CN107165664A - A kind of slope thick seam tunnels superelevation stope drift active workings Qie Dingliu lanes method along top - Google Patents
A kind of slope thick seam tunnels superelevation stope drift active workings Qie Dingliu lanes method along top Download PDFInfo
- Publication number
- CN107165664A CN107165664A CN201710559245.1A CN201710559245A CN107165664A CN 107165664 A CN107165664 A CN 107165664A CN 201710559245 A CN201710559245 A CN 201710559245A CN 107165664 A CN107165664 A CN 107165664A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- coal
- roadway
- shaped steel
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/0004—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor along the working face
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/0004—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor along the working face
- E21D23/0013—Frame type supports
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
- E21D23/0472—Supports specially adapted for people walking or transporting material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
- E21D23/06—Special mine caps or special tops of pit-props for permitting step-by-step movement
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
本发明涉及一种倾斜厚煤层沿顶掘进超高回采巷道切顶留巷的方法,采用分阶段联合掘进与控制技术,具体方法是:掘进回采巷道,采用锚网索联合支护;工作面回采前,对工作面前方回采巷道施工切顶锚索与切顶钻孔,之后进行卧底扩刷断面,补齐巷帮支护,同时在高帮侧挂网,对巷道施以“单体液压支柱+铰接顶梁+U型钢棚+木垛”加强支护;工作面回采期间,对高帮退锚,回收端头三角煤,在架后铺网,并连接高帮网片,形成切顶留巷并实现复用。本发明简单易行,可有效解决支护结构防推倒、煤帮片帮等问题,实现了巷道复用和支护材料回收,增加了端头三角煤回收率,降低生产成本,具有良好的经济和社会效益。
The invention relates to a method for excavating a super-high recovery roadway along the top of an inclined thick coal seam and cutting the top and retaining the roadway. It adopts the stage-by-stage joint excavation and control technology. Before the construction of the mining roadway in front of the working face, the top-cutting anchor cable and the top-cutting drilling will be carried out, and then the undercover section will be expanded and brushed, and the roadside support will be repaired. +Hinged roof beam+U-shaped steel shed+wooden stack" to strengthen support; during the mining face, remove the anchor for the high side, recover the triangular coal at the end, lay the mesh behind the frame, and connect the high side mesh to form a top-cut roof Lane and achieve multiplexing. The invention is simple and easy to implement, can effectively solve the problems of supporting structures such as anti-teardown, coal side slabs, etc., realizes roadway reuse and support material recovery, increases the recovery rate of triangular coal at the end, reduces production costs, and has good economic efficiency. and social benefits.
Description
技术领域technical field
本发明涉及煤矿开采及巷道掘进与支护技术,特别是一种倾斜厚煤层沿顶掘进超高回采巷道切顶留巷的方法。The invention relates to coal mine mining and roadway excavation and support technology, in particular to a method for excavating a super-high mining roadway along the top of an inclined thick coal seam by cutting the top and retaining the roadway.
背景技术Background technique
沿空留巷作为无煤柱护巷的一种布置方式,具有提高煤炭资源回收率、降低巷道掘进率、缓解工作面采掘接续紧张等优点,在煤矿生产中被广泛应用。但是,对于高瓦斯厚煤层沿空留巷,为方便工作面回采,回采巷道常采用沿底掘进方式,极易造成上隅角瓦斯积聚、顶板下沉等问题,给矿井安全生产带来了严重挑战。如果采用沿顶掘进方式,又会出现工作面端头三角煤大量损失的问题,增加了煤炭资源的损失量。Gobside entry retaining, as a layout method without coal pillars, has the advantages of improving the recovery rate of coal resources, reducing the rate of roadway excavation, and alleviating the tension of continuous excavation at the working face, etc., and is widely used in coal mine production. However, for gob-side entry retention in high gassy thick coal seams, in order to facilitate the mining of the working face, the mining roadway is often excavated along the bottom, which can easily cause problems such as gas accumulation in the upper corner and roof sinking, which has brought serious problems to mine safety. challenge. If the method of tunneling along the top is adopted, the problem of a large loss of triangular coal at the end of the working face will occur again, which increases the loss of coal resources.
