[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN106801612A - A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method - Google Patents

A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method Download PDF

Info

Publication number
CN106801612A
CN106801612A CN201710114878.1A CN201710114878A CN106801612A CN 106801612 A CN106801612 A CN 106801612A CN 201710114878 A CN201710114878 A CN 201710114878A CN 106801612 A CN106801612 A CN 106801612A
Authority
CN
China
Prior art keywords
pipe
rig
steel pipes
high intensity
type barrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710114878.1A
Other languages
Chinese (zh)
Inventor
苏春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201710114878.1A priority Critical patent/CN106801612A/en
Publication of CN106801612A publication Critical patent/CN106801612A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method, use T76S pipe boron steel pipes as passage in stratum inject cement mortar to form supporter, including construction drill operating room;Worked in rig and indoor location and adjust rig and slip casting machine;T76S pipe boron steel pipes and drill bit are installed, drive T76S pipe boron steels pipes to creep into by rig, and using slip casting machine by T76S pipe boron steel pipes to injecting cement mortar in stratum;After slip casting length reaches design requirement, tunneling.The beneficial effects of the invention are as follows:By the present invention in that effectively can be bonded with country rock with T76S pipe boron steels pipe such that it is able to avoid rock crushing, and form overall stress, the problems such as can effectively solve the problem that collapse hole, bit freezing.The present invention is applied to weak surrounding rock and the sandstone areas such as vcehicular tunnel, railway tunnel, water wood tunnel, nonferrous metals ore tunnel, colliery, and it has the advantages that the qualification that applied widely, difficulty of construction is small, easy to operate, be independent of workmen.

