CN106295810A CN201610590933.XA CN201610590933A CN106295810A CN 106295810 A CN106295810 A CN 106295810A CN 201610590933 A CN201610590933 A CN 201610590933A CN 106295810 A CN106295810 A CN 106295810A
Authority
CN
China
Prior art keywords
abort situation
work order
maintenance
maintaining unit
troublshooting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610590933.XA
Other languages
Chinese (zh)
Other versions
CN106295810B (en
Inventor
杨超
公伟勇
秦志龙
李煦
张发骏
王强
董林
王文刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610590933.XA priority Critical patent/CN106295810B/en
Publication of CN106295810A publication Critical patent/CN106295810A/en
Application granted granted Critical
Publication of CN106295810B publication Critical patent/CN106295810B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Exchanges In Wide-Area Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a kind of troublshooting work order distributing method and a kind of troublshooting work order distributes device, described method includes: receive troublshooting work order;Obtain the abort situation of described troublshooting work order;Judge whether described abort situation has maintenance record;If it is determined that described abort situation is without described maintenance record, then from the match information that prestores, obtain the first maintaining unit mated with described abort situation, described in the match information that prestores include: multiple positional informationes and the maintaining unit mated with multiple described positional informationes;Described troublshooting work order is distributed to described first maintaining unit.Pass through technical scheme, staff is greatly reduced and distributes the workload of work order, improve the safety coefficient of worksheet efficiency and power distribution network, thus overcome the defect that work order of the prior art dependence manually distributes and causing trouble maintenance efficiency is low, effectively reduce the power off time of trouble point, and then improve Consumer's Experience.

Description

A kind of troublshooting work order distributing method and device
Technical field
The present invention relates to distribution network failure repairing field, be specifically related to a kind of troublshooting work order distributing method and one event Barrier reports work order for repairment and distributes device.
Background technology
Guo Wang client service center is with " customer service " for guiding at present, for ensureing that the fault that client reports for repairment can quick obtain everywhere Reason, it is desirable to electric company, after Guo Wang client service center distributes the troublshooting work order of client, confirms within three minutes to accept work order, And complete work order distribute work, these work are the most all completed by relevant staff.
But, under specific condition (such as vile weather, electric power system fault etc.), 95598 troublshooting work order amount meetings The phenomenon increased sharply occur, simple dependence staff reports work order for repairment by manually distributing one by one, cannot meet state's netter Take the job requirement at center, and work order distributes and the most not only can affect first-aid repair efficiency, and wait that meeting is to client for a long time Bring bad experience.
Therefore, how to overcome troublshooting work order of the prior art to rely on manually to distribute and causing trouble maintenance efficiency is low Under defect, become a technical problem urgently to be resolved hurrily.
Summary of the invention
Therefore, the technical problem to be solved in the present invention is to overcome troublshooting work order of the prior art to rely on artificial group Send out and the low defect of causing trouble maintenance efficiency, thus a kind of automatic distributing method of troublshooting work order and a kind of fault are provided Report work order for repairment and automatically distribute device.
In view of this, an aspect of of the present present invention provides a kind of troublshooting work order distributing method, including: receive fault report Repair work order;Obtain the abort situation of described troublshooting work order;Judge whether described abort situation has maintenance record;If it is determined that institute State abort situation without described maintenance record, then the first maintenance list that acquisition is mated with described abort situation from the match information that prestores Position, described in the match information that prestores include: multiple positional informationes and the maintaining unit mated with multiple described positional informationes;By institute State troublshooting work order and be distributed to described first maintaining unit.
Preferentially, the described step obtaining the first maintaining unit mated with described abort situation from the match information that prestores Including: selecting the target location identical with described abort situation from multiple described positional informationes, described abort situation includes: institute State the province of abort situation, city and block information and/or the coordinate information of described abort situation;Obtain and described target location The target maintaining unit joined, and using described target maintaining unit as described first maintaining unit.
Preferentially, described judge whether described abort situation has maintenance record to include: whether judge in maintenance history information There is described abort situation, described maintenance history information includes: multiple maintenance positions and with multiple described in maintenance position The maintaining unit of coupling;If it is determined that there is described abort situation in described maintenance history information, it is determined that described fault bit is equipped with Described maintenance record;If it is determined that there is not described abort situation in described maintenance history information, it is determined that described abort situation without Described maintenance record.
Preferentially, also include: if it is determined that described abort situation has described maintenance record, then from described maintenance history information Obtain the second maintaining unit mated with described abort situation;Described troublshooting work order is distributed to described second maintenance single Position.
Preferentially, also include: the information that distributes of described troublshooting work order is stored in described maintenance history information.
Provide a kind of troublshooting work order according to a further aspect in the invention and distribute device, including: receiver module, it is used for Receive troublshooting work order;First acquisition module, for obtaining the abort situation of described troublshooting work order;Judge module, uses In judging whether described abort situation has maintenance record;Second acquisition module, for if it is determined that described abort situation is without described dimension Repair record, then from the match information that prestores, obtain the first maintaining unit of mate with described abort situation, described in prestore to mate and believe Breath includes: multiple positional informationes and the maintaining unit mated with multiple described positional informationes;First distributes module, for by institute State troublshooting work order and be distributed to described first maintaining unit.
Preferentially, described second acquisition module includes: select unit, for selecting and institute from multiple described positional informationes Stating the target location that abort situation is identical, described abort situation includes: the province of described abort situation, city and block information and/ Or the coordinate information of described abort situation;Acquiring unit, for obtaining the target maintaining unit mated with described target location, and It is the first maintaining unit described in described target maintaining unit is made.
Preferentially, described judge module includes: judging unit, is used for judging whether there is described event in maintenance history information Barrier position, described maintenance history information includes: multiple maintenance positions and with multiple described in maintenance position mates maintenance Unit;First determines unit, for if it is determined that there is described abort situation in described maintenance history information, it is determined that described fault There is described maintenance record position;Second determines unit, for if it is determined that there is not described fault bit in described maintenance history information Put, it is determined that described abort situation is without described maintenance record.