基于上述分析,沿顶掘进回采巷道、增加留巷高度、调整端头割煤角度等措施可有效解决上述问题,为此,本发明从现场生产实际出发,解决了超高巷道支护、煤帮片帮和冒落矸石进入巷道等问题,为沿顶掘进超高回采巷道沿空留巷提供了切实可行的途径。Based on the above analysis, measures such as excavating the recovery roadway along the top, increasing the height of the roadway, and adjusting the angle of coal cutting at the end can effectively solve the above problems. Problems such as sidewalls and falling gangue entering the roadway provide a practical way to keep the goaf along the top of the super-high mining roadway.
发明内容Contents of the invention
针对上述情况,为克服现有技术的缺陷,本发明提供了一种倾斜厚煤层沿顶掘进超高回采巷道切顶留巷方法,采用“锚网索+单体液压支柱+铰接顶梁+U型钢棚+木垛”分阶段联合掘进与控制技术,有效地解决了支护结构防推倒、煤帮片帮、冒落矸石进入巷道等问题,实现了单体液压支柱、铰接顶梁和U型钢等支护材料的回收利用,增加了工作面端头三角煤的回收率。In view of the above situation, in order to overcome the defects of the prior art, the present invention provides a method for cutting the top and retaining the roadway of the ultra-high recovery roadway excavating along the top of the inclined thick coal seam. The joint excavation and control technology of section steel shed + wooden pile" effectively solved the problems of anti-teardown of support structure, coal gangue gangue, and falling gangue into the roadway, and realized the single hydraulic prop, hinged roof beam and U-shaped steel Recycling and utilization of support materials, etc., increases the recovery rate of the triangular coal at the end of the working face.
本发明解决的技术方案是,包括以下步骤:The technical scheme that the present invention solves is, comprises the following steps:
(1)工作面回采巷道掘进期间,巷道沿顶掘进,巷道断面(宽×高)为4700mm×3500mm,断面高度为巷道中心线处高度,采用锚网索联合支护;(1) During the mining roadway excavation of the working face, the roadway is excavated along the top, the roadway section (width × height) is 4700mm × 3500mm, the height of the section is the height of the centerline of the roadway, and the joint support of the anchor net cable is used;
(2)工作面回采前,对工作面前方回采巷道施工切顶钻孔,使巷道顶板与工作面顶板可以顺利断开,保证巷道顶板的完整与稳定,切顶钻孔深度为15m,施工结束后,对顶板施工切顶锚索,对巷道实煤体帮进行锚索加强支护,然后卧底扩刷断面并补齐锚杆,扩大后巷道断面(宽×高)为4700mm×5500mm,扩刷断面后巷道变成超高巷道,减少了端头的三角煤,有效提高了工作面的回采率;(2) Before the mining of the working face, the top cutting drilling shall be carried out in the mining roadway in front of the working face, so that the roof of the roadway and the roof of the working face can be disconnected smoothly to ensure the integrity and stability of the roof of the roadway. The depth of the top cutting drilling is 15m, and the construction ends Finally, cut the anchor cable on the roof, strengthen the anchor cable support on the solid coal side of the roadway, and then expand the section undercover and fill up the anchor rod. The roadway after the section becomes a super-high roadway, which reduces the triangle coal at the end and effectively improves the recovery rate of the working face;
(3)对新掘出的巷道实煤体帮进行锚索加强支护,然后在巷道高帮侧顶板的切顶锚索上挂网,初次挂网的高度与巷道高帮平齐,使网片覆盖巷道高帮;(3) Strengthen the anchor cable support for the newly excavated roadway solid coal side, and then hang the mesh on the top-cut anchor cable of the side roof of the roadway high side. roadway high top;
(4)对巷道采取“单体液压支柱+铰接顶梁+U型钢棚+木垛”加强支护;(4) Adopt "single hydraulic prop + hinged roof beam + U-shaped steel shed + wooden pile" to strengthen the support of the roadway;
(5)工作面回采期间,对高帮退锚,回收端头的三角煤,根据采煤机性能,尽可能地增加端头的割煤角度,以提高端头三角煤的回收率,割煤完成后,移架并在支架后方铺设金属网,将网片与高帮网片连接,防止冒落矸石进入巷道,形成切顶留巷并实现复用。(5) During the mining of the working face, remove the anchor of the high side and recover the triangular coal at the end. According to the performance of the shearer, increase the coal cutting angle of the end as much as possible to improve the recovery rate of the triangular coal at the end. After the completion, move the frame and lay metal mesh behind the support, connect the mesh with the high-top mesh to prevent the falling gangue from entering the roadway, form the roof cut and retain the roadway and realize reuse.
