CN106995016B - A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration - Google Patents

A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration Download PDF

Info

Publication number
CN106995016B
CN106995016B CN201710096643.4A CN201710096643A CN106995016B CN 106995016 B CN106995016 B CN 106995016B CN 201710096643 A CN201710096643 A CN 201710096643A CN 106995016 B CN106995016 B CN 106995016B
Authority
CN
China
Prior art keywords
track
spliced
climbing
antifreeze
buildings
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710096643.4A
Other languages
Chinese (zh)
Other versions
CN106995016A (en
Inventor
郑义恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Dongye New Material Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710096643.4A priority Critical patent/CN106995016B/en
Priority to HK17103078.0A priority patent/HK1232391A2/en
Priority to US15/598,263 priority patent/US20180238063A1/en
Publication of CN106995016A publication Critical patent/CN106995016A/en
Priority to PCT/CN2017/101219 priority patent/WO2018153057A1/en
Application granted granted Critical
Publication of CN106995016B publication Critical patent/CN106995016B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • B66B9/02Kinds or types of lifts in, or associated with, buildings or other structures actuated mechanically otherwise than by rope or cable
    • B66B9/022Kinds or types of lifts in, or associated with, buildings or other structures actuated mechanically otherwise than by rope or cable by rack and pinion drives
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B62LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
    • B62DMOTOR VEHICLES; TRAILERS
    • B62D57/00Vehicles characterised by having other propulsion or other ground- engaging means than wheels or endless track, alone or in addition to wheels or endless track
    • B62D57/02Vehicles characterised by having other propulsion or other ground- engaging means than wheels or endless track, alone or in addition to wheels or endless track with ground-engaging propulsion means, e.g. walking members
    • B62D57/024Vehicles characterised by having other propulsion or other ground- engaging means than wheels or endless track, alone or in addition to wheels or endless track with ground-engaging propulsion means, e.g. walking members specially adapted for moving on inclined or vertical surfaces
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F19/00Hoisting, lifting, hauling or pushing, not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B25/00Tracks for special kinds of railways
    • E01B25/02Tracks for rack railways
    • E01B25/04Rack rails; Supports or connections for rack rails
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Transportation (AREA)
  • Chemical & Material Sciences (AREA)
  • Geology (AREA)
  • Combustion & Propulsion (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Central Heating Systems (AREA)
  • Braking Arrangements (AREA)
  • Train Traffic Observation, Control, And Security (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

The present invention relates to a kind of, and the spliced antifreeze exterior walls of buildings with deceleration climbs rail system, including fixing several spliced climbing tracks, connector, climbing device and several electric heating infrared deicing devices for connecting climbing track that are attached on building, mounting plate is provided on the inside of the climbing track, outside is provided with track plates, the surrounding edge of climbing track is provided with connecting column;Two column perforations are uniformly vertically arranged on the track plates;The connecting hole for installation connecting element is provided on the connecting column;It is provided in the middle part of the connector in the side wall surface of limiting stand, connector upper and lower side and is provided with screw hole;The side wall of the connecting hole is provided with to be passed through and through-hole corresponding with screw hole for screw.A kind of spliced antifreeze exterior walls of buildings with deceleration of the present invention climbs rail system, and structurally reasonable, elevating control safety prevents to use because track freezes, improves maintenance work efficiency.

Description

A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration
Technical field
The present invention relates to climbing track field, especially a kind of spliced antifreeze exterior walls of buildings with deceleration is climbed Climbing track system.
Background technique
The track of climbing rail system is made by aluminium alloy extruded technique, and the core of a whole set of climbing system Part.Track attaches building and is permanently fixed.Track maintenance-free and is adapted to by anodized Any extreme environment.Every track section can be stitched together by rivet and track fastening.Track is by spring clip and folder Tool is fixed on building, and the connection reliability between track requires high;Its climbing device is for carrying people, to building Safeguarded, when meeting freezing weather, track surface layer is easy one layer of thin ice of condensation, and climbing device is difficult with, do not accomplish and When safeguard and reduce the safety of construction personnel.
Summary of the invention
The technical problem to be solved by the present invention is it is above-mentioned in order to solve the problems, such as, it provides a kind of with deceleration The spliced antifreeze exterior walls of buildings of function climbs rail system, structurally reasonable, and elevating control safety prevents because of track ice It congeals knot thin ice and cannot use, improve maintenance work efficiency and the safety of construction personnel.
The technical solution adopted by the present invention to solve the technical problems is: a kind of spliced with deceleration antifreeze is built Beyond the region of objective existence wall climbing rail system is built, including the fixed several spliced climbing tracks being attached on building, for connecting climbing Connector, climbing device and several electric heating infrared deicing devices of track, be provided on the inside of the climbing track mounting plate, Outside is provided with track plates, the surrounding edge of climbing track is provided with connecting column;Two are uniformly vertically arranged on the track plates Column perforation;The connecting hole for installation connecting element is provided on the connecting column;Limit is provided in the middle part of the connector Platform, connector upper and lower side side wall surface on be provided with screw hole;The side wall of the connecting hole be provided with passed through for screw and with The corresponding through-hole of screw hole;
The climbing device includes the scramble main body being fastened on track plates, bearing box, is arranged in inside bearing box Driving device and control device for controlling driving device;
The drive dynamic control device include driving motor, the reduction gearbox being connect with the spindle drive of driving motor and with A pair of of Driven by Coaxial sprocket wheel of reduction gearbox transmission connection;The Driven by Coaxial sprocket wheel is mutually adapted with perforation;
The scramble main body both sides are respectively arranged with U-shaped snap openings, the both sides of the face of U-shaped snap openings and bottom surface difference The advance ball being bonded is slided with connecting column side equipped with a column;
The electric heating infrared deicing device includes infrared heating pipe, the curved reflection cover that infrared heating bottom of the tube is arranged in And the protective cover on the outside of infrared heating pipe is set;The electric heating infrared deicing device is mutually electrically connected with control device It connects;The electric heating infrared deicing device be separately positioned on advance ball top and with perforation respective sides.
As a preferred option, the scramble main body both sides are provided with handrail, and middle part is provided with safety belt;Described Carrying upper box part is provided with foot pedal.
As a preferred option, the control device include control circuit, the battery for providing power supply, setting exist Wireless communication device scramble main body positive control panel and connect with external remote controller.
As a preferred option, PLC control chip is provided in the control circuit.
As a preferred option, the wireless communication device is using GSM communication module.
The beneficial effects of the present invention are: a kind of spliced antifreeze exterior walls of buildings with deceleration climbs track system System, spliced climbing track can increase and decrease track length according to demand;It is gone up and down by double drive chain wheel drive, elevating control Safety;There is electric heating infrared deicing device on climbing device, the frost in respective carter region can be melted, prevent because of track ice Freeze and cannot use, improves maintenance work efficiency.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is a kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration of the present invention Overall structure diagram;
Fig. 2 is a kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration of the present invention The structural schematic diagram of connector;
Fig. 3 is a kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration of the present invention Overlooking structure diagram;
Fig. 4 is a kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration of the present invention Drive dynamic control device structural schematic diagram;
Fig. 5 is a kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration of the present invention Electric heating infrared deicing device structural schematic diagram.
Attached drawing acceptance of the bid note is described below: 1, spliced climbing track, 11, mounting plate, 12, track plates, 13, connecting column, 14, Perforation, 15, connecting hole, 2, connector, 21, limiting stand, 22, screw hole, 3, bearing box, 31, foot pedal, 4, scramble main body, 41, U Shape snap openings, 42, advance ball, 43, handrail, 44, control panel, 45, safety belt, 5, driving motor, 51, reduction gearbox, 52, same Axis drive sprocket, 6, battery, 7, infrared heating pipe, 71, curved reflection cover, 72, protective cover.
Specific embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These attached drawings are simplified schematic diagram, only with Illustration illustrates basic structure of the invention, therefore it only shows the composition relevant to the invention.
A kind of spliced antifreeze exterior walls of buildings with deceleration as illustrated in fig. 1 and 2 climbs rail system, including The fixed several spliced climbing tracks 1 being attached on building, for connect the connector 2 for climbing track 1, climbing device with And several electric heating infrared deicing devices, the inside of the climbing track 1 is provided with mounting plate 11, outside is provided with track plates 12, The surrounding edge for climbing track 1 is provided with connecting column 13;Two column perforations 14 are uniformly vertically arranged on the track plates 12;It is described Connecting column 13 on be provided with connecting hole 15 for installation connecting element 2;The middle part of the connector 2 be provided with limiting stand 21, Screw hole 22 is provided in the side wall surface of 2 upper and lower side of connector;The side wall of the connecting hole 15 be provided with passed through for screw and Through-hole corresponding with screw hole 22;The climbing device includes the scramble main body 4 being fastened on track plates 12, bearing box 3, setting Driving device inside bearing box 3 and the control device for controlling driving device;4 both sides of scramble main body are set It is equipped with handrail 43, middle part is provided with safety belt 45;3 top of bearing box is provided with foot pedal 31.The control device Battery 6 including control circuit, for providing power supply, setting the positive control panel 44 of scramble main body 4 and with outside The wireless communication device of remote controller connection.PLC control chip is provided in the control circuit, the wireless communication device is to adopt With GSM communication module.
A kind of spliced antifreeze exterior walls of buildings with deceleration as shown in Figure 3 climbs rail system, described 4 both sides of scramble main body are respectively arranged with U-shaped snap openings 41, and the both sides of the face of U-shaped snap openings 41 and bottom surface are equipped with one It arranges and slides the advance ball 42 being bonded with 13 side of connecting column.
A kind of spliced antifreeze exterior walls of buildings with deceleration as shown in Figure 4 climbs rail system, described Drive dynamic control device includes driving motor 5, the reduction gearbox connecting with the spindle drive of driving motor 5 51 and passes with reduction gearbox 51 A pair of of Driven by Coaxial sprocket wheel 52 of dynamic connection;The Driven by Coaxial sprocket wheel 52 is mutually adapted with perforation 14.
A kind of spliced antifreeze exterior walls of buildings with deceleration as shown in Figure 5 climbs rail system, described Electric heating infrared deicing device includes that infrared heating pipe 7, the curved reflection cover 71 that 7 bottom of infrared heating pipe is arranged in and setting exist The protective cover 72 in 7 outside of infrared heating pipe;The electric heating infrared deicing device is electrically connected to each other with control device;Described Electric heating infrared deicing device be separately positioned on 42 top of advance ball and with 14 respective sides of perforation.
A kind of spliced antifreeze exterior walls of buildings with deceleration of the present invention climbs rail system, spliced Climbing track, track length can be increased and decreased according to demand;It is gone up and down by double drive chain wheel drive, elevating control safety;Climbing There is electric heating infrared deicing device on device, the frost in respective carter region can be melted, preventing cannot because track freezes It uses, improves maintenance work efficiency.
Taking the above-mentioned ideal embodiment according to the present invention as inspiration, through the above description, relevant staff is complete Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention Property range is not limited to the contents of the specification, it is necessary to which the technical scope thereof is determined according to the scope of the claim.

Claims (5)

1. a kind of spliced antifreeze exterior walls of buildings with deceleration climbs rail system, it is characterized in that: including fixed patch Several spliced climbings track (1) for being attached on building, for connect climb the connector (2) of track (1), climbing device with And several electric heating infrared deicing devices, mounting plate (11) is provided on the inside of the climbing track (1), outside is provided with track plates (12), the surrounding edge for climbing track (1) is provided with connecting column (13);Two column are uniformly vertically arranged on the track plates (12) Perforation (14);The connecting hole (15) for installation connecting element (2) is provided on the connecting column (13);The connector (2) Middle part be provided in the side wall surface of limiting stand (21), connector (2) upper and lower side and be provided with screw hole (22);The connecting hole (15) side wall is provided with to be passed through and through-hole corresponding with screw hole (22) for screw;
The climbing device includes the scramble main body (4) being fastened on track plates (12), bearing box (3), is arranged in bearing box (3) internal driving device and the control device for controlling driving device;
The drive dynamic control device includes driving motor (5), the reduction gearbox (51) connecting with the spindle drive of driving motor (5) And a pair of of Driven by Coaxial sprocket wheel (52) with reduction gearbox (51) transmission connection;The Driven by Coaxial sprocket wheel (52) is and perforation (14) it is mutually adapted;
Described scramble main body (4) both sides are respectively arranged with U-shaped snap openings (41), the both sides of the face of U-shaped snap openings (41) and Bottom surface is equipped with a column and slides the advance ball (42) being bonded with connecting column (13) side;
The electric heating infrared deicing device include infrared heating pipe (7), setting infrared heating pipe (7) bottom curved reflection The protective cover (72) for covering (71) and being arranged on the outside of infrared heating pipe (7);The electric heating infrared deicing device is and control Device is electrically connected to each other;The electric heating infrared deicing device is to be separately positioned on advance ball (42) top and and perforation (14) respective sides.
2. a kind of spliced antifreeze exterior walls of buildings with deceleration according to claim 1 climbs rail system, It is characterized in that: described scramble main body (4) both sides are provided with handrail (43), middle part is provided with safety belt (45);Described holds It carries case (3) top and is provided with foot pedal (31).
3. a kind of spliced antifreeze exterior walls of buildings with deceleration according to claim 1 climbs rail system, It is characterized in that: the control device includes control circuit, the battery (6) for providing power supply, is arranged in scramble main body (4) Positive wireless communication device control panel (44) and connect with external remote controller.
4. a kind of spliced antifreeze exterior walls of buildings with deceleration according to claim 1 climbs rail system, It is characterized in that: being provided with PLC control chip in the control circuit.
5. a kind of spliced antifreeze exterior walls of buildings with deceleration according to claim 1 climbs rail system, It is characterized in that: the wireless communication device is using GSM communication module.
CN201710096643.4A 2017-02-22 2017-02-22 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration Active CN106995016B (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN201710096643.4A CN106995016B (en) 2017-02-22 2017-02-22 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration
HK17103078.0A HK1232391A2 (en) 2017-02-22 2017-03-25 Jointed coldproof rack railway system with braking feature
US15/598,263 US20180238063A1 (en) 2017-02-22 2017-05-17 Jointed coldproof rack railway system with braking feature
PCT/CN2017/101219 WO2018153057A1 (en) 2017-02-22 2017-09-11 Spliced and anti-freezing external wall climbing rail system having speed reduction function for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710096643.4A CN106995016B (en) 2017-02-22 2017-02-22 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration

Publications (2)

Publication Number Publication Date
CN106995016A CN106995016A (en) 2017-08-01
CN106995016B true CN106995016B (en) 2018-12-14

Family

ID=59431159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710096643.4A Active CN106995016B (en) 2017-02-22 2017-02-22 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration

Country Status (4)

Country Link
US (1) US20180238063A1 (en)
CN (1) CN106995016B (en)
HK (1) HK1232391A2 (en)
WO (1) WO2018153057A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106995016B (en) * 2017-02-22 2018-12-14 郑义恒 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration
US11655641B2 (en) * 2019-12-29 2023-05-23 The Third Construction Co., Ltd Of China Construction Third Engneering Bureau Construction building equipment and construction method thereof

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2181043A (en) * 1985-10-01 1987-04-15 Robert Herbert Maw Back scrubber brush/massage appliance
EP1506799A1 (en) * 2003-08-14 2005-02-16 M+F Ingenieur Beratungs AG Climbing aid
CH715330B1 (en) * 2005-11-07 2020-03-13 Highstep Systems Ag Arrangement for ascending and / or descending a person.
JP5781763B2 (en) * 2007-09-11 2015-09-24 ハイステップ・システムズ・アクチエンゲゼルシャフト Guide rail connection
CN201660379U (en) * 2010-01-28 2010-12-01 陈亚洲 Climbing system for tall towers or high-rise buildings
CN201843335U (en) * 2010-10-29 2011-05-25 北京韬盛科技发展有限公司 Electric climbing formwork device
CH704615A2 (en) * 2011-03-09 2012-09-14 Highstep Systems Ag Lift for high-voltage and wind turbine towers.
CN202295052U (en) * 2011-07-12 2012-07-04 山东科技大学 Rail-type motion structure for climbing robot
CN104276224A (en) * 2013-07-09 2015-01-14 谭少华 Wall climbing vehicle
CN104746394A (en) * 2013-12-26 2015-07-01 中铁工程设计咨询集团有限公司 Ice and snow melting device for steel track beam
CN103896127A (en) * 2014-03-19 2014-07-02 广州市京龙工程机械有限公司 Connecting structure of construction hoist and building climbing formwork frame
CN204199832U (en) * 2014-11-10 2015-03-11 云南电网公司昭通供电局 A kind of climbing system track for high-voltage transmission line towers
CN205206304U (en) * 2015-12-14 2016-05-04 中交一公局第三工程有限公司 Novel creeping formwork support body
CN105539625B (en) * 2016-01-12 2019-03-08 宁波天弘电力器具有限公司 Climbing robot based on guide rail
CN205294715U (en) * 2016-01-12 2016-06-08 宁波天弘电力器具有限公司 Lifting device for track structure
CN205524553U (en) * 2016-04-13 2016-08-31 西南石油大学 Novel wall climbing robot
CN106995016B (en) * 2017-02-22 2018-12-14 郑义恒 A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration
CN206734442U (en) * 2017-02-22 2017-12-12 郑义恒 A kind of spliced antifreeze skin climbing rail system with deceleration

Also Published As

Publication number Publication date
US20180238063A1 (en) 2018-08-23
HK1232391A2 (en) 2018-01-05
CN106995016A (en) 2017-08-01
WO2018153057A1 (en) 2018-08-30

Similar Documents

Publication Publication Date Title
CN106995016B (en) A kind of spliced antifreeze exterior walls of buildings climbing rail system with deceleration
CN1994844A (en) Lifting operation method and apparatus for mounting guide rail on outer wall of architecture
CN109340649B (en) Intelligent control track type movable lamp
CN101504877B (en) Ice coagulation preventing cable and auxiliary equipment
WO2012019120A2 (en) Photovoltaic cell module assembly
CN206734442U (en) A kind of spliced antifreeze skin climbing rail system with deceleration
CN106013877A (en) Electricity-free double-layer garage
CN106818702A (en) Scarer
CN203212192U (en) Escalator having rainwater sensing function
CN205063409U (en) Multi -functional public security police kiosk
CN204695560U (en) Wind light mutual complementing formula vehicle pass-through height limiter
CN206800090U (en) The anti-blocking bridge of urban transportation function
CN204199191U (en) Solar high-speed highway gallery
CN213420420U (en) Security protection camera
CN103623512B (en) A kind of escape device for high-rise buildings
CN207742798U (en) A kind of intelligent traffic signal controller
CN209469376U (en) A kind of fan tower staircase
CN210655736U (en) Ladder type modular electric lifting device for hydropower station generator set
CN203225018U (en) Traffic signal lamp provided with solar panel
CN209293263U (en) A kind of rain-proof structure of computer room roof fly net
CN207812255U (en) A kind of novel municipal track bridge
CN201265268Y (en) Multi-row connection multistoried parking facility
CN212716103U (en) Platform lifting type single-pipe communication tower
CN206722480U (en) A kind of novel parking position
CN110697069A (en) Staying unmanned aerial vehicle platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200318

Address after: Room 315, 3 / F, No.110, Xianlie Middle Road, Yuexiu District, Guangzhou, Guangdong Province

Patentee after: GUANGZHOU CHUQU TECHNOLOGY Co.,Ltd.

Address before: Room B, 12 / F, building 4, Jinlong Industrial Center, 182-190 Dalian Pai Road, Kwai Fong, Hong Kong, China

Patentee before: Zheng Yiheng

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221223

Address after: 250000 No. 22, Yuanshan Road, Laiwu high tech Zone, Jinan City, Shandong Province

Patentee after: Laiwu High tech Zone Tongsheng Industry and Trade Co.,Ltd.

Address before: 510000 315, room 3, 3, martyrs Road, Yuexiu District, Guangzhou, Guangdong.

Patentee before: GUANGZHOU CHUQU TECHNOLOGY CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240810

Address after: 276800 Inside the Entrepreneurship and Innovation Incubation Center Building, No. 511 Shandong Road, High tech Industrial Development Zone, Rizhao City, Shandong Province

Patentee after: Shandong Dongye New Material Technology Co.,Ltd.

Country or region after: China

Address before: 250000 No. 22, Yuanshan Road, Laiwu high tech Zone, Jinan City, Shandong Province

Patentee before: Laiwu High tech Zone Tongsheng Industry and Trade Co.,Ltd.

Country or region before: China