CN106006356A - a tower hanger - Google Patents
a tower hanger Download PDFInfo
- Publication number
- CN106006356A CN106006356A CN201610581949.4A CN201610581949A CN106006356A CN 106006356 A CN106006356 A CN 106006356A CN 201610581949 A CN201610581949 A CN 201610581949A CN 106006356 A CN106006356 A CN 106006356A
- Authority
- CN
- China
- Prior art keywords
- lifting
- hook
- reinforcing plate
- tower
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000002787 reinforcement Effects 0.000 claims description 27
- 239000000463 material Substances 0.000 claims description 3
- 230000006378 damage Effects 0.000 abstract description 6
- 230000003014 reinforcing effect Effects 0.000 abstract 9
- 235000017166 Bambusa arundinacea Nutrition 0.000 abstract 2
- 235000017491 Bambusa tulda Nutrition 0.000 abstract 2
- 241001330002 Bambuseae Species 0.000 abstract 2
- 235000015334 Phyllostachys viridis Nutrition 0.000 abstract 2
- 239000011425 bamboo Substances 0.000 abstract 2
- 208000027418 Wounds and injury Diseases 0.000 abstract 1
- 230000002146 bilateral effect Effects 0.000 abstract 1
- 208000014674 injury Diseases 0.000 abstract 1
- 238000010030 laminating Methods 0.000 abstract 1
- 239000003973 paint Substances 0.000 description 8
- 238000000034 method Methods 0.000 description 5
- 239000000725 suspension Substances 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000001066 destructive effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 238000009659 non-destructive testing Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 238000006748 scratching Methods 0.000 description 1
- 230000002393 scratching effect Effects 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/14—Slings with hooks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
- B66C1/34—Crane hooks
- B66C1/36—Crane hooks with means, e.g. spring-biased detents, for preventing inadvertent disengagement of loads
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
Description
技术领域 technical field
本发明涉及塔筒吊装设备技术领域,特别是一种塔筒吊具。 The invention relates to the technical field of tower tube hoisting equipment, in particular to a tower tube hoisting tool.
背景技术 Background technique
风能作为一种清洁的可再生能源,越来越受到世界各国的重视。其蕴量巨大,全球的风能约为2.74×109MW,其中可利用的风能为2×107MW,比地球上可开发利用的水能总量还要大10倍。中国风能储量很大、分布面广,仅陆地上的风能储量就有约2.53亿千瓦。2015年,我国新增装机3.05万兆瓦,占全球新增量的48.4%,我国风机安装总量达到了14.5万兆瓦。理论需要塔筒约1亿吨做支撑。在塔筒制作过程中,需要对成品、半成品塔筒倒运、吊装,每节塔筒重量一般在15-40吨左右,传统的吊装方式是采用吊带在塔筒两端离法兰200-400mm处吊装,在吊装过程中,因吊带会对漆面产生巨大的压力和吊带拉长,对塔筒表面油漆造成损伤,在喷下道油漆或产品出厂前,均安排人员对损伤漆面进行修补,耗费人工工时,浪费油漆,且补漆的效果与原油漆面相比,效果非常差。另外,采用吊带吊装,需要两台吊车同时起吊,吊带起吊时,若与塔筒不垂直或配合不默契,易发生吊带滑脱的危险,后果不堪设想。 As a clean and renewable energy, wind energy has been paid more and more attention by countries all over the world. Its reserves are huge. The global wind energy is about 2.74×10 9 MW, of which the usable wind energy is 2×10 7 MW, which is 10 times larger than the total amount of water energy that can be developed and utilized on the earth. China's wind energy reserves are large and widely distributed. The wind energy reserves on land alone are about 253 million kilowatts. In 2015, my country's new installed capacity was 30,500 MW, accounting for 48.4% of the global new increase, and the total installed capacity of wind turbines in my country reached 145,000 MW. In theory, about 100 million tons of towers are needed for support. In the process of tower tube production, it is necessary to transport and hoist the finished and semi-finished tower tubes. The weight of each tower tube is generally about 15-40 tons. The traditional hoisting method is to use slings at the two ends of the tower tube at a distance of 200-400mm from the flange. Hoisting, during the hoisting process, because the sling will exert huge pressure on the paint surface and the sling will be elongated, causing damage to the paint on the surface of the tower tube. Before the next paint is sprayed or the product leaves the factory, personnel are arranged to repair the damaged paint surface. It consumes man-hours, wastes paint, and the effect of touch-up paint is very poor compared with the original paint surface. In addition, the use of slings for hoisting requires two cranes to lift at the same time. When the slings are hoisted, if they are not perpendicular to the tower or do not cooperate tacitly, the danger of the slings slipping will easily occur, and the consequences will be disastrous.
发明内容 Contents of the invention
本发明解决现有技术的不足提供一种省工省时、吊装安全、不损伤漆面的塔筒吊装的吊具。 The invention solves the deficiencies of the prior art and provides a hoisting tool for tower tube hoisting that saves labor and time, is safe for hoisting, and does not damage the paint surface.
本发明解决其技术问题所采用的技术方案为: The technical scheme that the present invention solves its technical problem adopts is:
一种塔筒吊具,包括吊钩和吊绳;所述吊钩上开设凹槽,凹槽内设有支撑加强板。 A tower hanger includes a hook and a hanging rope; a groove is provided on the hook, and a support reinforcement plate is arranged in the groove.
所述支撑加强板上设有支撑缓冲衬垫。 A support buffer pad is provided on the support reinforcement plate.
还包括U型卡环,U型卡环和吊钩上开设销孔,销轴穿过U型卡环和吊钩的销孔, U型卡环与吊绳连接。 It also includes a U-shaped snap ring, a pin hole is provided on the U-shaped snap ring and the suspension hook, the pin shaft passes through the U-shaped snap ring and the pin hole of the suspension hook, and the U-shaped snap ring is connected with the suspension rope.
所述支撑加强板的宽度大于吊钩的宽度。 The width of the support reinforcement plate is greater than the width of the hook.
所述支撑加强板为弧形板。 The support reinforcement board is an arc board.
所述吊钩上设置防脱挂钩,吊钩的形状为G型。 An anti-off hook is arranged on the hook, and the shape of the hook is G type.
所述吊钩内侧设置缓冲衬垫。 A buffer pad is arranged inside the hook.
所述缓冲衬垫的材质为橡胶。 The cushion pad is made of rubber.
所述支撑缓冲衬垫的材质为橡胶。 The material of the supporting buffer pad is rubber.
所述吊钩两侧对称设置支撑加强板。 Both sides of the hook are symmetrically provided with supporting reinforcement plates.
本发明的有益效果为: The beneficial effects of the present invention are:
1、一种塔筒吊具,包括吊钩和吊绳,所述吊钩上开设凹槽,凹槽内设有支撑加强板,起吊时支撑加强板贴合法兰盘,不再使用吊绳捆绑塔筒,不会对塔筒筒体造成伤害。所述支撑加强板上设有支撑缓冲衬垫。起吊时减少支撑加强板对法兰盘的冲击。 1. A tower hanger, including a hook and a sling. A groove is provided on the hook, and a support reinforcement plate is provided in the groove. When lifting, the support reinforcement plate is attached to the flange plate, and the sling is no longer used for binding The tower tube will not cause damage to the tower tube body. A support buffer pad is provided on the support reinforcement plate. Reduce the impact of the support reinforcement plate on the flange during lifting.
2、塔筒吊装的吊具上还包括U型卡环,U型卡环和吊钩上开设销孔,销轴穿过U型卡环和吊钩的销孔, U型卡环与吊绳连接。可根据吊装重量调节U型卡环和吊绳型号。所述支撑加强板的宽度大于吊钩的宽度,吊钩两侧对称设置支撑加强板,提升支撑加强板支撑强度,吊装更加稳定。支撑加强板为弧形板。增大支撑加强板与塔筒贴合面积。 2. The spreader for hoisting the tower also includes a U-shaped snap ring. A pin hole is set on the U-shaped snap ring and the hook. The pin shaft passes through the pin hole of the U-shaped snap ring and the hook. The U-shaped snap ring and the lifting rope connect. The U-shaped snap ring and sling type can be adjusted according to the hoisting weight. The width of the support reinforcement plate is greater than the width of the hook, and the support reinforcement plates are arranged symmetrically on both sides of the hook, so as to improve the support strength of the support reinforcement plate and make the hoisting more stable. The support reinforcement board is an arc-shaped board. Increase the bonding area between the support reinforcement plate and the tower tube.
3、吊钩上设置防脱挂钩,吊钩的形状为G型。防止在起吊时脱钩,提升设备使用安全性。吊钩内侧设置缓冲衬垫,防止吊钩划伤塔筒筒壁。 3. An anti-off hook is set on the hook, and the shape of the hook is G type. Prevent decoupling during lifting and improve equipment safety. The inner side of the hook is provided with a buffer pad to prevent the hook from scratching the wall of the tower tube.
综上所述,本发明减少了对法兰的损伤,挂钩方便,起吊塔筒后不损失油漆面,不再需要喷漆,大幅节约了人力和物力成本。设备不再使用吊带且吊具不易损坏,可降低吊带的用量,节约了生产成本。 To sum up, the present invention reduces the damage to the flange, the hook is convenient, the painted surface is not lost after the tower is hoisted, painting is no longer required, and manpower and material costs are greatly saved. The equipment no longer uses slings and the slings are not easy to damage, which can reduce the amount of slings and save production costs.
附图说明 Description of drawings
图1为本发明的结构示意图; Fig. 1 is a structural representation of the present invention;
图2为本发明的侧视图。 Figure 2 is a side view of the present invention.
具体实施方式 detailed description
一种塔筒吊具,包括吊钩1和吊绳8;所述吊钩1上开设凹槽,凹槽内设有支撑加强板2。所述支撑加强板2上设有支撑缓冲衬垫3,支撑缓冲衬垫3通过螺钉5固定在支撑加强板2上。还包括U型卡环7,U型卡环7和吊钩1上开设销孔,销轴6穿过U型卡环7和吊钩1的销孔, U型卡环7与吊绳8连接。所述支撑加强板2的宽度大于吊钩1的宽度。所述支撑加强板2为弧形板。所述吊钩1上设置防脱挂钩9,吊钩1的形状为G型。所述吊钩1内侧设置缓冲衬垫4,缓冲衬垫4与吊钩1内侧粘接。所述缓冲衬垫4和支撑缓冲衬垫3的材质为橡胶。所述吊钩1两侧对称设置支撑加强板2。 A tower hanger includes a hook 1 and a hanging rope 8; a groove is provided on the hook 1, and a support reinforcement plate 2 is arranged in the groove. The support and reinforcement board 2 is provided with a support and buffer pad 3 , and the support and buffer pad 3 is fixed on the support and reinforcement board 2 by screws 5 . Also includes U-shaped snap ring 7, U-shaped snap ring 7 and suspension hook 1 provide pin holes, pin shaft 6 passes through U-shaped snap ring 7 and the pin hole of suspension hook 1, U-shaped snap ring 7 is connected with lifting rope 8 . The width of the support reinforcement plate 2 is greater than the width of the hook 1 . The support reinforcement plate 2 is an arc-shaped plate. An anti-off hook 9 is arranged on the hook 1, and the shape of the hook 1 is G type. The inner side of the hook 1 is provided with a buffer pad 4 , and the buffer pad 4 is bonded to the inner side of the hook 1 . The buffer pad 4 and the supporting buffer pad 3 are made of rubber. Both sides of the hook 1 are symmetrically provided with supporting reinforcement plates 2 .
支撑加强板焊接工序 Support reinforcement plate welding process
1、用碳弧气刨在吊钩1两侧刨开8mm-10mm深的U型坡口,清理至无氧化物、油污、铁锈、水分等杂物。 1. Use carbon arc gouging to plan a U-shaped groove with a depth of 8mm-10mm on both sides of the hook 1, and clean it until there is no oxide, oil, rust, water and other sundries.
2、两侧分别焊制支撑加强板2,清理多余熔渣和飞溅物。 2. Weld supporting reinforcement plates 2 on both sides to clean up excess slag and spatter.
3、对焊缝进行无损UT检测。UT标准满足《承压设备无损检测》JB4730 Ⅰ级要求。 3. Conduct non-destructive UT testing on the weld. The UT standard meets the requirements of JB4730 Class I of "Nondestructive Testing of Pressure Equipment".
吊装塔筒时, When hoisting the tower,
1、先将吊钩1钩挂在法兰盘上; 1. First hang the hook 1 on the flange;
2、拉紧吊绳8提升法兰盘,防脱挂钩9贴合法兰盘; 2. Tighten the lifting rope 8 to lift the flange, and the anti-off hook 9 to attach the flange;
3、缓冲衬垫4和支撑缓冲衬垫3贴合法兰盘,缓冲衬垫4防止法兰盘轴向窜动,支撑缓冲衬垫3防止法兰盘径向窜动,同时缓冲衬垫4和支撑缓冲衬垫3有效保护外壁。 3. The buffer pad 4 and the supporting buffer pad 3 are attached to the flange, the buffer pad 4 prevents the axial movement of the flange, the supporting buffer pad 3 prevents the radial movement of the flange, and the buffer pad 4 and The supporting buffer pad 3 effectively protects the outer wall.
4、吊运至指定位置,松开拉紧吊绳8,拆除防脱挂钩9,吊运中外壁不再受到损伤。 4. Hoist to the designated location, loosen and tighten the sling 8, remove the anti-off hook 9, and the outer wall will no longer be damaged during hoisting.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610581949.4A CN106006356A (en) | 2016-07-22 | 2016-07-22 | a tower hanger |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610581949.4A CN106006356A (en) | 2016-07-22 | 2016-07-22 | a tower hanger |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106006356A true CN106006356A (en) | 2016-10-12 |
Family
ID=57116849
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610581949.4A Pending CN106006356A (en) | 2016-07-22 | 2016-07-22 | a tower hanger |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106006356A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108792928A (en) * | 2018-07-10 | 2018-11-13 | 中交航局第三工程有限公司 | Large scale prefabricated concrete component lifting anticreep construction method and device |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB8528540D0 (en) * | 1985-11-20 | 1985-12-24 | Yang Tai Her | Tension apparatus |
KR20020050312A (en) * | 2000-12-21 | 2002-06-27 | 이구택 | Apparatus for preventing separation of hook |
CN201914836U (en) * | 2010-12-30 | 2011-08-03 | 新疆鑫风麒能源服务股份有限公司 | Tail dragging hoisting tool for draught fan tower barrel hoisting |
CN202296839U (en) * | 2011-10-28 | 2012-07-04 | 北车同力钢构有限公司 | Hanging hook device for wind power tower drum |
CN204342245U (en) * | 2014-11-03 | 2015-05-20 | 珠海南方广立风电设备有限公司 | A kind of wind-power tower hoisting sling |
CN204384715U (en) * | 2014-12-26 | 2015-06-10 | 江苏海灵重工设备科技有限公司 | A kind of overhead hoist of high-power blower tower cylinder |
CN205367468U (en) * | 2016-01-14 | 2016-07-06 | 新疆天山恒合能源装备有限责任公司 | Tower section of thick bamboo of wind power tower cylinder single hop transportation usefulness is lifted and is hung special lifting hook |
CN206033022U (en) * | 2016-07-22 | 2017-03-22 | 甘肃酒钢集团西部重工股份有限公司 | Tower section of thick bamboo hoist |
-
2016
- 2016-07-22 CN CN201610581949.4A patent/CN106006356A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB8528540D0 (en) * | 1985-11-20 | 1985-12-24 | Yang Tai Her | Tension apparatus |
KR20020050312A (en) * | 2000-12-21 | 2002-06-27 | 이구택 | Apparatus for preventing separation of hook |
CN201914836U (en) * | 2010-12-30 | 2011-08-03 | 新疆鑫风麒能源服务股份有限公司 | Tail dragging hoisting tool for draught fan tower barrel hoisting |
CN202296839U (en) * | 2011-10-28 | 2012-07-04 | 北车同力钢构有限公司 | Hanging hook device for wind power tower drum |
CN204342245U (en) * | 2014-11-03 | 2015-05-20 | 珠海南方广立风电设备有限公司 | A kind of wind-power tower hoisting sling |
CN204384715U (en) * | 2014-12-26 | 2015-06-10 | 江苏海灵重工设备科技有限公司 | A kind of overhead hoist of high-power blower tower cylinder |
CN205367468U (en) * | 2016-01-14 | 2016-07-06 | 新疆天山恒合能源装备有限责任公司 | Tower section of thick bamboo of wind power tower cylinder single hop transportation usefulness is lifted and is hung special lifting hook |
CN206033022U (en) * | 2016-07-22 | 2017-03-22 | 甘肃酒钢集团西部重工股份有限公司 | Tower section of thick bamboo hoist |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108792928A (en) * | 2018-07-10 | 2018-11-13 | 中交航局第三工程有限公司 | Large scale prefabricated concrete component lifting anticreep construction method and device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102530711B (en) | Hydraulic pressure adjustable type balance frame for hoisting engine room of wind turbine | |
CN205668579U (en) | A kind of Portable steel pipe mover | |
CN202967864U (en) | Hanger | |
CN206188203U (en) | Coincide floor overhead hoist | |
CN204873413U (en) | Portable concurrent hoist and mount frame | |
CN106006356A (en) | a tower hanger | |
CN106315393A (en) | Flexible lifting lug capable of being rapidly assembled and disassembled and applicable to H-shaped steel | |
CN202488034U (en) | Angle iron tower transmission line lifting device | |
CN204434123U (en) | Tower body in tower crane resistance to deformation | |
CN206033022U (en) | Tower section of thick bamboo hoist | |
CN204342245U (en) | A kind of wind-power tower hoisting sling | |
CN104528519A (en) | Clamping tool for assisting in hoisting cement electric poles | |
CN205740084U (en) | A kind of crane | |
CN204999509U (en) | Concurrent loading and unloading assistor | |
CN204727473U (en) | A kind of crane hanger antiswing device | |
CN203715156U (en) | Convenient crane | |
CN204198227U (en) | A kind of for the compound type hoisting disk device during maintenance of the equipment such as blast furnace, heat generator | |
CN207048295U (en) | A kind of scaffold clasp | |
CN206051284U (en) | A kind of instrument for lifting concrete reinforced pipe | |
CN207293927U (en) | A kind of interim suspender peculiar to vessel | |
CN202643210U (en) | Aluminum ingot putting equipment | |
CN206014244U (en) | A kind of impeller head of shot-blasting machine can fast assembling and disassembling device | |
CN204265230U (en) | A kind of slipping tail sling system | |
CN204324713U (en) | Cement electric pole lifting auxiliary clamp | |
CN206318603U (en) | A kind of special hanger of large-sized water turbine field ring integral hoisting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161012 |
|
RJ01 | Rejection of invention patent application after publication |