CN106887839A - The distribution terminal of the consideration information wrong influence of link data transfer is layouted optimization method - Google Patents
The distribution terminal of the consideration information wrong influence of link data transfer is layouted optimization method Download PDFInfo
- Publication number
- CN106887839A CN106887839A CN201710137585.5A CN201710137585A CN106887839A CN 106887839 A CN106887839 A CN 106887839A CN 201710137585 A CN201710137585 A CN 201710137585A CN 106887839 A CN106887839 A CN 106887839A
- Authority
- CN
- China
- Prior art keywords
- time
- centerdot
- event
- power failure
- formula
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
- H02H7/261—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations
- H02H7/262—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations involving transmissions of switching or blocking orders
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/001—Methods to deal with contingencies, e.g. abnormalities, faults or failures
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
A kind of distribution terminal of the wrong influence of consideration information link data transfer is layouted optimization method.It includes setup module;Feeder line species is divided;Distribution terminal deployment configuration is divided;Fault state is divided;Quantify data acquisition needed for Modeling Calculation;Quantify Modeling Calculation;The information wrong event of link data transfer is divided;Information data is gathered;Calculating process is modified;Feeder line distribution terminal is obtained to layout the steps such as program results.The present invention can effectively instruct to analyze influence of " three the is distant " function to system blackout time, mixed economy cost and to distribution terminal deployed position, contribute to the power supply reliability and quality of voltage of preferably raising power network, the efficiency of management of distribution terminal is lifted, there is guiding significance to improving China power distribution automation level, the intelligent grid construction of propulsion China.
Description
Technical field
The invention belongs to feeder line distribution power automation terminal configuring technical field, more particularly to a kind of consideration information link number
Layouted optimization method according to the distribution terminal for transmitting wrong influence.
Background technology
Power distribution automation (Distribution Automation, DA) system can be considered the information physical system of a quasi-representative
System (Cyber-Physical Systems, CPS), the safe and reliable power supply of physics distribution system of its information link to being managed
With the influence that can not ignore.In practical application, the often in summary spy of the substandard distribution power automation terminal of different classifications
Point, it is divided into " three is distant " distribution terminal and " two is distant " major class of distribution terminal two on the whole.Wherein, " three is distant " function refers to distant
Letter, telemetry and telecommand function.Power distribution automation is different from all standing of major network dispatching automation (EMS) grid nodes, equipment and supervises entirely
The requirement of control, distribution net equipment is multi-point and wide-ranging and the characteristics of radial operation and due to the aspect such as investment, distribution is automatic
The construction of change typically takes part of nodes remote control, the mode of part of nodes remote measurement to realize 10kV distribution information gatherings, by data
It is shared to complete all standing of distribution information and the control of 10kV key nodes.As in distribution network planning distribution automation planning it is important
One ring, the reasonable disposition of remote measuring and controlling terminal has vital influence for playing the benefit of power distribution automation.
Information link with power distribution communication as representative is to realize the important component of power distribution automation.At this stage, for
The research of power distribution automation information link has focused largely on power distribution automation communication network technology (political affairs of [1] South Korea, the third boundary bases of Xu
In senior power distribution automation open communication system [J] the electric power network techniques of IEC61850,2011,35 (4):183-186. [2] Lin
Beautiful China, mixed communication scheme [J] Automation of Electric Systems of Liu Jian electrical power distribution automatization systems, 2001,25 (23):52-54.
[3] Liu Jian, Zhang Zhihua, Zhang little Qing, wait distribution network failure treatment [J] power systems that relay protections coordinate with power distribution automation
Protection and control, 2011,39 (16):53-57.), ([3] Liu Jian, Zhang Zhihua opens small power distribution automation troubleshooting application technology
Celebrating, waits distribution network failure treatment [J] electric power system protection and controls that relay protections coordinate with power distribution automation, 2011,39
(16):53-57. [4] Liu Jian, Zhang little Qing, Zhao Shuren, waits power distribution automation troubleshooting performances main website to inject method of testing [J]
Automation of Electric Systems, 2012,36 (18):67-71) with the framework and construct and design ([5] Liu Wenxia, the glad of tension force of communication system
[J] east china electric powers, 2010,38 (1) are assessed based on electrical power distribution automatization system information security grade FAHP theoretical with D-S is improved:
67-71) how aspect, consider the influence of information link in electrical power distribution automatization system, is ground as a complete CPS system
The planning problem of layouting of the quantity planning and specific deployed position of studying carefully its terminal still has more element task urgently to carry out.Liu Xiaozhong
(Communication System for Distribution Automation design and realization [D] Beijing based on EPON technologies:North China Electric Power University, 2014) propose
Effective means of communication is taken in power distribution automation can improve the accuracy of data transfer so that distribution terminal equipment can be with standard
The really operational order of reflection operating personnel, and then raising Distribution Network Reliability.(wireless private network communication is automatic in Dalian distribution for Wu Lin etc.
Application [J] communication of power system in change, 2012,22 (231):107-111) elaborate Dalian wireless private network communication automation system
The key technology of middle application, it is proposed that wireless network encrypts the construction requirements with private network, can be built for power distribution automation communication network
If providing exemplary role.Tang Lin (design of Communication System for Distribution Automation and realization [J] communication of power system, 2003, (12):
45-47) on the basis of Communication System for Distribution Automation functional requirement is analyzed, it is proposed that power distribution automation hierarchical structure, communication
The requirement of mode etc. and implementation method.(information security research [C] China motor work in power distribution automation design such as Wang Xuelun
Cheng Xuehui annual meetings, Sichuan Chengdu, 2013) for power distribution automation network information security technology, it is proposed that a set of intelligent distribution network
Design of Information Security scheme.Lin Yongfeng etc. (distribution power automation terminal Information Security Risk assessment method research [J] automation with
Instrument, 2015, (12):System layer 11-14) from power distribution automation, communication layers and the configuration possible risk problem of layer analysis, carry
A set of information security evaluating method and evaluation and test flow are gone out, the information security issue to solving distribution power automation terminal has guidance
Property meaning, while for Security Testing and the Hole Detection of electrical power distribution automatization system provide platform.
To sum up, about the research of power distribution automation information link, to focus primarily upon Information Security Evaluation automatic with distribution at present
Change system architecture design etc., but lack the overall angle consideration from power distribution automation CPS, the influence of meter and information link is carried out
Take into account the research in terms of the Optimal Configuration Method of layouting of the specific deployed position of the distribution terminal of distribution Power System Reliability and economy.
The content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of wrong influence of consideration information link data transfer
Distribution terminal layout optimization method.
In order to achieve the above object, the distribution terminal cloth of the consideration information wrong influence of link data transfer that the present invention is provided
Point optimization method includes the following steps for carrying out in order:
1) content planned according to distribution terminal configuration quantity in electrical power distribution automatization system first, primary Calculation goes out to be analyzed
Feeder line needed for configuration distribution terminal quantity, then set perform this consideration information wrong influence of link data transfer distribution
Terminal is layouted module needed for optimization method, including:Feeder line species division module, distribution terminal deployment configuration division module, failure
Situation division module, data acquisition module, quantum chemical method module, the distribution terminal wrong event of planning module, data of layouting are divided
Module, information link data acquisition module, information link quantify correcting module and " three is distant " function effect analysis module;
2) feeder line species division module is utilized, feeder line is divided into following two according to whether interconnection switch is installed on feeder line
Class:1. the feeder line of interconnection switch is not installed;2. there is the feeder line of interconnection switch;
3) distribution terminal deployment configuration division module is utilized, the configuring condition of distribution terminal is divided into following three class:①
All configure " three is distant " distribution terminal;2. " two is distant " distribution terminal is all configured;3. mixed configuration " three is distant " and " two is distant " distribution
Terminal;
4) fault state division module is utilized, the treatment after failure is occurred to failure is divided into three phases, 1. failure is determined
The position stage;2. artificial fault isolation stage;3. fault restoration stage;
5) data acquisition module is utilized, according to the step 2), 3) and 4) in result, in above-mentioned three classes distribution terminal
Under configuring condition, system blackout time and power failure load in three troubleshooting stages of two class feeder lines quantify Modeling Calculation institute
Data are needed to be acquired, required data include:Got in touch with block switch quantity and present position, feeder line on feeder line number of switches and
It is equivalent load sum that present position, fault rate, each section length of feeder line are connected with sectional area, fault location time, artificial
Fault Isolation time and fault correction time;
6) using quantifying computing module, according to the step 2), 3) and 4) in result and step 5) in collection data,
To under above-mentioned three classes distribution terminal configuring condition, the system blackout time and power failure in three failure phases of two class feeder lines are negative
Lotus carries out quantization Modeling Calculation, wherein, the quantization Modeling Calculation of system blackout time and power failure load includes:1. contact is not installed
The system blackout time of the feeder line of switch and the quantization Modeling Calculation of power failure load;2. the system that there is the feeder line of interconnection switch is stopped
Electric time and the quantization Modeling Calculation of power failure load;
7) the information wrong event of link data transfer is divided using data wrong event division module:1. event
Remote signalling-the remote control of A --- distribution terminal is wrong but remote measurement is errorless;2. event B --- remote signalling-remote control is errorless but remote measurement is wrong;③
Event C --- remote signalling-remote control and remote measurement are wrong;
8) information link data acquisition module is utilized, according to the step 2) to step 7) in result, to step 7) in
Data needed for the quantization Modeling Calculation of divided event are acquired, and required data include:Remote signaling function is checked and right
The time that information is modified;Remote information is carried out to check amendment and the time needed for carrying out isolation processing to failure again;
Function and information to remote control and remote signalling carry out checking the time corrected needed for carrying out isolation processing to failure again;To remote measurement work(
Can be checked and information is corrected, the artificial time for finding the correct abort situation of positioning;Telemetry intelligence (TELINT) is entangled
Just, the time of failure mode is rejudged;The probability that each event occurs;
9) quantify correcting module using information link, according to the step 2) to the result and step 8 in 7)) in collection
Data, to the step 7) in all subevents carry out quantization Modeling Calculation, and calculating process is modified;
10) " three is distant " function effect analysis module is utilized, according to above-mentioned steps 2) to step 9) result it is automatic to distribution
Change specifically layout position of the terminal installation on feeder line and optimize configuration, on the basis of given distribution terminal configuration quantity,
Object function is set up using the power failure load of above-mentioned each configuring condition, with reliability conditions as constraint of powering, and then feeder line is obtained
Distribution terminal is layouted program results;And effectively instruct analysis " three is distant " function to the system blackout time, mixed economy cost and
Influence to distribution terminal deployed position.
The distribution terminal of the consideration information wrong influence of link data transfer that the present invention is provided layouts optimization method in failure
Positioning, artificial Fault Isolation and fault restoration stage introduce the information wrong influence of link data transfer, it is proposed that accordingly may be used
By property index correction model and correction strategy, position of specifically layouting that can be to distribution terminal on feeder line optimizes configuration,
And analysis " three is distant " function can be effectively instructed to system blackout time, mixed economy cost and to distribution terminal deployed position
Influence, contribute to preferably improve power network power supply reliability and quality of voltage, lifted distribution terminal the efficiency of management, to carrying
China's power distribution automation level high, the intelligent grid construction of propulsion China have guiding significance.
Brief description of the drawings
Fig. 1 layouts optimization method stream for the distribution terminal of the consideration information wrong influence of link data transfer that the present invention is provided
Cheng Tu.
Fig. 2-1 is the feeder line figure for not installing interconnection switch.
Fig. 2-2 is the feeder line figure that there is interconnection switch.
The feeder line schematic diagram that Fig. 3 is used by the embodiment of the present invention.
Fig. 4-1 is three distant accuracy to system blackout time and the influence schematic diagram of mixed economy cost.
Fig. 4-2 is that remote signalling accuracy is layouted the influence schematic diagram of position optimization result to distribution terminal.
Fig. 4-3 is that remote measurement accuracy is layouted the influence schematic diagram of position optimization result to distribution terminal.
Fig. 4-4 is that remote control accuracy is layouted the influence schematic diagram of position optimization result to distribution terminal.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment on the present invention provide the consideration information wrong influence of link data transfer distribution
Terminal optimization method of layouting is described in detail.
The optimization as shown in figure 1, distribution terminal of the consideration information wrong influence of link data transfer of present invention offer is layouted
Method includes the following steps for carrying out in order:
1) first according in electrical power distribution automatization system distribution terminal configuration quantity planning (the Automation of Electric Systems such as Liu Jian,
2013,37 (12):Content 44-50), primary Calculation goes out the distribution terminal quantity of configuration needed for feeder line to be analyzed, Ran Houshe
Put and perform the distribution terminal of this consideration information wrong influence of link data transfer and layout module needed for optimization method, including:Feeder line
Species division module, distribution terminal deployment configuration division module, fault state division module, data acquisition module, quantum chemical method
Module, distribution terminal are layouted the wrong event division module of planning module, data, information link data acquisition module, information link
Quantify correcting module and " three is distant " function effect analysis module;
2) feeder line species division module is utilized, feeder line is divided into following two according to whether interconnection switch is installed on feeder line
Class:1. the feeder line of interconnection switch is not installed, as shown in Fig. 2-1;2. there is the feeder line of interconnection switch, as shown in Fig. 2-2;Fig. 2-1
Contain m-1 line sectionalizing switch with feeder line shown in Fig. 2-2 and (disregard line outlet switch z1), it is divided into m sections, contain simultaneously
N interconnection switch (general m >=n);I is the numbering of sectional area;ynRepresent interconnection switch;
3) distribution terminal deployment configuration division module is utilized, the configuring condition of distribution terminal is divided into following three class:①
All configure " three is distant " distribution terminal;2. " two is distant " distribution terminal is all configured;3. mixed configuration " three is distant " and " two is distant " distribution
Terminal;
4) fault state division module is utilized, the treatment after failure is occurred to failure is divided into three phases, 1. failure is determined
The position stage;2. artificial fault isolation stage;3. fault restoration stage;
5) data acquisition module is utilized, according to the step 2), 3) and 4) in result, in above-mentioned three classes distribution terminal
Under configuring condition, system blackout time and power failure load in three troubleshooting stages of two class feeder lines quantify Modeling Calculation institute
Data are needed to be acquired, required data include:Got in touch with block switch quantity and present position, feeder line on feeder line number of switches and
It is equivalent load sum that present position, fault rate, each section length of feeder line are connected with sectional area, fault location time, artificial
Fault Isolation time and fault correction time;
6) using quantifying computing module, according to the step 2), 3) and 4) in result and step 5) in collection data,
To under above-mentioned three classes distribution terminal configuring condition, the system blackout time and power failure in three failure phases of two class feeder lines are negative
Lotus carries out quantization Modeling Calculation, wherein, the quantization Modeling Calculation of system blackout time and power failure load includes:1. contact is not installed
The system blackout time of the feeder line of switch and the quantization Modeling Calculation of power failure load;2. the system that there is the feeder line of interconnection switch is stopped
Electric time and the quantization Modeling Calculation of power failure load;
1. the system blackout time of the feeder line of interconnection switch and the quantization Modeling Calculation of power failure load are not installed according to distribution
The configuring condition of terminal is divided into following three class:A. all configuration " three is distant " distribution terminal when the system blackout time and power failure load
Quantization Modeling Calculation;The quantization modeling of system blackout time and power failure load when b. all configuring " two is distant " distribution terminal is counted
Calculate;C. the quantization Modeling Calculation of mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and power failure load;
A. system blackout time during whole configuration " three is distant " distribution terminals and the quantization Modeling Calculation step of power failure load
It is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage
System blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and power failure load
Quantify Modeling Calculation;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load:
The fault location stage corresponding system blackout time of i-th section of region wire failure is:
In formula, T1iRepresent the fault location stage corresponding system blackout time of i-th section of region wire failure, t1iIt is i-th
The fault location time in section region, UiRepresent i-th section of total number of users of block supply;liThe substitutional connection for representing i-th section of region is long
Degree;fiI-th section of equivalent of the apparatus fault rate in region is represented, unit is secondary/kma;M represents the number of fragments of feeder line;
Fault location stage corresponding system blackout time T1For:
System blackout load is accordingly:
In formula, E1iRepresent the corresponding system blackout load of fault location stage of i-th section of region wire failure, PiRepresent
The i sections of equivalent load sum of whole loads of block supply;
The corresponding system blackout load E of fault location stage1For:
(2) the quantization Modeling Calculation of artificial fault isolation stage system blackout time and power failure load:
The artificial fault isolation stage corresponding system blackout time of i-th section of region wire failure is:
In formula, T2iRepresent the artificial fault isolation stage corresponding system blackout time of i-th section of region wire failure, t2i
It is the i-th artificial Fault Isolation time in region;
Artificial fault isolation stage corresponding system blackout time T2For:
System blackout load is accordingly:
In formula, E2iRepresent the corresponding system blackout load of artificial fault isolation stage of i-th section of region wire failure;
The corresponding system blackout load E of artificial fault isolation stage2For:
(3) the quantization Modeling Calculation of fault restoration stage system power off time and power failure load:
The corresponding system blackout time in fault restoration stage of i-th section of region wire failure is:
In formula, T3iRepresent the corresponding system blackout time in fault restoration stage of i-th section of region wire failure, t3iIt is i-th
The fault correction time in section region;zk=0 represents relevant position configuration distribution terminal, zk=1 represents relevant position does not configure distribution
Terminal;
Corresponding system blackout time T in fault restoration stage3For:
System blackout load is accordingly:
In formula, E3iRepresent the fault restoration stage corresponding system blackout load of i-th section of region wire failure;
Fault restoration stage corresponding system blackout load E3For:
(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load:
T=T1+T2+T3 (13)
In formula, T is corresponding system blackout time in whole troubleshooting stage, unit h;T1、T2And T3Correspond to respectively above-mentioned
The system blackout time of fault location stage, artificial fault isolation stage and fault restoration stage, unit is h;
E=E1+E2+E3 (14)
In formula, E is corresponding system blackout load of whole troubleshooting stage, unit kWh;E1、E2And E3On corresponding to respectively
The system blackout load of fault location stage, artificial fault isolation stage and fault restoration stage is stated, unit is kWh;
B. system blackout time during whole configuration " two is distant " distribution terminals and the quantization Modeling Calculation step of power failure load
It is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage
System blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and power failure load
Quantify Modeling Calculation;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load and formula (1)-(4)
Cause, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation formula of artificial fault isolation stage system blackout time and power failure load and formula (5)-
(8) it is consistent, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (9)-(12)
Unanimously;
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14)
Unanimously.
C. the quantization modeling of mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and power failure load
Calculation procedure is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial failure
Isolation stage system blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and stop
The quantization Modeling Calculation of electric load;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load and formula (1)-(4)
Cause, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation of artificial fault isolation stage service system power off time and power failure load:
First, it is assumed that the line sectionalizing switch of configuration " three is distant " distribution terminal is common M-1, then based on all " three is distant " distribution
Terminated line block switch divides " three is distant " common M in region for obtaining.During for the system blackout for analyzing artificial fault isolation stage
Between and power failure load, use Ωi’The load aggregation in the i-th ' individual " three is distant " distribution terminal region is represented, | Ωi’| in the region
Total number of users;With event group W=(w1,w2,…,w2i’-1,w2i’,…,w2M-1,w2M) " three is distant " residing for representing fault position match somebody with somebody
The configuring condition of " two is distant " Distributing Terminal Assembly in region determined by electric terminals and region, altogether including 2M event, specific table
It is shown as:
w2i’-1:Failure occurs to be configured with " two in the i-th ' individual " three is distant " region determined by distribution terminal, and the region
It is distant " distribution terminal;
w2i’:" two is distant " is not configured with the i-th ' individual " three is distant " region, but region determined by distribution terminal of failure generation to match somebody with somebody
Electric terminals;
Then the artificial fault isolation stage of the i-th section of region wire failure corresponding system blackout time be:
System blackout load is accordingly:
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (9)-(12)
Unanimously.
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14)
Unanimously.
2. the system blackout time and power failure load modeling that there is the feeder line of interconnection switch calculate matching somebody with somebody according to distribution terminal
The situation of putting is divided into following three class:The quantization of system blackout time and power failure load when a. all configuring " three is distant " distribution terminal is built
Mould is calculated;B. system blackout time during whole configuration " two is distant " distribution terminals and the quantization Modeling Calculation of power failure load;C. mix
Close the quantization Modeling Calculation of the system blackout time and power failure load when configuring " three is distant " and " two is distant " distribution terminal;
A. system blackout time during whole configuration " three is distant " distribution terminals and the quantization Modeling Calculation step of power failure load
It is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage
System blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and power failure load
Quantify Modeling Calculation;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load and formula (1)-(4)
Cause, but due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0;
(2) the quantization Modeling Calculation formula of artificial fault isolation stage system blackout time and power failure load and formula (5)-
(8) it is consistent, but due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0.
(3) the quantization Modeling Calculation of fault restoration stage system power off time and power failure load:
The corresponding system blackout time in fault restoration stage of i-th section of region wire failure is:
In formula, T3iRepresent the corresponding system blackout time in fault restoration stage of i-th section of region wire failure, t3iIt is i-th
The fault correction time in section region;
The fault restoration stage, corresponding system blackout Time Calculation formula was consistent with formula (10).
System blackout load is accordingly:
In formula, E3iRepresent the fault restoration stage corresponding system blackout load of i-th section of region wire failure;
The fault restoration stage, corresponding system blackout carry calculation formula was consistent with formula (12).
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14)
Unanimously.
B. system blackout time during whole configuration " two is distant " distribution terminals and the quantization Modeling Calculation step of power failure load
It is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage
System blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and power failure load
Quantify Modeling Calculation;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load and formula (1)-(4)
Cause, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation formula of artificial fault isolation stage system blackout time and power failure load and formula (5)-
(8) it is consistent, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (10), (12),
(19) it is consistent with (20);
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14)
Unanimously;
C. the quantization modeling of mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and power failure load
Calculation procedure is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial failure
Isolation stage system blackout time and the quantization Modeling Calculation of power failure load;(3) fault restoration stage system power off time and stop
The quantization Modeling Calculation of electric load;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load and formula (1)-(4)
Cause, but due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0;
(2) the quantization Modeling Calculation formula of artificial fault isolation stage system blackout time and power failure load and formula (15)-
(18) it is consistent;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (10), (12),
(19) it is consistent with (20);
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14)
Unanimously;
7) the information wrong event of link data transfer is divided using data wrong event division module:1. event
Remote signalling-the remote control of A --- distribution terminal is wrong but remote measurement is errorless;2. event B --- remote signalling-remote control is errorless but remote measurement is wrong;③
Event C --- remote signalling-remote control and remote measurement are wrong.
1. event A includes following three classes subevent:A. event A1:Remote information is errorless, but remote signalling information is wrong.B. event
A2:Remote information is wrong, but remote signalling information is errorless;C. event A3:Remote information is wrong, and remote signalling information is wrong.
2. event B includes following three classes subevent:A. event B1:The determination of telemetry intelligence (TELINT) erroneous effects abort situation.b.
Event B2:The determination of telemetry intelligence (TELINT) erroneous effects failure mode.C. event B3:Telemetry intelligence (TELINT) mistake simultaneously influence abort situation and
The determination of species.
3. event C includes the nine class subevents determined by event A and event B:A. event C1:Remote information is errorless, but
Remote signalling information is wrong, and telemetry intelligence (TELINT) erroneous effects abort situation determination;B. event C2:Remote information is errorless, but remote signalling is believed
Breath is wrong, and information errors influence the determination of failure mode;C. event C3:Remote information is errorless, but remote signalling information is wrong, and distant
Measurement information mistake influences the determination of abort situation and species simultaneously;D. event C4:E. remote information is wrong, but remote signalling information without
By mistake, and telemetry intelligence (TELINT) erroneous effects abort situation determination;Event C5:Remote information is wrong, but remote signalling information is errorless, and information
The determination of erroneous effects failure mode;F. event C6:Remote information is wrong, but remote signalling information is errorless, and telemetry intelligence (TELINT) mistake is same
When influence abort situation and species determination;G. event C7:Remote control and remote signalling information are wrong, and the event of telemetry intelligence (TELINT) erroneous effects
Hinder the determination of position;H. event C8:Remote control and remote signalling information are wrong, and telemetry intelligence (TELINT) erroneous effects failure mode determination;
I. event C9:Remote control and remote signalling information are wrong, and telemetry intelligence (TELINT) mistake influences the determination of abort situation and species simultaneously.
8) information link data acquisition module is utilized, according to the step 2) to step 7) in result, to step 7) in
Data needed for the quantization Modeling Calculation of divided event are acquired, and required data include:Remote signaling function is checked and right
The time that information is modified;Remote information is carried out to check amendment and the time needed for carrying out isolation processing to failure again;
Function and information to remote control and remote signalling carry out checking the time corrected needed for carrying out isolation processing to failure again;To remote measurement work(
Can be checked and information is corrected, the artificial time for finding the correct abort situation of positioning;Telemetry intelligence (TELINT) is entangled
Just, the time of failure mode is rejudged;The probability that each event occurs;
9) quantify correcting module using information link, according to the step 2) to the result and step 8 in 7)) in collection
Data, to the step 7) in all subevents carry out quantization Modeling Calculation, and calculating process is modified;
The quantization correction model of all subevents is comprised the following steps that:
1. (it is p to set its probability of happening to event A1) quantify quantization correction model of the correction model including three class events:
A. (probability for setting its generation is p to event A111):When this occurs, relative to above-mentioned steps 6) in failure repair
The quantization formula in multiple stage, fault correction time therein need to be modified to:
In formula,It is the time for being checked remote signaling function and being modified to information.
B. (probability for setting its generation is p to event A212):When this occurs, relative to above-mentioned steps 6) in it is artificial therefore
Hinder the quantitative model of isolation stage, the system blackout load of artificial fault isolation stage therein is expressed as:
In formula, t2"=t2 12For remote information check amendment and needed for carrying out isolation processing to failure again when
Between.
C. (probability for setting its generation is p to event A313):When this occurs, relative to above-mentioned steps 6) in failure repair
The quantization formula in multiple stage, system blackout carry calculation formula and the formula (22) of artificial fault isolation stage therein
Cause, the t in this up-to-date style2" need to use t2 13Replace, t2 13Represent carries out checking amendment simultaneously to the function and information of remote control and remote signalling
Again the time needed for carrying out isolation processing to failure.
2. (it is p to set its probability of happening to event B2) quantify quantization correction model of the correction model including three class events:
B. (probability for setting its generation is p to event B121):When this occurs, relative to above-mentioned steps 6) in failure determine
The quantization formula in position stage, fault location time therein need to be modified to:
Wherein, t1 21It is telemetry function to be checked and information is corrected, it is artificial to find the correct fault bit of positioning
The time put.
B. (probability for setting its generation is p to event B222):When this occurs, relative to above-mentioned steps 6) in failure determine
The quantization formula in position stage, fault location time therein need to be modified to:
Wherein, t1 22It is that telemetry intelligence (TELINT) is corrected, rejudges the time of failure mode.
C. (probability for setting its generation is p to event B323):When this occurs, relative to above-mentioned steps 6) in failure determine
The quantization formula in position stage, fault location time therein need to be modified to:
3. event C quantifies correction model includes the quantization correction model of nine class events:
Due to nine class subevents in event C be to be combined with three class subevents in event B by three class subevents in event A and
Into, thus this nine classes event occur time quantization correction model be:
A. (probability for setting its generation is p to event C131):
tC11=t3i+t3 11 (26)
tC12=t1i+t1 21 (27)
tC1=tC11+tC12 (28)
B. (probability for setting its generation is p to event C232):
tC21=t3i+t3 11 (29)
tC22=t1i+t1 22 (30)
tC2=tC21+tC22 (31)
C. (probability for setting its generation is p to event C333):
tC31=t3i+t3 11 (32)
tC32=t1i+t1 21+t1 22 (33)
tC3=tC31+tC32 (34)
D. (probability for setting its generation is p to event C434):
tC41=t2i+t2 12 (35)
tC42=t1i+t1 21 (36)
tC4=tC41+tC42 (37)
E. (probability for setting its generation is p to event C535):
tC51=t2i+t2 12 (38)
tC52=t1i+t1 22 (39)
tC5=tC51+tC52 (40)
F. (probability for setting its generation is p to event C636):
tC61=t2i+t2 12 (41)
tC62=t1+t1i 21+t1 22 (42)
tC6=tC61+tC62 (43)
G. (probability for setting its generation is p to event C737):
tC71=t2i+t2 13 (44)
tC72=t1i+t1 21 (45)
tC7=tC71+tC72 (46)
H. (probability for setting its generation is p to event C838):
tC81=t2i+t2 13 (47)
tC82=t1i+t1 22 (48)
tC8=tC81+tC82 (49)
I. (probability for setting its generation is p to event C939):
tC91=t2i+t2 13 (50)
tC92=t1i+t1 21+t1 22 (51)
tC9=tC91+tC92 (52)
Assuming that the accuracy of remote information is pc;The accuracy of remote signalling information is ps;The accuracy of telemetry intelligence (TELINT) is pm, its
In, pmCan be expressed as again:
(1-pm)=pm1+pm2+pm3 (53)
Wherein, pm1Represent the wrong influence abort situation of remote measurement but the probability for not influenceing failure mode definite event to occur;
pm2Represent the wrong influence failure mode of remote measurement but the not probability of impact position definite event generation;pm3Represent the wrong shadow of remote measurement
Ring the probability that failure mode and position definite event occur.
Therefore, the probability that each subevent occurs can be expressed as:
P=1-pm·pc·ps (54)
Wherein, p is the probability that the wrong event of data occurs.
p1=(1-pc·ps)pm (55)
p2=(1-pm)·pc·ps (56)
p3=(1-pc·ps)·(1-pm) (57)
p11=pc·(1-ps)·pm (58)
p12=(1-pc)·ps·pm (59)
p13=(1-pc)(1-ps)·pm (60)
p21=pc·ps·pm1 (61)
p22=pc·ps·pm2 (62)
p23=pc·ps·pm3 (63)
p31=pc·(1-ps)·pm1 (64)
p32=pc·(1-ps)·pm2 (65)
p33=pc·(1-ps)·pm3 (66)
p34=(1-pc)·ps·pm1 (67)
p35=(1-pc)·ps·pm2 (68)
p36=(1-pc)·ps·pm3 (69)
p37=(1-pc)(1-ps)·pm1 (70)
p38=(1-pc)(1-ps)·pm2 (71)
p39=(1-pc)(1-ps)·pm3 (72)
Each phases-time is modified with expectation value analysis method, amendment in the case of " three is distant " terminal is configured with after amendment
Time it is as follows:
1. the time complexity curve of fault location stage:
Obtained after arrangement:
2. the time complexity curve of artificial fault isolation stage:
3. the time complexity curve in fault restoration stage:
Bring the revised time into above-mentioned steps 6) in Chinese style (1) to formula (20).
10) " three is distant " function effect analysis module is utilized, according to above-mentioned steps 2) to step 9) result it is automatic to distribution
Change specifically layout position of the terminal installation on feeder line and optimize configuration, on the basis of given distribution terminal configuration quantity,
Object function is set up using the power failure load of above-mentioned each configuring condition, with reliability conditions as constraint of powering, and then feeder line is obtained
Distribution terminal is layouted program results;And effectively instruct analysis " three is distant " function to the system blackout time, mixed economy cost and
Influence to distribution terminal deployed position.
Comprise the following steps that:
A. according to step 7) in formula (74)~(76) replacement step 6 for obtaining) in respective stage power off time, according to
Step 6) the power failure load that obtains sets up object function, and genetic algorithm for solving object function is used, carry out genetic manipulation;Target
Function is as follows:
In formula, CEIt is unit electricity loss of outage;N2And N3It is the configuration quantity of " two is distant " and " three is distant " distribution terminal;C2
And C3It is the initial outlay unit price of " two is distant " and " three is distant " distribution terminal;i2And i3For " two is distant " and " three is distant " distribution terminal is invested
Discount rate;a2And a3It is the Economic Life of " two is distant " and " three is distant " distribution terminal;
B. the fitness value in genetic algorithm judges whether to reach stopping criterion for iteration, and method is to build fitness letter
Number, reliability constraint is added in the object function shown in formula (77) in the form of penalty function, is fitted as hereditary individual
Response evaluation function;
Wherein, reliability constraint uses the power supply reliability threshold value constraint condition of setting, i.e.,
β1> βset (78)
Wherein, βsetIt is the power supply reliability requirement of feeder line;β1It is the power supply reliability under distribution terminal sensor distributing,
Shown in expression such as formula (23):
Wherein, T considers that the influence of information system is calculated using formula (13) with formula (74)~(76);
C. when reliability constraint is unsatisfactory in continuous m generations, then return to step 1), readjust required on feeder line matching somebody with somebody
The distribution terminal quantity put;Otherwise terminate, the optimal program results of layouting of output feeder distribution terminal.
Now have to the consideration information link data transfer that the present invention is provided by taking the feeder line of the IEEE33 nodes shown in Fig. 3 as an example
The distribution terminal optimization method of layouting of influence is illustrated by mistake.And " three is distant " and " two the is distant " distribution terminal to be of universal significance
It is combined as a example by configuration, the feeder line gate out switch of Fig. 3 median generatrixs-node 0, node 1-2,2-3,4-5,8-9 and 14-15 circuits
Block switch (need to carry out distribution power automation terminal layout optimization choosing for position) and interconnection switch the system is divided into 6 segmentations
Region, respectively such as z in figure1,z2,..,z6It is shown.Each sectional area internal loading P1,P2…,P5Be followed successively by 100kW, 400kW,
400kW、500kW、2500kW、400kW;Sectional area number of users is 10, substitutional connection length l1,l2,..,l6It is followed successively by
1.275km、0.26km、0.108km、0.17km、0.09km、0.22km;Feeder fault rate is 0.23 time/km;Correspondence event
Barrier positioning stage, artificial fault isolation stage and the fault handling time t in fault restoration stage1,t2,t3Be followed successively by 1h, 0.5h,
4h;Consider that " three is distant " distribution terminal and the procurement price of " two is distant " distribution terminal are respectively 50,000 yuan and 10,000 yuan;Distribution terminal is thrown
Money return rate takes 0.1, in 20 years life-spans, takes unit quantity of electricity loss of outage CE=5 yuan.If the system power supply block supply reliability will
Seek βsetIt is 99.9%.The content primary Calculation planned according to distribution terminal configuration quantity in above-mentioned electrical power distribution automatization system first
The distribution terminal quantity for going out required configuration on the feeder line is 3..
If system power supply block supply reliability requirement is 99.9%.Simultaneously for ease of comparative analysis, it is considered to following three
Individual scene:(1) scene one:It is 100% that telemetry and telecommand accuracy is constant, and remote signalling accuracy changes;(2) scene two:Remote signalling and
It is 100% that remote control accuracy is constant, and remote measurement accuracy changes;(3) scene three:Remote signalling and remote measurement accuracy it is constant be 100%, it is distant
Control accuracy changes.And set the wrong event A of data message1,A2,A3,B1,B2Corresponding time complexity curve is followed successively by t3 11=0.2h,
t2 12=0.4h, t2 13=0.6h, t1 21=0.15h, t1 22=0.15h, it is assumed that the wrong corresponding three events hair of telemetry intelligence (TELINT)
Raw Probability pm1,pm2,pm3It is identical, i.e. pm1=pm2=pm3=(1-pm)/3。
Using the inventive method, it is considered to after the wrong influence of information link data transfer is modified to quantum chemical method model,
Result is as shown in Fig. 4-1-Fig. 4-4 and table 1-1-table 1-3:
(1) to the influence of system blackout time and mixed economy cost
It is in z when distribution terminal configuration is constant2And z6Place's configuration " two is distant " distribution terminal, z5Place's configuration " three is distant " distribution end
During end, Fig. 4-1 gives the influence situation of one, two, three pairs of system blackout times of scene and mixed economy cost.Can from Fig. 4-1
See, the accuracy of " three is distant " function affects the mixed economy cost and power off time of system, and mixed economy cost simultaneously
Reduced with the raising of " three is distant " function accuracy with power off time.Specific amplification ratio situation such as table 1-1-table 1-3 institutes
Show.From the longitudinal direction contrast of table 1-1-table 1-3, with the reduction of remote signaling function accuracy, the financial cost of system and power failure
The amplification ratio of time is basically unchanged;With the reduction of remote measurement accuracy, the financial cost of system and the amplification ratio of power off time
Example is slightly reduced;As the reduction of remote control accuracy, financial cost and power off time the reduction amplitude of system are larger, illustrate distant
When control accuracy is higher, system can obtain larger economy and reliability benefits.From the across comparison of table 1-1-table 1-3
See, the accuracy of remote control, remote measurement and remote signaling function is apparent successively to system reliability and the presentation of financial cost influence degree
Decline trend, illustrates in the case of identical initial outlay, it is ensured that the accuracy of distant control function can obtain larger economical and can
By property income.
Table 1-1 remote signalling accuracy changes the influence to mixed economy cost and system blackout time
Table 1-2 remote measurements accuracy changes the influence to mixed economy cost and system blackout time
Table 1-3 remote controls accuracy changes the influence to mixed economy cost and system blackout time
(2) to the influence of distribution power automation terminal deployed position
Because the wrong influence to system reliability of information is relatively small, therefore investigating the accuracy pair of " three is distant " function
Distribution terminal is layouted when optimizing influence, the threshold value that the present invention is set as power supply reliability requirement by 99.992%, less than the threshold value
The allocation plan that then needs to layout distribution terminal is modified.Fig. 4-2-Fig. 4-4 sets forth " three is distant " function accuracy
Change the influence of optimum results of being layouted to distribution terminal.
As shown in the Fig. 4-2, as remote signalling accuracy is raised, the mixed economy cost reduction of distribution terminal, power supply reliability
Raise;99.992% requirement limitation is satisfied by due to power supply reliability, therefore is layouted and is distributed result rationally with remote signalling and remote measurement
The change of accuracy does not change, is z2And z6Place's configuration " two is distant " distribution terminal, z5Place's configuration " three is distant " distribution end
End.From Fig. 4-3 and Fig. 4-4, with the lifting of telemetry and telecommand accuracy, the reduction of distribution terminal mixed economy cost is supplied
Electric reliability is raised;When remote control accuracy is less than 70%, power supply reliability is less than 99.992%;Remote measurement success rate is less than 40%
When, power supply reliability is less than 99.992%;After taking correction measure, power supply reliability has clear improvement, but required input warp
Ji cost is improved;Program results of layouting also changes with remote control and the change of remote measurement accuracy, as 30%≤pc<When 35%, match somebody with somebody
Scheme is put for z2And z6Place's configuration " two is distant " distribution terminal, z4Place's configuration " three is distant " distribution terminal;As 35%≤pc<When 70%, match somebody with somebody
Scheme is put for z5And z6Place's configuration " two is distant " distribution terminal, z2Place's configuration " three is distant " distribution terminal;Work as pcWhen >=70%, distribution end
End allocation plan is former allocation plan;As 30%≤pm<When 40%, allocation plan is z5And z6Place's configuration " two is distant " distribution terminal,
z2Place's configuration " three is distant " Distributing Terminal Assembly, works as pmWhen >=40%, distribution terminal allocation plan is former allocation plan.
The various embodiments described above are merely to illustrate the present invention, and wherein each step of method etc. all can be what is be varied from,
Every equivalents carried out on the basis of technical solution of the present invention and improvement, should not exclude in protection scope of the present invention
Outside.
Claims (5)
1. a kind of distribution terminal of the wrong influence of consideration information link data transfer is layouted optimization method, it is characterised in that:It is described
Method include the following steps for carrying out in order:
1) content planned according to distribution terminal configuration quantity in electrical power distribution automatization system first, primary Calculation goes out feedback to be analyzed
The distribution terminal quantity of configuration needed for line, then sets the distribution terminal for performing this consideration information wrong influence of link data transfer
Layout module needed for optimization method, including:Feeder line species division module, distribution terminal deployment configuration division module, fault state
Division module, data acquisition module, quantum chemical method module, distribution terminal layout the wrong event division module of planning module, data,
Information link data acquisition module, information link quantify correcting module and " three is distant " function effect analysis module;
2) feeder line species division module is utilized, feeder line is divided into two categories below according to whether interconnection switch is installed on feeder line:①
The feeder line of interconnection switch is not installed;2. there is the feeder line of interconnection switch;
3) distribution terminal deployment configuration division module is utilized, the configuring condition of distribution terminal is divided into following three class:1. all
Configuration " three is distant " distribution terminal;2. " two is distant " distribution terminal is all configured;3. mixed configuration " three is distant " and " two is distant " distribution terminal;
4) fault state division module is utilized, the treatment after failure is occurred to failure is divided into three phases, 1. fault location rank
Section;2. artificial fault isolation stage;3. fault restoration stage;
5) data acquisition module is utilized, according to the step 2), 3) and 4) in result, in the configuration of above-mentioned three classes distribution terminal
In the case of, system blackout time and power failure load in three troubleshooting stages of two class feeder lines quantify number needed for Modeling Calculation
According to being acquired, required data include:Number of switches and residing is got in touch with feeder line on block switch quantity and present position, feeder line
Equivalent load sum, fault location time, artificial failure that position, fault rate, each section length of feeder line are connected with sectional area
Isolation time and fault correction time;
6) using quantifying computing module, according to the step 2), 3) and 4) in result and step 5) in collection data, to
Under above-mentioned three classes distribution terminal configuring condition, system blackout time and power failure load in three failure phases of two class feeder lines enter
Row quantifies Modeling Calculation, wherein, the quantization Modeling Calculation of system blackout time and power failure load includes:1. interconnection switch is not installed
Feeder line the system blackout time and the quantization Modeling Calculation of power failure load;During the system blackout of the feeder line that 2. there is interconnection switch
Between and power failure load quantization Modeling Calculation;
7) the information wrong event of link data transfer is divided using data wrong event division module:1. event A ---
Remote signalling-the remote control of distribution terminal is wrong but remote measurement is errorless;2. event B --- remote signalling-remote control is errorless but remote measurement is wrong;3. event
C --- remote signalling-remote control and remote measurement are wrong;
8) information link data acquisition module is utilized, according to the step 2) to step 7) in result, to step 7) in draw
Data needed for the quantization Modeling Calculation of point event are acquired, and required data include:Remote signaling function is checked and to information
The time being modified;Remote information is carried out to check amendment and the time needed for carrying out isolation processing to failure again;To distant
The function and information of control and remote signalling carry out checking the time corrected needed for carrying out isolation processing to failure again;Telemetry function is entered
Row checks and information is corrected, artificial to find the time for positioning correct abort situation;Telemetry intelligence (TELINT) is corrected, weight
The time of new failure judgement species;The probability that each event occurs;
9) quantify correcting module using information link, according to the step 2) to the result and step 8 in 7)) in collection number
According to the step 7) in all subevents carry out quantization Modeling Calculation, and calculating process is modified;
10) " three is distant " function effect analysis module is utilized, according to above-mentioned steps 2) to step 9) result to power distribution automation end
Specifically layout position of the end device on feeder line optimizes configuration, on the basis of given distribution terminal configuration quantity, utilizes
The power failure load of above-mentioned each configuring condition sets up object function, with reliability conditions as constraint of powering, and then obtains feeder line distribution
Terminal is layouted program results;And analysis " three is distant " function is effectively instructed to system blackout time, mixed economy cost and to matching somebody with somebody
The influence of electric terminals deployed position.
2. the distribution terminal of the wrong influence of consideration information link data transfer according to claim 1 is layouted optimization method,
It is characterized in that:In step 6) in, the system blackout time of the described feeder line for not installing interconnection switch and the amount of power failure load
Change Modeling Calculation and be divided into following three class according to the configuring condition of distribution terminal:A. system during " three is distant " distribution terminal is all configured
The quantization Modeling Calculation of power off time and power failure load;B. all configuration " two is distant " distribution terminal when the system blackout time and stop
The quantization Modeling Calculation of electric load;C. mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and have a power failure negative
The quantization Modeling Calculation of lotus;
A. the system blackout time and the quantization Modeling Calculation step of power failure load during whole configuration " three is distant " distribution terminals is as follows:
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage system is stopped
Electric time and the quantization Modeling Calculation of power failure load;(3) quantization of fault restoration stage system power off time and power failure load is built
Mould is calculated;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load:
The fault location stage corresponding system blackout time of i-th section of region wire failure is:
In formula, T1iRepresent the fault location stage corresponding system blackout time of i-th section of region wire failure, t1iIt is i-th section of area
The fault location time in domain, UiRepresent i-th section of total number of users of block supply;liRepresent i-th section of substitutional connection length in region;
fiI-th section of equivalent of the apparatus fault rate in region is represented, unit is secondary/kma;M represents the number of fragments of feeder line;
Fault location stage corresponding system blackout time T1For:
System blackout load is accordingly:
In formula, E1iRepresent the corresponding system blackout load of fault location stage of i-th section of region wire failure, PiRepresent i-th section
The equivalent load sum of whole loads of block supply;
The corresponding system blackout load E of fault location stage1For:
(2) the quantization Modeling Calculation of artificial fault isolation stage system blackout time and power failure load:
The artificial fault isolation stage corresponding system blackout time of i-th section of region wire failure is:
In formula, T2iRepresent the artificial fault isolation stage corresponding system blackout time of i-th section of region wire failure, t2iIt is i-th
The artificial Fault Isolation time in section region;
Artificial fault isolation stage corresponding system blackout time T2For:
System blackout load is accordingly:
In formula, E2iRepresent the corresponding system blackout load of artificial fault isolation stage of i-th section of region wire failure;
The corresponding system blackout load E of artificial fault isolation stage2For:
(3) the quantization Modeling Calculation of fault restoration stage system power off time and power failure load:
The corresponding system blackout time in fault restoration stage of i-th section of region wire failure is:
In formula, T3iRepresent the corresponding system blackout time in fault restoration stage of i-th section of region wire failure, t3iIt is i-th section of area
The fault correction time in domain;zk=0 represents relevant position configuration distribution terminal, zk=1 represents relevant position does not configure distribution end
End;
Corresponding system blackout time T in fault restoration stage3For:
System blackout load is accordingly:
In formula, E3iRepresent the fault restoration stage corresponding system blackout load of i-th section of region wire failure;
Fault restoration stage corresponding system blackout load E3For:
(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load:
T=T1+T2+T3 (13)
In formula, T is corresponding system blackout time in whole troubleshooting stage, unit h;T1、T2And T3Above-mentioned failure is corresponded to respectively
The system blackout time of positioning stage, artificial fault isolation stage and fault restoration stage, unit is h;
E=E1+E2+E3 (14)
In formula, E is corresponding system blackout load of whole troubleshooting stage, unit kWh;E1、E2And E3Above-mentioned event is corresponded to respectively
Barrier positioning stage, artificial fault isolation stage and the system blackout load in fault restoration stage, unit are kWh;
B. the system blackout time and the quantization Modeling Calculation step of power failure load during whole configuration " two is distant " distribution terminals is as follows:
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage system is stopped
Electric time and the quantization Modeling Calculation of power failure load;(3) quantization of fault restoration stage system power off time and power failure load is built
Mould is calculated;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load is consistent with formula (1)-(4),
But due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation formula and formula (5)-(8) of artificial fault isolation stage system blackout time and power failure load
Cause, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load is consistent with formula (9)-(12);
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14) one
Cause.
C. the quantization Modeling Calculation of mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and power failure load
Step is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial Fault Isolation
The quantization Modeling Calculation of stage system power off time and power failure load;(3) fault restoration stage system power off time and power failure are negative
The quantization Modeling Calculation of lotus;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load is consistent with formula (1)-(4),
But due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation of artificial fault isolation stage service system power off time and power failure load:
First, it is assumed that the line sectionalizing switch of configuration " three is distant " distribution terminal is common M-1, then based on all " three is distant " distribution terminals
Line sectionalizing switch divides " three is distant " common M in region for obtaining.For analyze artificial fault isolation stage the system blackout time and
Power failure load, uses Ωi’The load aggregation in the i-th ' individual " three is distant " distribution terminal region is represented, | Ωi’| it is the user in the region
Sum;With event group W=(w1,w2,…,w2i’-1,w2i’,…,w2M-1,w2M) " three is distant " distribution end residing for representing fault position
The configuring condition of " two is distant " Distributing Terminal Assembly, altogether including 2M event, is embodied as in region determined by end and region:
w2i’-1:Failure generation is configured with " two is distant " and matches somebody with somebody in the i-th ' individual " three is distant " region determined by distribution terminal, and the region
Electric terminals;
w2i’:Failure occurs to be not configured with " two is distant " distribution end in the i-th ' individual " three is distant " region, but region determined by distribution terminal
End;
Then the artificial fault isolation stage of the i-th section of region wire failure corresponding system blackout time be:
System blackout load is accordingly:
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load is consistent with formula (9)-(12).
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14) one
Cause.
The system blackout time and power failure load modeling that there is the feeder line of interconnection switch are calculated according to the configuring condition of distribution terminal
It is divided into following three class:The quantization modeling of system blackout time and power failure load when a. all configuring " three is distant " distribution terminal is counted
Calculate;B. system blackout time during whole configuration " two is distant " distribution terminals and the quantization Modeling Calculation of power failure load;C. mixing is matched somebody with somebody
The quantization Modeling Calculation of system blackout time and power failure load when putting " three is distant " and " two is distant " distribution terminal;
A. the system blackout time and the quantization Modeling Calculation step of power failure load during whole configuration " three is distant " distribution terminals is as follows:
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage system is stopped
Electric time and the quantization Modeling Calculation of power failure load;(3) quantization of fault restoration stage system power off time and power failure load is built
Mould is calculated;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load is consistent with formula (1)-(4),
But due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0;
(2) the quantization Modeling Calculation formula and formula (5)-(8) of artificial fault isolation stage system blackout time and power failure load
Cause, but due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0.
(3) the quantization Modeling Calculation of fault restoration stage system power off time and power failure load:
The corresponding system blackout time in fault restoration stage of i-th section of region wire failure is:
In formula, T3iRepresent the corresponding system blackout time in fault restoration stage of i-th section of region wire failure, t3iIt is i-th section of area
The fault correction time in domain;
The fault restoration stage, corresponding system blackout Time Calculation formula was consistent with formula (10).
System blackout load is accordingly:
In formula, E3iRepresent the fault restoration stage corresponding system blackout load of i-th section of region wire failure;
The fault restoration stage, corresponding system blackout carry calculation formula was consistent with formula (12).
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14) one
Cause.
B. the system blackout time and the quantization Modeling Calculation step of power failure load during whole configuration " two is distant " distribution terminals is as follows:
(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial fault isolation stage system is stopped
Electric time and the quantization Modeling Calculation of power failure load;(3) quantization of fault restoration stage system power off time and power failure load is built
Mould is calculated;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load is consistent with formula (1)-(4),
But due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(2) the quantization Modeling Calculation formula and formula (5)-(8) of artificial fault isolation stage system blackout time and power failure load
Cause, but due to each section of artificial failure load isolation time t in region2iIt is not 0, therefore result of calculation is not 0;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (10), (12), (19)
(20) it is consistent;
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14) one
Cause;
C. the quantization Modeling Calculation of mixed configuration " three is distant " and system blackout time during " two is distant " distribution terminal and power failure load
Step is as follows:(1) the quantization Modeling Calculation of fault location stage system blackout time and power failure load;(2) artificial Fault Isolation
The quantization Modeling Calculation of stage system power off time and power failure load;(3) fault restoration stage system power off time and power failure are negative
The quantization Modeling Calculation of lotus;(4) the quantization Modeling Calculation of troubleshooting stage system power off time and power failure load;
(1) the quantization Modeling Calculation formula of fault location stage system blackout time and power failure load is consistent with formula (1)-(4),
But due to each section of artificial failure load isolation time t in region2iIt is 0, therefore result of calculation is 0;
(2) the quantization Modeling Calculation formula and formula (15)-(18) of artificial fault isolation stage system blackout time and power failure load
Unanimously;
(3) the quantization Modeling Calculation formula of fault restoration stage system power off time and power failure load and formula (10), (12), (19)
(20) it is consistent;
(4) the quantization Modeling Calculation formula of troubleshooting stage system power off time and power failure load and formula (13) and (14) one
Cause.
3. the distribution terminal of the wrong influence of consideration information link data transfer according to claim 1 is layouted optimization method,
It is characterized in that:In step 7) in, described event A includes following three classes subevent:A. event A1:Remote information is errorless, but
Remote signalling information is wrong.B. event A2:Remote information is wrong, but remote signalling information is errorless;C. event A3:Remote information is wrong, and distant
Letter information is wrong;
Event B includes following three classes subevent:A. event B1:The determination of telemetry intelligence (TELINT) erroneous effects abort situation.B. event B2:
The determination of telemetry intelligence (TELINT) erroneous effects failure mode.C. event B3:Telemetry intelligence (TELINT) mistake influences abort situation and species simultaneously
It is determined that;
Event C includes the nine class subevents determined by event A and event B:A. event C1:Remote information is errorless, but remote signalling is believed
Breath it is wrong, and telemetry intelligence (TELINT) erroneous effects abort situation determination;B. event C2:Remote information is errorless, but remote signalling information is wrong,
And information errors influence the determination of failure mode;C. event C3:Remote information is errorless, but remote signalling information is wrong, and telemetry intelligence (TELINT)
Mistake influences the determination of abort situation and species simultaneously;D. event C4:E. remote information is wrong, but remote signalling information is errorless, and distant
The determination of measurement information erroneous effects abort situation;Event C5:Remote information is wrong, but remote signalling information is errorless, and information errors shadow
Ring the determination of failure mode;F. event C6:Remote information is wrong, but remote signalling information is errorless, and telemetry intelligence (TELINT) mistake influences simultaneously
The determination of abort situation and species;G. event C7:Remote control and remote signalling information are wrong, and telemetry intelligence (TELINT) erroneous effects abort situation
Determination;H. event C8:Remote control and remote signalling information are wrong, and telemetry intelligence (TELINT) erroneous effects failure mode determination;I. event
C9:Remote control and remote signalling information are wrong, and telemetry intelligence (TELINT) mistake influences the determination of abort situation and species simultaneously.
4. the distribution terminal of the wrong influence of consideration information link data transfer according to claim 1 is layouted optimization method,
It is characterized in that:In step 9) in, it is described to step 7) in all subevents quantify the specific steps of Modeling Calculation such as
Under:
1. event A quantifies correction model includes the quantization correction model of three class events:
A. event A1:When this occurs, relative to above-mentioned steps 6) in the fault restoration stage quantization formula, wherein
Fault correction time need to be modified to:
In formula,It is the time for being checked remote signaling function and being modified to information;
B. event A2:When this occurs, relative to above-mentioned steps 6) in artificial fault isolation stage quantitative model, wherein
The system blackout load of artificial fault isolation stage be expressed as:
In formula, t2"=t2 12Time for needed for inspection amendment being carried out to remote information and carry out isolation processing to failure again;
C. event A3:When this occurs, relative to above-mentioned steps 6) in the fault restoration stage quantization formula, wherein
Artificial fault isolation stage system blackout carry calculation formula it is consistent with formula (22), the t in this up-to-date style2" need to use t2 13
Replace, t2 13Represent needed for the function and information of remote control and remote signalling check amendment and carrying out to failure isolation processing again
Time;
2. event B quantifies correction model includes the quantization correction model of three class events:
A. event B1:When this occurs, relative to above-mentioned steps 6) in fault location stage quantization formula, wherein
Fault location time need to be modified to:
Wherein, t1 21It is telemetry function to be checked and information is corrected, artificial searching positions correct abort situation
Time.
B. event B2:When this occurs, relative to above-mentioned steps 6) in fault location stage quantization formula, wherein
Fault location time need to be modified to:
Wherein, t1 22It is that telemetry intelligence (TELINT) is corrected, rejudges the time of failure mode;
C. event B3:When this occurs, relative to above-mentioned steps 6) in fault location stage quantization formula, wherein
Fault location time need to be modified to:
3. event C quantifies correction model includes the quantization correction model of nine class events:
Because nine class subevents in event C are combined with three class subevents in event B by three class subevents in event A,
Therefore the time quantization correction model of this nine classes event generation is:
A. (probability for setting its generation is p to event C131):
tC11=t3i+t3 11 (26)
tC12=t1i+t1 21 (27)
tC1=tC11+tC12 (28)
B. (probability for setting its generation is p to event C232):
tC21=t3i+t3 11 (29)
tC22=t1i+t1 22 (30)
tC2=tC21+tC22 (31)
C. (probability for setting its generation is p to event C333):
tC31=t3i+t3 11 (32)
tC32=t1i+t1 21+t1 22 (33)
tC3=tC31+tC32 (34)
D. (probability for setting its generation is p to event C434):
tC41=t2i+t2 12 (35)
tC42=t1i+t1 21 (36)
tC4=tC41+tC42 (37)
E. (probability for setting its generation is p to event C535):
tC51=t2i+t2 12 (38)
tC52=t1i+t1 22 (39)
tC5=tC51+tC52 (40)
F. (probability for setting its generation is p to event C636):
tC61=t2i+t2 12 (41)
tC62=t1+t1i 21+t1 22 (42)
tC6=tC61+tC62 (43)
G. (probability for setting its generation is p to event C737):
tC71=t2i+t2 13 (44)
tC72=t1i+t1 21 (45)
tC7=tC71+tC72 (46)
H. (probability for setting its generation is p to event C838):
tC81=t2i+t2 13 (47)
tC82=t1i+t1 22 (48)
tC8=tC81+tC82 (49)
I. (probability for setting its generation is p to event C939):
tC91=t2i+t2 13 (50)
tC92=t1i+t1 21+t1 22 (51)
tC9=tC91+tC92 (52)
Assuming that the accuracy of remote information is pc;The accuracy of remote signalling information is ps;The accuracy of telemetry intelligence (TELINT) is pm, wherein, pm
Can be expressed as again:
(1-pm)=pm1+pm2+pm3 (53)
Wherein, pm1Represent the wrong influence abort situation of remote measurement but the probability for not influenceing failure mode definite event to occur;pm2Generation
The wrong influence failure mode of table remote measurement but the probability that impact position definite event does not occur;pm3Represent the wrong influence failure of remote measurement
The probability that species and position definite event occur;
Therefore, the probability that each subevent occurs can be expressed as:
P=1-pm·pc·ps (54)
Wherein, p is the probability that the wrong event of data occurs.
p1=(1-pc·ps)pm (55)
p2=(1-pm)·pc·ps (56)
p3=(1-pc·ps)·(1-pm) (57)
p11=pc·(1-ps)·pm (58)
p12=(1-pc)·ps·pm (59)
p13=(1-pc)(1-ps)·pm (60)
p21=pc·ps·pm1 (61)
p22=pc·ps·pm2 (62)
p23=pc·ps·pm3 (63)
p31=pc·(1-ps)·pm1 (64)
p32=pc·(1-ps)·pm2 (65)
p33=pc·(1-ps)·pm3 (66)
p34=(1-pc)·ps·pm1 (67)
p35=(1-pc)·ps·pm2 (68)
p36=(1-pc)·ps·pm3 (69)
p37=(1-pc)(1-ps)·pm1 (70)
p38=(1-pc)(1-ps)·pm2 (71)
p39=(1-pc)(1-ps)·pm3 (72)
Each phases-time is modified with expectation value analysis method, be configured with after amendment correct in the case of " three is distant " terminal when
Between it is as follows:
1. the time complexity curve of fault location stage:
Obtained after arrangement:
2. the time complexity curve of artificial fault isolation stage:
3. the time complexity curve in fault restoration stage:
Bring the revised time into above-mentioned steps 6) in Chinese style (1) to formula (20).
5. the distribution terminal of the wrong influence of consideration information link data transfer according to claim 1 is layouted optimization method,
It is characterized in that:In step 10) in, described utilization " three is distant " function effect analysis module, according to above-mentioned steps 2) to step
9) specifically layout position of the result to distribution power automation terminal device on feeder line optimizes configuration, in given distribution terminal
On the basis of configuration quantity, object function is set up using the power failure load of above-mentioned each configuring condition, reliability conditions are to power
Constraint, and then obtain feeder line distribution terminal and layout the comprising the following steps that of program results:
A. according to step 7) in formula (74)~(76) replacement step 6 for obtaining) in respective stage power off time, according to step
6) the power failure load for obtaining sets up object function, and uses genetic algorithm for solving object function, carries out genetic manipulation;Object function
It is as follows:
In formula, CEIt is unit electricity loss of outage;N2And N3It is the configuration quantity of " two is distant " and " three is distant " distribution terminal;C2And C3For
The initial outlay unit price of " two is distant " and " three is distant " distribution terminal;i2And i3It is discounting for " two is distant " and " three is distant " distribution terminal investment
Rate;a2And a3It is the Economic Life of " two is distant " and " three is distant " distribution terminal;
B. the fitness value in genetic algorithm judges whether to reach stopping criterion for iteration, and method is to build fitness function,
Reliability constraint is added in the object function shown in formula (77) in the form of penalty function, as hereditary individual fitness
Evaluation function;
Wherein, reliability constraint uses the power supply reliability threshold value constraint condition of setting, i.e.,
β1> βset (78)
Wherein, βsetIt is the power supply reliability requirement of feeder line;β1It is the power supply reliability under distribution terminal sensor distributing, specific table
Up to formula such as formula (23) Suo Shi:
Wherein, T considers that the influence of information system is calculated using formula (13) with formula (74)~(76);
C. when reliability constraint is unsatisfactory in continuous m generations, then return to step 1), readjust required configuration on feeder line
Distribution terminal quantity;Otherwise terminate, the optimal program results of layouting of output feeder distribution terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710137585.5A CN106887839B (en) | 2017-03-09 | 2017-03-09 | Distribution terminal distribution optimization method considering data transmission error influence of information link |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710137585.5A CN106887839B (en) | 2017-03-09 | 2017-03-09 | Distribution terminal distribution optimization method considering data transmission error influence of information link |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106887839A true CN106887839A (en) | 2017-06-23 |
CN106887839B CN106887839B (en) | 2020-05-12 |
Family
ID=59180263
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710137585.5A Active CN106887839B (en) | 2017-03-09 | 2017-03-09 | Distribution terminal distribution optimization method considering data transmission error influence of information link |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106887839B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108521124A (en) * | 2018-04-26 | 2018-09-11 | 福建积微科技有限公司 | A kind of visual distribution network failure section partition method |
CN108595382A (en) * | 2018-06-22 | 2018-09-28 | 天津大学 | Distribution network structure class parametric sensitivity computational methods based on fault estimator |
CN108711852A (en) * | 2018-06-22 | 2018-10-26 | 天津大学 | A kind of distribution network failure parametric sensitivity computational methods based on fault estimator |
CN110932272A (en) * | 2019-12-13 | 2020-03-27 | 国网福建省电力有限公司三明供电公司 | Three-remote power distribution terminal optimal configuration method |
CN111382392A (en) * | 2020-03-23 | 2020-07-07 | 国网江西省电力有限公司经济技术研究院 | Method for calculating total time of fault handling of power distribution network and method for calculating reliability of total time |
CN111884335A (en) * | 2020-07-02 | 2020-11-03 | 武汉理工大学 | Feeder automation terminal optimization method based on section switch importance degree |
CN115099651A (en) * | 2022-07-04 | 2022-09-23 | 西安理工大学 | Power distribution network information physical system operation risk assessment method considering information events |
CN116073381A (en) * | 2023-03-21 | 2023-05-05 | 国网湖北省电力有限公司武汉供电公司 | Automatic equipment point distribution decision method considering reliability of power distribution network |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009230167A (en) * | 2008-03-19 | 2009-10-08 | Nec Infrontia Corp | Master data management system, master data management method, master data management program and program recording medium |
CN102882274A (en) * | 2012-09-07 | 2013-01-16 | 中国电力科学研究院 | Terminal fusion system applied to distribution network |
CN202749911U (en) * | 2012-08-23 | 2013-02-20 | 国家电网公司 | Power distribution terminal |
US20140207300A1 (en) * | 2011-08-26 | 2014-07-24 | Korea Electric Power Corporation | System and method for managing a power distribution system |
CN105356610A (en) * | 2015-11-26 | 2016-02-24 | 江苏省电力公司南京供电公司 | Configuration method of distribution automation terminal of intelligent power distribution network |
CN106374463A (en) * | 2016-10-27 | 2017-02-01 | 国家电网公司 | A+ power supply region power distribution network power supply mode configuration method |
-
2017
- 2017-03-09 CN CN201710137585.5A patent/CN106887839B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009230167A (en) * | 2008-03-19 | 2009-10-08 | Nec Infrontia Corp | Master data management system, master data management method, master data management program and program recording medium |
US20140207300A1 (en) * | 2011-08-26 | 2014-07-24 | Korea Electric Power Corporation | System and method for managing a power distribution system |
CN202749911U (en) * | 2012-08-23 | 2013-02-20 | 国家电网公司 | Power distribution terminal |
CN102882274A (en) * | 2012-09-07 | 2013-01-16 | 中国电力科学研究院 | Terminal fusion system applied to distribution network |
CN105356610A (en) * | 2015-11-26 | 2016-02-24 | 江苏省电力公司南京供电公司 | Configuration method of distribution automation terminal of intelligent power distribution network |
CN106374463A (en) * | 2016-10-27 | 2017-02-01 | 国家电网公司 | A+ power supply region power distribution network power supply mode configuration method |
Non-Patent Citations (1)
Title |
---|
刘健等: "面向供电可靠性的配电自动化系统规划研究", 《电力系统自动化》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108521124A (en) * | 2018-04-26 | 2018-09-11 | 福建积微科技有限公司 | A kind of visual distribution network failure section partition method |
CN108595382B (en) * | 2018-06-22 | 2021-08-27 | 天津大学 | Fault correlation matrix-based power distribution network structure parameter sensitivity calculation method |
CN108595382A (en) * | 2018-06-22 | 2018-09-28 | 天津大学 | Distribution network structure class parametric sensitivity computational methods based on fault estimator |
CN108711852A (en) * | 2018-06-22 | 2018-10-26 | 天津大学 | A kind of distribution network failure parametric sensitivity computational methods based on fault estimator |
CN110932272A (en) * | 2019-12-13 | 2020-03-27 | 国网福建省电力有限公司三明供电公司 | Three-remote power distribution terminal optimal configuration method |
CN111382392A (en) * | 2020-03-23 | 2020-07-07 | 国网江西省电力有限公司经济技术研究院 | Method for calculating total time of fault handling of power distribution network and method for calculating reliability of total time |
CN111382392B (en) * | 2020-03-23 | 2023-04-18 | 国网江西省电力有限公司经济技术研究院 | Method for calculating total time of fault handling of power distribution network and method for calculating reliability of total time |
CN111884335A (en) * | 2020-07-02 | 2020-11-03 | 武汉理工大学 | Feeder automation terminal optimization method based on section switch importance degree |
CN111884335B (en) * | 2020-07-02 | 2022-06-14 | 武汉理工大学 | Feeder automation terminal optimization method based on section switch importance degree |
CN115099651A (en) * | 2022-07-04 | 2022-09-23 | 西安理工大学 | Power distribution network information physical system operation risk assessment method considering information events |
CN115099651B (en) * | 2022-07-04 | 2024-08-27 | 西安理工大学 | Power distribution network information physical system operation risk assessment method considering information event |
CN116073381A (en) * | 2023-03-21 | 2023-05-05 | 国网湖北省电力有限公司武汉供电公司 | Automatic equipment point distribution decision method considering reliability of power distribution network |
CN116073381B (en) * | 2023-03-21 | 2023-06-13 | 国网湖北省电力有限公司武汉供电公司 | Automatic equipment point distribution decision method considering reliability of power distribution network |
Also Published As
Publication number | Publication date |
---|---|
CN106887839B (en) | 2020-05-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106887839A (en) | The distribution terminal of the consideration information wrong influence of link data transfer is layouted optimization method | |
Lei et al. | Radiality constraints for resilient reconfiguration of distribution systems: Formulation and application to microgrid formation | |
Esmaili et al. | Redundant observability PMU placement in the presence of flow measurements considering contingencies | |
Fu et al. | Risk assessment for special protection systems | |
CN109146124B (en) | Power distribution terminal transformation decision method based on time-varying failure rate | |
CN109617134A (en) | The robust Unit Combination method of meter and Uncertainty prediction error temporal correlation | |
CN103942738A (en) | Comprehensive evaluation method and system for electric energy meter | |
CN107609725A (en) | A kind of power transmission network methods of risk assessment for considering transformer station and influenceing | |
Guo et al. | A stochastic multiagent optimization framework for interdependent transportation and power system analyses | |
CN106251045A (en) | Distribution network reliability appraisal procedure based on multiple leading factor | |
CN105356461B (en) | A kind of accounting method of the load unbalanced administration project carbon emission reduction amount of low voltage electric network | |
CN109038568A (en) | Voltage dip comprehensive processing method based on co-ordination of supply and demand | |
CN104008455B (en) | Forward-back substitution method for reliability assessment of complex radial power distribution networks | |
Choi et al. | Impact analysis of locational marginal price subject to power system topology errors | |
Wang et al. | Fast supply reliability evaluation of integrated power-gas system based on stochastic capacity network model and importance sampling | |
CN102570451A (en) | Static reliability assessment method for power transmission network | |
CN106130189A (en) | Job site temporary power condition monitoring system and method | |
CN104361531A (en) | Identification method and system for high-risk failure equipment of substation automation system | |
CN106559242A (en) | A kind of balancing method of power telecom network operation troubles | |
CN106548284A (en) | A kind of adaptive mode massing power grid security Alarm Assessment method towards operation regulation and control | |
Gao et al. | Assessing the comprehensive importance of power grid nodes based on DEA | |
CN105335824B (en) | Distribution network failure repairing command methods and system based on data center | |
Tian et al. | A multi-agent system based fault diagnosis for active distribution systems | |
CN107292524A (en) | Intelligent substation secondary safety measure automatic generation method and device | |
Zhang et al. | Collaborative stochastic expansion planning of cyber‐physical system considering extreme scenarios |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |