste material selects cement single slurry, and grouting parameter is as follows: the cement slurry ratio of mud, that is, water and 42.5R light water shale Amount is than 0.8:1~1:1,4 ~ 5MPa of grouting pressure.
The step F) in, during drilling applies and Grouting engineering is implemented, according to country rock situation in seepage failure damage type Monitoring section is arranged in catastrophe area and the zone of influence, and catastrophe area monitoring section spacing is 3 ~ 5m, and zone of influence monitoring section is 5 ~ 10m, with Top plate sedimentation and lateral wall convergent deformation situation during supervision control engineering is implemented;Monitoring curve is drawn simultaneously, instructs the dynamic of grouting pressure State adjustment.
The beneficial effects of the present invention are: the present invention solves existing method punishment roof rock mass because of seepage failure while causing Concentrate the improvement period of the geological disasters such as water burst and rock stratum large deformation is long, effect is undesirable, easily causes secondary geological disaster etc. to ask Topic.After taking this engineering method to construct, by weak cementing rock mass reinforcing and high-pressure high-flow water burst block by different level, it is real stage by stage It applies, shortens the punishment duration of the weak cementing country rock seepage failure type geological disaster of top of underground, ensured surrounding rock consolidation model It encloses and intensity, especially centralized high voltage big flow concentrates water burst area country rock to be reinforced by different level, avoid mandatory static pressure note Secondary geological disaster caused by slurry occurs, and effectively increases governance quality, creates good Social benefit and economic benefit.
Detailed description of the invention
Fig. 1 is construction technology process block diagram of the invention;
Fig. 2 is the diagrammatic cross-section of resolution of the present invention;
Fig. 3 is sluicing decompression hole structural schematic diagram of the invention;
Fig. 4 is that sluicing decompression hole of the invention blocks schematic diagram;
In figure, 1, rich water water-bearing layer;2, weak cementing rock mass (relative water resisting layer);3, the underground space;4, separated strata seeper area;5, Permeable structure;6, sluicing decompression hole;7, interim rigid protection;8, temporary flexible supporting;9, delamination pour slurry reinforced hole;10, level-one Orifice tube;11,1# mould bag;12,1# limiter;13,1# Grouting Pipe;14, second level orifice tube;15, overflow hole;16, quick-hardening cement Volume;17, tapping pipe;18,2# mould bag;19,2# limiter;20,2# Grouting Pipe;21,1# filling adaptor;22, slurries diffusion annular Space;23,3# Grouting Pipe;24,2# filling adaptor;25, high-pressure ball valve;26,4# Grouting Pipe;27, monitoring section.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
This specification structure depicted in this specification institute accompanying drawings, ratio, size etc., only to cooperate specification revealed interior Hold, so that those skilled in the art understands and reads, is not intended to limit the invention enforceable qualifications, therefore does not have skill Essential meaning in art, the modification of any structure, the change of proportionate relationship or the adjustment of size can be produced not influencing the present invention Under raw effect and the purpose that can reach, should all still it fall in the range of disclosed technology contents obtain and can cover. Meanwhile cited such as "upper" in this specification, "lower", "left", "right", " centre " and " one " term, be merely convenient to Narration is illustrated, rather than to limit the scope of the invention, relativeness is altered or modified, without substantive change Under technology contents, when being also considered as the enforceable scope of the present invention.
As Figure 1-Figure 4, the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, including with Lower step:
1, conjunctive use geological analysis and geophysical exploration about exhausted means are found out and administer area's hydrogeologic condition
According to the geological prospecting borehole data near the underground engineerings such as tunnel or tunnel, draws and administer area's large scale hydrology Log sheet analyzes the lithology combination feature and geological structure developmental state of superstratum, determines 1 layer of cause calamity water-bearing layer (body) Position and geological structure type.Research causes the weak cementing rock mass (relative water resisting layer) 2 between calamity water-bearing layer (body) 1 and underground engineering 3 Lithology and thickness space Distribution Characteristics, qualitative analysis administer area's rock mass underground aquaporin forming process and rock mass reduction deformation The reason of, judge a possibility that absciss layer 4 occurs.
Research area's top plate is detected using the geophysical exploration about exhausted such as transient electromagnetic, geological radar method, analyzes top plate Rich water zone position and form.By with hydrogeologic section joint interpretation, draw a circle to approve the controllings such as absciss layer area 4 or permeable structure 5 contain Hydrospace (conduit pipe) range, instructs inlet well and drain hole pattern and depth.
2, seepage failure destroys supporting in section and the zone of influence and strengthens
Section and adjacent 10 ~ 20m model are destroyed to seepage failure using the means that interim rigid protection is combined with flexible support Enclose interior formation supporting strengthening segment.
