CN106844432A - Data processing method and device - Google Patents

Data processing method and device Download PDF

Info

Publication number
CN106844432A
CN106844432A CN201611147756.4A CN201611147756A CN106844432A CN 106844432 A CN106844432 A CN 106844432A CN 201611147756 A CN201611147756 A CN 201611147756A CN 106844432 A CN106844432 A CN 106844432A
Authority
CN
China
Prior art keywords
renewal
configuration
transformer substation
configuration file
files
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611147756.4A
Other languages
Chinese (zh)
Inventor
肖永立
孙军
张伟程
蔡庆
郑同伟
范金龙
刘少波
钱志国
任建军
见伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Beijing Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201611147756.4A priority Critical patent/CN106844432A/en
Publication of CN106844432A publication Critical patent/CN106844432A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/10File systems; File servers
    • G06F16/16File or folder operations, e.g. details of user interfaces specifically adapted to file systems
    • G06F16/164File meta data generation

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Data Mining & Analysis (AREA)
  • Databases & Information Systems (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of data processing method and device.Wherein, the data processing method is used to determine transformer substation configuration file variation after the updating that the method to include:Transformer substation configuration file after obtaining the transformer substation configuration file before updating and updating;Transformer substation configuration file before renewal is parsed, the configuration before being updated, wherein, configuration includes the Content of Communication between the topological relation between device attribute, equipment and equipment;Transformer substation configuration file after renewal is parsed, the configuration after being updated;Configuration after configuration before renewal and renewal is compared to determine transformer substation configuration file variation after the updating one by one.The present invention solves the less efficient technical problem that the SCD file before and after updating is detected in correlation technique.