Description

A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method
Technical field
It is a kind of T76S high intensity self-drilling type barrel vault advanced support work specifically the present invention relates to constructing tunnel field Method.
Background technology
Under the conditions of prior art, the inducer enclosing lithologies of some Tunnel Engineering are mud stone, marl, belong to soft rockmass, Shale content is heavier, developmental joint fissure, and it is in chunky shape that rock mass after being cut more, partly for powdered.After rock mass meets water immersion Easily soften, self is poor, it is necessary to ensure construction safety using advance support measure before tunnel excavation.Due to rock mass Broken, in Shed-pipe Advanced Support work progress, frequently, installing the pipe canopies of tradition φ 108 needs pipe-following drilling, causes to apply for collapse hole, bit freezing Work progress is slow, and security risk is very high in work progress, can have a strong impact on the duration.
The content of the invention
It is an object of the invention to provide a kind of short construction period, the T76S for reinforcing efficiency high, construction risk being evaded High intensity self-drilling type barrel vault advanced support engineering method.
The present invention is achieved through the following technical solutions:A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method, uses T76S pipe boron steel pipes are as passage to injecting cement mortar in stratum forming supporter.
Including following steps:
Step S1:Construction drill operating room;
Step S2:Worked in rig and indoor location and adjust rig and slip casting machine;
Step S3:T76S pipe boron steel pipes and drill bit are installed, drive T76S pipe boron steels pipe to creep into by rig, and pass through using slip casting machine T76S pipe boron steel pipes in stratum to injecting cement mortar;
Step S4:After previous section T76S pipe boron steels pipe drilling terminates, rig is return, in the free end of previous section T76S pipe boron steel pipes Adapter sleeve is installed, and next section T76S pipe boron steel pipes are socketed by adapter sleeve, continue to drive drilling using rig, and use slip casting Machine is by T76S pipe boron steel pipes to injecting cement mortar in stratum;
Step S5:Repeat step S4, after slip casting length reaches design requirement, tunneling.
In described step S1, including holed mouth according to excavation contour line, the vault of tunnel face and side spray plus reinforcing bar Concrete, face element pneumatically placed concrete.
In described step S1, also including performing shield arch, described shield arch is a Pin I-steel.
Several holes are opened up on described I-steel, the guiding steel pipe for installing T76S pipe boron steel pipes is welded in hole.
Described guiding steel pipe is interconnected by the way of welded reinforcement.
The described gap pneumatically placed concrete filling for being oriented to steel pipe and tunnel wall.
In described step S2, the drill rod axis of rig and the axis coaxle of T76S pipe boron steel pipes.
Described rig lower section is installed by sleeper.
The present invention compared with prior art, with advantages below and beneficial effect:
By the present invention in that effectively can be bonded with country rock with T76S pipe boron steels pipe such that it is able to avoid rock crushing, and formed Overall stress, the problems such as can effectively solve the problem that collapse hole, bit freezing.The present invention be applied to vcehicular tunnel, railway tunnel, water wood tunnel, The weak surrounding rocks such as nonferrous metals ore tunnel, colliery and sandstone area, it has applied widely, difficulty of construction small, easy to operate, no The advantages of relying on the qualification of workmen.
Brief description of the drawings
Fig. 1 is schematic flow sheet of the invention.
Specific embodiment
The present invention is described in further detail with reference to embodiment, but embodiments of the present invention not limited to this.
Embodiment 1:
In the present embodiment, a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method, using T76S pipe boron steel pipes as passage To injecting cement mortar in stratum to form supporter, T76S pipe boron steels pipe is continuous T type threaded heavy wall steel pipe, thread depth 3mm, It effectively can be bonded with country rock such that it is able to avoid rock crushing, cement mortar, can be mutual from after the outflow of T76S pipe boron steels pipe Bonding and form an entirety with T76S pipe boron steels pipe, cement mortar dilation angle is big, can effectively improve country rock, and by making T76S pipe boron steel pipes and cement mortar bond to form overall stress, the problems such as can effectively solve the problem that collapse hole, bit freezing.
Embodiment 2:
On the basis of embodiment 1, in the present embodiment, it specifically includes following steps:
Step S1:Construction drill operating room, holes mouth according to excavation contour line, digs into depth for 6m, the vault of tunnel face and Side spray plus the thick armored concrete of 10cm, the size of reinforced mesh is 100cm*100cm, φ 12cm, face element spray 10cm Concrete, is conducive to the protection rig operating room will not to cave in, and avoid the vibrations that rig operating room produces to rock mass with this Impact and occur slack, ensured construction safety.
Step S2:Worked in rig and indoor location and adjust rig and slip casting machine, the drill rod axis and T76S for making rig are managed The axis coaxle of boron steel pipe, in the present embodiment, uses C6 rigs.
Step S3:T76S pipe boron steel pipes and drill bit are installed, drill bit is arranged on one end of T76S pipe boron steel pipes, T76S pipe boron steels The other end of pipe is connected with the drilling rod of rig, drives T76S pipe boron steel pipes to be crept into along the construction direction in tunnel by rig, During drilling using slip casting machine by T76S pipe boron steel pipes to pumping cement mortar in stratum, in the present embodiment, described brill Head using φ 130mm drill bit, slip casting machine uses pulsed slip casting machine, before drilling, with the slip casting passage of water lubrication rig and T76S pipe boron steel pipes.Ensure that cement mortar is smoothly pumped with this, it is to avoid occur blocking.Cement mortar is using 32.5 cement according to water Gray scale is formulated for 0.5.In the present embodiment, when starting rig and creeping into, just start using low speed low pressure drilling, when from pore-forming 1m Adjustment drilling speed is gradually adjusted according to geological condition afterwards and is finally stablized and keep having water in drilling during 100r/min, drilling Mud.
Step S4:After previous section T76S pipe boron steels pipe drilling terminates, make slip casting machine termination of pumping, and return rig, in previous section Adapter sleeve is installed in the free end of T76S pipe boron steel pipes, and is socketed next section T76S pipe boron steel pipes by adapter sleeve, using rig after It is continuous to drive drilling, and using slip casting machine by T76S pipe boron steel pipes to injecting cement mortar in stratum.
Step S5:Repeat step S4, T76S pipe boron steel pipe is arranged according to the profile of face, using odevity T76S Pipe boron steel pipe is spaced slip casting, the order of slip casting first to note odd number pipe, and according to order slip casting from down to up, from left to right, very After the completion of number pipe slip casting, then even number pipe is noted, slip casting passes through one end of T76S pipe canopy fastener for connection drill bits to external diffusion, all T76S After pipe boron steel pipe all completes slip casting, cement mortar can be adhered to one another and form an entirety, cement mortar dilation angle is big, Neng Gouyou Effect improvement country rock, so as to play a part of to prevent collapsing, after slip casting reaches design requirement, tunneling.
Embodiment 3:
On the basis of above-described embodiment, in the present embodiment, in described step S1, also including performing shield arch, described shield arch It is a Pin I-steel, support can be played a part of to rig operating room with this, so as to strengthens the energy that rig operating room prevents collapsing Power.
Embodiment 4:
On the basis of above-described embodiment, in the present embodiment, 50 holes of diameter 150mm, pitch-row are opened up on described I-steel 40cm, welds the φ 150mm for installing T76S pipe boron steel pipes and is oriented to steel pipe in hole, be oriented to steel pipe theodolite and existed with coordinate method Its plan-position is made on I-steel.Gradient plate is coordinated to set the inclination angle for being oriented to steel pipe with levelling rod.Set away from method with pre-post difference It is oriented to the outer limb of steel pipe.The installation accuracy for being oriented to steel pipe is improved with this, so as to improve the Drilling Precision of T76S pipe boron steel pipes, is protected Demonstrate,prove the precision and efficiency of construction.In the present embodiment, described adjacent guiding steel pipe is mutually connected by the way of welded reinforcement Connect, the installation accuracy and bonding strength of steel pipe are oriented to protect, construction precision is influenceed so as to prevent guiding steel pipe to be moved.This In embodiment, the described gap pneumatically placed concrete filling for being oriented to steel pipe and tunnel wall, to prevent guiding steel pipe from shifting and shadow Ring construction precision.
Embodiment 5:
On the basis of above-described embodiment, in the present embodiment, sleeper is installed in described rig lower section, ensures that rig is arranged on this On the basis of firm, construction precision is influenceed so as to avoid rig from situations such as uneven subsidence, swing, displacement occur.
Embodiment 6:
On the basis of above-described embodiment, in the present embodiment, high-pressure water pipe is connected in described rig operating room, in order to carry out Hole flushing etc. is operated.
Embodiment 7:
On the basis of above-described embodiment, in the present embodiment, after slip casting terminates, the cement in T76S pipe boron steel pipes is removed in time Slurry, and the termination of T76S pipe boron steel pipes is crammed with Anchor Agent, to strengthen the rigidity and intensity of T76S pipe boron steel pipes.
The above, is only presently preferred embodiments of the present invention, not does any formal limitation to the present invention, it is every according to Any simple modification, the equivalent variations made to above example according to technical spirit of the invention, each fall within protection of the invention Within the scope of.

Claims (9)

1. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method, it is characterised in that:Using T76S pipe boron steel pipes as logical Road is to injecting cement mortar forming supporter in stratum.
2. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 1, it is characterised in that:Including Following steps:
Step S1:Construction drill operating room;
Step S2:Worked in rig and indoor location and adjust rig and slip casting machine;
Step S3:T76S pipe boron steel pipes and drill bit are installed, drive T76S pipe boron steels pipe to creep into by rig, and pass through using slip casting machine T76S pipe boron steel pipes in stratum to injecting cement mortar;
Step S4:After previous section T76S pipe boron steels pipe drilling terminates, rig is return, in the free end of previous section T76S pipe boron steel pipes Adapter sleeve is installed, and next section T76S pipe boron steel pipes are socketed by adapter sleeve, continue to drive drilling using rig, and use slip casting Machine is by T76S pipe boron steel pipes to injecting cement mortar in stratum;
Step S5:Repeat step S4, after slip casting length reaches design requirement, tunneling.
3. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 2, it is characterised in that:It is described The step of S1 in, including holed mouth according to excavation contour line, the vault of tunnel face and side spray plus armored concrete, face Plain pneumatically placed concrete.
4. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to Claims 2 or 3, it is characterised in that: In described step S1, also including performing shield arch, described shield arch is a Pin I-steel.
5. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 4, it is characterised in that:It is described I-steel on open up several holes, the guiding steel pipe for installing T76S pipe boron steel pipes is welded in hole.
6. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 5, it is characterised in that:It is described Guiding steel pipe interconnected by the way of welded reinforcement.
7. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 6, it is characterised in that:It is described The gap pneumatically placed concrete filling for being oriented to steel pipe and tunnel wall.
8. a kind of T76S high intensity self-drilling type barrel vault advanced support work according to any one of claim 2,3,5,6,7 Method, it is characterised in that:In described step S2, the drill rod axis of rig and the axis coaxle of T76S pipe boron steel pipes.
9. a kind of T76S high intensity self-drilling type barrel vault advanced support engineering method according to claim 8, it is characterised in that:It is described Rig lower section install sleeper.
CN201710114878.1A 2017-02-28 2017-02-28 A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method Pending CN106801612A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710114878.1A CN106801612A (en) 2017-02-28 2017-02-28 A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710114878.1A CN106801612A (en) 2017-02-28 2017-02-28 A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method

Publications (1)

Publication Number Publication Date
CN106801612A true CN106801612A (en) 2017-06-06

Family

ID=58987944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710114878.1A Pending CN106801612A (en) 2017-02-28 2017-02-28 A kind of T76S high intensity self-drilling type barrel vault advanced support engineering method

Country Status (1)

Country Link
CN (1) CN106801612A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736824A (en) * 2018-12-10 2019-05-10 中交一公局桥隧工程有限公司 Construction process of T76 high-strength self-drilling spiral pipe shed

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4129991A (en) * 1977-10-28 1978-12-19 Karl Schaden Method of producing a concrete lined tunnel or other underground excavation
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN104481550A (en) * 2014-10-23 2015-04-01 中国二十冶集团有限公司 Tunnel collapse treatment advance support method
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205117356U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Self -drilling spiral pipe canopy

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4129991A (en) * 1977-10-28 1978-12-19 Karl Schaden Method of producing a concrete lined tunnel or other underground excavation
CN101624910A (en) * 2009-07-31 2010-01-13 广州市建筑机械施工有限公司 Method for reinforcing concealed tunnel
CN104481550A (en) * 2014-10-23 2015-04-01 中国二十冶集团有限公司 Tunnel collapse treatment advance support method
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205117356U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Self -drilling spiral pipe canopy

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
冯军武: "T76S自钻式螺旋管棚在软弱围岩超前支护中的应用", 《石家庄铁道大学学报(自然科学版)》 *
王政栋: "自进式小管棚在大断面深埋软岩隧道的工程应用研究", 《工程科技II辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736824A (en) * 2018-12-10 2019-05-10 中交一公局桥隧工程有限公司 Construction process of T76 high-strength self-drilling spiral pipe shed

Similar Documents

Publication Publication Date Title
CN103306687B (en) Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN101328811B (en) TGRM subsection moving-on type advanced deep hole grouting construction process
CN104790978B (en) The tunnel ring-shaped base tunnel construction method of small interval crossings on different level
CN104790873B (en) Soft rock layer jet is oriented to the integrated drilling method of the anti-collapse hole of pore-forming reaming
CN101603431B (en) Method for reinforcing outburst-prone coal seam cross-cut coal uncovering
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN101709651A (en) Grouting water blocking method for undersea tunnel
CN104747075A (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN103089276B (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN102278130A (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN103510957A (en) Combined rock cross-cut coal uncovering method
CN105715296A (en) Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN101509383A (en) Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN103835648A (en) Raise-boring technology for improving rock stratum performance through ground grouting
CN103321235A (en) Composite soil nailing wall slope support method
CN106837382B (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN106437796A (en) Rock stratum shield tunnel end reinforcing structure and reinforcing method
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
JP7292772B2 (en) External expansion pipe construction method for drilling in the mining zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170606

RJ01 Rejection of invention patent application after publication