The interim rigid protection can be selected as grillage according to construction condition, cross section is the mixed of 500 × 500mm Solidifying earth pillar or 25b I-steel bracing members, 1000 ~ 2000mm of every Pin spacing.The flexible support uses thick with a thickness of 250mm C20 gunite concrete, the long steel mesh multiplied by wide 400m × 400m, φ 8mm of built-in single layer.
3, sluicing decompression-delamination pour slurry resolution design
According to geological analysis and geophysical exploration about exhausted synthesis result, in roof strata hydrous fluids construction sluicing decompression hole 6.Institute The purpose is to reduce roof overburden mesohigh water during slip casting to prevent roof strata to the penetration of rock stratum for the sluicing decompression hole 6 stated It is middle to form the Lentic environment for sealing high pressure and country rock compressive deformation is caused to destroy.
If top plate hydrous fluids are separated strata seeper area 4, directly against sluicing decompression hole of constructing in the middle part of absciss layer area;
If surrounding rock deterioration is mainly caused by the permeable structures such as tomography 5, the decompression hole that sluices is applied in master control structure containing water guide Upstream is made, Groundwater movement channel is truncated, underground water is forced mainly to be discharged along drain hole.
Delamination pour slurry reinforced hole 9 is applied around sluicing decompression hole 6, injected hole point sequence is constructed, and using protrusive segmentation note Slurry mode gradually reinforces superstratum from shallow to deep.Finally sluicing decompression hole slip casting is blocked, completes harnessing project.
4, sluice decompression drilling construction and delamination pour slurry engineering construction and dynamic adjustment
Sluicing decompression hole is applied for the concentration hydrous fluids in underground engineering superstratum, sluicing decompression hole 6 uses geology Drilling machine construction elevation angle hole, step are as follows:
First using outer diameter φ 168mm Noncoring drill bit aperture to 6m, the long 5m outer diameter φ 146mm seamless steel pipe of tripping in makees level-one Orifice tube 10.
It is cased with the 1# mould bag 11 processed by geotextiles on the outside of level-one orifice tube, and mould bag is located at and is welded on level-one orifice tube Two 1# limiters 12 between.
11 upper/lower terminal head of 1# mould bag is fixed on level-one outside of sleeve using wire binding mode, and lower end connects 1# note Starch pipe 13.
Pass through the slip casting into 1# mould bag 11 of 1# Grouting Pipe 13 behind level-one orifice tube tripping in hole.
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows: (water is common with 42.5R for the cement slurry ratio of mud Cement quality ratio) it is 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cement single slurry and Waterglass volume ratio is 2:1, and slip casting termination pressure is selected as 2.5MPa.
The grout cures back brace molding bag of injection, while squeezing and being around crushed soft rock mass, reach level-one orifice tube and breaking Broken country rock is closely engaged and the purpose of fixed orifice pipe.
After level-one orifice tube is fixed, constructed using outer diameter φ 137mm Noncoring drill bit to design hole depth, tripping in outer diameter φ The second level orifice tube 14 of 108mm seamless steel pipe production.
Second level aperture length of tube is fixed according to the actual situation, and generally 10 ~ 15m, 5 ~ 10m of front end is fabricated to floral tube, is drilled with more Group water seepage hole 15, both plays the role of borehole wall-protection, prevents drilling from blocking, and underground water in water abundant ground can be made to be discharged.
16 fixing seals are rolled up by quick-hardening cement between second level orifice tube 14 and level-one orifice tube, which is known Engineering method;After the completion of the construction of sluicing decompression hole, disaster area underground water mainly passes through drain hole centralized discharge, and other locations of country rock are seeped Discharge reduction.
It is depressured drilling laying delamination pour slurry reinforced hole around sluicing, laying mode is arranged as annular according to construction condition Or rectangle.
Grouting and reinforcing hole is divided into 3 sequences, wherein I sequence hole, 3 spacing is 4 ~ 6m, II sequence hole, 4 spacing is 2 ~ 3m, III sequence hole 5 spacing are 1m, successively implement slip casting to each sequence hole according to I ~ III sequence in work progress.
Grouting process is protrusive segmenting slip casting technique, and this method is known engineering method, is repeated no more.
Injecting paste material selects cement-sodium silicate double liquid, and grouting parameter is as follows: (water is common with 42.5R for the cement slurry ratio of mud Cement quality ratio) it is 0.8:1 ~ 1:1;For concentration of sodium silicate between 35 ~ 42Be, modulus is 2.3 ~ 3.0,42.5R ordinary cement list Slurry and waterglass volume ratio are 1:1 ~ 3:1, and slip casting termination pressure is selected as 2 ~ 3MPa.Above-mentioned grout coordinate ratio and grouting parameter are Applicant is obtained by long-term engineering practice and summary of experience, ensure that slip casting effect.
Sluicing decompression drilling hole amount, position etc. can be adjusted according to field condition;Inlet well lays mode, grouting sequence Dynamic need to be needed to adjust according to scene.