Description

Data processing method and device
Technical field
The present invention relates to data processing field, in particular to a kind of data processing method and device.
Background technology
The correctness of transformer substation configuration file (abbreviation SCD), is related to the correctness of secondary device operation in transformer station, closes The reliability of relay protection and automation equipment action is tied to, is related to the security of the work such as transformer station's enlarging, transformation.In intelligence In energy transformer station, whole station configuration file SCD is the basis of secondary device communication, but SCD file is main by system integrator's establishment And maintenance, after SCD file version change, its local transfer portion is unknown on the coverage and influence program of other parts, has New mistake may be introduced, it is therefore desirable to debug unit and be driven development SCD just by carrying out actual signal to secondary device True property, but actual transmission wastes time and energy, and inefficiency is also difficult to test whole of the SCD institutes comprising signal.
At present, for SCD file grammer in itself correctness detection have Some tools, such as foreign countries' KEMA laboratory developments Service-oriented consistency testing system series of products, including IEC61850 clients and service end communication service simulation tool, GOOSE publish/subscribe simulation tools, model checking tools and IEC61850 communication monitorings and analysis tool etc., these instruments master It is used for KEMA laboratories IEC61850 standard authentications, is directed to the most basic instrument of IEC61850 model inspections;Domestic mesh The secondary equipment of intelligent converting station product producer of preceding each main flow develops privately owned model checking tools, for icd, cid, Whether the grammer of scd meets 61850 standards is detected, but for model difference in version analysis etc. be not directed to.If SCD and the difference of legacy version after Direct Analysis and intuitively displaying version change, analyze its coverage and influence degree, then may be used Human error is reduced, efficiency is improved, it is ensured that engineering debugs quality.
For the less efficient technical problem that the SCD file before and after updating is detected in correlation technique, not yet propose at present Effective solution.
The content of the invention
A kind of data processing method and device are the embodiment of the invention provides, at least to solve to detect renewal in correlation technique The less efficient technical problem of front and rear SCD file.
One side according to embodiments of the present invention, there is provided a kind of data processing method, it is characterised in that at the data Reason method is used to determine transformer substation configuration file variation after the updating that the method to include:The transformer station before updating is obtained to match somebody with somebody Transformer substation configuration file after putting file and updating;Transformer substation configuration file before renewal is parsed, before being updated Configuration, wherein, configuration includes the Content of Communication between the topological relation between device attribute, equipment and equipment;After renewal Transformer substation configuration file is parsed, the configuration after being updated;Configuration after configuration before renewal and renewal is compared one by one To determine transformer substation configuration file variation after the updating.
Further, before to renewal configuration and the configuration after updating compare to determine that transformer substation configuration file exists one by one Before variation after renewal, the method also includes:Obtain in the transformer substation configuration file before updating the check code that includes and more The check code included in transformer substation configuration file after new;Judge in the transformer substation configuration file before updating the check code that includes and Whether the check code included in the transformer substation configuration file after renewal is identical, wherein, check code is by presetting checking algorithm pair The content of transformer substation configuration file performs the data being calculated;If it is judged that be no, then to the configuration before renewal and more Configuration after new compares to determine transformer substation configuration file variation after the updating one by one;Otherwise, do not perform to before renewal Configuration after configuration and renewal is compared one by one.
Further, transformer substation configuration file is parsed, obtaining configuration includes:Obtain transformer substation configuration file IED files and Communication files;Device attribute is determined according to IED files;Determined according to Communication files The Content of Communication between topological relation and equipment between equipment.
Further, to the configuration before renewal and update after configuration compare one by one including:Compare update before configuration in It is whether identical with the quantity of the IED files in the configuration after renewal, title;Setting after comparing the device attribute before updating and updating Whether standby attribute is identical;Whether the topological relation between equipment after comparing the topological relation between the equipment before updating and updating It is identical;Whether the Content of Communication between equipment after comparing the Content of Communication between the equipment before updating and updating is identical.
Further, IED files include multiple IED files, and multiple IED files include an IED files, before to renewal Configuration and update after configuration compare one by one after, method also include displaying update after configuration, wherein, displaying update after Configuration includes:Show that physical couplings and link in an IED files and multiple IED files between other IED files connect Connect relation;Show the empty loop between each link.
Another aspect according to embodiments of the present invention, additionally provides a kind of data processing equipment, and the data processing equipment is used In it is determined that transformer substation configuration file variation after the updating, the device includes:First acquisition unit, before obtaining renewal Transformer substation configuration file after transformer substation configuration file and renewal;First resolution unit, for the transformer station's configuration before renewal File is parsed, the configuration before being updated, wherein, configuration includes the topological relation and equipment between device attribute, equipment Between Content of Communication;Second resolution unit, for being parsed to the transformer substation configuration file after renewal, after being updated Configuration;First comparing unit, for comparing the configuration after the configuration before renewal and renewal to determine transformer station's configuration text one by one Part variation after the updating.
Further, the device also includes:Second acquisition unit, for the configuration after the configuration before to renewal and renewal Compare one by one with before determining transformer substation configuration file variation after the updating, in obtaining the transformer substation configuration file before updating Comprising check code and transformer substation configuration file after updating in the check code that includes;Judging unit, before judging to update Whether the check code included in the transformer substation configuration file after the check code included in transformer substation configuration file and renewal is identical, its In, check code is to perform the data being calculated to the content of transformer substation configuration file by presetting checking algorithm;Second compares Unit, for if it is judged that be it is no, then to the configuration before renewal and update after configuration compare to determine transformer station one by one Configuration file variation after the updating;Logic unit, for when judged result is to be, not performing to the configuration before renewal and Configuration after renewal is compared one by one.