本发明简单易行,可有效解决支护结构防推倒等巷道支护相关问题,实现切顶留巷及复用,并可回收利用单体液压支柱、铰接顶梁和U型钢等支护材料,增加工作面端头三角煤的回收率,最大程度的降低成本,取得良好的经济和社会效益。The invention is simple and easy to implement, can effectively solve the problems related to roadway support such as anti-teardown of the support structure, realize roof cutting and retain roadway and reuse, and can recycle supporting materials such as single hydraulic props, hinged roof beams and U-shaped steel, Increase the recovery rate of the triangular coal at the end of the working face, reduce the cost to the greatest extent, and achieve good economic and social benefits.
附图说明Description of drawings
图1 为本发明回采巷道掘进完成时的示意图;Fig. 1 is the schematic diagram when the mining roadway excavation of the present invention is completed;
图2 为本发明回采巷道采取超前卧底扩刷断面后的示意图;Fig. 2 is the schematic diagram after the mining roadway of the present invention adopts the undercover expansion brush section in advance;
图3 为本发明工作面回采后切顶留巷的示意图。Fig. 3 is a schematic diagram of cutting the roof and retaining the roadway after mining in the working face of the present invention.
具体实施方式detailed description
以下结合附图和具体情况对本发明的具体实施方式作详细说明。The specific implementation of the present invention will be described in detail below in conjunction with the accompanying drawings and specific conditions.
由图1-3所示,本发明在具体实施中,由以下步骤实现:Shown in Fig. 1-3, the present invention is realized by the following steps in concrete implementation:
(1)工作面回采巷道掘进期间,巷道沿顶板1掘进,巷道底部水平,两帮竖直,顶部沿岩层倾角倾斜,去除伪顶,巷道断面(宽×高)为4700mm×3500mm,断面高度为巷道中心线处高度,采用锚网索联合支护4;(1) During the mining roadway excavation of the working face, the roadway is excavated along the roof 1, the bottom of the roadway is horizontal, the two sides are vertical, the top is inclined along the inclination angle of the rock formation, and the false roof is removed. The height at the centerline of the roadway is supported by anchor net cable joint support 4;
(2)工作面回采前,对工作面前方回采巷道,在巷道高帮2侧顶部边缘,施工切顶钻孔6,使巷道顶板与工作面顶板可以顺利断开,保证巷道顶板的完整与稳定,切顶钻孔6深度为15m,施工结束后,在顶板1靠近巷道高帮2侧补打两根切顶锚索14,在巷道实煤体帮2适当位置,倾斜向上补打一根加强锚索5,补打的各根锚索须确保锚固在老顶上,然后卧底扩刷断面并补齐锚杆,扩大后巷道断面(宽×高)为4700mm×5500mm,扩刷断面后巷道变成超高巷道,减少了端头的三角煤,有效提高了工作面的回采率,根据现场实际,超前施工的距离可以选在10m-40m之间;(2) Before the mining of the working face, in the mining roadway in front of the working face, the top edge of the roadway high side 2 side is top-cut and drilled 6, so that the roof of the roadway and the roof of the working face can be disconnected smoothly, ensuring the integrity and stability of the roof of the roadway , the depth of the top cutting drill hole 6 is 15m. After the construction is completed, two top cutting anchor cables 14 are added on the side of the roof 1 close to the high side of the roadway 2, and a reinforcement is installed on the side of the roadway solid coal body side 2 at an appropriate position. Anchor cable 5. The repaired anchor cables must be anchored on the old roof, and then the undercover section will be expanded and the anchor rods will be repaired. Form a super-high roadway, reduce the triangular coal at the end, and effectively improve the recovery rate of the working face. According to the actual situation on site, the distance of advanced construction can be selected between 10m-40m;