5, sluicing decompression hole high-pressure high-flow blocking in flowing water
After underground engineering roof cracking rock mass is reinforced, the sluicing decompression hole as concentration issue need to be sealed in time It is stifled.Water burst has high-pressure high-flow feature in sluicing decompression hole, and long-time water burst will cause to wash away to hole wall rock mass, and cause to infuse It starches stabilization zone rock mass water content to increase, slip casting effect reduces under long term, or even seepage failure damage type disaster occurs again. In addition, the presence of sluicing decompression hole will lead to operating condition deterioration unless being used as dewatering orifice, it is unfavorable for keeping the safety in production, therefore must It need be blocked.
Sluicing decompression hole is blocked to be carried out using sluicing-slip casting and static pressure grouting two stages grouting method.
It is processed into the tapping pipe 17 of single long 1500mm first with the seamless steel pipe of outer diameter Φ 63.5mm, wall thickness 8mm, lets out Water pipe both ends thread, is connected to each other by screw thread.The 2# mould bag 18 processed by geotextiles, and 2# are cased on the outside of the tapping pipe of the top Mould bag is between 2# limiter 19.
2# mould bag upper/lower terminal head is fixed on the outside of tapping pipe using wire binding mode, and lower end connects 2# Grouting Pipe 20。
Tapping pipe is sent to predetermined position through screwed connection drilling machine, by drilling machine, i.e. 2# mould bag 18 is arranged to main in drilling 1 ~ 2m below conduct aquaporin position.
After tapping pipe tripping in, using 2# Grouting Pipe 20 to 19 slip casting of 2# mould bag.
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows: (water is common with 42.5R for the cement slurry ratio of mud Cement quality ratio) it is 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cement single slurry and Waterglass volume ratio is 2:1, and slip casting termination pressure is selected as 2 ~ 3MPa.
2# mould bag is propped up after injection grout cures, while squeezing and being crushed soft rock mass around to fix tapping pipe, and forcing Water burst is flowed out through tapping pipe in hole.
17 lower end of tapping pipe is connect with second level orifice tube through 1# filling adaptor 21.1# filling adaptor passes through screwed connection second level Orifice tube, bottom plate process two circular holes and are each passed through tapping pipe 17 and 2# Grouting Pipe 20, install latter three to tapping pipe It is welded and fixed.
Annular space 22 between tapping pipe 17 and hole wall becomes the slurries diffusion admittance of first stage slip casting.
First stage slip casting be sluicing-slip casting stage sluiced by the 3# Grouting Pipe 23 being connect with 1# filling adaptor Pipe is implemented under the conditions of sluicing, and reinforces drain hole superficial part country rock.Injecting paste material uses cement single slurry, and grouting parameter is as follows: cement Pulp-water gray scale (water and 42.5R ordinary cement mass ratio) 0.8:1~1:1,3 ~ 4MPa of grouting pressure.
After sluicing-slip casting stage terminates 48 hours, slurries gelinite has some strength, and Surrounding Rock Strength is higher, Neng Goucheng By grouting pressure.
Being blocked using tapping pipe slip casting containing conduit pipe is the static pressure grouting stage.
Through 2# filling adaptor 24 by screwed connection sluicing tube end, water burst can be closed by closing high-pressure ball valve 25.Through 4# Grouting Pipe 26 implements static pressure grouting, and static pressure grouting is mainly the conduit pipe that contains for filling tapping pipe and its exposure, and by underground water Existing space metathesis is slurries, blocks channel to reach, intercepts water source, reinforce the multipurpose of water barrier.Injecting paste material Cement single slurry is selected, grouting parameter is as follows: the cement slurry ratio of mud (water and 42.5R ordinary cement mass ratio) 0.8:1~1:1, 4 ~ 5MPa of grouting pressure.
6, surrouding rock deformation real-time monitoring ensures that engineering safety is implemented
During drilling applies and Grouting engineering is implemented, according to country rock situation in seepage failure damage type catastrophe area and the zone of influence Arrange monitoring section, catastrophe area monitoring section spacing is 3 ~ 5m, and zone of influence monitoring section is 5 ~ 10m, implements the phase with supervision control engineering Between top plate sedimentation and lateral wall convergent deformation situation.Monitoring curve is drawn simultaneously, the dynamic of grouting pressure is instructed to adjust.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not protects model to the present invention The limitation enclosed, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not Need to make the creative labor the various modifications or changes that can be made still within protection scope of the present invention.