Further, the first resolution unit and the second resolution unit are resolution unit, and resolution unit includes:Acquisition module, IED files and Communication files for obtaining transformer substation configuration file;First determining module, for according to IED texts Part determines device attribute;Second determining module, for determined according to Communication files the topological relation between equipment and Content of Communication between equipment.
Further, the first comparing unit includes:First comparison module, after comparing the configuration neutralization renewal before updating Configuration in the quantity of IED files, title it is whether identical;Second comparison module, for compare update before device attribute and Whether the device attribute after renewal is identical;3rd comparison module, for comparing the topological relation and more between the equipment before updating Whether the topological relation between equipment after new is identical;4th comparison module, for comparing the communication between the equipment before updating Whether the Content of Communication between equipment after content and renewal is identical.
Further, IED files include multiple IED files, and multiple IED files include an IED files, and device also includes Display unit, the configuration after display unit is used for the configuration before to renewal and updates relatively shows matching somebody with somebody after updating afterwards one by one Put, wherein, display unit includes:First display module, for showing an IED files with other IED texts in multiple IED files Physical couplings and link connection relation between part;Second display module, for showing the empty loop between each link.
In embodiments of the present invention, the transformer station after obtaining the transformer substation configuration file before updating and updating configures text Part;Transformer substation configuration file before renewal is parsed, the configuration before being updated, wherein, configuration includes device attribute, sets The Content of Communication between topological relation and equipment between standby;Transformer substation configuration file after renewal is parsed, is obtained more Configuration after new;Configuration after configuration before renewal and renewal is compared to determine transformer substation configuration file after the updating one by one Variation, solve the less efficient technical problem that the SCD file before and after updating is detected in correlation technique, and then realize more The technique effect of the SCD file before and after efficiently detection updates.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, this hair Bright schematic description and description does not constitute inappropriate limitation of the present invention for explaining the present invention.In the accompanying drawings:
Fig. 1 is the flow chart of a kind of optional data processing method according to embodiments of the present invention;
Fig. 2 is the schematic diagram of the topological relation between a kind of optional power transformation station equipment according to embodiments of the present invention;
Fig. 3 is the schematic diagram of the Content of Communication between a kind of optional power transformation station equipment according to embodiments of the present invention;
Fig. 4 is the schematic diagram of a kind of optional data processing equipment according to embodiments of the present invention.
Specific embodiment
In order that those skilled in the art more fully understand the present invention program, below in conjunction with the embodiment of the present invention Accompanying drawing, is clearly and completely described to the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only The embodiment of a part of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill people The every other embodiment that member is obtained under the premise of creative work is not made, should all belong to the model of present invention protection Enclose.
It should be noted that term " first ", " in description and claims of this specification and above-mentioned accompanying drawing Two " it is etc. for distinguishing similar object, without for describing specific order or precedence.It should be appreciated that so using Data can exchange in the appropriate case, so as to embodiments of the invention described herein can with except illustrating herein or Order beyond those of description is implemented.Additionally, term " comprising " and " having " and their any deformation, it is intended that cover Lid is non-exclusive to be included, for example, the process, method, system, product or the equipment that contain series of steps or unit are not necessarily limited to Those steps or unit clearly listed, but may include not list clearly or for these processes, method, product Or other intrinsic steps of equipment or unit.
According to the embodiment of the present application, there is provided a kind of data processing method.
Fig. 1 is the flow chart of a kind of optional data processing method according to embodiments of the present invention, the data processing method For determining transformer substation configuration file variation after the updating, as shown in figure 1, the method comprises the following steps:
Step S101, the transformer substation configuration file after obtaining the transformer substation configuration file before updating and updating;
Step S102, parses to the transformer substation configuration file before renewal, the configuration before being updated, wherein, configuration Including the Content of Communication between the topological relation and equipment between device attribute, equipment;
Step S103, parses to the transformer substation configuration file after renewal, the configuration after being updated;
Step S104, compares to determine transformer substation configuration file more one by one to the configuration after the configuration before renewal and renewal Variation after new.
Transformer substation configuration file of the embodiment after obtaining the transformer substation configuration file before updating and updating;To updating Preceding transformer substation configuration file is parsed, the configuration before being updated, wherein, configuration is included between device attribute, equipment Content of Communication between topological relation and equipment;Transformer substation configuration file after renewal is parsed, matching somebody with somebody after being updated Put;Configuration after configuration before renewal and renewal is compared to determine transformer substation configuration file variation after the updating one by one, The less efficient technical problem that the SCD file before and after updating is detected in correlation technique is solved, and then is realized more efficiently The technique effect of the SCD file before and after detection renewal.
Preferably, before to renewal configuration and the configuration after updating compare to determine transformer substation configuration file more one by one Before variation after new, the method also includes:Obtain the check code and renewal included in the transformer substation configuration file before updating The check code included in transformer substation configuration file afterwards;Judge in the transformer substation configuration file before updating the check code that includes and more Whether the check code included in the transformer substation configuration file after new is identical, wherein, check code is to becoming by default checking algorithm The content of power station configuration file performs the data being calculated;If it is judged that be no, then to the configuration and renewal before renewal Configuration afterwards compares to determine transformer substation configuration file variation after the updating one by one;Otherwise, matching somebody with somebody before not performing to renewal Configuration after putting and updating is compared one by one.
