Stacking method for engineering materials based on BIM Download PDFInfo
- Publication number
- CN106326583A CN106326583A CN201610760439.3A CN201610760439A CN106326583A CN 106326583 A CN106326583 A CN 106326583A CN 201610760439 A CN201610760439 A CN 201610760439A CN 106326583 A CN106326583 A CN 106326583A
- Authority
- CN
- China
- Prior art keywords
- construction
- bim
- information data
- building materials
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000000463 material Substances 0.000 title claims abstract description 32
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000010276 construction Methods 0.000 claims abstract description 21
- 239000004035 construction material Substances 0.000 claims description 28
- 238000004088 simulation Methods 0.000 claims description 11
- 238000013440 design planning Methods 0.000 claims description 6
- 239000004566 building material Substances 0.000 abstract 6
- 238000000354 decomposition reaction Methods 0.000 abstract 1
- 230000001105 regulatory effect Effects 0.000 abstract 1
- 238000009430 construction management Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Human Resources & Organizations (AREA)
- General Physics & Mathematics (AREA)
- Geometry (AREA)
- Strategic Management (AREA)
- Computer Hardware Design (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Primary Health Care (AREA)
- Mathematical Analysis (AREA)
- General Health & Medical Sciences (AREA)
- Structural Engineering (AREA)
- Health & Medical Sciences (AREA)
- Pure & Applied Mathematics (AREA)
- Civil Engineering (AREA)
- Computational Mathematics (AREA)
- Architecture (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Mathematical Optimization (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Provided in particular is a stacking method for engineering materials based on BIM; the method is characterized by collecting planning programming drawings; inputting the drawings into a BIM system and conducting 3D modeling; conducting operation of decomposition of materials to classify building materials to form building materials information data; inputting the building materials information data into the BIM system and conducting simulating operation of stacking and transporting; outputting the building materials information data and form text after the successful simulating. According to the method, buildings, roads and sites in the construction region are taken into consideration when simulated modeling is conducted, and amounts, types, service condition are calculated in advance and in real time and matched with the dynamic data in actual construction operation, allocation for the building materials is simulated, announced and carried By doing so, even in a construction site of high density, building materials can also be allocated and regulated reasonably, accurately, and in time so as to improve the efficiency of the construction operation.
Description
Technical field
The present invention relates to large-scale engineering construction field, a kind of engineering material stacking method based on BIM.
Background technology
General in high density groups of building engineering construction, owing to construction material or other material have enormous amount, model is complicated,
Placing of material has a strong impact on construction speed, affects construction management.
Summary of the invention
It is an object of the invention to, it is provided that a kind of engineering material stacking method based on BIM software, it has stacking efficiency
Feature high, easily allotment.
In order to achieve the above object, the present invention is achieved in that
A kind of engineering material stacking method based on BIM, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area
Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building
The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect
Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported;
Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Described engineering material stacking method based on BIM, step 4 also includes: the three-dimensional modeling of construction material, to difference
Region is stacked in the permission of material, zones of different placing of material is controlled the size and added up;Run simulation and include any floor or portion
The quantities output of position, the simulation of material stockyard capacity and automatically distributing;Form graphics according to simulation conclusion and export.
This stacking method is simulated modeling to the building of construction area, road, place, and by the quantity of construction material,
Classification, service condition are carried out in advance, real-time statistics, then coordinate the tune to construction material of the dynamic data in practice of construction operation
Join simulation and carry out.So, even if in highdensity construction place, also can rationally, accurately and timely to building
Build material allocate and regulate and control, and then improve the efficiency of construction operation.
Detailed description of the invention
The present invention is further illustrated below by way of specific embodiment.
A kind of engineering material stacking method based on BIM, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area
Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building
The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect
Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported;
Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Described engineering material stacking method based on BIM, step 4 also includes: the three-dimensional modeling of construction material, to difference
Region is stacked in the permission of material, zones of different placing of material is controlled the size and added up;Run simulation and include any floor or portion
The quantities output of position, the simulation of material stockyard capacity and automatically distributing;Form graphics according to simulation conclusion and export.
This stacking method is simulated modeling to the building of construction area, road, place, and by the quantity of construction material,
Classification, service condition are carried out in advance, real-time statistics, then coordinate the tune to construction material of the dynamic data in practice of construction operation
Join simulation and carry out.So, even if in highdensity construction place, also can rationally, accurately and timely to building
Build material allocate and regulate and control, and then improve the efficiency of construction operation.
Claims (2)
1. an engineering material stacking method based on BIM, is characterized in that, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area
Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building
The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect
Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported;
Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Engineering material stacking method based on BIM the most according to claim 1, is characterized in that, step 4 also includes: building
The three-dimensional modeling of material, permission stacking region, zones of different placing of material to different materials are controlled the size and are added up;Run
Simulation includes the quantities output at any floor or position, the simulation of material stockyard capacity and automatically distributes;According to simulation conclusion
Form graphics and export.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610760439.3A CN106326583A (en) | 2016-08-30 | 2016-08-30 | Stacking method for engineering materials based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610760439.3A CN106326583A (en) | 2016-08-30 | 2016-08-30 | Stacking method for engineering materials based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106326583A true CN106326583A (en) | 2017-01-11 |
Family
ID=57789135
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610760439.3A Pending CN106326583A (en) | 2016-08-30 | 2016-08-30 | Stacking method for engineering materials based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106326583A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107292538A (en) * | 2017-07-25 | 2017-10-24 | 浙江精工钢结构集团有限公司 | A kind of live material visual intelligent management system of Construction of Steel Structure |
CN108427787A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of assembled stockyard layout management method and system based on BIM |
CN108427790A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | The component logistics management emulation mode and device of erecting yard based on BIM |
CN109403630A (en) * | 2018-11-05 | 2019-03-01 | 江苏东保装饰集团有限公司 | A kind of public building interior decoration engineering sample construction method |
CN109872110A (en) * | 2019-03-05 | 2019-06-11 | 深圳市国晨工程造价咨询有限公司 | A kind of project materials purchasing management system |
CN110580574A (en) * | 2019-08-26 | 2019-12-17 | 交通运输部水运科学研究所 | method, system, device, medium and computing equipment for acquiring container stacking risk |
CN113326963A (en) * | 2020-02-28 | 2021-08-31 | 天津大学 | Storage yard optimization method based on prefabricated part transportation tracking and real-time progress |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104680321A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM technology-based visual material control system and method |
CN105868502A (en) * | 2016-04-22 | 2016-08-17 | 广州硕品物联网科技有限公司 | BIM (building information modeling) based material management system and control method thereof |
-
2016
- 2016-08-30 CN CN201610760439.3A patent/CN106326583A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104680321A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM technology-based visual material control system and method |
CN105868502A (en) * | 2016-04-22 | 2016-08-17 | 广州硕品物联网科技有限公司 | BIM (building information modeling) based material management system and control method thereof |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107292538A (en) * | 2017-07-25 | 2017-10-24 | 浙江精工钢结构集团有限公司 | A kind of live material visual intelligent management system of Construction of Steel Structure |
CN108427787A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of assembled stockyard layout management method and system based on BIM |
CN108427790A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | The component logistics management emulation mode and device of erecting yard based on BIM |
CN109403630A (en) * | 2018-11-05 | 2019-03-01 | 江苏东保装饰集团有限公司 | A kind of public building interior decoration engineering sample construction method |
CN109872110A (en) * | 2019-03-05 | 2019-06-11 | 深圳市国晨工程造价咨询有限公司 | A kind of project materials purchasing management system |
CN110580574A (en) * | 2019-08-26 | 2019-12-17 | 交通运输部水运科学研究所 | method, system, device, medium and computing equipment for acquiring container stacking risk |
CN110580574B (en) * | 2019-08-26 | 2024-02-20 | 交通运输部水运科学研究所 | Method, system, device, medium and computing equipment for acquiring container stacking risk |
CN113326963A (en) * | 2020-02-28 | 2021-08-31 | 天津大学 | Storage yard optimization method based on prefabricated part transportation tracking and real-time progress |
CN113326963B (en) * | 2020-02-28 | 2022-12-20 | 天津大学 | Storage yard optimization method based on prefabricated part transportation tracking and real-time progress |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106326583A (en) | Stacking method for engineering materials based on BIM | |
CN105868502A (en) | BIM (building information modeling) based material management system and control method thereof | |
CN108428194A (en) | A kind of management method and device of the building material processing dispatching based on BIM | |
CN107967399A (en) | A kind of assembled architecture Deepen Design method based on BIM softwares | |
Yu et al. | A BIM-based dynamic model for site material supply | |
CN106326536A (en) | Standardized construction method for hydraulic prefabricated member based on BIM (Building Information Modeling) | |
CN101814174A (en) | Optimization method of agricultural material chain operation logistics center site selection | |
CN103606124A (en) | Microscopic simulation method of handling traffic system layout and traffic organization of container terminal | |
CN105243453A (en) | Dynamic ore matching optimization method for mined ore | |
CN106773686A (en) | With piler scheduling path model method for building up under the double car operational modes of rail | |
Straka et al. | Simulation of homogeneous production processes | |
CN104680352A (en) | Fresh agricultural product cold-chain logistics system network layout optimization method | |
Sakhaii et al. | A robust model for a dynamic cellular manufacturing system with production planning | |
Huka et al. | Log yard logistics | |
CN113190885A (en) | Layout planning method for industrial assembly line workshop | |
Huang et al. | Estimation of construction waste generation and management in Taiwan | |
CN106203716A (en) | A kind of analysis method and apparatus of the dual resource distribution of production unit | |
Baek et al. | An Earthwork Districting Model for Large Construction Projects | |
Malé‐Alemany et al. | Soft tolerance: an approach for additive construction on site | |
CN108268962A (en) | Construction supply chain management method and apparatus based on 4D BIM and GIS | |
Le et al. | Complex simulation of stockyard mining operations | |
Brandtner et al. | A data structures for purpose of the BIM-based Life Cycle Assessment: A review and theoretical background | |
CN105844016A (en) | Planned building engineering quantity acquisition method based on building model cutting | |
CN110414904A (en) | A kind of container intelligence station system | |
Gwiazda et al. | Application of the advanced engineering systems for modeling logistics processes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170111 |