Claims (10)

1.一种地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是, 包括以下步骤:1. a comprehensive control method for grouting in the permeation failure zone of weakly cemented rock mass at the top of an underground project, is characterized in that, comprises the following steps: A). 联合运用地质分析与地球物理探查手段,查明治理区水文地质条件,包括:A). Combine geological analysis and geophysical exploration methods to identify the hydrogeological conditions of the treatment area, including: 1).绘制研究区水文地质剖面图,分析地下工程上覆地层岩性组合特征,确定致灾含水层及主控导水通道类型;1) Draw the hydrogeological profile of the study area, analyze the lithological combination characteristics of the overlying strata of the underground engineering, and determine the type of the disaster-causing aquifer and the main control water channel; 2).进行顶板地球物理探查工作,圈定覆岩富水区形态和范围,指导灾害治理工作;2) Carry out the geophysical exploration of the roof, delineate the shape and scope of the overlying rock and water-rich area, and guide the disaster management work; B). 渗透失稳破坏段及影响区内支护强化,即采用临时刚性支护与柔性支护相结合的手段对渗透失稳破坏段及相邻10~20m范围内形成支护强化段;B). Strengthening of the support in the seepage instability failure section and the affected area, that is, the combination of temporary rigid support and flexible support is used to form the support reinforcement section in the seepage instability failure section and the adjacent 10-20m range; C). 泄水降压-分层注浆治理方案设计,即在顶板岩层富水区施工泄水降压孔,围绕泄水降压孔施作分层注浆加固孔,注浆孔分序施工,且采用前进式分段注浆方式对上覆地层由浅而深逐步加固;最后将泄水降压孔注浆封堵;C). Design of drainage and depressurization-layered grouting treatment plan, that is, to construct drainage and decompression holes in the water-rich area of the roof rock layer, and to construct layered grouting reinforcement holes around the drainage and decompression holes, and the grouting holes are sequenced. construction, and the overlying stratum is gradually strengthened from shallow to deep by means of forward segmented grouting; finally, the drainage and pressure relief holes are grouted and plugged; D). 对步骤C)的泄水降压孔施工与分层注浆工程实施,充分加固围岩中高压含水构造与地下工程之间的弱胶结岩体充,注浆钻孔布置及注浆参数按照实际情况动态调整;D). Carry out the construction of the drainage and pressure relief hole and the layered grouting project in step C), fully reinforce the weakly cemented rock mass between the high-pressure water-bearing structure in the surrounding rock and the underground engineering, grouting drilling arrangement and grouting The parameters are dynamically adjusted according to the actual situation; E). 泄水降压孔高压大流量动水封堵,包括泄水降压孔采用泄水-注浆和静压注浆两阶段注浆方法进行;泄水降压孔内通过泄水管将孔内涌水控制性排泄,钢管通过模袋固定并与孔壁构成泄水-注浆阶段的环形扩散空间;待浆液凝固后,封闭泄水管并开启静压注浆阶段;E). The drainage and pressure relief holes are sealed with high pressure and large flow of dynamic water, including the drainage and pressure relief holes using the two-stage grouting method of drainage - grouting and static pressure grouting; Controlled drainage of water in the hole, the steel pipe is fixed by the mold bag and forms an annular diffusion space in the drainage-grouting stage with the hole wall; after the slurry solidifies, the drainage pipe is closed and the static pressure grouting stage is started; F). 围岩变形实时监测,保障工程安全实施。F). Real-time monitoring of surrounding rock deformation to ensure the safe implementation of the project. 2.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤A)中1)具体包括研究致灾含水层与地下工程之间的弱胶结隔水层的岩性及厚度空间展布特征,定性分析治理区岩体地下水通道形成过程以及岩体弱化变形的原因,评判离层发生的可能性。2. The comprehensive control method for grouting in the seepage failure zone of the weakly cemented rock mass at the top of the underground engineering according to claim 1, wherein 1) in the step A) specifically includes studying the relationship between the disaster-causing aquifer and the underground engineering. The lithology and thickness spatial distribution characteristics of the weakly cemented aquifer, qualitatively analyze the formation process of groundwater channels in the rock mass in the treatment area and the reasons for the weakening and deformation of the rock mass, and judge the possibility of separation. 3.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤A中2)具体包括利用瞬变电磁、地质雷达地球物理探查方法对研究区顶板进行探查,分析顶板富水区位置及形态;通过与水文地质剖面联合解释,圈定离层区或导水构造控制性含水空间即导水通道范围,指导注浆钻孔及泄水降压孔布孔方式及深度。