Preferably, transformer substation configuration file is parsed, obtaining configuration includes:Obtain the IED of transformer substation configuration file File and Communication files;Device attribute is determined according to IED files;Equipment is determined according to Communication files Between topological relation and equipment between Content of Communication.
Preferably, to the configuration before renewal and update after configuration compare one by one including:Compare the configuration before updating to neutralize Whether the quantity of the IED files in the configuration after renewal, title are identical;Equipment after comparing the device attribute before updating and updating Whether attribute is identical;Compare update before equipment between topological relation and update after equipment between topological relation whether phase Together;Whether the Content of Communication between equipment after comparing the Content of Communication between the equipment before updating and updating is identical.
Preferably, IED files include multiple IED files, and multiple IED files include an IED files, before to renewal After configuration after configuration and renewal is compared one by one, the method also includes the configuration after displaying renewal, wherein, after displaying renewal Configuration includes:Show that physical couplings and link in an IED files and multiple IED files between other IED files connect Connect relation;Show the empty loop between each link.
Alternatively, a kind of preferred embodiment of above-described embodiment is described with reference to a kind of concrete application scene:
(1) check code to the SCD file before and after renewal is compared
Whether there is difference with the SCD configuration files after upgrading before determining upgrading first, can be calculated by CRC check or MD5 Method is checked to file related content and information.MD5 algorithms are frequently used to verify the integrality of web document transfer, prevent File is distorted by people.MD5 full name are message digest algorithm (Message-Digest Algorithm 5), and this algorithm is to arbitrarily long The information of degree is calculated by turn, and it is " fingerprint " of 128 (hexadecimal length is exactly 32) to produce a binary length (or " message digest "), it is very very small that different files produces the possibility of identical message digest, so logical Cross and compare the MD5 values of two files and be compared, you can determine whether two file contents are variant.If two before and after updating The check code of SCD file is identical, then illustrate that SCD file content is unchanged, if it is different, then explanation SCD file content is changed, Content to the SCD file before and after renewal is parsed.
(2) difference analysis of SCD file before and after updating
Will the SCD file different to two be compared, it is necessary first to each SCD file will be parsed, respectively Obtain all devices attribute in two files, topological relation and Content of Communication.
The analytic method of SCD file:
Because SCD file follows xml specifications, each element in SCD is obtained, can be increased income storehouse, base using such as TinyXML Parsed in DOM methods.
In the Communication parts of SCD file, describe station level mms networks, process layer goose networks with And the messaging parameter of the related secondary device of process layer sv networks, each network is according to voltage class in more perfect SCD Distinguish each network equipment.By parsing the field, can obtain the associate device of every primary network station access point ConnectedAP and Its mailing address, the IP address of equipment station level interface or the MAC Address of process layer interface, APPID and vlan information.
In IED (project file index) part of SCD file, all smart machines for participating in communication in station are described, Such as protection device, measure and control device, combining unit, intelligent terminal.There is network access point under the server fields of IED, such as stand Control layer network accessing points S1, process layer GOOSE network accessing points G1, process layer SV accessing points M1.Each logic under S1 accessing points In the LLNO of equipment, the data set that device sends to clients such as monitoring or scheduling systems is defined.Respectively patrolled under G1 accessing points In the LLN0 of the equipment of collecting, the GOOSE data sets (if having) that device is externally issued are defined;Each logical device under M1 accessing points In LLN0, the SV data sets (if having) that device is externally issued are defined.By parsing each IED parts, device is can obtain to outgoing Per signal all the way in the data set and data set of cloth.IED needs the external signal subscribed to, by each logic under accessing points G1 or M1 Inputs field definitions in the LLN0 of equipment, including the SV/GOOSE lines of the equipment are input into, each line contains this and patrols The output signal information of the empty terminal signals of device interior input and external device (ED) is collected, empty terminal is one with each external output signal One corresponding relation.It can thus be concluded that all information such as correspondence to IED, LD, LN, DO, DA and IED.
The otherness comparative approach of SCD file:
The data parsed for following several aspects contrast be compared one by one:1) quantity and IedName of IED are It is no consistent;2) whether device communication parameter is consistent, including SV accessing points MAC Address, the control block title of GOOSE accessing points, reality Example name, MAC Address, VLAN-ID, APPID, the IP address of MMS accessing points;3) whether the services that IED is supported is consistent;Comprising Logical device LD it is whether consistent with preceding version;Whether logical node number amount and type are consistent;In logical node zero, IED issues Whether consistent with the data set subscribed to, whether the information of GSE control blocks is consistent;Whether logic contact LN is consistent;Data object and Whether data attribute is consistent.
(3) the otherness displaying of the SCD file before and after updating
Centered on IED, show according to layering principle.
Ground floor, shows the annexation of the IED and other IED, i.e., whether existence reason is connected, and Fig. 2 is according to this hair The schematic diagram of the topological relation between a kind of optional power transformation station equipment of bright embodiment, is illustrated in figure 2 a kind of optional Topological relation schematic diagram between the power transformation station equipment for showing, shows monitoring system and protection circuit, measure and control device, line Topological relation between the combining unit and intelligent terminal on road 1;
The second layer, shows the link relation of the IED and other IED, i.e. virtual connections, such as SV links, GOOSE links or TCP Connection;
Third layer, the empty loop between displaying link, all empty loop information for such as being included in GOOSE links, Fig. 3 is root According to the schematic diagram of the Content of Communication between a kind of optional power transformation station equipment of the embodiment of the present invention, circuit 1 is illustrated in figure 3 Intelligent terminal and the measure and control device that is communicated with circuit 1 between Content of Communication, including for example:A phases circuit breaker position, B phases are broken Road device position, C phases circuit breaker position, intelligent terminal 1 are overhauled, the trouble-signal of intelligent terminal 1, the optocoupler abnormity of power supply of intelligent terminal 1, The control loop template of intelligent terminal 1, bus starting abnormal signal, GOOSE inputs long-term action, receiving circuit protection GOOSE break The signals such as chain, reception bus protection GOOSE chain ruptures.