Preferentially, also include: the 3rd acquisition module, for if it is determined that described abort situation has a described maintenance record, then from Described maintenance history information obtains the second maintaining unit mated with described abort situation;Second distributes module, for by institute State troublshooting work order and be distributed to described second maintaining unit.
Preferentially, also include: memory module, go through for the information that distributes of described troublshooting work order is stored in described maintenance In history information.
Technical scheme has the advantage that
The troublshooting work order distributing method that the present invention provides, after confirming to accept troublshooting work order, from this fault report Repair in work order extract to abort situation, by the maintaining unit new for there is not the abort situation Auto-matching of maintenance record, For there is the abort situation of maintenance record according to the former maintaining unit of maintenance history Auto-matching, finally realize breakdown maintenance work order Automatically distribute.Compared with prior art, staff is greatly reduced and distributes the workload of work order, improve worksheet effect Rate and the safety coefficient of power distribution network, thus overcome work order of the prior art dependence and manually distribute and causing trouble maintenance efficiency Low defect, effectively reduces the power off time of trouble point, and then improves Consumer's Experience.
Accompanying drawing explanation
In order to be illustrated more clearly that the specific embodiment of the invention or technical scheme of the prior art, below will be to specifically In embodiment or description of the prior art, the required accompanying drawing used is briefly described, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not paying creative work Put, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is a flow chart of the troublshooting work order distributing method of the embodiment of the present invention 1;
Fig. 2 is another flow chart of the troublshooting work order distributing method of the embodiment of the present invention 1;
Fig. 3 is the block diagram that the troublshooting work order of the embodiment of the present invention 2 distributes device.
Detailed description of the invention
Below in conjunction with accompanying drawing, technical scheme is clearly and completely described, it is clear that described enforcement Example is a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under not making creative work premise, broadly falls into the scope of protection of the invention.
In describing the invention, it should be noted that term " first ", " second " are only used for describing purpose, and can not It is interpreted as instruction or hint relative importance.
If additionally, the most non-structure of technical characteristic involved in invention described below difference embodiment Become conflict just can be combined with each other.
Embodiment 1
The present embodiment provides a kind of troublshooting work order distributing method, can be applicable in power distribution network repairing command system, energy Enough realizations distribute troublshooting work order, automatically as it is shown in figure 1, comprise the steps:
S11: receiving troublshooting work order, troublshooting work order herein is from 95598 customer service systems, and this process also includes Troublshooting work order carries out quickly (such as one minute) order automatically confirm.
S12: obtain the abort situation of troublshooting work order, after i.e. confirming order, extracts event from troublshooting work order The abort situation of barrier point.
Whether S13: whether failure judgement position has maintenance record, exist maintenance record here by failure judgement position Troublshooting work order is classified, in order to simplify work order and distribute process, if it is judged that be no, then performs step S14-S15, Otherwise perform step S16-S17.
S14: if it is determined that abort situation is without maintenance record, i.e. illustrates that this trouble point is to carry out troublshooting, before for the first time The most corresponding maintaining unit, then obtain the first maintaining unit mated with abort situation from the match information that prestores, as A kind of preferential selection scheme, the match information that herein prestores including but not limited to: multiple positional informationes and is believed with multiple positions The maintaining unit of breath coupling, i.e. can most suitable (such as distance be previously according to needing to choose to the multiple positions in power distribution network Short) repairing unit, specifically, the customer information in command system data base can be rushed to repair based on GIS geographical map and power distribution network, The maintaining unit of coupling is chosen for each position to be repaired, and by positional information to be repaired and matched repairing unit Information is stored in data base, calls for the later stage.
S15: troublshooting work order is distributed to the first maintaining unit, i.e. according to the matching result of step S14, automatically should Troublshooting work order distributes to the first repairing unit.
The method that above-mentioned troublshooting work order distributes automatically, after confirming to accept troublshooting work order, from this troublshooting Work order is extracted to abort situation, by the maintaining unit new for there is not the abort situation Auto-matching of maintenance record, reality Show the automatic reception of breakdown maintenance work order and distributed.
As a kind of preferential selection scheme, step S14 comprises the steps:
First selecting the target location identical with abort situation from multiple positional informationes, abort situation comprises but does not limits In: the province of abort situation, city and block information and/or the coordinate information of abort situation, herein can be by by abort situation Province, city and block information mate with the multiple positional informationes prestored in match information, it is also possible to pass through abort situation Coordinate information mate with above-mentioned multiple positional informationes, finally select the target location identical with this abort situation.
Then obtaining the target maintaining unit mated with target location, the maintaining unit herein mated with target location is permissible There is one, it is possibility to have multiple, select most suitable maintaining unit as target maintaining unit, and target maintaining unit is made It it is the first maintaining unit.
As a kind of preferential selection scheme, step S13 comprises the steps:
Judge whether maintenance history information exists abort situation, maintenance history information including but not limited to: multiple tie up Repair position and the maintaining unit mated with multiple maintenance positions, as a kind of concrete implementation mode, can be by judging Whether the repair address in maintenance history information comprises abort situation to determine whether this abort situation exists maintenance record. If it is determined that there is abort situation in maintenance history information, it is determined that fault bit is equipped with maintenance record;If it is determined that maintenance history information In there is not abort situation, it is determined that abort situation is without maintenance record.
As a kind of preferential selection scheme, as in figure 2 it is shown, further comprise the steps of:
S16: if it is determined that fault bit is equipped with maintenance record, then obtain the mated with abort situation from maintenance history information Two maintaining units;
S17: troublshooting work order is distributed to the second maintaining unit.
As a kind of concrete implementation mode, if it is decided that this abort situation exists maintenance record, this trouble point is described not It is to report for repairment for the first time, can exist in maintenance history information and once carry out, for this abort situation, the maintaining unit (i.e. second that keeps in repair Maintaining unit), from the point of view of contrast, it is contemplated that this trouble point is become more apparent upon by this maintaining unit, then directly by this troublshooting work order It is distributed to the second maintaining unit, is favorably improved breakdown maintenance efficiency.
As a kind of preferential selection scheme, after the step s 15 and further comprise the steps of: after step S17
S18: the information that distributes of troublshooting work order be stored in maintenance history information, completes after work order distributes the most every time, Automatically this is distributed information and be stored in data base, distribute record according to this when again reporting for repairment for this abort situation and quickly carry out Choosing of maintaining unit.
The present embodiment provide troublshooting work order distributing method, by be do not exist maintenance record abort situation oneself The maintaining unit that dynamic coupling is new, for there is the abort situation of maintenance record according to the former maintaining unit of maintenance history Auto-matching, Finally realize automatically distributing of breakdown maintenance work order.Compared with prior art, staff is greatly reduced and distributes the work of work order Measure, improve the safety coefficient of worksheet efficiency and power distribution network, thus overcome work order of the prior art and rely on artificial Distribute and the low defect of causing trouble maintenance efficiency, effectively reduce the power off time of trouble point, and then improve user's body Test.
Embodiment 2
The present embodiment has supplied a kind of troublshooting work order to distribute device 3, can be applicable in power distribution network repairing command system, energy Enough realizations distribute troublshooting work order, automatically as it is shown on figure 3, include: receiver module 31, are used for receiving troublshooting work order;The One acquisition module 32, for obtaining the abort situation of troublshooting work order;Whether judge module 33, have for failure judgement position Maintenance record;Second acquisition module 34, for if it is determined that abort situation is without maintenance record, then obtain from the match information that prestores with Abort situation coupling the first maintaining unit, the match information that prestores includes: multiple positional informationes and with multiple positional informationes The maintaining unit joined;First distributes module 35, for troublshooting work order is distributed to the first maintaining unit.
As a kind of preferential selection scheme, the second acquisition module includes: select unit 341, for believing from multiple positions Selecting the target location identical with abort situation in breath, abort situation includes: the province of abort situation, city and block information and/ Or the coordinate information of abort situation;Acquiring unit 342, for obtaining the target maintaining unit mated with target location, and by mesh Mark maintaining unit is as the first maintaining unit.
As a kind of preferential selection scheme, it is judged that module 33 includes: judging unit 331, it is used for judging that maintenance history is believed Whether there is abort situation in breath, maintenance history information includes: multiple maintenance positions and mating with multiple maintenance positions Maintaining unit;First determines unit 332, for if it is determined that there is abort situation in maintenance history information, it is determined that fault bit It is equipped with maintenance record;Second determines unit 333, for if it is determined that there is not abort situation in maintenance history information, it is determined that therefore Barrier position is without maintenance record.
As a kind of preferential selection scheme, also include: the 3rd acquisition module 36, for if it is determined that fault bit is equipped with maintenance Record, then obtain the second maintaining unit mated with abort situation from maintenance history information;Second distributes module 37, and being used for will Troublshooting work order is distributed to the second maintaining unit.
As a kind of preferential selection scheme, also include: memory module 38, for distributing module 35 and second by first Distribute the troublshooting work order of module 37 to distribute information and be stored in maintenance history information.
What the present embodiment provided troublshooting work order distributes device 3, can be the abort situation that there is not maintenance record The maintaining unit that Auto-matching is new, single according to the former maintenance of maintenance history Auto-matching for there is the abort situation of maintenance record Position, finally realizes automatically distributing of breakdown maintenance work order.Compared with prior art, staff is greatly reduced and distributes work order Workload, improves the safety coefficient of worksheet efficiency and power distribution network, thus overcomes work order of the prior art and rely on people Work distributes and the low defect of causing trouble maintenance efficiency, effectively reduces the power off time of trouble point, and then improves user Experience.
Obviously, above-described embodiment is only for clearly demonstrating example, and not restriction to embodiment.Right For those of ordinary skill in the field, can also make on the basis of the above description other multi-form change or Variation.Here without also cannot all of embodiment be given exhaustive.And the obvious change thus extended out or Change among still in the protection domain of the invention.

Claims (10)

1. a troublshooting work order distributing method, it is characterised in that including:
Receive troublshooting work order;
Obtain the abort situation of described troublshooting work order;
Judge whether described abort situation has maintenance record;
If it is determined that described abort situation is without described maintenance record, then obtains from the match information that prestores and mate with described abort situation The first maintaining unit, described in the match information that prestores include: multiple positional informationes and mating with multiple described positional informationes Maintaining unit;
Described troublshooting work order is distributed to described first maintaining unit.
Troublshooting work order distributing method the most according to claim 1, it is characterised in that described from the match information that prestores The step obtaining the first maintaining unit mated with described abort situation includes:
Selecting the target location identical with described abort situation from multiple described positional informationes, described abort situation includes: institute State the province of abort situation, city and block information and/or the coordinate information of described abort situation;
Obtain the target maintaining unit mated with described target location, and using described target maintaining unit as described first maintenance Unit.
Troublshooting work order distributing method the most according to claim 2, it is characterised in that the described abort situation of described judgement Maintenance record whether is had to include:
Judging whether to exist in maintenance history information described abort situation, described maintenance history information includes: multiple keeped in repair position Put and with multiple described in maintenance position mates maintaining unit;
If it is determined that there is described abort situation in described maintenance history information, it is determined that described abort situation has described maintenance note Record;
If it is determined that there is not described abort situation in described maintenance history information, it is determined that described abort situation is without described maintenance note Record.
Troublshooting work order distributing method the most according to claim 3, it is characterised in that also include:
If it is determined that described abort situation has described maintenance record, then obtain and described abort situation from described maintenance history information Second maintaining unit of coupling;
Described troublshooting work order is distributed to described second maintaining unit.
Troublshooting work order distributing method the most according to any one of claim 1 to 4, it is characterised in that also include:
The information that distributes of described troublshooting work order is stored in described maintenance history information.
6. a troublshooting work order distributes device, it is characterised in that including:
Receiver module, is used for receiving troublshooting work order;
First acquisition module, for obtaining the abort situation of described troublshooting work order;
Judge module, is used for judging whether described abort situation has maintenance record;
Second acquisition module, for if it is determined that described abort situation is without described maintenance record, then obtains from the match information that prestores The first maintaining unit mated with described abort situation, described in the match information that prestores include: multiple positional informationes and with multiple The maintaining unit of described positional information coupling;
First distributes module, for described troublshooting work order is distributed to described first maintaining unit.
Troublshooting work order the most according to claim 6 distributes device, it is characterised in that described second acquisition module bag Include:
Select unit, for selecting the target location identical with described abort situation from multiple described positional informationes, described event Barrier position includes: the province of described abort situation, city and block information and/or the coordinate information of described abort situation;
Acquiring unit, for obtaining the target maintaining unit mated with described target location, and makees described target maintaining unit For described first maintaining unit.
Troublshooting work order the most according to claim 7 distributes device, it is characterised in that described judge module includes:
Judging unit, is used for judging whether to exist in maintenance history information described abort situation, and described maintenance history information includes: Multiple maintenance positions and with multiple described in maintenance position mates maintaining unit;
First determines unit, for if it is determined that there is described abort situation in described maintenance history information, it is determined that described fault There is described maintenance record position;
Second determines unit, for if it is determined that there is not described abort situation in described maintenance history information, it is determined that described event Barrier position is without described maintenance record.
Troublshooting work order the most according to claim 8 distributes device, it is characterised in that also include:
3rd acquisition module, for if it is determined that described abort situation has described maintenance record, then from described maintenance history information Obtain the second maintaining unit mated with described abort situation;
Second distributes module, for described troublshooting work order is distributed to described second maintaining unit.
10. distribute device according to the troublshooting work order according to any one of claim 6 to 9, it is characterised in that also include: Memory module, for being stored in the information that distributes of described troublshooting work order in described maintenance history information.
CN201610590933.XA 2016-07-25 2016-07-25 Fault repair work order distribution method and device Active CN106295810B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610590933.XA CN106295810B (en) 2016-07-25 2016-07-25 Fault repair work order distribution method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610590933.XA CN106295810B (en) 2016-07-25 2016-07-25 Fault repair work order distribution method and device

Publications (2)

Publication Number Publication Date
CN106295810A true CN106295810A (en) 2017-01-04
CN106295810B CN106295810B (en) 2020-09-08

Family

ID=57652394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610590933.XA Active CN106295810B (en) 2016-07-25 2016-07-25 Fault repair work order distribution method and device

Country Status (1)

Country Link
CN (1) CN106295810B (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106787182A (en) * 2016-12-09 2017-05-31 国网山东省电力公司微山县供电公司 Distribution fault processing method and system
CN107067163A (en) * 2017-03-24 2017-08-18 青岛海信网络科技股份有限公司 A kind of breakdown maintenance work dispatching method and device
CN107403225A (en) * 2017-06-23 2017-11-28 深圳市盛路物联通讯技术有限公司 Method and device is reported in a kind of shared equipment fault for repairment
CN108537386A (en) * 2018-04-13 2018-09-14 上海财经大学 Maintenance forecast device based on history maintenance record
CN108564181A (en) * 2018-04-10 2018-09-21 国家电网公司 Electrical equipment fault detects and method for maintaining and terminal device
CN108596494A (en) * 2018-04-25 2018-09-28 广州供电局有限公司 The business work order generation method and device of power failure impaired report information
CN109635968A (en) * 2019-01-21 2019-04-16 嘉兴恒创电力集团有限公司佳创综合服务分公司 A kind of troublshooting management method based on intelligent customer service
CN109712036A (en) * 2019-01-21 2019-05-03 嘉兴恒创电力集团有限公司华创信息科技分公司 A kind of troublshooting management method, system and relevant apparatus
CN110058606A (en) * 2019-03-29 2019-07-26 国网山东省电力公司梁山县供电公司 Power circuit O&M examination and repair system and method
WO2019232966A1 (en) * 2018-06-06 2019-12-12 平安科技(深圳)有限公司 Operation and maintenance method, device, terminal apparatus, and medium
CN110657072A (en) * 2018-06-29 2020-01-07 中车株洲电力机车研究所有限公司 Wind power fault maintenance method and system based on structured knowledge base
CN111275215A (en) * 2020-02-29 2020-06-12 云南电网有限责任公司西双版纳供电局 Voltage monitor fault self-diagnosis method and system based on Internet of things
CN112348345A (en) * 2020-10-30 2021-02-09 国网山东省电力公司临沂供电公司 Intelligent automatic order dispatching method and system
CN113625673A (en) * 2021-08-17 2021-11-09 国网宁夏电力有限公司 Dynamic scheduling method, device and system for power safety inspection personnel and storage device
CN113919710A (en) * 2021-10-15 2022-01-11 国网四川省电力公司成都供电公司 Regression prediction analysis-based order dispatching method and system
CN115269245A (en) * 2022-07-21 2022-11-01 超聚变数字技术有限公司 Memory fault processing method and computing device
CN115511397A (en) * 2022-11-23 2022-12-23 广东华居科技有限公司 Intelligent work order data dispatching method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101022362A (en) * 2007-03-27 2007-08-22 华为技术有限公司 Method for positioning fault and service maintenance platform
CN105373839A (en) * 2015-12-15 2016-03-02 国网北京市电力公司 Intelligent worksheet dispatching method and apparatus
CN105632175A (en) * 2016-01-08 2016-06-01 上海微锐智能科技有限公司 Vehicle behavior analysis method and system
US20160171427A1 (en) * 2014-12-10 2016-06-16 Fu Tai Hua Industry (Shenzhen) Co., Ltd. Parcel delivery management system and method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101022362A (en) * 2007-03-27 2007-08-22 华为技术有限公司 Method for positioning fault and service maintenance platform
US20160171427A1 (en) * 2014-12-10 2016-06-16 Fu Tai Hua Industry (Shenzhen) Co., Ltd. Parcel delivery management system and method thereof
CN105373839A (en) * 2015-12-15 2016-03-02 国网北京市电力公司 Intelligent worksheet dispatching method and apparatus
CN105632175A (en) * 2016-01-08 2016-06-01 上海微锐智能科技有限公司 Vehicle behavior analysis method and system

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106787182B (en) * 2016-12-09 2019-06-04 国网山东省电力公司微山县供电公司 Distribution fault processing method and system
CN106787182A (en) * 2016-12-09 2017-05-31 国网山东省电力公司微山县供电公司 Distribution fault processing method and system
CN107067163A (en) * 2017-03-24 2017-08-18 青岛海信网络科技股份有限公司 A kind of breakdown maintenance work dispatching method and device
CN107403225A (en) * 2017-06-23 2017-11-28 深圳市盛路物联通讯技术有限公司 Method and device is reported in a kind of shared equipment fault for repairment
CN107403225B (en) * 2017-06-23 2020-12-01 深圳市盛路物联通讯技术有限公司 Shared device fault repair method and device
CN108564181A (en) * 2018-04-10 2018-09-21 国家电网公司 Electrical equipment fault detects and method for maintaining and terminal device
CN108564181B (en) * 2018-04-10 2021-10-01 国家电网公司 Power equipment fault detection and maintenance method and terminal equipment
CN108537386A (en) * 2018-04-13 2018-09-14 上海财经大学 Maintenance forecast device based on history maintenance record
CN108596494A (en) * 2018-04-25 2018-09-28 广州供电局有限公司 The business work order generation method and device of power failure impaired report information
WO2019232966A1 (en) * 2018-06-06 2019-12-12 平安科技(深圳)有限公司 Operation and maintenance method, device, terminal apparatus, and medium
CN110657072A (en) * 2018-06-29 2020-01-07 中车株洲电力机车研究所有限公司 Wind power fault maintenance method and system based on structured knowledge base
CN109635968A (en) * 2019-01-21 2019-04-16 嘉兴恒创电力集团有限公司佳创综合服务分公司 A kind of troublshooting management method based on intelligent customer service
CN109712036A (en) * 2019-01-21 2019-05-03 嘉兴恒创电力集团有限公司华创信息科技分公司 A kind of troublshooting management method, system and relevant apparatus
CN110058606A (en) * 2019-03-29 2019-07-26 国网山东省电力公司梁山县供电公司 Power circuit O&M examination and repair system and method
CN111275215A (en) * 2020-02-29 2020-06-12 云南电网有限责任公司西双版纳供电局 Voltage monitor fault self-diagnosis method and system based on Internet of things
CN112348345A (en) * 2020-10-30 2021-02-09 国网山东省电力公司临沂供电公司 Intelligent automatic order dispatching method and system
CN113625673A (en) * 2021-08-17 2021-11-09 国网宁夏电力有限公司 Dynamic scheduling method, device and system for power safety inspection personnel and storage device
CN113919710A (en) * 2021-10-15 2022-01-11 国网四川省电力公司成都供电公司 Regression prediction analysis-based order dispatching method and system
CN113919710B (en) * 2021-10-15 2024-08-06 国网四川省电力公司成都供电公司 Dispatching method and dispatching system based on regression prediction analysis
CN115269245A (en) * 2022-07-21 2022-11-01 超聚变数字技术有限公司 Memory fault processing method and computing device
CN115269245B (en) * 2022-07-21 2024-03-19 超聚变数字技术有限公司 Memory fault processing method and computing device
CN115511397A (en) * 2022-11-23 2022-12-23 广东华居科技有限公司 Intelligent work order data dispatching method and system

Also Published As

Publication number Publication date
CN106295810B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN106295810A (en) A kind of troublshooting work order distributing method and device
CN107368898B (en) Intelligent fault reporting and maintenance monitoring method
US11049195B2 (en) Modeling analysis method based on geographic targets
EP2538378A1 (en) A system for using attributes to deploy demand response resources
CN108053042A (en) A kind of outage information is reported and submitted and delivery system
CN103763122A (en) Fault information processing method and service system
CN109523038A (en) Gridding power failure analysis method and system
CN104616108A (en) Method for distributing and recovering electric power overhaul tool
CN104951994A (en) GIS-based comprehensive display method and system of distribution network production special topic view
CN105471982A (en) Interaction method and system for internet-of-things gateway and cloud platform
CN105553677A (en) Charging verification audit system
CN105260837A (en) Teaching management system and teaching management method thereof
CN104936157A (en) Mobile phone number bound account acquisition method and system
CN104599068A (en) Method for positioning user fault through comprehensive analysis of repair request information
CN109168173B (en) Base station operation and maintenance management method and device and electronic equipment
CN105654283A (en) Safety payment method and apparatus thereof
CN107358562A (en) For the electric network emergency repairing flattening command system and method under Rainfall Disaster
KR20160141984A (en) bike rental device using smart phone
CN112907157A (en) Power grid risk visualization method and system based on meteorological early warning
CN106557986B (en) Photovoltaic power station equipment maintenance method
CN102571511A (en) Local area network access control system and method, and server
CN110535911B (en) Distributed management method of open wireless network
JP2010239528A (en) Management system and method for provided services in communication network
CN104732339A (en) Gas emergency repair treatment optimization method and system based on emergency plan
CN109523140A (en) A kind of management method and system of the vehicle of speedily carrying out rescue work based on dipper system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17

Applicant after: Qingdao Power Supply Company, State Grid Shandong Electric Power Company

Applicant after: State Grid Co., Ltd.

Address before: Shinan District 266003 Shandong city of Qingdao province Liujiaxia Road No. 17

Applicant before: Qingdao Power Supply Company, State Grid Shandong Electric Power Company

Applicant before: State Grid Corporation

GR01 Patent grant
GR01 Patent grant