3. The comprehensive control method for grouting in the permeation failure zone of weakly cemented rock mass at the top of an underground project as claimed in claim 1, wherein 2) in the step A specifically includes using transient electromagnetic and geological radar geophysical exploration methods to The roof of the study area is explored to analyze the location and shape of the water-rich area on the roof; through joint interpretation with the hydrogeological profile, the delineation zone or water-conducting structure-controlled water-bearing space, that is, the water-conducting channel range, is used to guide grouting drilling and drainage and drainage. Press hole layout method and depth. 4.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤B中的临时刚性支护根据现场施工条件选择为木垛、混凝土柱或工字钢钢支撑,每榀间距1000~2000mm;所述柔性支护采用厚度为250mm厚的C20喷射混凝土,内置单层钢筋网。4. The comprehensive control method for grouting in the penetration failure zone of weakly cemented rock mass at the top of an underground project as claimed in claim 1, wherein the temporary rigid support in the step B is selected as a wooden stack, a concrete column according to on-site construction conditions Or I-beam steel support, with a spacing of 1000~2000mm between each beam; the flexible support is made of C20 shotcrete with a thickness of 250mm, with a built-in single-layer steel mesh. 5.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤C)中,若顶板富水区为离层积水区,则直接针对离层区中部施工泄水降压孔;若围岩劣化主要是由断层类导水构造引起,则泄水降压孔施作于主控含导水构造上游,以截断地下水运移通道,迫使地下水主要沿泄水降压孔排出。5. The comprehensive control method for grouting in the seepage failure zone of the weakly cemented rock mass at the top of the underground engineering according to claim 1, wherein in the step C), if the water-rich zone on the roof is a layered water zone, then directly For the construction of drainage and pressure relief holes in the middle of the separation zone; if the deterioration of surrounding rock is mainly caused by fault-type water-conducting structures, the drainage and pressure-reducing holes should be installed upstream of the main control water-conducting structure to cut off the groundwater migration channel. The groundwater is forced to be discharged mainly along the drainage and pressure relief holes. 6.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤D)中,针对地下工程上覆地层内的顶板岩层富水区施作泄水降压孔,泄水降压孔采用地质钻机施工仰角孔,步骤如下:6. The comprehensive control method for grouting in the penetration failure zone of the weakly cemented rock mass at the top of the underground project according to claim 1, wherein in the step D), the water-rich zone of the roof rock layer in the overlying stratum of the underground project is applied. As drainage and pressure relief holes, the drainage and pressure relief holes are constructed with geological drilling rigs as elevation holes. The steps are as follows: 首先使用无芯钻头开孔至6m,下入长5m外径无缝钢管作一级孔口管;First, use a coreless drill to drill a hole to 6m, and run a 5m long outer diameter seamless steel pipe as a first-level orifice pipe; 所述一级孔口管外侧套有由土工布加工的1#模袋,且模袋位于焊接在一级孔口管上的两个1#限位器之间;The outer side of the first-level orifice pipe is covered with a 1# mold bag processed by geotextile, and the mold bag is located between two 1# limiters welded on the first-level orifice pipe; 所述1#模袋上、下两端头采用钢丝捆扎方式固定在一级套管外侧,下端头连接1#注浆管;The upper and lower ends of the 1# mold bag are fixed on the outside of the primary casing by means of wire bundling, and the lower end is connected to the 1# grouting pipe; 一级孔口管下入孔后通过1#注浆管向1#模袋内注浆;After the first-level orifice pipe is lowered into the hole, grouting is carried out into the 1# mold bag through the 1# grouting pipe; 注浆材料采用水泥-水玻璃双液浆,注浆参数如下:水泥浆水灰比即水与42.5R普通水泥质量比为1:1;水玻璃浓度在35~42Be之间,模数为2.3~3.0,42.5R普通水泥单液浆和水玻璃体积比为2:1,注浆终止压力选择为2.5MPa;The grouting material adopts cement-water glass double-liquid slurry. The grouting parameters are as follows: the water-cement ratio of the cement slurry, that is, the mass ratio of water to 42.5R ordinary cement, is 1:1; the water glass concentration is between 35~42Be, and the modulus is 2.3 ~3.0, the volume ratio of 42.5R ordinary cement single slurry and water glass is 2:1, and the final pressure of grouting is selected as 2.5MPa; 注入的浆液凝固后撑起1#模袋,同时挤压周围破碎软弱岩体,达到一级孔口管与破碎围岩紧密咬合且固定孔口管的目的;After the injected slurry solidifies, the 1# mold bag is propped up, and the surrounding broken and weak rock mass is squeezed at the same time, so as to achieve the purpose of tightly engaging the first-level orifice pipe with the broken surrounding rock and fixing the orifice pipe; 一级孔口管固定后,使用无芯钻头施工至设计孔深,下入无缝钢管制作的二级孔口管;所述的二级孔口管和一级孔口管之间通过快硬水泥卷固定密封。After the first-level orifice pipe is fixed, use a coreless drill to construct the designed hole depth, and then lower the second-level orifice pipe made of seamless steel pipe; between the second-level orifice pipe and the first-level orifice pipe The cement roll is fixed and sealed. 7.如权利要求6所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述二级孔口管长度为10~15m,前端5~10m制作成花管,钻设多组渗水孔。7. The comprehensive control method for grouting in the permeation failure zone of weakly cemented rock mass at the top of an underground project as claimed in claim 6, wherein the length of the secondary orifice pipe is 10 to 15 m, and the front end 5 to 10 m is made into a flower tube , drill multiple groups of seepage holes. 8.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤D)中,围绕泄水降压孔布设分层注浆加固孔,布设方式根据现场施工条件布置为环形或矩形;所述的注浆加固孔划分为3个序列,其中Ⅰ序孔间距为4~6m,Ⅱ序孔间距为2~3m,Ⅲ序孔间距为1m,施工过程中按照Ⅰ~Ⅲ的顺序依次对各序孔实施注浆;8 . The comprehensive control method for grouting in the penetration failure zone of weakly cemented rock mass at the top of an underground project according to claim 1 , wherein in the step D), layered grouting reinforcement holes are arranged around the drainage and pressure relief holes, The layout method is arranged in a ring or rectangle according to the site construction conditions; the grouting reinforcement holes are divided into 3 sequences, among which the hole spacing of sequence I is 4~6m, the spacing of sequence II holes is 2~3m, and the spacing of sequence III holes is 1m , in the construction process, grouting is carried out for each sequence hole in sequence according to the order of I~III; 注浆材料选用水泥-水玻璃双液浆,注浆参数如下:水泥浆水灰比即水与42.5R普通水泥质量比为0.8:1~1:1;水玻璃浓度在35~42Be之间,模数为2.3~3.0,42.5R普通水泥单液浆和水玻璃体积比为1:1~3:1,注浆终止压力选择为2~3MPa。The grouting material is cement-water glass double-liquid slurry. The grouting parameters are as follows: the water-cement ratio of the cement slurry, that is, the mass ratio of water to 42.5R ordinary cement, is 0.8:1~1:1; the water glass concentration is between 35~42Be, The modulus is 2.3~3.0, the volume ratio of 42.5R ordinary cement single slurry and water glass is 1:1~3:1, and the final pressure of grouting is 2~3MPa. 9.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤E)中,泄水降压孔封堵采用泄水-注浆和静压注浆两阶段注浆方法,包括以下步骤:9 . The comprehensive control method for grouting in the seepage failure zone of weakly cemented rock mass at the top of an underground project according to claim 1 , wherein in the step E), the drainage and pressure relief holes are blocked by drainage-grouting and The two-stage grouting method of hydrostatic grouting includes the following steps: 首先利用无缝钢管加工成泄水管,泄水管两端车丝,通过丝扣彼此连接;First, the seamless steel pipe is used to process the drain pipe, and the two ends of the drain pipe are threaded and connected to each other through the thread; 最上端泄水管外侧套有由土工布加工的2#模袋,且2#模袋位于2#限位器之间;The outer side of the top drain pipe is covered with a 2# mold bag made of geotextile, and the 2# mold bag is located between the 2# limiters; 2#模袋上、下两端头采用钢丝捆扎方式固定在泄水管外侧,下端头连接2#注浆管;The upper and lower ends of the 2# mold bag are fixed on the outside of the drain pipe by means of wire bundling, and the lower end is connected to the 2# grouting pipe; 泄水管经丝扣连接钻机,通过钻机被送至预定位置,即2#模袋安置到钻孔内主控导水通道位置以下1~2m;The drain pipe is connected to the drilling rig through the thread, and is sent to the predetermined position through the drilling rig, that is, the 2# mold bag is placed 1~2m below the position of the main control water guiding channel in the drilling hole; 泄水管下入后,利用2#注浆管向2#模袋注浆;After the drain pipe is put in, use the 2# grouting pipe to inject grouting into the 2# mold bag; 注浆材料采用水泥-水玻璃双液浆,注浆参数如下:水泥浆水灰比即水与42.5R普通水泥质量比为1:1;水玻璃浓度在35~42Be之间,模数为2.3~3.0,42.5R普通水泥单液浆和水玻璃体积比为2:1,注浆终止压力选择为2~3MPa;The