(3)对新掘出的巷道实煤体帮3进行锚索加强支护,在巷道实煤体帮3下部适当位置,倾斜向下补打一根加强锚索5,然后在巷道高帮2侧顶部的切顶锚索14上挂金属网11,初次挂网的高度与巷道高帮2平齐,使金属网11覆盖巷道高帮2;(3) Carry out anchor cable reinforcement support for the newly excavated solid coal body side 3 of the roadway. At an appropriate position at the lower part of the roadway solid coal body side 3, a reinforced anchor cable 5 is installed obliquely downward, and then a reinforced anchor cable 5 is installed on the roadway high side 2 Hang the metal mesh 11 on the top-cut anchor cable 14 at the top of the side, and the height of the initial hanging mesh is flush with the high side 2 of the roadway, so that the metal mesh 11 covers the high side 2 of the roadway;
(4)对巷道进行“单体液压支柱7+铰接顶梁9+U型钢棚8+木垛12”加强支护,方法是,在距巷道实煤体帮500mm处设置单体液压支柱7,间隔适当距离再设置一个单体液压支柱7,在单体液压支柱7上方架设U型钢顶梁,在巷道高帮2侧架设U型钢棚腿,且与U型钢顶梁用卡缆10连接成一体,形成U型钢棚8,控制冒落矸石13产生的水平推力,U型钢棚8高度为4500mm,巷道高帮2侧挂的金属网11置于U型钢棚8外,移动后架设的单体液压支柱7至距巷道实煤体帮1000mm处,并在单体液压支柱7上增加铰接顶梁9,增加单体液压支柱7的支护面积,形成单体液压支柱7+铰接顶梁9+U型钢棚8支护结构,U型钢棚8上方未接顶位置采用木垛12背实,减少顶板变形空间,最终形成“单体液压支柱7+铰接顶梁9+U型钢棚8+木垛12”加强支护;(4) Strengthen the support of the roadway with "single hydraulic prop 7 + hinged top beam 9 + U-shaped steel shed 8 + wooden pile 12". Set up a single hydraulic prop 7 at an appropriate distance, erect a U-shaped steel roof beam on the top of the single hydraulic prop 7, and erect U-shaped steel shed legs on the side of the roadway high side 2, and connect the U-shaped steel roof beam with a card cable 10 to form a whole , forming a U-shaped steel shed 8 to control the horizontal thrust generated by the falling gangue 13. The height of the U-shaped steel shed 8 is 4500mm, and the metal mesh 11 hung on the side of the roadway high side 2 is placed outside the U-shaped steel shed 8. From the pillar 7 to the distance of 1000mm from the solid coal body of the roadway, add a hinged roof beam 9 to the single hydraulic pillar 7 to increase the supporting area of the single hydraulic pillar 7, forming a single hydraulic pillar 7 + hinged roof beam 9 + U The supporting structure of 8-shaped steel shed, and the position above the U-shaped steel shed 8 that is not connected to the roof is backed by wooden piles 12 to reduce the deformation space of the roof, and finally form a "single hydraulic prop 7 + hinged roof beam 9 + U-shaped steel shed 8 + wooden piles 12 "Strengthen support;
(5)工作面回采期间,对巷道高帮2退锚,回收端头的三角煤,根据采煤机的性能,要尽可能地增加端头的割煤角度,以提高端头三角煤的回收率,割煤完成后,移架并在支架后方铺设金属网11,将网片与高帮网片连接,防止冒落矸石13进入巷道,形成切顶留巷并实现复用。(5) During the mining of the working face, withdraw the anchor of the roadway high side 2 and recover the triangular coal at the end. According to the performance of the shearer, the coal cutting angle at the end should be increased as much as possible to improve the recovery of the triangular coal at the end After the coal cutting is completed, the frame is moved and the metal mesh 11 is laid behind the support, and the mesh is connected with the high-top mesh to prevent the falling gangue 13 from entering the roadway, forming a top-cut roadway and realizing reuse.
本发明简单易行,可有效解决支护结构防推倒等巷道支护相关问题,实现切顶留巷及复用,并可回收利用单体液压支柱、铰接顶梁和U型钢等支护材料,增加工作面端头三角煤的回收率,最大程度的降低成本,取得良好的经济和社会效益。The invention is simple and easy to implement, can effectively solve the problems related to roadway support such as anti-teardown of the support structure, realize roof cutting and retain roadway and reuse, and can recycle supporting materials such as single hydraulic props, hinged roof beams and U-shaped steel, Increase the recovery rate of the triangular coal at the end of the working face, reduce the cost to the greatest extent, and achieve good economic and social benefits.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710559245.1A CN107165664B (en) | 2017-07-11 | 2017-07-11 | A method of roof cutting and retaining roadway for super-high mining roadway excavation along the top of inclined thick coal seam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710559245.1A CN107165664B (en) | 2017-07-11 | 2017-07-11 | A method of roof cutting and retaining roadway for super-high mining roadway excavation along the top of inclined thick coal seam |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107165664A true CN107165664A (en) | 2017-09-15 |
CN107165664B CN107165664B (en) | 2019-04-30 |
Family
ID=59823766
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710559245.1A Active CN107165664B (en) | 2017-07-11 | 2017-07-11 | A method of roof cutting and retaining roadway for super-high mining roadway excavation along the top of inclined thick coal seam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107165664B (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107630700A (en) * | 2017-10-25 | 2018-01-26 | 山西晋煤集团技术研究院有限责任公司 | A kind of superelevation tunnel " first choose and dig afterwards " is into lane method |
CN108049896A (en) * | 2017-12-19 | 2018-05-18 | 河南力行科创矿山技术开发有限公司 | A method for retaining gob-side entry in fully mechanized caving face |
CN108150170A (en) * | 2017-12-27 | 2018-06-12 | 中国矿业大学(北京) | The Support Method with sinking along bottom back is administered along top Floor Heave in Roadway |
CN108316925A (en) * | 2018-04-16 | 2018-07-24 | 河南理工大学 | A kind of thick disconnected simple gob-side entry retaining method in top of directly top working face drilling of three-soft seam |
CN108643907A (en) * | 2018-05-11 | 2018-10-12 | 山东科技大学 | One kind being crushed direct top edge sky caving into lane without pillar mining method |
CN108661640A (en) * | 2018-03-12 | 2018-10-16 | 张庆振 | Half-edge coal seam longwall top coal caving technique based on the U-shaped horizontal ventilation in artificial tunnel |
CN108798723A (en) * | 2018-06-29 | 2018-11-13 | 河南理工大学 | A kind of superelevation stope drift active workings method for protecting support of the coal containing jacking applied to high seam |
CN108868833A (en) * | 2018-06-29 | 2018-11-23 | 河南理工大学 | A method of it carries out cutting gob side entry retaining in the relieving roadway of top in U-shaped steel supported laneway |
CN112610218A (en) * | 2020-12-02 | 2021-04-06 | 中国矿业大学(北京) | Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method |
CN113669095A (en) * | 2021-08-02 | 2021-11-19 | 中国矿业大学 | A kind of advanced support method applied to super high section of mining roadway |
CN113982626A (en) * | 2021-10-14 | 2022-01-28 | 中煤能源研究院有限责任公司 | Method for calculating supporting resistance of roof in gob-side entry retaining roadway without coal pillar roof cutting |
CN114704314A (en) * | 2021-12-23 | 2022-07-05 | 中国矿业大学 | A kind of large inclination angle loose and soft coal seam roadway high-top collaborative anchoring structure and construction method |
CN114738026A (en) * | 2022-04-18 | 2022-07-12 | 兖矿能源集团股份有限公司 | Coal face end support method |
CN114810122A (en) * | 2022-05-05 | 2022-07-29 | 江苏徐矿能源股份有限公司张双楼煤矿 | Method for arranging all-high roadway and supporting top plate for one-time mining of inclined thick coal seam |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101280684A (en) * | 2008-05-12 | 2008-10-08 | 淮南矿业(集团)有限责任公司 | Surrounding rock support method for retaining roadway in goaf under three-soft geological conditions |
CN104405392A (en) * | 2014-10-16 | 2015-03-11 | 河南理工大学 | Three-soft thick coal seam roadway top-support bottom-retaining anchor-net cable active supporting fully-mechanized caving mining method |
CN104594926A (en) * | 2014-11-27 | 2015-05-06 | 太原理工大学 | Rapid composite roof roadway support method for high-stress water guiding karst cave group |
CN104929666A (en) * | 2015-04-30 | 2015-09-23 | 中国矿业大学 | Top breaking gob-side entry retaining method for tender roofs |
CN105134212A (en) * | 2015-08-10 | 2015-12-09 | 河南理工大学 | Method for ensuring fully-mechanized top coal caving recovery rate of three-soft thick coal seam roadway tunneling along top |
CN205349380U (en) * | 2016-02-03 | 2016-06-29 | 山西古县老母坡煤业有限公司 | Prevent whole crest truncation support of gob entry pucking |
CN206000543U (en) * | 2016-08-26 | 2017-03-08 | 百色百矿集团有限公司 | A kind of supporting construction protecting lane for gob side entry retaining |
-
2017
- 2017-07-11 CN CN201710559245.1A patent/CN107165664B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101280684A (en) * | 2008-05-12 | 2008-10-08 | 淮南矿业(集团)有限责任公司 | Surrounding rock support method for retaining roadway in goaf under three-soft geological conditions |
CN104405392A (en) * | 2014-10-16 | 2015-03-11 | 河南理工大学 | Three-soft thick coal seam roadway top-support bottom-retaining anchor-net cable active supporting fully-mechanized caving mining method |
CN104594926A (en) * | 2014-11-27 | 2015-05-06 | 太原理工大学 | Rapid composite roof roadway support method for high-stress water guiding karst cave group |
CN104929666A (en) * | 2015-04-30 | 2015-09-23 | 中国矿业大学 | Top breaking gob-side entry retaining method for tender roofs |
CN105134212A (en) * | 2015-08-10 | 2015-12-09 | 河南理工大学 | Method for ensuring fully-mechanized top coal caving recovery rate of three-soft thick coal seam roadway tunneling along top |
CN205349380U (en) * | 2016-02-03 | 2016-06-29 | 山西古县老母坡煤业有限公司 | Prevent whole crest truncation support of gob entry pucking |
CN206000543U (en) * | 2016-08-26 | 2017-03-08 | 百色百矿集团有限公司 | A kind of supporting construction protecting lane for gob side entry retaining |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107630700A (en) * | 2017-10-25 | 2018-01-26 | 山西晋煤集团技术研究院有限责任公司 | A kind of superelevation tunnel " first choose and dig afterwards " is into lane method |
CN107630700B (en) * | 2017-10-25 | 2019-07-30 | 山西晋煤集团技术研究院有限责任公司 | A kind of superelevation tunnel " first choose and dig afterwards " is at lane method |
CN108049896A (en) * | 2017-12-19 | 2018-05-18 | 河南力行科创矿山技术开发有限公司 | A method for retaining gob-side entry in fully mechanized caving face |
CN108150170A (en) * | 2017-12-27 | 2018-06-12 | 中国矿业大学(北京) | The Support Method with sinking along bottom back is administered along top Floor Heave in Roadway |
CN108661640B (en) * | 2018-03-12 | 2019-05-24 | 张庆振 | Half-edge coal seam longwall top coal caving technique based on artificial tunnel U-shaped horizontal ventilation |
CN108661640A (en) * | 2018-03-12 | 2018-10-16 | 张庆振 | Half-edge coal seam longwall top coal caving technique based on the U-shaped horizontal ventilation in artificial tunnel |
CN108316925A (en) * | 2018-04-16 | 2018-07-24 | 河南理工大学 | A kind of thick disconnected simple gob-side entry retaining method in top of directly top working face drilling of three-soft seam |
CN108316925B (en) * | 2018-04-16 | 2023-12-12 | 河南理工大学 | Simple gob-side entry retaining method for drilling and roof breaking of working face with three-soft coal layer thickness direct roof |
CN108643907B (en) * | 2018-05-11 | 2020-02-25 | 山东科技大学 | A method for mining without coal pillars by caving roof with broken direct roof along the air |
CN108643907A (en) * | 2018-05-11 | 2018-10-12 | 山东科技大学 | One kind being crushed direct top edge sky caving into lane without pillar mining method |
CN108798723A (en) * | 2018-06-29 | 2018-11-13 | 河南理工大学 | A kind of superelevation stope drift active workings method for protecting support of the coal containing jacking applied to high seam |
CN108868833A (en) * | 2018-06-29 | 2018-11-23 | 河南理工大学 | A method of it carries out cutting gob side entry retaining in the relieving roadway of top in U-shaped steel supported laneway |
CN112610218A (en) * | 2020-12-02 | 2021-04-06 | 中国矿业大学(北京) | Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method |
CN112610218B (en) * | 2020-12-02 | 2022-05-13 | 中国矿业大学(北京) | Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method |
CN113669095A (en) * | 2021-08-02 | 2021-11-19 | 中国矿业大学 | A kind of advanced support method applied to super high section of mining roadway |
CN113982626B (en) * | 2021-10-14 | 2023-08-22 | 中煤能源研究院有限责任公司 | Calculation method for roof supporting resistance in gob-side entry retaining roadway without coal pillar roof cutting |
CN113982626A (en) * | 2021-10-14 | 2022-01-28 | 中煤能源研究院有限责任公司 | Method for calculating supporting resistance of roof in gob-side entry retaining roadway without coal pillar roof cutting |
CN114704314A (en) * | 2021-12-23 | 2022-07-05 | 中国矿业大学 | A kind of large inclination angle loose and soft coal seam roadway high-top collaborative anchoring structure and construction method |
CN114704314B (en) * | 2021-12-23 | 2023-08-22 | 中国矿业大学 | High-slope cooperative anchoring structure of large-inclination-angle soft coal seam roadway and construction method |
CN114738026A (en) * | 2022-04-18 | 2022-07-12 | 兖矿能源集团股份有限公司 | Coal face end support method |
CN114810122A (en) * | 2022-05-05 | 2022-07-29 | 江苏徐矿能源股份有限公司张双楼煤矿 | Method for arranging all-high roadway and supporting top plate for one-time mining of inclined thick coal seam |
CN114810122B (en) * | 2022-05-05 | 2024-04-26 | 江苏徐矿能源股份有限公司张双楼煤矿 | Method for arranging inclined thick coal seam one-time mining full-height roadway and supporting roof |
Also Published As
Publication number | Publication date |
---|---|
CN107165664B (en) | 2019-04-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107165664A (en) | A kind of slope thick seam tunnels superelevation stope drift active workings Qie Dingliu lanes method along top | |
CN108643907B (en) | A method for mining without coal pillars by caving roof with broken direct roof along the air | |
CN100577986C (en) | Surrounding rock support method for retaining roadway in goaf under three-soft geological conditions | |
CN101372891B (en) | Strip filling integral backstopping coal mining method | |
CN103161480B (en) | Initiatively support the method for roadside packing gob side entry retaining | |
CN110939466B (en) | Pier stud non-blasting roof cutting gob-side entry driving method | |
CN103470261B (en) | The method of gob side entry driving under the former back in mining goaf | |
CN110529144B (en) | A hybrid advance support method for small section mining roadway | |
CN105804748B (en) | A kind of method of block mining Wall ore under open air transport system | |
CN105952453B (en) | Longwell protrusive working face of coal seam mechanization exploits complete set of equipments without lane | |
CN104533419B (en) | Method for partial recovery of residual coal from wide coal pillar | |
CN107091091A (en) | A kind of steeply-inclined seam mining gob-side entry retaining method of prefabricated arc support | |
CN109882172B (en) | Gob-side entry retaining method by using cut-off direct roof as roadside support wall | |
CN102678123A (en) | Gob-side entry retaining method for thin coal layer under hard limestone top plate | |
CN108951647A (en) | Construction method for supporting is excavated in hole in the hole of open trench tunnel | |
CN108843339B (en) | The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs | |
CN110118085A (en) | A kind of compound advanced secondary tunneling method in two lane of top working face of large mining depth high working face | |
CN205422777U (en) | A gob entry support system for roof is unstable | |
CN207348862U (en) | A kind of comprehensive pick construction system | |
CN113847055B (en) | A roadway layout and support method for down-mining coal seam groups at extremely short distances | |
CN111828015B (en) | Roadway construction method | |
CN108104813B (en) | A kind of coal-mining method by roof collapse area | |
CN106948836B (en) | Breaking surrounding rock stope drift active workings method for protecting support in a kind of three-soft seam goaf | |
CN104453966A (en) | large mining height end-mining fully-mechanized excavating machine manufacturing removing frame channel collapse column passing leg-less supporting erecting construction method | |
CN111173512B (en) | A method of retaining half-way along the gob |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20210511 Address after: 225000 Industrial Concentration Zone of Chenji Town, Yizheng City, Yangzhou City, Jiangsu Province Patentee after: YANGZHOU ZHONGKUANG BUILDING NEW MATERIAL TECHNOLOGY Co.,Ltd. Address before: 454000 2001 Century Road, hi tech Zone, Jiaozuo, Henan Patentee before: HENAN POLYTECHNIC University |