Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, right
The present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, and
It is not used in the restriction present invention.
Fig. 1 is the indicative flowchart of the expense control settlement function method of testing of the expense control electric energy meter of an embodiment.Such as Fig. 1 institute
Showing, the expense control settlement function method of testing of the expense control electric energy meter in the present embodiment includes step:
S1, the remaining sum of check fee control electric energy meter, obtain respectively and take control electric energy meter at remaining sum less than default the
Warning execution information during the one warning amount of money, at remaining sum more than the described first warning amount of money and less than the second warning preset
The warning during amount of money performs information;The warning execution information got is compared with corresponding preset alarm information respectively,
Judge that according to comparison result the warning of expense control electric energy meter performs the most correct;
In the present embodiment, before step S1, also need the expense control pattern that the electric energy meter of check fee control in advance is current;If it is non-local
Take control pattern, then expense control electric energy meter is switched to local charge control pattern;Also need in advance to described expense control electric energy meter open an account with
And Initialize installation, wherein Initialize installation includes but not limited to: when arranging current rate electricity price, deferred duty electricity price, rate
Segment table, voltage current transformer no-load voltage ratio, the first warning amount of money and the setting of the second warning amount of money, prepare for test.
In the present embodiment, described warning execution information includes but not limited to: closing frequencies/combined floodgate logout, tripping operation control
The character prompt information of terminal output signal processed, LED status, the backlight state of liquid crystal display and output.
As a preferred implementation, step S1 also includes: detection is closed a floodgate telegram in reply instruction, and obtain to receive combined floodgate multiple
Warning in the case of electricity instruction performs information;The warning execution information got is compared with corresponding preset alarm information
Right, judge that according to comparison result the warning of expense control electric energy meter performs the most correct.
As a preferred implementation, the embodiment of step S1 includes with lower part:
S1-1, expense control electric energy meter is set to protect electrolysis except state, then sends word instruction, detection to expense control electric energy meter
Take the remaining sum of control electric energy meter;When the remaining sum taking control electric energy meter is less than the first warning amount of money preset, take to described
Control electric energy meter sends halt instruction of having good luck;Obtain the described warning taking control electric energy meter current and perform information, the warning that will get
Execution information is compared with the first warning execution information preset, it is judged that the testing whether of this step is passed through.
S1-2, to described expense control electric energy meter send walk word instruction, the remaining sum of check fee control electric energy meter;Control is taken when described
When the remaining sum of electric energy meter is more than the first warning amount of money and less than the second warning amount of money preset, send out to described expense control electric energy meter
See word halt instruction off;Obtain and described take the control current warning of electric energy meter and perform information, the warning got is performed information with
The the second warning execution information preset is compared, it is judged that the testing whether of this step is passed through.
S1-3, send, to the described control electric energy meter that takes, telegram in reply instruction of closing a floodgate, obtain the described expense control current warning of electric energy meter and hold
Row information, compares the warning execution information got with the 3rd warning execution information preset, it is judged that the survey of this step
Whether examination is passed through.
S1-4, by expense control electric energy meter be set to protect electricity condition, then to expense control electric energy meter send walk word instruction, check fee control
The remaining sum of electric energy meter;When the described remaining sum of control electric energy meter that takes is more than the first warning amount of money and less than the Secondary Report preset
During the alert amount of money, send, to described expense control electric energy meter, halt instruction of having good luck;Obtain the described warning taking control electric energy meter current and perform letter
Breath, compares the warning execution information got with the 4th warning execution information preset, it is judged that the test of this step is
No pass through;
If the arbitrary testing result of S1-1, S1-2, S1-3, S1-4 is not for pass through, then it is judged as the report of described expense control electric energy meter
Alert execution is incorrect;If the testing result of S1-1, S1-2, S1-3, S1-4 is pass through, be then judged as described expense control electric energy meter
Reporting to the police, it is correct to perform.
Wherein, the execution sequence of above-mentioned S1-1, S1-2, S1-3, S1-4 part is not limited to its number order, and also interchangeable is held
Row order.
S2, the remaining sum of check fee control electric energy meter and overdraw the amount of money, respectively obtain take control electric energy meter big at remaining sum
In zero and allow overdraw execution information during amount of money limit value less than combined floodgate, be more than when closing a floodgate permission amount of money limit value at remaining sum
Overdraw execution information, overdraw the amount of money less than overdraw the amount of money limit value time overdraw perform information, overdraw the amount of money equal to overdraw gold
Overdraw execution information during volume limit value, the overdraw when the amount of money of overdrawing is more than overdraw amount of money limit value perform information;By get
Overdraw execution information is compared with corresponding default overdraw information respectively, judges to take the overdraw of control electric energy meter according to comparison result
Perform the most correct;
In the present embodiment, before step S2, also need the expense control pattern that the electric energy meter of check fee control in advance is current;If it is non-local
Take control pattern, then expense control electric energy meter is switched to local charge control pattern;Also need described expense control electric energy meter is opened an account and just
Beginningization is arranged, and prepares for test.
In the present embodiment, described overdraw execution information includes but not limited to: closing frequencies/combined floodgate logout, tripping operation control
The character prompt information of terminal output signal processed, LED status, the backlight state of liquid crystal display and output.
As a preferred implementation, the most also include: detection is closed a floodgate telegram in reply instruction, and obtains and receiving combined floodgate
Overdraw in the case of telegram in reply instruction performs information;The overdraw execution information got is compared with corresponding default overdraw information
Right, judge that according to comparison result the overdraw of expense control electric energy meter performs the most correct.
As a preferred implementation, the detailed description of the invention of step S2 can include with lower part:
S2-1, by expense control electric energy meter be set to protect electricity condition, and arrange its overdraw amount of money limit value be zero;Control electricity is taken to described
Word instruction be can send by table, remaining sum and the overdraw amount of money of described expense control electric energy meter detected;When remaining sum equal to zero and thoroughly
When propping up the amount of money more than 1, send, to described expense control electric energy meter, halt instruction of having good luck;The overdraw obtaining described expense control electric energy meter current is held
Row information, compares the overdraw execution information got with the first overdraw execution information preset, it is judged that the survey of this step
Whether examination is passed through;
S2-2, to expense control electric energy meter send supplement instruction with money so that described take control electric energy meter remaining sum be more than zero, then
It is set to protect electrolysis except state by expense control electric energy meter;Send word instruction to described expense control electric energy meter, detect described expense control electric energy
The remaining sum of table and the overdraw amount of money;When remaining sum is equal to zero and the overdraw amount of money is more than 1, send to the described control electric energy meter that takes
Having good luck halt instruction, the overdraw obtaining described expense control electric energy meter current performs information;The information that the overdraw got performed is with pre-
If the second overdraw execution information compare, it is judged that the testing whether of this step is passed through;
S2-3, send to expense control electric energy meter and supplement instruction with money, make the remaining sum of expense control electric energy meter more than zero and less than presetting
Combined floodgate allow amount of money limit value;Obtain the described overdraw taking control electric energy meter current and perform information, the overdraw got is performed letter
Breath and the 3rd preset execution information of overdrawing is compared, it is judged that the testing whether of this step is passed through;
S2-4, send to expense control electric energy meter and supplement instruction with money, make the remaining sum of expense control electric energy meter allow more than described combined floodgate
Amount of money limit value;Obtain and described take the control current overdraw of electric energy meter and perform information, by the overdraw execution information got with preset
4th overdraw execution information is compared, it is judged that the testing whether of this step is passed through;
S2-5, described overdraw amount of money limit value is updated to more than 1, sends word instruction, detection to described expense control electric energy meter
The described remaining sum taking control electric energy meter and the overdraw amount of money;When remaining sum, equal to zero and the overdraw amount of money is more than 1 less than overdraw gold
During volume limit value, send, to described expense control electric energy meter, halt instruction of having good luck;Obtain the described overdraw taking control electric energy meter current and perform letter
Breath, compares the overdraw execution information got with the 5th overdraw execution information preset, it is judged that the test of this step is
No pass through;
S2-6, send, to the described control electric energy meter that takes, telegram in reply instruction of closing a floodgate, obtain the described expense control current overdraw of electric energy meter and hold
Row information, compares the overdraw execution information got with the 6th overdraw execution information preset, it is judged that the survey of this step
Whether examination is passed through;
S2-7, send word instruction to described expense control electric energy meter, detect the described expense control remaining sum of electric energy meter and overdraw
The amount of money;When remaining sum equal to zero and the overdraw amount of money equal to the overdraw amount of money limit value time, send to described expense control electric energy meter and have good luck and stop
Only instruction;Obtain and described take the control current overdraw of electric energy meter and perform information, by the overdraw execution information got and the preset
Seven overdraw execution information are compared, it is judged that the testing whether of this step is passed through;
S2-8, send word instruction to described expense control electric energy meter, detect the described expense control remaining sum of electric energy meter and overdraw
The amount of money;When remaining sum equal to zero and the overdraw amount of money more than the overdraw amount of money limit value time, send to described expense control electric energy meter and have good luck and stop
Only instruction;Obtain and described take the control current overdraw of electric energy meter and perform information, by the overdraw execution information got and the preset
Eight overdraw execution information are compared, it is judged that the testing whether of this step is passed through;
If the arbitrary testing result of S2-1 to S2-8 is not for pass through, then it is judged as that the overdraw of described expense control electric energy meter is the most just performing
Really;If the testing result of S2-1 to S2-8 is pass through, be then judged as that the overdraw of described expense control electric energy meter performs correct.Wherein,
The execution sequence of above-mentioned S2-1 to S2-8 part is not limited to its number order, also interchangeable execution sequence.
If the arbitrary judged result of S3 above-mentioned S1, S2 is incorrect, it is determined that for the described expense control clearing merit taking control electric energy meter
Can be defective;If the judged result of above-mentioned S1 and S2 is correctly, it is determined that for the described expense control settlement function taking control electric energy meter
Qualified.
It should be noted that above-mentioned steps S1, the execution sequence of S2 are not only restricted to its number order in the present embodiment, also may be used
Exchange execution sequence, such as, it is possible to first carry out step S2, then perform step S1.
Below by concrete example, the present invention is taken the expense control settlement function method of testing work of control electric energy meter further
Explanation.Wherein, expense control electric energy meter to be tested is bimodulus expense control electric energy meter, and its expense control settlement function is only applicable to local charge control mould
Formula.Under local charge control pattern, bimodulus takes control electric energy meter can be according to metering energy value, the electricity rate table of current setting and tariff period
It is automatically performed charge calculation, and automatically sends out according to arranging overdraw amount of money threshold values, combined floodgate permission amount of money limit value and the current residual amount of money
Go out correspondence prompt alarm information, and/or perform switching tripping operation control terminal output switching signal thus control external load
Switch operates a switch or closes a floodgate, realize arrearage power-off and supplement with money after the action such as telegram in reply.
Expense control settlement function test to bimodulus expense control electric energy meter to be tested below is specifically described, and is divided into two parts
Testing, a part is tested for warning implementation status, and a part is overdraw implementation status test, specific as follows.
1. " warning function " concrete testing process comprises the following steps:
Step 11: bimodulus expense control electric energy meter is in local charge control pattern.Bimodulus expense control electric energy meter is initialized, opens an account
And supplement with money, recharge amount should enough ensure whole testing process.Arrange when protheca rate electricity price and standby set rate electricity
Valency, current 1st ladder table step price, when protheca ladder time-piece, voltage current transformer no-load voltage ratio, the warning amount of money 1 and report
The alert amount of money 2, also can arrange and hoard amount of money limit value and close a floodgate that to allow amount of money limit value be zero.
Step 12: arrange electric energy meter for protecting electrolysis and remove state, arranges overdraw amount of money limit value.Bimodulus expense control electric energy meter is made to walk
Word, when its remaining sum being detected less than the warning amount of money 1, makes bimodulus expense control electric energy meter stop having good luck.Check that bimodulus takes control electric energy
The warning function implementation status of table, including pre-trip alarm condition position, tripping operation number of times and trip event record, tripping operation control terminal
Output signal and the backlight of liquid crystal display and character prompt.
The warning function implementation status detected is compared with the corresponding informance preset, it is judged that the test of this step is
No pass through.In the present embodiment, when the whole warning function implementation status only detected all are mated with corresponding presupposed information, just sentence
The test of this step disconnected is passed through, otherwise, it is judged that the test of this step is not passed through.
Step 13: make bimodulus expense control electric energy meter continue to have good luck, when its remaining sum is more than the warning amount of money 1 and less than gold of reporting to the police
During volume 2, bimodulus expense control electric energy meter is made to stop having good luck.Check that bimodulus takes the warning function implementation status of control electric energy meter, including tripping operation
Number of times and trip event record, tripping operation control terminal output signal and the backlight of liquid crystal display and character prompt;Will detection
To warning function implementation status compare with the corresponding informance preset, it is judged that the testing whether of this step is passed through.This enforcement
In example, when the whole warning function implementation status only detected all are mated with corresponding presupposed information, just judge the survey of this step
Pinged, otherwise, it is judged that the test of this step is not passed through.
By in step 12 and 13, the shadow that the warning function of bimodulus expense control electric energy meter is performed by the warning amount of money can be tested comprehensively
Ring.
Step 14: to bimodulus take control electric energy meter insert close a floodgate telegram in reply card, or carry out button close a floodgate telegram in reply.Check that bimodulus takes control
The warning function implementation status of electric energy meter, including closing frequencies and combined floodgate logout, tripping operation control terminal output signal and
The backlight of liquid crystal display and character prompt;The warning function implementation status detected is compared with default corresponding informance
Right, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole warning function implementation status only detected are all with corresponding
Presupposed information coupling time, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not passed through.
By in step 14, can test and receive the shadow that the warning function of bimodulus expense control electric energy meter is performed by telegram in reply instruction of closing a floodgate
Ring.
Step 15: bimodulus expense control electric energy meter is set for protecting electricity condition.Bimodulus expense control electric energy meter is supplemented with money, remains after making to supplement with money
The amount of money is less than the warning amount of money 1.Have good luck, when remaining sum is more than the warning amount of money 1 and is less than the warning amount of money 2, stop.Check bimodulus
Take control electric energy meter warning function implementation status, including tripping operation number of times and trip event record, tripping operation control terminal output signal,
And the backlight of liquid crystal display and character prompt.The warning function implementation status detected is carried out with the corresponding informance preset
Comparison, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole warning function implementation status only detected are all with right
During the presupposed information coupling answered, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not passed through.
Step 16: check step 12~the detection case of 15, if step 12~15 arbitrary testing results are not for pass through, the most always
Body test result is " incorrect ", only when the testing result of step 12~15 be by time, overall test result side " is just
Really ".Wherein, step 12~15 execution be successively not limited to its number order, it is possible to exchange execution sequence.
2. " overdraw function " concrete testing process comprises the following steps:
Step 21: bimodulus expense control electric energy meter is in local charge control pattern.Bimodulus expense control electric energy meter is initialized, opens an account
And supplement with money, recharge amount should enough ensure whole testing process.Arrange when protheca rate electricity price and standby set rate electricity
Valency, current 1st ladder table step price, when protheca ladder time-piece, voltage current transformer no-load voltage ratio.Amount of money limit is hoarded in setting
Value, the warning amount of money 1, the warning amount of money 2 and the permission amount of money limit value that closes a floodgate are zero.
Step 22: arranging bimodulus expense control electric energy meter is guarantor's electricity condition, and arranging overdraw amount of money limit value is zero.Control bimodulus and take control
Electric energy meter is had good luck, when its remaining sum be zero, the overdraw amount of money more than 1, control bimodulus expense control electric energy meter and stop having good luck.Check bimodulus
Take control electric energy meter overdraw function executing situation, including tripping operation number of times and trip event record, tripping operation control terminal output signal,
LED status and the backlight of liquid crystal display and character prompt;By the overdraw function executing situation that detects with preset
Corresponding informance is compared, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole overdraw functions only detected are held
When market condition is all mated with corresponding presupposed information, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not
Pass through.
By in step 22, the impact protecting electricity condition to the overdraw function executing of bimodulus expense control electric energy meter can be tested.
Step 23: bimodulus expense control electric energy meter is supplemented with money, makes its remaining sum more than zero.Bimodulus expense control electric energy meter is set for protecting
Electrolysis is except state.Control bimodulus expense control electric energy meter to have good luck, when its remaining sum be zero, the overdraw amount of money more than 1 time, control bimodulus and take
Control electric energy meter stops having good luck.Check that bimodulus takes the overdraw function executing situation of control electric energy meter, including tripping operation number of times and trip event
Record, tripping operation control terminal output signal, LED status and the backlight of liquid crystal display and character prompt;To detect
Overdraw function executing situation compare with the corresponding informance preset, it is judged that the testing whether of this step is passed through.The present embodiment
In, when the whole overdraw function executing situations only detected all are mated with corresponding presupposed information, just judge the test of this step
Pass through, otherwise, it is judged that the test of this step is not passed through.
By in step 23, guarantor's electrolysis can be tested except, under state, bimodulus is taken the overdraw of control electric energy meter by overdraw amount of money limit value
The impact of function executing.
Step 24: combined floodgate is set and allows amount of money limit value more than zero.Bimodulus expense control electric energy meter is supplemented with money, makes its remaining sum big
In zero and allow amount of money limit value less than closing a floodgate.Check that bimodulus takes the overdraw function executing situation of control electric energy meter, including closing frequencies
Carry with combined floodgate logout, tripping operation control terminal output signal, LED status and the backlight of liquid crystal display and character
Show;The overdraw function executing situation detected is compared with the corresponding informance preset, it is judged that the testing whether of this step is led to
Cross.In the present embodiment, when the whole overdraw function executing situations only detected all are mated with corresponding presupposed information, just judge this
The test of step is passed through, otherwise, it is judged that the test of this step is not passed through.
Step 25: bimodulus expense control electric energy meter is supplemented with money, makes its remaining sum allow amount of money limit value more than closing a floodgate.Check bimodulus
Take the overdraw function executing situation of control electric energy meter, including closing frequencies and combined floodgate logout, tripping operation control terminal output signal,
LED status and the backlight of liquid crystal display and character prompt;By the overdraw function executing situation that detects with preset
Corresponding informance is compared, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole overdraw functions only detected are held
When market condition is all mated with corresponding presupposed information, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not
Pass through.
Step 26: overdraw amount of money limit value is set more than 1.Control bimodulus expense control electric energy meter to have good luck, when its remaining sum be zero,
When the overdraw amount of money is more than 1 and less than overdraw amount of money limit value, controls bimodulus expense control electric energy meter and stop having good luck.Check that bimodulus takes control electric energy
The overdraw function executing situation of table, including tripping operation number of times and trip event record, tripping operation control terminal output signal, display lamp shape
State and the backlight of liquid crystal display and character prompt;By the overdraw function executing situation detected and the corresponding informance preset
Compare, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole overdraw function executing situations only detected are equal
When mating with corresponding presupposed information, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not passed through.
Step 27: electric energy meter is carried out button combined floodgate.Check that bimodulus takes the overdraw function executing situation of control electric energy meter, including
Closing frequencies and combined floodgate logout, tripping operation control terminal output signal, LED status and the backlight of liquid crystal display and
Character prompt;The overdraw function executing situation detected is compared with the corresponding informance preset, it is judged that the test of this step
Whether pass through.In the present embodiment, when the whole overdraw function executing situations only detected all are mated with corresponding presupposed information,
Judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not passed through.
By in step 27, can test receiving telegram in reply instruction of closing a floodgate and bimodulus expense control electric energy meter is overdrawed the shadow of function executing
Ring.
Step 28: control bimodulus expense control electric energy meter and have good luck, when its overdraw amount of money is equal to overdraw amount of money limit value, control bimodulus
Expense control electric energy meter stops having good luck.Check that bimodulus takes the overdraw function executing situation of control electric energy meter, including tripping operation number of times and tripping operation thing
Part record, tripping operation control terminal output signal, LED status and the backlight of liquid crystal display and character prompt;Will detection
To overdraw function executing situation compare with the corresponding informance preset, it is judged that the testing whether of this step is passed through.This enforcement
In example, when the whole overdraw function executing situations only detected all are mated with corresponding presupposed information, just judge the survey of this step
Pinged, otherwise, it is judged that the test of this step is not passed through.
Step 29: control bimodulus expense control electric energy meter and have good luck, when its overdraw amount of money is more than overdraw amount of money limit value, control bimodulus
Expense control electric energy meter stops having good luck.Check that bimodulus takes the overdraw function executing situation of control electric energy meter, including closing frequencies and combined floodgate thing
Part record, tripping operation control terminal output signal, LED status and the backlight of liquid crystal display and character prompt;Will detection
To overdraw function executing situation compare with the corresponding informance preset, it is judged that the testing whether of this step is passed through.This enforcement
In example, when the whole overdraw function executing situations only detected all are mated with corresponding presupposed information, just judge the survey of this step
Pinged, otherwise, it is judged that the test of this step is not passed through.
By in step 26,28 and 29, guarantor's electrolysis can be tested except, under state, bimodulus is taken control electricity by overdraw amount of money limit value comprehensively
The impact of the overdraw function executing of energy table.
Step 30: bimodulus expense control electric energy meter is supplemented with money, makes its remaining sum allow amount of money limit value less than closing a floodgate.Check bimodulus
Take the overdraw function executing situation of control electric energy meter, including closing frequencies and combined floodgate logout, tripping operation control terminal output signal,
LED status and the backlight of liquid crystal display and character prompt;By the overdraw function executing situation that detects with preset
Corresponding informance is compared, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole overdraw functions only detected are held
When market condition is all mated with corresponding presupposed information, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not
Pass through.
Step 31: bimodulus expense control electric energy meter is supplemented with money, makes its remaining sum allow amount of money limit value more than closing a floodgate.Check bimodulus
Take the overdraw function executing situation of control electric energy meter, including closing frequencies and combined floodgate logout, tripping operation control terminal output signal,
LED status and the backlight of liquid crystal display and character prompt;By the overdraw function executing situation that detects with preset
Corresponding informance is compared, it is judged that the testing whether of this step is passed through.In the present embodiment, the whole overdraw functions only detected are held
When market condition is all mated with corresponding presupposed information, just judge that the test of this step is passed through, otherwise, it is judged that the test of this step is not
Pass through.
By step 24 and 25, step 30 and 31, guarantor's electrolysis can be tested except, under state, closing a floodgate and allow amount of money limit value pair comprehensively
Bimodulus takes the impact of the overdraw function executing of control electric energy meter.
Step 32: check step 22~the detection case of 31, if step 22~31 arbitrary testing results are not for pass through, the most always
Body test result is " incorrect ", only when step 22~31 testing result all by time, overall test result side is " correctly ".
In the present embodiment, when above-mentioned two-part test result is " correctly ", just determine the expense control of expense control electric energy meter
Settlement function test is for qualified, otherwise, it determines test as defective for taking the expense control settlement function of control electric energy meter.
The expense control settlement function method of testing taking control electric energy meter of above-described embodiment, pre-by priority check fee control electric energy meter
If each in the case of warning perform information and overdraw execution information, combine preset warning perform information judge take control electric energy meter
Warning perform whether correct, combining the overdraw execution information preset, to judge that expense controls the overdraw execution of electric energy meter the most correct;If
Report to the police perform and overdraw perform the most correct, it is determined that for described take control electric energy meter expense control settlement function qualified, otherwise, it determines be
Described take control electric energy meter expense control settlement function defective.It is possible to the expense control clearing of the electric energy meter of check fee control comprehensively and effectively
Function, it is adaptable to expense control electric energy meter expense control settlement function is evaluated by constituent parts, and the suitability is wide.
It should be noted that for aforesaid embodiment of the method, in order to simplicity describes, it is all expressed as a series of dynamic
Combining, but those skilled in the art should know, the present invention is not limited by described sequence of movement, because foundation
The present invention, some step can use other order or carry out simultaneously.
Based on the thought identical with the expense control settlement function method of testing taking control electric energy meter in above-described embodiment, the present invention
Also providing for the expense control settlement function test system of expense control electric energy meter, this system can be used for performing the expense control knot of above-mentioned expense control electric energy meter
Calculate function test method.For convenience of description, the structural representation of the expense control settlement function test system embodiment of control electric energy meter is taken
In figure, illustrate only the part relevant to the embodiment of the present invention, it will be understood by those skilled in the art that schematic structure not structure
The restriction of system in pairs, can include that ratio illustrates more or less of parts, or combine some parts, or different parts
Arrange.
Fig. 2 is the schematic diagram of the expense control settlement function test system of the expense control electric energy meter of one embodiment of the invention;
As in figure 2 it is shown, the expense control settlement function test system of the expense control electric energy meter of the present embodiment includes: first detection module 210, second
Detection module 220 and judge module 230, details are as follows for each module:
Above-mentioned first detection module 210, for the remaining sum of check fee control electric energy meter, respectively obtain take control electric energy meter exist
Remaining sum performs information less than warning during the first warning amount of money preset, is more than the described first warning amount of money at remaining sum
And perform information less than warning during the second warning amount of money preset;The warning execution information that gets is pre-with corresponding respectively
If warning message is compared, judge that according to comparison result the warning of expense control electric energy meter performs the most correct;
Above-mentioned second detection module 220, for remaining sum and the overdraw amount of money of check fee control electric energy meter, obtains expense respectively
Control electric energy meter is more than zero at remaining sum and performs information less than the overdraw closed a floodgate when allowing amount of money limit value, be more than at remaining sum
Close a floodgate allow the amount of money limit value time overdraw execution information, overdraw the amount of money less than overdraw the amount of money limit value time overdraw perform information,
Overdraw execution information when the amount of money of overdrawing is equal to overdraw amount of money limit value, the overdraw when the amount of money of overdrawing is more than overdraw amount of money limit value
Execution information;The overdraw execution information got is compared, according to comparison result with corresponding default overdraw information respectively
Judge that the overdraw of expense control electric energy meter performs the most correct;
Above-mentioned judge module 230, if the judged result for any of the above-described detection module is incorrect, it is determined that for described
The expense control settlement function taking control electric energy meter is defective;If the judged result of above-mentioned detection module is correctly, it is determined that for described
The expense control settlement function taking control electric energy meter is qualified;
As a preferred implementation, the expense control settlement function test system of above-mentioned expense control electric energy meter also includes initial setting up
Module (not shown), for check fee control electric energy meter current take control pattern;If non-local control pattern of taking, then will take control
Electric energy meter switches to local charge control pattern;It is additionally operable to described expense control electric energy meter is opened an account and Initialize installation.Preferably,
Initialize installation includes: arrange current rate electricity price, deferred duty electricity price, tariff period table, voltage current transformer no-load voltage ratio,
The one warning amount of money and the second warning amount of money;Wherein the second warning amount of money need to be more than the first warning amount of money.
As a preferred implementation, above-mentioned first detection module 210 is additionally operable to detection combined floodgate telegram in reply instruction, and obtains
Receive the warning in the case of telegram in reply instruction of closing a floodgate and perform information;The warning execution information got is believed with corresponding preset alarm
Breath is compared, and judges that according to comparison result the warning of expense control electric energy meter performs the most correct.
As a preferred implementation, above-mentioned second detection module 220 is additionally operable to detection combined floodgate telegram in reply instruction, and obtains
Receive the overdraw in the case of telegram in reply instruction of closing a floodgate and perform information;By the overdraw execution information got and corresponding default overdraw letter
Breath is compared, and judges that according to comparison result the overdraw of expense control electric energy meter performs the most correct.
The information of warning execution described in the present embodiment/overdraw execution information includes but not limited to: closing frequencies/combined floodgate event
The character prompt letter of record, tripping operation control terminal output signal, LED status, the backlight state of liquid crystal display and output
Breath.
The expense control settlement function test system taking control electric energy meter of above-described embodiment, covers technical standard about expense control electricity
Can take the every technology requirement controlling settlement function by table, content of the test is comprehensive;It is applicable to constituent parts to bimodulus expense control electric energy meter expense control
Settlement function implementation evaluation, the suitability is wide;Clear process, step are clear and definite, it is simple to testing crew operates
It should be noted that in the embodiment of expense control settlement function test system taking control electric energy meter of above-mentioned example,
The contents such as the information between each module is mutual, execution process, due to preceding method embodiment of the present invention based on same design, its
The technique effect brought is identical with preceding method embodiment of the present invention, and particular content can be found in chatting in the inventive method embodiment
Stating, here is omitted.
Additionally, in the embodiment of expense control settlement function test system taking control electric energy meter of above-mentioned example, each function mould
The logical partitioning of block is merely illustrative of, in actual application can as required, such as corresponding hardware configuration requirement or
The convenient consideration of the realization of person's software, is completed above-mentioned functions distribution by different functional modules, described will take control electric energy meter
The internal structure of expense control settlement function test system be divided into different functional modules, with complete described above all or
Partial function.The most each function mould both can realize to use the form of hardware, it would however also be possible to employ the form of software function module is real
Existing.
It will appreciated by the skilled person that all or part of flow process realizing in above-described embodiment method, be can
Completing instructing relevant hardware by computer program, described program can be stored in an embodied on computer readable storage and be situated between
In matter, as independent production marketing or use.Described program upon execution, can perform the complete of the embodiment such as above-mentioned each method
Portion or part steps.Wherein, described storage medium can be magnetic disc, CD, read-only store-memory body (Read-Only
Memory, ROM) or random store-memory body (Random Access Memory, RAM) etc..
In the above-described embodiments, the description to each embodiment all emphasizes particularly on different fields, and does not has the portion described in detail in certain embodiment
Point, may refer to the associated description of other embodiments.It is appreciated that the term " first " used in it, " second " etc. are at this
Literary composition is used for distinguishing object, but these objects should not be limited by these terms.
Embodiment described above only have expressed the several embodiments of the present invention, it is impossible to is interpreted as the scope of the claims of the present invention
Restriction.It should be pointed out that, for the person of ordinary skill of the art, without departing from the inventive concept of the premise,
Can also make some deformation and improvement, these broadly fall into protection scope of the present invention.Therefore, the protection domain of patent of the present invention
Should be as the criterion with claims.