It should be noted that though it is shown that logical order the step of the flow of accompanying drawing is illustrated, but in some feelings Under condition, shown or described step can be performed with different from order herein.
According to the embodiment of the present application, there is provided a kind of data processing equipment.
Fig. 4 is the schematic diagram of a kind of optional data processing equipment according to embodiments of the present invention, the data processing equipment For determining transformer substation configuration file variation after the updating, as shown in figure 4, the device includes first acquisition unit 10, the One resolution unit 20, the second resolution unit 30 and the first comparing unit 40.
First acquisition unit is used to obtain the transformer substation configuration file before updating and the transformer substation configuration file after renewal;The One resolution unit is used to parse the transformer substation configuration file before renewal, the configuration before being updated, wherein, configuration includes The Content of Communication between topological relation and equipment between device attribute, equipment;Second resolution unit is used for the change after renewal Power station configuration file is parsed, the configuration after being updated;After first comparing unit is used for the configuration before renewal and updating Configuration compare to determine transformer substation configuration file variation after the updating one by one.
Preferably, the device also includes:Second acquisition unit, for the configuration before to renewal and update after configuration by One compares before determining transformer substation configuration file variation after the updating, to be wrapped in the transformer substation configuration file before acquisition renewal The check code included in transformer substation configuration file after the check code for containing and renewal;Judging unit, for judging the change before updating Whether the check code included in the transformer substation configuration file after the check code included in the configuration file of power station and renewal is identical, its In, check code is to perform the data being calculated to the content of transformer substation configuration file by presetting checking algorithm;Second compares Unit, for if it is judged that be it is no, then to the configuration before renewal and update after configuration compare to determine transformer station one by one Configuration file variation after the updating;Logic unit, for when judged result is to be, not performing to the configuration before renewal and Configuration after renewal is compared one by one.
Preferably, the first resolution unit and the second resolution unit are resolution unit, and resolution unit includes:Acquisition module, uses In the IED files and Communication files that obtain transformer substation configuration file;First determining module, for according to IED files Determine device attribute;Second determining module, for determining the topological relation between equipment according to Communication files and setting Content of Communication between standby.
Preferably, the first comparing unit includes:First comparison module, after comparing the configuration neutralization renewal before updating Whether the quantity of the IED files in configuration, title are identical;Second comparison module, for comparing the device attribute and more before updating Whether the device attribute after new is identical;3rd comparison module, for comparing topological relation and renewal between the equipment before updating Whether the topological relation between equipment afterwards is identical;4th comparison module, for comparing in the communication between the equipment before updating Whether the Content of Communication between equipment after holding and updating is identical.
Preferably, IED files include multiple IED files, and multiple IED files include an IED files, and device also includes exhibition Show unit, display unit is used for the configuration before to renewal and the configuration after renewal relatively shows matching somebody with somebody after updating afterwards one by one Put, wherein, display unit includes:First display module, for showing an IED files with other IED texts in multiple IED files Physical couplings and link connection relation between part;Second display module, for showing the empty loop between each link.
Above-mentioned device can include processor and memory, and said units can be as program unit storage in storage In device, corresponding function is realized by computing device storage said procedure unit in memory.
Memory potentially includes the volatile memory in computer-readable medium, random access memory (RAM) and/ Or the form, such as read-only storage (ROM) or flash memory (flashRAM) such as Nonvolatile memory, memory includes at least one storage Chip.
Above-mentioned the embodiment of the present application sequence number is for illustration only, and the quality of embodiment is not represented.
In above-described embodiment of the application, the description to each embodiment all emphasizes particularly on different fields, and does not have in certain embodiment The part of detailed description, may refer to the associated description of other embodiment.
In several embodiments provided herein, it should be understood that disclosed technology contents, can be by other Mode is realized.Wherein, device embodiment described above is only schematical, such as division of described unit, Ke Yiwei A kind of division of logic function, can there is other dividing mode when actually realizing, such as multiple units or component can combine or Person is desirably integrated into another system, or some features can be ignored, or does not perform.Another, shown or discussed is mutual Between coupling or direct-coupling or communication connection can be the INDIRECT COUPLING or communication link of unit or module by some interfaces Connect, can be electrical or other forms.
In addition, during each functional unit in the application each embodiment can be integrated in a processing unit, it is also possible to It is that unit is individually physically present, it is also possible to which two or more units are integrated in a unit.Above-mentioned integrated list Unit can both be realized in the form of hardware, it would however also be possible to employ the form of SFU software functional unit is realized.
If the integrated unit is to realize in the form of SFU software functional unit and as independent production marketing or use When, can store in a computer read/write memory medium.Based on such understanding, the technical scheme of the application is substantially The part for being contributed to prior art in other words or all or part of the technical scheme can be in the form of software products Embody, the computer software product is stored in a storage medium, including some instructions are used to so that a computer Equipment (can be personal computer, server or network equipment etc.) perform the application each embodiment methods described whole or Part steps.And foregoing storage medium includes:USB flash disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic disc or CD etc. are various can be with store program codes Medium.
The above is only the preferred embodiment of the application, it is noted that for the ordinary skill people of the art For member, on the premise of the application principle is not departed from, some improvements and modifications can also be made, these improvements and modifications also should It is considered as the protection domain of the application.