grouting material adopts cement-water glass double-liquid slurry. The grouting parameters are as follows: the water-cement ratio of the cement slurry, that is, the mass ratio of water to 42.5R ordinary cement, is 1:1; the water glass concentration is between 35~42Be, and the modulus is 2.3 ~3.0, the volume ratio of 42.5R ordinary cement single slurry and water glass is 2:1, and the final pressure of grouting is selected as 2~3MPa; 注入浆液凝固后撑起2#模袋,同时挤压周围破碎软弱岩体以固定泄水管,并迫使孔内涌水经泄水管流出;After the injected slurry solidifies, hold up the 2# mold bag, squeeze the surrounding broken and weak rock mass to fix the drain pipe, and force the water in the hole to flow out through the drain pipe; 泄水管下端与二级孔口管经1#注浆接头连接;The lower end of the drain pipe is connected with the secondary orifice pipe through a 1# grouting joint; 1#注浆接头通过丝扣连接二级孔口管,其底板加工两个圆孔分别穿过泄水管及2#注浆管,待泄水降压孔固定后三者焊接固定;The 1# grouting joint is connected to the secondary orifice pipe through a thread, and two round holes are machined on the bottom plate to pass through the drain pipe and the 2# grouting pipe respectively. After the drain and pressure relief holes are fixed, the three are welded and fixed; 泄水管与孔壁之间的环形空间成为第一阶段注浆的浆液扩散通道;The annular space between the drain pipe and the hole wall becomes the slurry diffusion channel of the first stage grouting; 第一阶段注浆为泄水-注浆阶段,通过与1#注浆接头连接的3#注浆管,在泄水管泄水条件下实施,加固泄水降压孔浅部围岩;The first stage of grouting is the water discharge-grouting stage, through the 3# grouting pipe connected with the 1# grouting joint, under the condition of water discharge from the discharge pipe, to reinforce the shallow surrounding rock of the discharge and pressure relief hole; 注浆材料采用水泥单液浆,注浆参数如下:水泥浆水灰比即水与42.5R普通水泥质量比0.8:1~1:1,注浆压力3~4MPa;The grouting material adopts cement single-liquid slurry, and the grouting parameters are as follows: the water-cement ratio of the cement slurry, that is, the mass ratio of water to 42.5R ordinary cement is 0.8:1~1:1, and the grouting pressure is 3~4MPa; 泄水-注浆阶段结束48小时后,浆液凝胶体能够承受注浆压力;48 hours after the end of the drainage-grouting stage, the slurry gel can withstand the grouting pressure; 利用泄水管注浆封堵含导水通道即为静压注浆阶段,经2#注浆接头通过丝扣连接泄水管端部,关闭高压球阀即可封闭涌水;The hydrostatic grouting stage is the stage of static pressure grouting by grouting the drain pipe to block the water-conducting channel. The end of the drain pipe is connected by the screw thread through the 2# grouting joint, and the water gushing can be closed by closing the high-pressure ball valve; 经4#注浆管实施静压注浆,静压注浆主要是充填泄水管及其揭露的含导水通道,并将地下水存在的空间置换为浆液,从而达到封堵通道,堵截水源,加固隔水层的多重目的;The static pressure grouting is carried out through the 4# grouting pipe. The static pressure grouting mainly fills the drain pipe and the exposed water-conducting channel, and replaces the space where the groundwater exists with slurry, so as to block the channel, block the water source, and reinforce the The multiple purposes of the aquifer; 注浆材料选择水泥单液浆,注浆参数如下:水泥浆水灰比即水与42.5R普通水泥质量比0.8:1~1:1,注浆压力4~5MPa。The grouting material is cement single-liquid slurry, and the grouting parameters are as follows: the water-cement ratio of the cement slurry, that is, the mass ratio of water to 42.5R ordinary cement is 0.8:1~1:1, and the grouting pressure is 4~5MPa. 10.如权利要求1所述的地下工程顶部弱胶结岩体渗透破坏区注浆综合控制方法,其特征是,所述步骤F)中,钻孔施作及注浆工程实施期间,根据围岩情况在渗透失稳破坏型灾变区及影响区布置监测断面,灾变区监测断面间距为3~5m,影响区监测断面为5~10m,以监控工程实施期间顶板沉降及侧帮收敛变形情况;同时绘制监测曲线,指导注浆压力的动态调整。10. The comprehensive control method for grouting in the permeation failure zone of the weakly cemented rock mass at the top of an underground project according to claim 1, wherein in the step F), during the drilling operation and the grouting project implementation, according to the surrounding rock The monitoring section is arranged in the seepage instability and damage type disaster area and the affected area. The distance between the monitoring sections in the disaster area is 3~5m, and the monitoring section in the affected area is 5~10m, so as to monitor the roof settlement and the lateral side convergence deformation during the implementation of the project; Draw a monitoring curve to guide the dynamic adjustment of grouting pressure.
