[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN105926676A - Comprehensive pipe rack system with sponge urban function - Google Patents

Comprehensive pipe rack system with sponge urban function Download PDF

Info

Publication number
CN105926676A
CN105926676A CN201610458895.2A CN201610458895A CN105926676A CN 105926676 A CN105926676 A CN 105926676A CN 201610458895 A CN201610458895 A CN 201610458895A CN 105926676 A CN105926676 A CN 105926676A
Authority
CN
China
Prior art keywords
storehouse
rainwater
cabin
pipe
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610458895.2A
Other languages
Chinese (zh)
Other versions
CN105926676B (en
Inventor
汪胜
王家华
张显忠
李兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201610458895.2A priority Critical patent/CN105926676B/en
Publication of CN105926676A publication Critical patent/CN105926676A/en
Application granted granted Critical
Publication of CN105926676B publication Critical patent/CN105926676B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F2201/00Details, devices or methods not otherwise provided for
    • E03F2201/10Dividing the first rain flush out of the stormwater flow

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Health & Medical Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a comprehensive pipe rack system with a sponge urban function. Rainwater inspection wells are arranged above a rainwater cabin; rainwater enter the rainwater cabin through rainwater inlets; people enter the rainwater cabin through the rainwater inspection wells to dredge; an initial rainwater cabin is arranged under the rainwater cabin; the rainwater cabin is connected with the initial rainwater cabin through a plurality of communication holes; a clean water cabin is arranged under the initial rainwater cabin; the rainwater cabin is connected with the clean water cabin through a purification treatment device; a clean water lifting pump is arranged at the tail end of the clean water cabin, and is connected with a sprinkler head on the ground through a reclaimed water pipe; a fuel gas cabin is arranged above the clean water cabin; an inspector hole is formed on a clapboard between the clean water cabin and the fuel gas cabin; a waste water lifting pump is arranged at the tail end of the initial rainwater cabin, and is connected with a sewage pipe arranged at one side in a comprehensive cabin through a waste water pipe; electric power pipes, communication pipes, a water supply pipe and the sewage pipe are also arranged in the comprehensive cabin. The comprehensive pipe rack system with the sponge urban function provided by the invention has the functions of seepage, stagnation, storage, purification, application and drainage, and is strong in practicability, and easy to popularize and use.

Description

Pipe gallery system with sponge city function
Technical field
The present invention relates to pipe gallery technical field, particularly relate to the pipe gallery system with sponge city function System.
Background technology
In existing pipe gallery engineering, the most do not consider to include in pipe gallery by rainwater, sewage pipe, mesh Front all in constantly seeking.It is to utilize comprehensive pipe gallery structure body as rainwater that rainwater enters in pipe gallery Storehouse, elevation meets gravity stream requirement, and can enter river course by gravity stream, and sewage inlet pipe corridor is generally pipeline Pattern, the sewage pipe entering piping lane can be pressure current and gravity stream.
Sponge city overview is got up six words: ooze, stagnant, store, clean, with, row, piping lane is entered for rainwater, The body generally using piping lane replaces storm sewer, and rain sewage pipe is must take in pipe gallery design Planting pipeline, traditional design is generally not consider to include in pipe gallery rain sewage pipe in, even if considering, also Being simply to utilize piping lane body to replace rain pipe, size is generally equivalent to directly buried pipeline size, is slightly larger than once in a while Directly buried pipeline, the rainwater storehouse in usual pipe gallery arranges size and only considers the size of direct-burried rainwater pipeline, even You see rainwater storehouse do big after, there is the function of part storage, but other function of sponge city do not embody.
Therefore, those skilled in the art is devoted to develop a kind of pipe gallery system with sponge city function System.
Summary of the invention
Because the drawbacks described above of prior art, the technical problem to be solved be to provide a kind of with The pipe gallery system of sponge city function, reasonable in design, have oozing in sponge city, stagnant, store, Only, with, row function, practical, it is easy to promote the use of.
For achieving the above object, the invention provides the pipe gallery system with sponge city function, including Rainwater storehouse, early-stage rainwater storehouse, clear water storehouse, combustion gas storehouse, comprehensive storehouse, inlet for stom water that rainwater storehouse and top are arranged, Rainwater inspection well connect, the lower floor in rainwater storehouse is provided with early-stage rainwater storehouse, rainwater storehouse by multiple intercommunicating pores with Early-stage rainwater storehouse connects, and the end in rainwater storehouse is provided with river course connected entrance and purifying processing device connected entrance, Early-stage rainwater storehouse lower floor is provided with clear water storehouse, and rainwater storehouse is connected with clear water storehouse by purifying processing device, clear water Storehouse end is provided with clear water elevator pump, and clear water elevator pump spills greening and road by being used for watering on middle water pipe and ground The watering on road tethers and connects, and clear water storehouse is provided above combustion gas storehouse, the dividing plate between clear water storehouse and combustion gas storehouse setting Being equipped with inspection chamber, the end in early-stage rainwater storehouse is provided with waste water lifting pump, and waste water lifting pump passes through waste pipe The sewage pipe arranged with side in comprehensive storehouse is connected, and is additionally provided with power pipe, communication tube, feedwater in comprehensive storehouse Pipe, sewage pipe;The top in described rainwater storehouse is provided with the inlet for stom water of band audit function, car lane road two The inlet for stom water of side was connected by the inlet for stom water communicating pipe tilted;Plot, road intersection set outside pavement Two rainwater inspection wells put access rainwater storehouse by rain pipe;Machine between cycle track and car lane is non- Being provided with inlet for stom water in grass planting ditch in dividing strip, inlet for stom water is located at rain by inlet for stom water communicating pipe and side The rainwater inspection well connection of sump.
As preferably, described intercommunicating pore is arranged on the dividing plate between rainwater storehouse and early-stage rainwater storehouse, adjacent Distance between intercommunicating pore is 20m, it is ensured that the communication in two storehouses.
As preferably, the bottom in described rainwater storehouse is provided with the chute avoiding sedimentation.
As preferably, described clear water storehouse (3) end is provided with clear water elevator pump (15), clear water elevator pump (15) Greening is spilt and the watering bolt (17) of road is connected with on ground for watering by middle water pipe (16).
As preferably, the dividing plate between described clear water storehouse (3) and combustion gas storehouse (4) is provided with inspection chamber (18)。
The invention has the beneficial effects as follows:
The pipe gallery system with sponge city function of the present invention, road arranges grass-planting ecological ditch, plants Arranging inlet for stom water in grass ditch, the rainwater inspection well that top, rainwater storehouse is arranged, rainwater enters rainwater by inlet for stom water Cabin, personnel enter rainwater cabin by rainwater inspection well and carry out desilting, and the lower floor in rainwater storehouse is provided with early-stage rainwater Storehouse, rainwater storehouse is connected with early-stage rainwater storehouse by multiple intercommunicating pores, and early-stage rainwater storehouse lower floor is provided with clear water storehouse, Rainwater storehouse is connected with clear water storehouse by purifying processing device, and clear water storehouse end is provided with clear water elevator pump, clear water Elevator pump is tethered with ground watering by middle water pipe and connects, and clear water storehouse is provided above combustion gas storehouse, clear water storehouse And being provided with inspection chamber on the dividing plate between combustion gas storehouse, the end in early-stage rainwater storehouse is provided with waste water lifting Pump, the sewage pipe that waste water lifting pump is arranged with side in comprehensive storehouse by waste pipe is connected, and also sets in comprehensive storehouse It is equipped with power pipe, communication tube, feed pipe, sewage pipe.Have oozing in sponge city, stagnant, store, clean, With, row function, preferred arrangement space, topology layout is reasonable, has certain practicality, has promotion price Value.
Below with reference to accompanying drawing, the technique effect of design, concrete structure and the generation of the present invention is made furtherly Bright, to be fully understood from the purpose of the present invention, feature and effect.
Accompanying drawing explanation
Fig. 1 is the application schematic diagram of the present invention;
Fig. 2 is the A-A face sectional view in Fig. 1;
Fig. 3 is the B-B face sectional view in Fig. 1;
Fig. 4 is the C-C face sectional view in Fig. 1.
Detailed description of the invention
With reference to Fig. 1-Fig. 4, this detailed description of the invention by the following technical solutions: with sponge city function Pipe gallery system, including rainwater storehouse 1, early-stage rainwater storehouse 2, clear water storehouse 3, combustion gas storehouse 4, comprehensive storehouse 5, Inlet for stom water 6, rainwater inspection well 7 that rainwater storehouse 1 is arranged with top connect, and the lower floor in rainwater storehouse 1 is provided with Early-stage rainwater storehouse 2, rainwater storehouse 1 is connected with early-stage rainwater storehouse 2 by multiple intercommunicating pores 8, rainwater storehouse 1 End is provided with river course connected entrance and purifying processing device connected entrance, and early-stage rainwater storehouse 2 lower floor is provided with clearly Sump 3, rainwater storehouse 1 is connected with clear water storehouse 3 by purifying processing device, and clear water storehouse 3 is provided above combustion Gas storehouse 4, is disposed with sewage pipe 11, power pipe 12, communication tube 13, feed pipe 14 in comprehensive storehouse 5.
It should be noted that described intercommunicating pore 8 is arranged between rainwater storehouse 1 and early-stage rainwater storehouse 2 every On plate, the distance between adjacent intercommunicating pore 8 is 20m.
It should be noted that and be provided with inspection chamber on the dividing plate between described clear water storehouse 3 and combustion gas storehouse 4 18。
Additionally, the bottom in described rainwater storehouse 1 is provided with the chute 19 avoiding sedimentation.
The rainwater storehouse of original structure is divided three cabins to arrange by this detailed description of the invention, and ground floor is rainwater storehouse 1, uses Making to discharge rainwater, top is provided with inspection hole;A storehouse below, rainwater storehouse 1 is early-stage rainwater storehouse 2, and rainwater is relatively Hour, rainwater initially enters early-stage rainwater storehouse 2, the dividing plate between rainwater storehouse 1 and storehouse, 2 liang of early-stage rainwater storehouse The intercommunicating pore 8 arranged every 20m ensures the communication in two storehouses, the terminally positioned waste water lifting in early-stage rainwater storehouse 2 Pump 9, the sewage pipe 11 early-stage rainwater being promoted in comprehensive storehouse 5 by waste pipe 10;Early-stage rainwater storehouse 2 Following cabin is clear water storehouse 3, and the rainwater after the rainwater storehouse 1 purified processing means of rainwater processes enters clear water Storehouse 3, in clear water storehouse 3, end arranges clear water elevator pump 15, by middle water pipe 16, clear water is promoted to ground Watering bolt 17, be used as to water and spill greening and road, and clear water storehouse 3 is before very heavy rains, carries out pre-emptying, The heavy rain if outlet exceeds standard, can enter clear water storehouse 3 by unnecessary rainwater, improves standard of controlling flood and draining flooded fields;Combustion gas storehouse 4 individually become storehouse, highly meet People's Bank of China's headroom requirement, and unnecessary height space is used as to arrange rainwater cabin; Power pipe 12, communication tube 13, feed pipe 14, sewage pipe 11, wherein sewage pipe 11 are received in comprehensive storehouse 5 Side is arranged, sewage pipe 11 is gravity stream, and the gradient can be carried out with height spatially by the piping lane gradient Adjust and realize, solve the problem that sewage pipe enters corridor.
The inlet for stom water being provided with audit function at top, this detailed description of the invention rainwater storehouse 1, road both sides Inlet for stom water 6 is by inlet for stom water communicating pipe 21 connecting (Fig. 2), it is achieved the rainwater of inlet for stom water enters rainwater storehouse 1; Pipe gallery mode (Fig. 3) is entered for plot, road intersection rain pipe: top, rainwater storehouse 1 arranges rainwater Inspection shaft 7, two inspection shafts arranged outside road pavement 22 use rain pipe 23 by plot, intersect Road rain water accesses rainwater storehouse 1, according to the different perforates of access point height, rainwater inspection well 7 and rainwater storehouse 1 openings in the ceiling;Rainwater for grass planting ditch enters pipe gallery rainwater storehouse (Fig. 4): grass planting ditch 26 is arranged on In the non-dividing strip of machine 25 between cycle track 24 and car lane 20, grass planting ditch 26 have ooze, stagnant merit Can, it is provided with inlet for stom water 6 in grass planting ditch 26, rainwater inspection well 7 is set at top, rainwater storehouse 1, uses rainwater Inlet for stom water 6 in grass planting ditch is connected communicating pipe 21 by mouth with rainwater inspection well 7, rainwater inspection well 7 and rain Sump 1 openings in the ceiling.
Rainwater storehouse, in view of the feature of early-stage rainwater, is separated into several cabins, often by this detailed description of the invention Individual cabin has different functions, this system have oozing in sponge city, stagnant, store, clean, by, row's merit Can, pipe gallery have collected municipally conventional pipeline, containing draining, burning line, has certain practicality Property and wide market application foreground.
The preferred embodiment of the present invention described in detail above.Should be appreciated that the ordinary skill of this area Personnel just can make many modifications and variations according to the design of the present invention without creative work.Therefore, all Technical staff passes through logic analysis the most on the basis of existing technology, pushes away in the art Reason or the limited available technical scheme of experiment, all should be at the protection model being defined in the patent claims In enclosing.

Claims (5)

1. the pipe gallery system with sponge city function, it is characterised in that: include rainwater storehouse (1), Early-stage rainwater storehouse (2), clear water storehouse (3), combustion gas storehouse (4), comprehensive storehouse (5), rainwater storehouse (1) is arranged with top Inlet for stom water (6), rainwater inspection well (7) connection, the lower floor of rainwater storehouse (1) is provided with early-stage rainwater storehouse (2), Rainwater storehouse (1) is connected with early-stage rainwater storehouse (2) by multiple intercommunicating pores (8), and the end of rainwater storehouse (1) is provided with River course connected entrance and purifying processing device connected entrance, early-stage rainwater storehouse (2) lower floor is provided with clear water storehouse (3), Rainwater storehouse (1) is connected with clear water storehouse (3) by purifying processing device, and clear water storehouse (3) are provided above combustion gas storehouse (4), the end of early-stage rainwater storehouse (2) is provided with waste water lifting pump (9), and waste water lifting pump (9) passes through waste pipe (10) sewage pipe (11) arranged with side in comprehensive storehouse (5) is connected, and comprehensive storehouse is additionally provided with power pipe in (5) (12), communication tube (13), feed pipe (14), sewage pipe (11);The top of described rainwater storehouse (1) is arranged Having the inlet for stom water (6) of band audit function, the inlet for stom water (6) of car lane (20) road both sides is by the rain tilted Mouth of a river communicating pipe (21) connects;Two rainwater inspections that pavement (22) outside is arranged in plot, road intersection Look into well (7) and access rainwater storehouse (1) by rain pipe (23);Between cycle track (24) and car lane (20) Being provided with inlet for stom water (6) in grass planting ditch (26) in the non-dividing strip of machine (25), inlet for stom water (6) is by inlet for stom water even Siphunculus (21) connects with the rainwater inspection well (7) being located at rainwater storehouse (1) of side.
2. as claimed in claim 1 with the pipe gallery system of sponge city function, it is characterised in that: Described intercommunicating pore (8) is arranged on the dividing plate between rainwater storehouse (1) and early-stage rainwater storehouse (2), adjacent intercommunicating pore (8) distance between is 20m.
3. as claimed in claim 1 with the pipe gallery system of sponge city function, it is characterised in that: Described clear water storehouse (3) end is provided with clear water elevator pump (15), and described clear water elevator pump (15) passes through middle water pipe (16) greening is spilt and the watering bolt (17) of road is connected with on ground for watering.
4. as claimed in claim 1 with the pipe gallery system of sponge city function, it is characterised in that: It is provided with inspection chamber (18) on dividing plate between described clear water storehouse (3) and combustion gas storehouse (4).
5. as claimed in claim 1 with the pipe gallery system of sponge city function, it is characterised in that: The bottom of described rainwater storehouse (1) is provided with the chute (19) avoiding sedimentation.
CN201610458895.2A 2016-06-23 2016-06-23 Pipe gallery system with sponge city function Active CN105926676B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610458895.2A CN105926676B (en) 2016-06-23 2016-06-23 Pipe gallery system with sponge city function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610458895.2A CN105926676B (en) 2016-06-23 2016-06-23 Pipe gallery system with sponge city function