Claims (10)

1. a kind of data processing method, it is characterised in that the data processing method is used to determine transformer substation configuration file more Variation after new, methods described includes:
Transformer substation configuration file after obtaining the transformer substation configuration file before updating and updating;
Transformer substation configuration file before the renewal is parsed, the configuration before being updated, wherein, the configuration includes setting Content of Communication between standby topological relation and equipment between attribute, equipment;
Transformer substation configuration file after the renewal is parsed, the configuration after being updated;
Configuration after configuration and the renewal before the renewal is compared to determine the transformer substation configuration file more one by one Variation after new.
2. method according to claim 1, it is characterised in that matching somebody with somebody after the configuration and the renewal before to the renewal Put and compare one by one so that before determining transformer substation configuration file variation after the updating, methods described also includes:
Obtain the transformer substation configuration file after the check code and the renewal included in the transformer substation configuration file before the renewal In the check code that includes;
Judge the transformer substation configuration file after the check code that is included in the transformer substation configuration file before the renewal and the renewal In the check code that includes it is whether identical, wherein, the check code is in transformer substation configuration file by default checking algorithm Hold the data for performing and being calculated;
If it is judged that being no, then described to determine is compared one by one to the configuration after the configuration and the renewal before the renewal Transformer substation configuration file variation after the updating;
Otherwise, do not perform and the configuration after the configuration and the renewal before the renewal is compared one by one.
3. method according to claim 1, it is characterised in that parsed to the transformer substation configuration file, matched somebody with somebody Put including:
Obtain the IED files and Communication files of the transformer substation configuration file;
The device attribute is determined according to the IED files;
Determined in the communication between the topological relation between the equipment and the equipment according to the Communication files Hold.
4. method according to claim 3, it is characterised in that to the configuration after the configuration and the renewal before the renewal Compare one by one including:
Whether comparing the configuration before the renewal, to neutralize the quantity of IED files in the configuration after the renewal, title identical;
Whether the device attribute after comparing the device attribute before updating and updating is identical;
Whether the topological relation between equipment after comparing the topological relation between the equipment before updating and updating is identical;
Whether the Content of Communication between equipment after comparing the Content of Communication between the equipment before updating and updating is identical.
5. method according to claim 1, it is characterised in that the IED files include multiple IED files, the multiple IED files include an IED files, after the configuration after configuration and the renewal before to the renewal is compared one by one, institute Stating method also includes showing the configuration after the renewal, wherein, show that the configuration after the renewal includes:
Show physical couplings and link between other IED files in an IED files and the multiple IED files Annexation;
Show the empty loop between each link.
6. a kind of data processing equipment, it is characterised in that the data processing equipment is used to determine transformer substation configuration file more Variation after new, described device includes:
First acquisition unit, for obtaining the transformer substation configuration file before updating and the transformer substation configuration file after renewal;
First resolution unit, for being parsed to the transformer substation configuration file before the renewal, the configuration before being updated, its In, the configuration includes the Content of Communication between the topological relation between device attribute, equipment and equipment;
Second resolution unit, for being parsed to the transformer substation configuration file after the renewal, the configuration after being updated;
First comparing unit, for comparing to determine the change one by one to the configuration after the configuration and the renewal before the renewal The variation after the updating of power station configuration file.
7. device according to claim 6, it is characterised in that described device also includes:
Second acquisition unit, compares described to determine one by one for the configuration after the configuration and the renewal before to the renewal Before transformer substation configuration file variation after the updating, the verification included in the transformer substation configuration file before the renewal is obtained The check code included in transformer substation configuration file after code and the renewal;
Judging unit, for the change after the check code for judging to be included in the transformer substation configuration file before the renewal and the renewal Whether the check code included in the configuration file of power station is identical, wherein, the check code is to transformer station by default checking algorithm The content of configuration file performs the data being calculated;
Second comparing unit, for if it is judged that be it is no, then to before the renewal configuration and the renewal after configuration Compare to determine transformer substation configuration file variation after the updating one by one;
Logic unit, for when judged result is to be, not performing to the configuration after the configuration and the renewal before the renewal Compare one by one.
8. device according to claim 6, it is characterised in that first resolution unit and second resolution unit are Resolution unit, the resolution unit includes:
Acquisition module, IED files and Communication files for obtaining the transformer substation configuration file;
First determining module, for determining the device attribute according to the IED files;
Second determining module, for determining the topological relation between the equipment and institute according to the Communication files State the Content of Communication between equipment.
9. device according to claim 8, it is characterised in that first comparing unit includes:
First comparison module, the number of the IED files in the configuration after the renewal is neutralized for comparing the configuration before the renewal Whether amount, title are identical;
Whether the second comparison module is identical for the device attribute after comparing the device attribute before updating and updating;
3rd comparison module, closes for comparing the topology between the topological relation between the equipment before updating and the equipment after renewal Whether system is identical;
4th comparison module, for comparing in the communication between the Content of Communication between the equipment before updating and the equipment after renewal Whether identical hold.
10. device according to claim 6, it is characterised in that the IED files include multiple IED files, the multiple IED files include an IED files, and described device also includes display unit, and the display unit is used for before to the renewal Configuration and the renewal after configuration one by one relatively after show the configuration after the renewal, wherein, the display unit bag Include:
First display module, for showing in an IED files and the multiple IED files between other IED files Physical couplings and link connection relation;
Second display module, for showing the empty loop between each link.
CN201611147756.4A 2016-12-13 2016-12-13 Data processing method and device Pending CN106844432A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611147756.4A CN106844432A (en) 2016-12-13 2016-12-13 Data processing method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611147756.4A CN106844432A (en) 2016-12-13 2016-12-13 Data processing method and device

Publications (1)

Publication Number Publication Date
CN106844432A true CN106844432A (en) 2017-06-13

Family

ID=59139831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611147756.4A Pending CN106844432A (en) 2016-12-13 2016-12-13 Data processing method and device

Country Status (1)

Country Link
CN (1) CN106844432A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109062639A (en) * 2018-06-19 2018-12-21 国网宁夏电力有限公司电力科学研究院 A kind of display methods and system of the upgrade information of substation's SCD file
CN109245316A (en) * 2018-11-28 2019-01-18 国网宁夏电力有限公司检修公司 Intelligent substation reorganization and expansion bus protection on-site calibration device and method
CN109888914A (en) * 2019-01-08 2019-06-14 许昌许继软件技术有限公司 A kind of major-minor interlock method of substation and device
CN111026726A (en) * 2019-10-24 2020-04-17 贵州电网有限责任公司 Method and system for comparing different versions of SCD file of intelligent substation and storage medium
CN112350846A (en) * 2019-08-07 2021-02-09 杭州木链物联网科技有限公司 Asset learning method, device, equipment and storage medium for intelligent substation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102546396A (en) * 2011-12-15 2012-07-04 广东电网公司电力科学研究院 Configuration method and system of instation exchanger of electric device remote supervision system
CN103077212A (en) * 2012-12-28 2013-05-01 广东电网公司电力科学研究院 Transformer substation configuration file control method and system
CN103578048A (en) * 2013-11-13 2014-02-12 国家电网公司 Method for checking and comparing configuration related information of intelligent substation SCL documents
CN104579748A (en) * 2014-12-10 2015-04-29 国家电网公司 SCD (substation configuration description) online checking network analysis method and system
CN105184189A (en) * 2015-08-26 2015-12-23 国家电网公司 Online control and management system for intelligent substation SCD file

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102546396A (en) * 2011-12-15 2012-07-04 广东电网公司电力科学研究院 Configuration method and system of instation exchanger of electric device remote supervision system
CN103077212A (en) * 2012-12-28 2013-05-01 广东电网公司电力科学研究院 Transformer substation configuration file control method and system
CN103578048A (en) * 2013-11-13 2014-02-12 国家电网公司 Method for checking and comparing configuration related information of intelligent substation SCL documents
CN104579748A (en) * 2014-12-10 2015-04-29 国家电网公司 SCD (substation configuration description) online checking network analysis method and system
CN105184189A (en) * 2015-08-26 2015-12-23 国家电网公司 Online control and management system for intelligent substation SCD file

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
洪梅子等: ""智能变电站配置文件管控技术研究"", 《湖北电力》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109062639A (en) * 2018-06-19 2018-12-21 国网宁夏电力有限公司电力科学研究院 A kind of display methods and system of the upgrade information of substation's SCD file
CN109245316A (en) * 2018-11-28 2019-01-18 国网宁夏电力有限公司检修公司 Intelligent substation reorganization and expansion bus protection on-site calibration device and method
CN109245316B (en) * 2018-11-28 2021-09-24 国网宁夏电力有限公司检修公司 Intelligent substation reconstruction and extension bus protection field calibration device and method
CN109888914A (en) * 2019-01-08 2019-06-14 许昌许继软件技术有限公司 A kind of major-minor interlock method of substation and device
CN112350846A (en) * 2019-08-07 2021-02-09 杭州木链物联网科技有限公司 Asset learning method, device, equipment and storage medium for intelligent substation
CN112350846B (en) * 2019-08-07 2024-01-09 浙江木链物联网科技有限公司 Asset learning method, device and equipment of intelligent substation and storage medium
CN111026726A (en) * 2019-10-24 2020-04-17 贵州电网有限责任公司 Method and system for comparing different versions of SCD file of intelligent substation and storage medium

Similar Documents

Publication Publication Date Title
US10325062B2 (en) Method and device for generating engineering topology of digital substation
CN106844432A (en) Data processing method and device
US8792385B2 (en) Method and device for auto-generating goose signal connection topology from substation level
CN103792448B (en) A kind of digital protection device automatic test control system and control method thereof
CN105184189A (en) Online control and management system for intelligent substation SCD file
CN104978391A (en) System and method for automated substation design and configuration
CN112800637B (en) Intelligent substation simulation test device and method
CN108595390B (en) Method for verifying parameter consistency of SCD and IED of intelligent substation
Ayello et al. Interoperability based on IEC 61850 standard: Systematic literature review, certification method proposal, and case study
Chopade et al. Structural and functional vulnerability analysis for survivability of Smart Grid and SCADA network under severe emergencies and WMD attacks
CN106301976A (en) A kind of intelligent substation schedule information automated testing method
CN107545116A (en) A kind of intelligent substation reorganization and expansion change impact analysis method based on model decoupling
CN110868341B (en) Method and device for testing intelligent management unit of in-situ protection
CN106841842A (en) The method of testing and device in the empty loop of secondary device
CN113095059A (en) Method, device, equipment and storage medium for verifying substation configuration description file
CN106855850A (en) Based on portable equipment intelligent substation secondary void terminal figure reality symbol detection method
CN111327465B (en) Intelligent distributed feeder automation terminal node configuration method
CN106301833A (en) A kind of transformer station schedule information method of testing
CN109976797B (en) Algorithm configuration and management method and system based on SCD file information object model
CN112698584B (en) Substation one-key sequential control simulation test method, device, equipment and medium
CN109376436B (en) Method and device for generating strong network line topology
CN110391935B (en) Measurement degree evaluation method and system considering information physical coupling characteristics and information disturbance
CN103678054B (en) Test method and device for BACnet equipment
CN113660286A (en) Communication protocol fusion method combined with Kalman filtering data fusion and related equipment
CN110119337A (en) A kind of data analysing method, device and server

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613