CN201710660504.XA 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground Active CN107288657B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710660504.XA CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710660504.XA CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Publications (2)

Publication Number Publication Date
CN107288657A CN107288657A (en) 2017-10-24
CN107288657B true CN107288657B (en) 2019-01-29

Family

ID=60105256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710660504.XA Active CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Country Status (1)

Country Link
CN (1) CN107288657B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956225A (en) * 2017-11-22 2018-04-24 中国煤炭地质总局水文地质局 Discarded small-size coal mine top panel area administers the processing method for reducing the increment of groundwater
CN108487918B (en) * 2018-03-06 2019-04-02 山东科技大学 Tunneling and underground engineering wall-rock crack water grouting treatment design method
CN108412498B (en) * 2018-03-06 2019-04-02 山东科技大学 Freeze sinking construction pit shaft annular causes calamity channel grouting treatment design method
CN108915736B (en) * 2018-07-13 2020-04-24 中煤科工集团西安研究院有限公司 Method for preventing and controlling water damage of roadway tunneling under strong water-rich and weak-cementation aquifer
CN109611109B (en) * 2018-11-05 2019-12-24 青岛市地铁一号线有限公司 Method and system for advanced control of disaster sources in tunnel TBM construction through broken zone
CN109611146B (en) * 2018-11-29 2020-10-13 山东科技大学 Separation layer water drainage grouting method
CN110331994B (en) * 2019-04-30 2023-08-15 宁夏久威矿山安全工程有限责任公司 Method for preventing and controlling water spraying of separation broken roof of tunneling roadway
CN110159307A (en) * 2019-05-16 2019-08-23 北京市政建设集团有限责任公司 A kind of tunnel multilayer grouting process
CN110017155B (en) * 2019-05-23 2020-11-06 合肥工业大学 Grouting reinforcement water-proof method for water-rich gravel layer of top plate of coal face
CN110499757A (en) * 2019-08-27 2019-11-26 中铁二局集团有限公司 A kind of water-rich sand layer three axes agitating pile construction method
CN110905556B (en) * 2019-12-20 2021-01-05 山东科技大学 A high-efficiency mixed-alternating double-hole segmented grouting method
CN112281878B (en) * 2020-08-28 2021-07-09 浙大城市学院 Positioning grouting reinforcement method for groundwater seepage damage control in foundation pit engineering
CN112049139B (en) * 2020-08-28 2021-07-09 浙大城市学院 Drainage grouting guide pipe and using method thereof
CN112832810B (en) * 2021-03-04 2022-03-22 淮北市平远软岩支护工程技术有限公司 Support method for fractured-interval argillization rheological rock mass
CN114737883A (en) * 2022-04-08 2022-07-12 山东万祥矿业有限公司 Construction technology of hydrological observation hole and casing of hydrological observation hole
CN114837608B (en) * 2022-05-31 2022-12-23 中国矿业大学 Multi-stage graded grouting method for rebuilding mined overlying rock water-resisting layer

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101839139A (en) * 2010-02-09 2010-09-22 铁道部工程管理中心 Information tracking grouting method
CN102493822A (en) * 2011-12-29 2012-06-13 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN104370508A (en) * 2014-10-15 2015-02-25 山东科技大学 Coal mine floor rock mass grouting reinforcement method and grouting slurry
CN105625292A (en) * 2016-02-03 2016-06-01 山东科技大学 Grouting reinforcement effect three-dimensional spatial data acquisition method for weak broken rock body

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02215887A (en) * 1989-02-17 1990-08-28 Taguchi Kenkyusho:Kk Grouting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101839139A (en) * 2010-02-09 2010-09-22 铁道部工程管理中心 Information tracking grouting method
CN102493822A (en) * 2011-12-29 2012-06-13 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN104370508A (en) * 2014-10-15 2015-02-25 山东科技大学 Coal mine floor rock mass grouting reinforcement method and grouting slurry
CN105625292A (en) * 2016-02-03 2016-06-01 山东科技大学 Grouting reinforcement effect three-dimensional spatial data acquisition method for weak broken rock body

Also Published As

Publication number Publication date
CN107288657A (en) 2017-10-24

Similar Documents

Publication Publication Date Title
CN107288657B (en) The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN108915736B (en) Method for preventing and controlling water damage of roadway tunneling under strong water-rich and weak-cementation aquifer
CN107060834B (en) Drainage and slow seepage grouting control technology under water-rich and broken condition of roadway roof
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN109595029B (en) Local filling support structure and its construction method in goaf under hard roof condition
CN104533452B (en) A kind of underground coal mine crushes coal body stagewise grouting strengthening method
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
JP5182922B2 (en) Water stop grout method and system under high water pressure
CN105201448A (en) Method for water-stopping grouting plugging in high-pressure high-flow water gush channel
CN108678772A (en) A kind of multilevel hierarchy suspension device and its construction method for rich water sandy gravel stratum tunnel
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN101638987A (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
CN105155563A (en) Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit
CN104453943A (en) Method for controlling water-rich fractured rock mass comprehensive grouting under effective sealing batholite shortage condition
CN103867229A (en) Coal mine large-mining-depth and next-group coal exploitation water control comprehensive treatment method
CN103628912A (en) Goaf management filling grouting construction method
CN107513995A (en) A kind of bridge struction pile post grouting construction method
Zhou et al. Effect of localized water pressure on mountain tunnels crossing fracture zone
CN107339108A (en) The layer of sand location subway pipe shed construction method of underground water enrichment
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN107060821A (en) A kind of many lithology method for protecting support of face
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant