CN106408259A - Construction project site work task pushing and plan feedback linking method - Google Patents
Construction project site work task pushing and plan feedback linking method Download PDFInfo
- Publication number
- CN106408259A CN106408259A CN201610838226.8A CN201610838226A CN106408259A CN 106408259 A CN106408259 A CN 106408259A CN 201610838226 A CN201610838226 A CN 201610838226A CN 106408259 A CN106408259 A CN 106408259A
- Authority
- CN
- China
- Prior art keywords
- plan
- task
- work
- progress
- project
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 34
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 238000007726 management method Methods 0.000 claims abstract description 15
- 238000004422 calculation algorithm Methods 0.000 claims abstract description 11
- 230000008569 process Effects 0.000 claims description 15
- 230000004048 modification Effects 0.000 claims description 4
- 238000012986 modification Methods 0.000 claims description 4
- 230000008713 feedback mechanism Effects 0.000 claims description 3
- 238000007667 floating Methods 0.000 claims description 2
- 230000008901 benefit Effects 0.000 abstract description 5
- 230000003111 delayed effect Effects 0.000 description 3
- 238000003325 tomography Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000001932 seasonal effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a construction project site work task pushing and plan feedback linking method. The method comprises the following steps: S1, a work plan is automatically executed on the basis of a project plan progress algorithm engine; S2, a construction site personal work task is effectively associated with a plan, and the plan automatically triggers personal work task pushing; S3, the completing situation of the personal work task is fed back to the corresponding plan, and the progress status and completing situation of the plan are automatically adjusted; and S4, linked feedback of the associated plans is performed from bottom to top. The method combines construction project site progress with a work management method, effectively associates the actual progress situation of a project site with plan progress by means of software advantages, and avoids the problem of progress lagging of the project site as the plan is out of line with the actual progress. Through association of the plan and the personal work task, the personal task is efficiently executed according to the project site plan, so that the plan progress can be more effectively guaranteed.
Description
Technical field
The present invention relates to the schedule management and control field at the project of construction scene is and in particular to a kind of construction project work on the spot
The method that task pushes and planned feedback links.
Background technology
Under China's off-the-shelf item management system (taking the construction stage as a example), job site is mainly owner, construction, management three
Individual unit is operated together, and is ensured construction quality, progress, is invested three big targets by the project management means under regulations
Realize, the progress that prevents is delayed, security incident etc..Because benefits of different parties demand is different, in engineering construction practice process
Often because influence factor is intricate persistant, lead to various problems, and make engineering construction become society and government
How work on the spot situation is therefore fed back by focus in time, and with plan efficient association, reach plan propulsion work, work
Make feedback plan it is ensured that engineering construction is completed by matter on schedule, be the starting point of our whole products.Existing market tradition plan pipe
Reason software is based on plan, ignores and pushes personal work task, and the function of feedback real-time adjustment plan by plan, each other
It is tomography isolation, also makes work on the spot situation and actual master plan generation deviation it is impossible to be adjusted in time, actual refer to
Lead work and top-level plan tomography cannot pass on so that plan to float on surface it is impossible to real the working and keep of guide field
Cause, this problem annoyings project always and builds progress management and control overall process.
Content of the invention
For solving the above problems, the invention provides a kind of construction project work on the spot task pushes and planned feedback linkage
Method, integration project progress algorithm and build project scene personal work, ask for solving the scene progress management and control etc. of construction project
Topic provides a kind of general solution.
For achieving the above object, the technical scheme that the present invention takes is:
The method that construction project work on the spot task pushes and planned feedback links, comprises the steps:
S1, realize the automatic execution of work plan based on project plan progress algorithm engine;
S2, by build on-site personal work task and plan efficient association, realize a plan automatic triggering personal work task
Push;
S3, individual are committed to system after completing task, system phase to plan operation according to the task data submitted to
Close attribute to modify;
S4, association plan linkage feedback from bottom to top.
Specifically include following steps:
Step 1, create the project plan, according to overall goal plan -- professional coordination plan -- implement plan carries out/amounts to
Draw -- construction unit general plan -- plan of annual plan -- monthly plan -- week is decomposed refinement layer by layer, and by personal work task
Carry out efficient association with implement plan/week plan;
Step 2, intended services program, daily according to the automatic implement plan of current time, push same day task to individual
Mobile working platform;
Step 3, individual feed back to plan after completing task, the beginning performance of impact plan and complete percentage
Than, understanding plan operation complete be in progress, if produce deviation with plan, be controlled in time, evade schedule delay risk;
Step 4, implement plan/week plan, by feedback mechanism upwards, realizes the plan of top-level plan real-time awareness subordinate
Progress, more effective management and control project process.
Preferably, in described step S1, project process computational algorithm is efficiently realized by code, from multiple dimensions to work
Plan is processed, comprise critical path, floating when, planned time, actual time, data summarization data associated modification etc..
Preferably, in described step S2, understand build on-site personal work task in depth, by personal work task and plan
It is associated, using the time as engine, rely on progress algorithm, realize a plan and serve as theme, the task of pushing the work forward is carried out.
Preferably, in described step S3, directly affect the state of corresponding plan work data after personal work task feedback
And completeness, the effective combination realizing a plan with live personal work.
Preferably, in described step S4, plan is by decomposing construction project scene executable week from top to bottom layer by layer
Plan carries out real work guidance, and is associated with personal work task by week plan, after week plan is fed back, realizes upwards
Planning data automatic feedback, realize corporate plan and working site job schedule efficient association.
The present invention builds project field programs and personal work and organically combines method, mainly using project process algorithm and build
Make project Field Force work exploitation.
The invention has the advantages that:
Project scene progress will be built be combined with work management method, by software advantage by actual progress live for project
Situation and target advance carry out efficient association, it is to avoid due to plan and actual progress disconnection, project scene leads to that progress is delayed to ask
Topic, associate with personal work task by plan and reaches worker tasks and efficiently execute around project field programs, raising project shows
Field progress management and control ability.
Brief description
Fig. 1 builds the flow process of the method that project work on the spot task pushes and planned feedback links for the embodiment of the present invention
Figure.
Specific embodiment
In order that objects and advantages of the present invention become more apparent, with reference to embodiments the present invention is carried out further
Describe in detail.It should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to limit this
Bright.
As shown in figure 1, embodiments provide a kind of construction project work on the spot task pushing and planned feedback connection
Dynamic method, comprises the steps:
S1, realize the automatic execution of work plan based on project plan progress algorithm engine;
S2, by build on-site personal work task and plan efficient association, realize a plan automatic triggering personal work task
Push;
S3, individual are committed to system after completing task, system phase to plan operation according to the task data submitted to
Close attribute to modify;
S4, association plan linkage feedback from bottom to top
Specifically include following steps:
Step one, create project organization framework after, generate the plan of implementation plan/week, and complete work plan work out perfect,
Project scene personal work task is associated with plan;According to the classification of the project plan, comprise project master plan, unit work
Journey general plan, annual plan, seasonal plan, monthly plan, the taxonomic structure of week plan, each level is planned under corresponding classification
Generate;
Step 2, according to current time, intended services system is processed to the project plan automatically, extract the same day work appoint
Business pushes to personal mobile working platform;
Step 3, individual complete task and submit to, and system automatically processes and feedbacks data to implementation plan/week plan,
The state of processing plan and Percent Complete data value, realize the feedback procedure of personal work task and plan;
Step 4, implementation plan/week plan, successively feedback operation performance, to planning, is realized from bottom plan upwards
The performance planned to upper strata effectively knows and controls.
Originally it is embodied as the research of project management and the practical exploration being combined with schedule with work on the spot, clothes
It is engaged in building progress management and control overall process in engineering project.Under existing construction and management system, it then follows traditional overall process project process pipe
Reason thinking, understands Field Force's working condition, to the thinking solving the problems, such as in project construction process plan implementation progress and method
Carry out combing and adjustment, be effectively combined into starting point from the project plan and personal work emphatically, and to plan as engine, automatically
Push personal work task, the project that effectively pushes is carried out on time in order.Pass through personal work task performance to feed back simultaneously, real
Effective adjustment of the Shi Jinhang project plan, the live actual development situation of reflection, and feed back from bottom to top, reach high-rise understanding in real time
Project scene actual progress situation.Evade plan inside management system and implement not in place, scene progress is delayed, and plan is taken off with scene
Section equivalent risk.Ensure that building project process really realizes a plan guide field job schedule.
Originally it is embodied as with project process algorithm as core, realize a plan establishment and dynamic timing calculating, and associates individual
Real work task, realizes the seamless combination of personal work task and plan, and according to personal work task feedback mechanism, reaches
Plan linkage feedback effect, effectively realize each level personnel to planning guide understand, the progress monitoring of work influence plan and
Adjustment demand, promotes project objective and the realization being on schedule smoothly completed.
The above is only the preferred embodiment of the present invention it is noted that ordinary skill people for the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (6)
1. build the method that project work on the spot task pushes and planned feedback links it is characterised in that comprising the steps:
S1, realize the automatic execution of work plan based on project plan progress algorithm engine;
S2, by build on-site personal work task and plan efficient association, the pushing away of the automatic triggering personal work task that realizes a plan
Send;
S3, individual are committed to system after completing task, system related genus to plan operation according to the task data submitted to
Property is modified;
S4, association plan linkage feedback from bottom to top.
2. the method that construction project work on the spot task as claimed in claim 1 pushes and planned feedback links, its feature exists
In specifically including following steps:
Step 1, the establishment project plan, -- the professional coordination plan -- implement plan carries out/general plan -- according to overall goal plan
Construction unit general plan -- annual plan -- monthly plan -- week plan decomposed refinement layer by layer, and by personal work task with hold
Row plan/week plan carries out efficient association;
Step 2, intended services program, daily according to the automatic implement plan of current time, push same day task and move to personal
Work platformses;
Step 3, individual are committed to system after completing task, system correlation to plan operation according to the task data submitted to
Attribute is modified, understanding plan operation actually accomplish progress, if with plan produce deviation, be controlled in time, evade
Schedule delay risk;
Step 4, implement plan/week plan, by feedback mechanism upwards, realizes the progress of top-level plan real-time awareness subordinate plan
Situation, more effective management and control project process.
3. the method that construction project work on the spot task as claimed in claim 1 pushes and planned feedback links, its feature exists
In in described step S1, project process computational algorithm efficiently being realized by code, from multiple dimensions are carried out to work plan
Reason, comprise critical path, floating when, planned time, actual time, data summarization data associated modification.
4. the method that construction project work on the spot task as claimed in claim 1 pushes and planned feedback links, its feature exists
In, in described step S2, understand build on-site personal work task in depth, personal work task and plan are associated, with
Time, as engine, relies on progress algorithm, realizes a plan and serve as theme, the task of pushing the work forward is carried out.
5. the method that construction project work on the spot task as claimed in claim 1 pushes and planned feedback links, its feature exists
In, in described step S3, personal work task directly affects state and the completeness of corresponding plan operation after feeding back, realize a plan
Effective combination with live personal work.
6. the method that construction project work on the spot task as claimed in claim 1 pushes and planned feedback links, its feature exists
In, in described step S4, plan carries out reality by decomposing the plan of executable week of construction project scene from top to bottom layer by layer
Job guide, and associate with personal work task by week plan, after week plan is fed back, realization planning data upwards is certainly
Dynamic feedback, effective guarantee corporate plan and working site progress true association.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610838226.8A CN106408259A (en) | 2016-09-18 | 2016-09-18 | Construction project site work task pushing and plan feedback linking method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610838226.8A CN106408259A (en) | 2016-09-18 | 2016-09-18 | Construction project site work task pushing and plan feedback linking method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106408259A true CN106408259A (en) | 2017-02-15 |
Family
ID=57997136
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610838226.8A Pending CN106408259A (en) | 2016-09-18 | 2016-09-18 | Construction project site work task pushing and plan feedback linking method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106408259A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108171442A (en) * | 2018-01-18 | 2018-06-15 | 深圳市伟博思技术有限公司 | A kind of Intelligent Dynamic project management method and relevant device |
CN109165841A (en) * | 2018-08-21 | 2019-01-08 | 麦格创科技(深圳)有限公司 | A kind of project management platform and project management method based on cloud service |
CN110458398A (en) * | 2019-07-05 | 2019-11-15 | 重庆金融资产交易所有限责任公司 | Project data monitoring method, server and storage medium |
CN110533260A (en) * | 2019-09-06 | 2019-12-03 | 烟台大学 | A kind of Job-Shop optimization method |
CN111967838A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | Intelligent 4D plan management and control method based on BIM |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102592195A (en) * | 2011-12-28 | 2012-07-18 | Tcl集团股份有限公司 | Project control system and method based on development of products |
CN102938103A (en) * | 2012-10-19 | 2013-02-20 | 北京神舟航天软件技术有限公司 | Plan information synchronizing system and method in project managing process |
CN103440558A (en) * | 2013-09-06 | 2013-12-11 | 中国铁道科学研究院 | Method and system for managing railway electric service system task |
CN105844380A (en) * | 2016-01-26 | 2016-08-10 | 湖北文理学院 | BIM-based BIM project element management method and system |
-
2016
- 2016-09-18 CN CN201610838226.8A patent/CN106408259A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102592195A (en) * | 2011-12-28 | 2012-07-18 | Tcl集团股份有限公司 | Project control system and method based on development of products |
CN102938103A (en) * | 2012-10-19 | 2013-02-20 | 北京神舟航天软件技术有限公司 | Plan information synchronizing system and method in project managing process |
CN103440558A (en) * | 2013-09-06 | 2013-12-11 | 中国铁道科学研究院 | Method and system for managing railway electric service system task |
CN105844380A (en) * | 2016-01-26 | 2016-08-10 | 湖北文理学院 | BIM-based BIM project element management method and system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108171442A (en) * | 2018-01-18 | 2018-06-15 | 深圳市伟博思技术有限公司 | A kind of Intelligent Dynamic project management method and relevant device |
CN109165841A (en) * | 2018-08-21 | 2019-01-08 | 麦格创科技(深圳)有限公司 | A kind of project management platform and project management method based on cloud service |
CN110458398A (en) * | 2019-07-05 | 2019-11-15 | 重庆金融资产交易所有限责任公司 | Project data monitoring method, server and storage medium |
CN110533260A (en) * | 2019-09-06 | 2019-12-03 | 烟台大学 | A kind of Job-Shop optimization method |
CN111967838A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | Intelligent 4D plan management and control method based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106408259A (en) | Construction project site work task pushing and plan feedback linking method | |
CN106886853A (en) | Based on the workflow correlating method and its system of quoting initiation | |
CN104216785A (en) | Common policy task system and implementing method thereof | |
CN105654243B (en) | A kind of project information automated programming system based on trajectory diagram | |
CN104953707A (en) | Intelligent error prevention method and system for monitoring operation order | |
CN109359851A (en) | A kind of task processing method based on micro- assistance the superior and the subordinate office group | |
Vergara Fernandez et al. | Processes and tools to manage CERN programmed stops applied to the second long shutdown of the Accelerator Complex | |
Adamsky | Defense innovation in Russia: The current state and prospects for revival | |
CN105913192A (en) | Management construction operation phase operation method based on building information model | |
CN109284935A (en) | A kind of task processing system based on micro- assistance the superior and the subordinate office group | |
Yu-jing | Application of system dynamics in construction project planning and control | |
CN102073909A (en) | Implementation method for high-efficiency semiautomatic artificial intelligence (AI) software | |
Yasmin et al. | Implementation of Critical Path Method and What If Analysis in Project Management Information System | |
Gritskevich et al. | Research of the mechanisms for coordinating the work of personnel when implementing 3D technologies | |
Lavagna et al. | The temporary structures for Expo Milan 2015: environmental assessment and solutions for the end of life management | |
Feder | Parallel Simulation and Cloud Computing Can Optimize Large-Scale Field Development | |
Xue | A task life cycle management method to ensure the safe use of resources | |
Balan et al. | Moдeлювaннya paдiaцiйнoї oбcTaнoвki пpi пoвoджeннi з вiдпpaцьoвaнin yaдepнin пaлiвon; Moдeлювaннya paдiaцiйнoї oбcTaнoвki пpi пoвoджeннi з вiдпpaцьoвaнin yaдepнin пaлiвon; Simulation of the radiation environment during spent nuclear fuel management | |
Arteaga-Romani et al. | Model of a Safety Management System through Continuous Improvement (PDCA) for Artisanal Mining | |
Nordin et al. | Concept+ 2.0-The Revolution of Small and Marginal Fields | |
Clery | ITER faces further five-year delay | |
Hongmei et al. | The research and application of earthquake disaster comprehensive evaluation based on multi-source earthquake disaster information | |
Romanak et al. | Sharing Experience and Stimulating Interest in Ccs in Developing Countries Using Unfccc Funding Mechanisms | |
Allen | Europe plans quantum technology flagship | |
Tower et al. | Quark-Gluon Discrimination at the Large Hadron Collider |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170215 |
|
RJ01 | Rejection of invention patent application after publication |