Publications (2)

Publication Number Publication Date
CN105926676A true CN105926676A (en) 2016-09-07
CN105926676B CN105926676B (en) 2017-12-01

Family

ID=56831933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610458895.2A Active CN105926676B (en) 2016-06-23 2016-06-23 Pipe gallery system with sponge city function

Country Status (1)

Country Link
CN (1) CN105926676B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480902A (en) * 2016-11-25 2017-03-08 沈阳建筑大学 There is water-retention and the underground pipe gallery of preliminary filtering function
CN106592625A (en) * 2016-12-12 2017-04-26 珠海市规划设计研究院 Urban road comprehensive pipe gallery wire-outgoing connection structure
CN106638681A (en) * 2016-12-19 2017-05-10 北京建筑大学 Integrated pipe gallery
CN107354956A (en) * 2017-07-19 2017-11-17 河南永立电力杆塔有限公司 A kind of pipe gallery system with sponge city function
CN107761763A (en) * 2017-10-18 2018-03-06 西安交通大学 A kind of pipe gallery and its application method
CN108265616A (en) * 2018-03-26 2018-07-10 上海市城市建设设计研究总院(集团)有限公司 Piping lane builds structure jointly with overhead
CN108374435A (en) * 2018-05-08 2018-08-07 杭州伟业建设集团有限公司 Underground pipe gallery construction method with rainwater cabin and combustion gas cabin
CN108894246A (en) * 2018-06-25 2018-11-27 四川省场道工程有限公司 A kind of Urban Underground Complex
CN111608228A (en) * 2020-04-16 2020-09-01 中国一冶集团有限公司 Sponge city and utility tunnel integration system
CN112459111A (en) * 2020-10-27 2021-03-09 江苏旭松建设工程有限公司 Pipe gallery protection device based on sponge city and construction method thereof
WO2022037364A1 (en) * 2020-08-18 2022-02-24 中铁二院工程集团有限责任公司 Ecological integrated pipe gallery

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003060242A1 (en) * 2002-01-16 2003-07-24 Angel Garcia Ballesteros Underground pipe and cable gallery which can be inspected
KR20060063827A (en) * 2006-04-27 2006-06-12 권순일 Prefabricated drainage pipe and rapid drainage method using the same
CN102660961A (en) * 2012-06-06 2012-09-12 上海市城市建设设计研究总院 Integral underground comprehensive pipe rack
CN203878609U (en) * 2014-05-19 2014-10-15 上海市城市建设设计研究总院 Comprehensive pipe corridor structure
CN205688460U (en) * 2016-06-23 2016-11-16 上海市城市建设设计研究总院 Pipe gallery system with sponge city function

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003060242A1 (en) * 2002-01-16 2003-07-24 Angel Garcia Ballesteros Underground pipe and cable gallery which can be inspected
KR20060063827A (en) * 2006-04-27 2006-06-12 권순일 Prefabricated drainage pipe and rapid drainage method using the same
CN102660961A (en) * 2012-06-06 2012-09-12 上海市城市建设设计研究总院 Integral underground comprehensive pipe rack
CN203878609U (en) * 2014-05-19 2014-10-15 上海市城市建设设计研究总院 Comprehensive pipe corridor structure
CN205688460U (en) * 2016-06-23 2016-11-16 上海市城市建设设计研究总院 Pipe gallery system with sponge city function

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480902A (en) * 2016-11-25 2017-03-08 沈阳建筑大学 There is water-retention and the underground pipe gallery of preliminary filtering function
CN106480902B (en) * 2016-11-25 2019-10-15 沈阳建筑大学 Underground pipe gallery with water storage and primary filtration function
CN106592625A (en) * 2016-12-12 2017-04-26 珠海市规划设计研究院 Urban road comprehensive pipe gallery wire-outgoing connection structure
CN106638681B (en) * 2016-12-19 2019-07-19 北京建筑大学 A kind of pipe gallery
CN106638681A (en) * 2016-12-19 2017-05-10 北京建筑大学 Integrated pipe gallery
CN107354956A (en) * 2017-07-19 2017-11-17 河南永立电力杆塔有限公司 A kind of pipe gallery system with sponge city function
CN107761763A (en) * 2017-10-18 2018-03-06 西安交通大学 A kind of pipe gallery and its application method
CN108265616A (en) * 2018-03-26 2018-07-10 上海市城市建设设计研究总院(集团)有限公司 Piping lane builds structure jointly with overhead
CN108374435A (en) * 2018-05-08 2018-08-07 杭州伟业建设集团有限公司 Underground pipe gallery construction method with rainwater cabin and combustion gas cabin
CN108894246A (en) * 2018-06-25 2018-11-27 四川省场道工程有限公司 A kind of Urban Underground Complex
CN111608228A (en) * 2020-04-16 2020-09-01 中国一冶集团有限公司 Sponge city and utility tunnel integration system
WO2022037364A1 (en) * 2020-08-18 2022-02-24 中铁二院工程集团有限责任公司 Ecological integrated pipe gallery
EP4133935A4 (en) * 2020-08-18 2024-01-24 China Railway Eryuan Engineering Group Co. Ltd Ecological integrated pipe gallery
CN112459111A (en) * 2020-10-27 2021-03-09 江苏旭松建设工程有限公司 Pipe gallery protection device based on sponge city and construction method thereof

Also Published As

Publication number Publication date
CN105926676B (en) 2017-12-01

Similar Documents

Publication Publication Date Title
CN105926676A (en) Comprehensive pipe rack system with sponge urban function
CN205688461U (en) Pipe gallery section structure
CN103739167B (en) Rain and sewage dual-purpose landscape type ecological purification system
CN205688460U (en) Pipe gallery system with sponge city function
CN106638681B (en) A kind of pipe gallery
CN104213599B (en) Zero energy consumption roof rain water reclaims Waste water utilization system
CN107816082A (en) A kind of sponge roof rainwater collection reutilization system
CN105735449B (en) A kind of urban road rainwater collecting and treating system
CN104929684A (en) Underground rain sewage pre-treatment station connected to deep layer tunnel drainage system
CN204530842U (en) Rain water collecting system
CN201972229U (en) Residential rainwater comprehensive utilization system device
CN204865234U (en) Rain water filtering device
CN203938558U (en) Rain, dirty dual-purpose landscape type ecological purification system
CN206368389U (en) One kind backwash and sewage sucking system
CN206784544U (en) A kind of sponge city water guider
CN105544345B (en) A kind of rainwater on road surface Collection utilization system
CN203173911U (en) Precipitation device
CN105442668A (en) Roof rainwater recycling system
CN108056004A (en) A kind of overpass rainwater catchment system irrigation system
CN104532907B (en) pump station structure
CN207211190U (en) A kind of pipe gallery
CN207160179U (en) Circularly purifying and reuse rainwater structures in a kind of greenery patches
CN104909482A (en) Construction site water recovery and recycling system comprehensive purification tank and manufacturing method thereof
CN205776495U (en) Sponge type solid rainwater reuse for sponge urban construction is regulated and stored system
CN207331931U (en) A kind of water seepage prevention floor drain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 200011 Tibet South Road, Shanghai, No. 1170, No.

Applicant after: Shanghai urban construction design & Research Institute (Group) Co., Ltd.

Address before: 200011 Tibet South Road, Shanghai, No. 1170, No.

Applicant before: Shanghai Urban Construction Design & Research Institute

GR01 Patent grant
GR01 Patent grant